Minutes from Meeting

Meeting Week No: 06 Document stored:


/PC

Subject:
Lahore Region BTS Rollout Project Review

Date/Time: Place:
August 18, 2014 @ 10:00 RO, Lahore

File No.: From:


20140818_MoM_Lahore_Region Minutes by Shoaib Rehman

Participants: Distribution:

Abdul Ghaffar Participants list+


Syed Muhammad Afraz
Syed Nasir Imam Bukhari Muhammad Adnan Ashraf,
Mohammad Qasim Awan Hasrat Mehmood
Muhammad Ali Bukhari Ghulam Husnain Nasir
Muhammad Abbas Hayat Muhammad Javed
Tahir Hafeez Toor Rai Fakhar
Mansoor Dildar Sheraz Aslam
Shoaib Rehman
Ahsan Arshad

Weekly Lahore Region BTS Rollout Progress Meeting

Agenda

1. Progress on Lahore Region BTS Rollout Target


2. Action points from the last meeting to be revised
3. Delays and plans to catch up
4. Rolling plans for next 1 week
5. Risks/Dependencies
6. Blocking (escalation) issues
7. Action Points

Weekly Lahore Region BTS Rollout Progress Meeting


1/5
COMPANY CONFIDENTIAL

Action Points

AP/WK ISSUES Raised Responsible Due Date Status

01/27 Network Commerical Network Every Progress for Lahore and Central
Implementation will Implementation Meeting Region Delivery plan was
present the Progress presented in the meeting.
Report on Central [Week34]
Region

01/28 It was Communicated Network Network 14.07.14 BTS Equipment is expected


to all stakeholders that Implementat Implementation 11.08.14 to be arrived by August 20,
we are not going to on- ion 18.08.14 2014.
Air the new BTS Rollout It is updated in the meeting
sites in July because of that 2G/3G Rollout
the unavailability of the shipment have been taken
BTS Equipment. over by Custom’s
Meanwhile Civil Work is Intelligence for
on-going and it will be investigation. [Week34]
completed in July.

01/29 It has been informed by PGA TP Regulatory 14.07.2014 OPEN. [Week34]


PGA that FAB 28.07.2014
application has been 11.08.2014
applied on May 10, 18.08.14
2014 on all D.H.A Sites.
As per the SOP it will
take 12 to 16 weeks to
get the FAB NOC.

02/30 It has been informed PGA Site Acquisition 21.07.2014 OPEN. [Week34]
to all stakeholders
that Confusion has
been cleared to all
TP Site Acquisition
vendors regarding
the 2013 TMA NOC
policy.

Earlier The TP Site


Acquisition vendors
raised the concerns
regarding the 2013
TMA NOC policy.
They claim that it is
mentioned clearly
that the BTS Towers
shall not be installed
in the residential
area.

It has been informed


in the meeting that
all TMA and vendors
has misinterpreted
the 2013 TMA NOC

Weekly_Regional_Meeting 2/5
COMPANY CONFIDENTIAL

policy but the


confusion has now
been cleared and
further clarity has
been given to TP
Site Acquisition
vendors.

It has been updated


to all stakeholders
that following TMA
has been secured by
the vendor.

1. LLR372 - Taj
Bagh Lahore
2. LMB013 -
Mandi
Bahauddin
3. LGW333 -
Gujranwala

01/33 It has been informed PGA Commercial 11.08.14 TP Commercial will Update
to all stakeholders 18.08.14 about the Business decision
that Risk based for implementing the IBS
analysis has been [In Hosiptal] in the next
required to meeting. [Week34]
Implement the IBS
sites. It has been
informed to
Commerical that
TMA will not issue
the TMA NOC for the
Hospitals[IBS] as
this is against the
TMA Policy. A
complete business
decision is required
from TP Commerical
for the implementing
of IBS without the
TMA.

01/34 RF will share the Commercial RF 18.08.14 OPEN. [Week34]


franchise ID with
Implementation
team.

02/34 It has been informed Network Commercial 18.08.14 OPEN. [Week34]


that following Implementat
exhausted sharing ion
sites are still not
converted to TP-
Built.

Weekly_Regional_Meeting 3/5
COMPANY CONFIDENTIAL

1. LLR157
2. LLR554
3. LLR832
4. LLR060
5. LLR171
6. LLR285
7. LLR572
8. LLR845

03/34 Telenor will discuss PGA Commercial 18.08.14 OPEN. [Week34]


the IBS Rollout sites
with Concern
Medical superitant as
these sites are
Planned in Hospital.
There is a possibility
that these sites got
Rejected due to
Punjab BTS policy
2013 if any Medical
superitant ask for
the approval.

It has been informed


to Commerical that
TMA will not issue
the TMA NOC for the
Hospitals[IBS] as
this is against the
TMA Policy.

To proceed without
TMA NOC is
calculated risk that
TMA can order for
dismantling the
sites.

The IBS Sites are as


follows:

1. LLR957 -
Sheikh Zayd
Hospital
Lahore
2. LLR958 -
Mayo Hospital
Lahore
3. LLR961 -
Children
Hospital,
Lahore.
4. LLR963 -
Ganga Ram

Weekly_Regional_Meeting 4/5
COMPANY CONFIDENTIAL

Hospital,
Lahore
5. LLR965 -
National
Hospital
(Chughtai
Labs)

Next weekly progress Meeting # 6

Monday August 25, 2014 @ TP D.H.A RO, Lahore.