FINAL RELEASE NOTE

Ref : FRN/13068/001

CLIENT : PETRONAS

PROJECT : FUEL GAS CONDITIONING UNIT COMPRESSOR SKID-1

PROJECT TITLE : SUPPLY AND DELIVERY OF FUEL GAS CONDITIONING


UNIT(FGCU) AND ASSOCIATED EQUIPMENT FOR 15 MW
POWER PLANT FOR GARRAF DEVELOPMENT FACILITY
OPERATION

PROJECT NO. : TOE-13068

P/O No. : ET/GDFP/001

SUBJECT OF INSPECTION QTY

FUEL GAS CONDITIONING UNIT COMPRESSOR SKID-1 1

The above item have been released in accordance with specifications and purchase
order requirements on hand at TOE's premises at the time of Inspections.

Release :

Release with comments :

Punch List no. : 13068-PLR-01 Pages: 2 Closed on: SEE ATTACHED

ADDITIONAL COMMENTS:

Manufacturer: QA/QC Department WITNESSED BY B.V.INSPECTOR

Signature: Signature:

Name: TILAK Name:


Date Of Issue : 01-04-2014 Date Of Issue : 01-04-2014
FINAL RELEASE NOTE

Ref : FRN/13026/002

CLIENT : PC VIETNAM LIMITED

PROJECT : DIAMOND DEVELOPMENT PROJECT GAS LIFT COMPRESSOR


PACKAGE

PROJECT TITLE : GAS LIFT COMPRESSOR PACKAGE (A-0610)

PROJECT NO. : TOE-13026E

P/O No. : PCV/DMDP-A/2012/614

SUBJECT OF INSPECTION TAG NO. QTY

GAS LIFT COMPRESSOR PACKAGE A-0610 1

The above item have been released in accordance with specifications and purchase
order requirements on hand at TOE's premises at the time of Inspections.

Release :

Release with comments :

Punch List no. : Pages: Closed on:

ADDITIONAL COMMENTS:

Manufacturer: QA/QC Department Client :

Name: TILAK Name :


Date Of Issue :