METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
CONTENTS
1. ACTIVITY
2. INTRODUCTION
3. TERMINOLOGY
4. SIGNIFICANT HAZARDS IDENTIFIED
5. ROLES & RESPONSIBILITIES & ORGANIZATION CHART
6. SEQUENCE OF ACTIVITIES WITH RESPONSIBILITIES
6.1 Pre-commencement Requirements
6.2 General Requirements
6.3 Co-ordination with Other Trades
6.4 Scaffolding
6.5 Delivery, Storage & Handling of Materials
6.6 Execution
7. REQUIREMENTS
7.1 Plans/Records & Job instructions (Documentations)
7.2 Training
7.3 PPE (Personal Protective Equipment)
7.4 Equipment & Tools required
7.4 Risk Assessment
8. EMERGENCY PROCEDURES
9. REFERENCES
10. ATTACHMENTS
Page 2 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
Page 3 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
PROJECT
o Ensuring availability of all activity relevant latest approved drawing and documents
PROJECT
6.1 Pre-commencement Requirements
• Approved drawings and work procedures shall be obtained from O / E prior to the start of
activity
• Safety regulations as per specifications and standard.
• Ascertain the nature and location of all existing above and underground services on site by
visual survey.
6.2 General Requirements
Before start of the work the following shall be ensured:
• Tools, Equipment & Machinery is suitable and approved for use.
• Availability of suitable quantity of approved material for the works as per specification and O/E
requirements.
• Area clearance obtained from other discipline/subcontractor.
6.3 Co-ordination with Other Trades
• No Tiling works to be started on any wall until and unless it is cleared for tiling.
• Prior to start of tiling works, check all architectural, mechanical and electrical works are
completed and MEP clearances shall be taken as required.
6.4 Scaffolding
• Scaffolding will be erected using standard and ledgers by well trained scaffolders for doing
painting above 1.5m high. Wooden planks should be placed over ledgers to serve as working
platform with proper toe board.
6.5 Delivery, Storage & Handling of Materials
• All materials shall comply with the specifications regarding quality, dimensions, strength etc.
• The material shall be approved and shall be used as per the Finishing Schedule.
• The color of the Ceramic Tile shall match the appropriate approved sample.
• The Ceramic tile shall be stored under covered area to prevent damage and soiling and kept in
cartoons until removed for fixing.
• Manufacturer’s recommendations shall be followed for storage and handling.
6.6 Execution
Surface Preparation
• All surfaces to received tile shall be structurally sound clean, dry and free from oil and all
foreign matters.
Page 6 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
• Surfaces to receive tile shall be plumb, horizontal level or at the slope as specified and true with
square corners.
• Prior to placing of tile the concrete surface shall be kept thoroughly wet.
Mixing
• Mixing and applications of Adhesive and grouting shall be complied with manufacture’s
procedure and recommendations.
• The wall to receive tiles shall be finished with cement/ sand plaster as per approved method
statement.
• The plastering to the wall surfaces must be fully cured and free from any contamination, dust
and crack before commencing the wall tile works.
• Setting out shall be done as per approved shop drawings.
• The surveyor shall mark the finished floor level on the wall of the room.
• The wooden plywood strip shall be fixed above 2 tile high from FFL on the wall.
• Ceramic tile shall be soaked in water and it should be removed 20 minutes before use.
• Wall tile fixing shall start from the fixed wooden strip level.
• Approved adhesive materials shall be applied to the wall as continuous even float coat and the
wall tiles are fixed to the adhesive with twisting/sliding action to give the finished bed thickness
not more than 3mm.
• Tile shall be correctly positioned in both directions by using 2-3mm plastic spacers to achieve
even joints.
• To check the adhesion as the work proceeds, a sample tile shall be removed immediately after
fixing as per O/E instructions and refixed without any delay.
• The tile shall be fixed in away to get solid bedding and adhesion over the whole of the tile
background.
• Excessive adhesive material shall be removed with damp cloth without disturbing tiles.
• The cut tiles and the tiles on the sides of sanitary fittings and fixings shall be properly cut and
laid in a neat manner.
• After fixing wall tiles floor tile shall be started as mentioned in section 6.62
• The fixed tile shall be left for minimum of 24 hrs to cure before grouting.
Page 7 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
• NO ACCESS or Warning tapes to be fixed upon completing tile fixing and no other activities
shall be allowed until the tiles are firmly set.
• Before start grouting, all spacers should be removed and ensure that there is no damages.
• Simultaneously the tile shall be cleaned with the dry cloth to give a aesthetic look.
• The grouting mixing and application shall be followed as per manufacturer’s data
sheet/recommendations.
• In interior finishing works, all tiles shall only be set and laid after the fixing of window and door
frames and trims, stop rails, electrical, plumbing installations as well as the application of plaster
unless otherwise specified.
• All anchors, recessed frames, electrical and mechanical items shall be installed tested and
approved prior to commence with floor tilling.
• For wet area only the approved water proofing system shall be installed.
• Carry out a 24 hrs water test for water tight purpose prior to start with tile activity for wet area
only.
