Project Name : FIT OUT FOR PODIUM AT QATAR PETROLEUM DISTRICT
Package No. : 2 Contract No. : GC18108100
Contractor Prj. No. : MJ-175 Form No. : P07-F14/ Rev. 0/ Jul. 2018
Client: Consultant: Contractor:
Submitted for :
- IFC : Issued for comment - IFA : Issued for Approval - IFI : Issued For Information - RET : Issued For Retention
Note : Approval or comments made to this submittal does not relieve the Contractor from their responsibilities. The assessment is to review the general conformance and compliance of the submittals to the contract and
specification requirements.
MG TN #21014
Document Submittal Form AEB - Quality Forms 1 of 1 Form No.: P07-F14 / Rev. 0 / Jul. 2018
Project Name: Fit Out for Podium at QPD
Elec:
1. 2
Provide name and contact details of each designated NOTED & COMPLIED; please refer Section-
responsible persons. 10.1, Page# 19.
HSE: section 2: HSE objective is missing. Method The document structure is laid with reference
statements are document that detail exactly how to carry to previously approved (code-10) templates
out work safely. which do not have “HSE Objective” but the
Contractor to incorporate the HSE objective. whole document (including Risk Assessment)
is drawn considering the same and in
compliance with HSE Plan. However, since
2. 2 only now this ‘new’ section is been requested,
it is incorporated for this document and all
future new submissions (if any). Hence -
Document Reference: QPD-9-K19-0021 Rev. 0 Page 1 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
Document Reference: QPD-9-K19-0041 Rev. 0 Page 2 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
Document Reference: QPD-9-K19-0041 Rev. 0 Page 3 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
Document Reference: QPD-9-K19-0041 Rev. 0 Page 4 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
Document Status: 10 = Approved 2 = Approved with Comments (Incorporate comments 3 = Not Approved (Incorporate comments and
(Resubmission not and resubmit - work may proceed subject to resubmit - work shall not proceed)
required) incorporation of comments)
6 = For Information 1 = Approved without Comments (Resubmission 11 = Cancellation Accepted
Only required - work may proceed)
Note 1: A unique CDF serial number will be allocated with document initial submission; subsequent revisions will be reflected in CDF revisions (applicable at least by QRC and QP)
Note 2: Originator - QP/ QRC
Note 3: Please encode separate number for each CDF in the footer with revision number
Document Reference: QPD-9-K19-0041 Rev. 0 Page 5 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
CONTRACT REF.: GC18108100
DOCUMENT TITLE :
METHOD STATEMENT FOR TESTING AND COMMISSIONING OF
CROWN LIGHTING SYSTEM
QRC:
CONTRACTOR :
Contents
1. PURPOSE: ............................................................................................................................................. 3
2. SCOPE& OBJECTIVE ........................................................................................................................... 3
3. REFERENCES ....................................................................................................................................... 3
4. ABBREVIATIONS .................................................................................................................................. 4
5. HEALTH & SAFETY HAZARDS: ........................................................................................................... 5
6. RESPONSIBILITY ................................................................................................................................. 9
7. PROCEDURE / METHOD TO BE EMPLOYED .................................................................................. 11
7.1 Pre-Commissioning: ................................................................................................................ 11
7.2 Commissioning: ....................................................................................................................... 11
7.3 Third Party Interface Testing (SIT - System Integration/ Interface Test):........................... 15
7.4 SITE ACCEPTANCE / OPERATIONAL & PERFORMANCE TEST (SAT) .............................. 16
7.5 Witness Demonstrations/ Completion ................................................................................... 16
8. WORK PERMIT ................................................................................................................................... 19
9. WORKING HOURS .............................................................................................................................. 19
10. MANPOWER ........................................................................................................................................ 19
11. LOGISTICS .......................................................................................................................................... 21
12. MATERIAL REQUIREMENT ............................................................................................................... 21
13. PLANT & EQUIPMENT REQUIREMENT ............................................................................................ 21
14. COLOR CODING ................................................................................................................................. 21
15. HOUSE KEEPING................................................................................................................................ 21
16. SCAFFOLDING (where necessary) ................................................................................................... 22
17. QC APPROVAL AND OTHER DOCUMENTARY REQUIREMENTS ................................................. 22
18. SUPPORTING DOCUMENT ................................................................................................................ 22
19. DISTRIBUTION .................................................................................................................................... 22
20. OTHER INFORMATION ...................................................................................................................... 23
21. MAIN CONTRACTORS SAFETY ENGINEERS APPROVAL ............................................................. 23
22. ATTACHMENTS .................................................................................................................................. 23
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 3 of 25
1. PURPOSE:
This Method Statement covers the Testing and Commissioning procedure of the Crown Lighting
within the QPD Project (roof levels of Tower 1 to 9 and Tower 10) to insure proper operation of all
components of the systems and their compliance with project requirements & specifications.
