QF/PRP/22

LIQUID PENETRANT INSPECTION REPORT


Client : Bharat Petroleum Corporation Ltd Title : New Salt Drier
Mfgr. : Expo Gas Containers Ltd Eqpt. No. : 120-NV-15
Inspection : CEIL Expo Job No : T-1012
P.O.No. : 4505750101 Dt- 01/09/2016 Drg. No. : P45801A1HV0001 Rev-2
Date: : 28/01/2017

Material Form : Plate/Welded Pipe Surface Condition : As Welded/Ground


Pre cleaning : Cleaner Post Cleaning : Done

Penetrant Penetrant Remover Cleaner Developer


Make-Spray Fill Make-Spray Fill Make-Spray Fill
Brand-SC10 Brand-SC30 Brand-SC20
Type-Solvent Removable Type-Solvent Type-Non Aqueous
Method-Visible Application-Wiping by Cleaner Application-Spraying
Application-Spraying Dampened Cloth Visible Light- More than 1000 Lx
Dwell Time- 20 Minutes Drying Time-02 Minutes Dwell Time- 10 Minutes
Batch No.-DYE251501 Batch No.-FTC 251501 Lighting Equipment-100 w Bulb
Exp. Date- 10/03/18 Exp. Date-FEB.-18 Batch No.-FTD 251501
Exp. Date-FEB.-18

Dye Penetrant Testing carried out on Inside & Outside of Knuckle Area, Straight Face, and Weld
Edge Preparation, Chordal Long Seam

Found No Recordable Indication Observed.

REMARKS:- Test Found Satisfactory.

For Expo Gas Containers Ltd. For CEIL

Insp. Engg. Surveyor