• The surveyor shall mark the required level of the bedding screed /protection screed to the
specified thickness and in true alignment and horizontally or to slope as specified as per the
approved drawings.
• Install polythene sheet and a protection screed of 50-60mm thickness with slope 1% towards the
floor drain shall be applied and it should be cleaned.
• Setting out shall be done as per approved layout drawings. Joints shall be true to line, truly
horizontal, continuous and without steps.
• For wet and dry area, ceramic tile shall be fixed by approved Tile adhesive.
• Ceramic tile shall be soaked in water and it should be removed 20 minutes before use.
• Adhesive shall be applied on working area not more than one square meter at a time or as per
manufacturer’s recommendations/procedure.
• Tile shall then be laid on the adhesive layer with a twisting motion ensuring good contact
between tile and adhesive bed. For this purpose the adhesive manufacturer’s instructions should
be followed strictly to achieve the 100% mortar coverage.
• Tile shall be correctly positioned in both direction by using 2-3mm plastic spacers in order to
accommodate the difference between wall and floor tiles as per approved drawings.
• The tile shall be neatly cut to a close fit where the necessary at abutments, around the outlets,
pipes and the like.
• Particular care will be taken in ‘Wet’ areas to prevent low spots that may promote water pooling
the tolerance in the overall level shall not be more than5mm from required level.
Page 8 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
• Localized variation in level for nominally flat floor shall be max of + or – 3mm, when tested by
3meters straight edge.
• Excessive adhesive shall be removed with damp cloth before the material has set.
• The fixed tile shall be left for minimum of 24 hrs to cure before grouting.
• NO ACCESS or Warning tapes to be fixed upon completing tile fixing and no other activities
shall be allowed until the tiles are firmly set.
• Before start grouting, all spacers should be removed and ensure that there is no damages.
• Simultaneously the tile shall be cleaned with the dry cloth to give a aesthetic look.
• The grouting mixing and application shall be followed as per manufacturer’s data
sheet/recommendations.
7) REQUIREMENTS
7.1 Plans /Records and Job instructions (Documentations)
Before commencing the work the following things should be available:
• Approved drawings / Material approval for the work
• Approved Sample Board
• Method statement for the work
• Civil Work inspection
• QA/QC Check sheet
• Key site plan for that work area
• All tools & machineries
• Emergency escape route without obstructions
7.2 Trainings
• Trained/Experienced & Skilled persons shall be used for the work
• All operator / Laborers are safety trained and toolbox shall be conducted.
7.3 PPE (Personal Protective Equipment)
• Protective footwear
• Protective clothing
• Safety helmet
• Safety goggles
• Hi-visibility jacket
• Flagging tape
• Warning tape
Page 9 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
• Flasher light
• Safety Harness (above 1.8m)
1. Tile cutter
2. Pallet
3. Hand tools such as trowels, plumb, Spirit level etc.,
4. Grinder, Scrapper
5. Aluminum straight edge
6. Brush/Electric air blower/air compressor for cleaning
7. Exhaust fans/ventilation for indoor workings
8. Scaffoldings and proper platform for working at heights.
Page 10 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
In case of major Injuries
Do not panic. Call ambulance and notify emergency team at site
Do not move the injured unless he is in danger
If danger exists, he shall be assessed by a trained and qualified first aider
before moving. Use a stretcher.
Do not crowd around the victim. Do not give anything to eat or drink.
Ensure adequate air and lighting.
Only trained and qualified first aider shall treat the victim and ensure that
his airway is kept clear.
Victim shall be transported to hospital in an ambulance.
Preserve the accident scene for further investigation.
In case of Fire
Follow Transco/s approved emergency procedure as per HSE Plan.
In Case of Flood
Evacuate immediately to the nearest highest location you are in.
Notify the Emergency Controller of the site
EMERGENCY CONTACT NUMBERS:
POLICE 999
AMBULANCE 998
FIRE SERVICE 997
MAFRAQ
HOSPITAL
02 5823100
Page 11 of 11
METHOD STATEMENT FOR
CERAMIC TILE WORKS
Effective Date :
Document No : MOS-17-CTW
Revision No : 00
Approved By :
PROJECT
9). REFERENCES
138807928.DOC
138807928.DOC
DRWG. NO. N7204.1E-R-E-5370-S-7204 REV. 0 SHEET 1~1
DRWG. NO. N7204.1E-R-E5300-S-7153 REV. A SHEET 1~1
DRWG. NO. N7204.1E-R-E5300-S-7154 REV. A SHEET 1~1
DRWG. NO. N7204.1E-R-E5300-S-7155 REV. A SHEET 1~1
DRWG. NO. N7204.1E-R-E5370-S-7157 REV. A SHEET 1~5
REF: N-7204.1E/MASS/0080 – CERAMIC TILE
REF: N-7204.1E/MASS/0155 – TILE ADHESIVE
REF: N-7204.1E/MASS/0155 – TILE GROUTING
10). ATTACHMENTS
138807928.DOC
138807928.DOC
ORGANIZATION CHART
RISK ASSESSMENT SHEETS