2. SCOPE& OBJECTIVE
This Method Statement is applicable for Testing & Commissioning of Crown Lighting System
(CLS) in Fit Out works for Package 2 at QPD Project (under Appendix-F, several modifications
Item# 7). The scope of this document is to provide the implementation of the commissioning
process regarding specific system being commissioned. Commissioning includes performance
testing to demonstrate that CLS and accessories meet the contract performance of the system
installation per manufacturer’s recommendation, industry accepted standard and project
specification.
2.1 HSE Objective:
The HSE objective is to deploy standard procedures in ensuring no harm befalls anyone
during the T&C of the system.
3. REFERENCES
Contract Documents, Scope of Work Appendix F Several modifications, Item# 7, Package 2
Electrical specification (QPD-9-A14-2000)
QATARENERGY safety Regulations QP-REG-S-001, Corporate Quality Standards QP-REG-Q-
003 & QP-STD-Q-004
QatarEnergy lifesaving rules; QATARENERGY Code of Practice for Life Saving rules (NEW)
(QP-SOF-COP-21)
Workers welfare standards edition-2
Labour Laws; Qatar Law No.14 of the Year 2004 – The Labor Law, and the ministerial decisions
issued (No.14 of 2004, and its amendment)
Worker Rights Booklet 2009
Approved For Construction (AFC) Drawings
Approved Shop Drawing
Approved Material Submittal for lighting type- L01F, L01W, L02F, L02W, L03F, L03W (roof light)
(QPD-9-MAR-E-0444-2)
Specialist Contractor for Commissioning of the system (Pre-Qualification for Techno-Q Light
Fitting Supplier) – Prequalification Document (QPD-9-PQD-E-0134-1)
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 4 of 25
Note: Revision reference numbers of the above mentioned documents are subject to frequent
change (resubmission), and hence latest revision shall be cross checked from the document
register.
4. ABBREVIATIONS
AEB Arab Engineering Bureau
AFC Approved for Construction
FM Facility Management
MG Medgulf (Main Contractor)
Client QatarEnergy
Supplier/ Vendor Gulf Lights
Specialist Subcontractor for Commissioning Techno-Q
Pre-task briefing, Toolbox talk (TBT) and Risk assessment matrix (RAMS) to be briefed /
communicated to the workforce prior to commencement of the activity
Safety toolbox talks
Environmental toolbox talks
HSE training records / Toolbox attendance register
Internal Safety Awareness courses
HSE Bulletin / HSE Site Notice Boards
HSE Personnel site instructions
Site Engineers, Site Supervisors and Site Foreman will ensure safe work method is adopted.
Emergency Procedure: All running machines shall be switched off before leaving the site.
All project personnel, subcontractors and visitors shall be required to wear as a minimum the
following PPE:
Safety boots (with steel toecaps and insoles)
Safety helmets
Eye protection
Ear plugs / Earmuff
High visibility vest
Full body harness as per QATARENERGY standard (for height more than 1.8m)
Gloves; electrician/operatives should wear the electric shock proof gloves during any live
testing & commission works
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 7 of 25
Face Masks
Ear defenders, if working near to the equipment.
Emergency procedures to be communicated to all assigned employees for this scope of work
before commencement of activity.
All communications to be documented and made available for the client whenever requested
Copies of emergency procedure to be kept at site for and available for reference at any point
during the work
• Report other Information-Company name, the location where incident occurred and your
name and contact Number.
• Evacuation should be prompt and calm, with everyone making their way to the designated
assembly point.
• Await further instructions. A roll call shall be taken to ensure all workers are present.
• Work Activity shall resume only after obtaining permission from AEB, MCFM and QE and
revalidation of Permit.
Follow the client / consultants approved Fire Emergency Procedure and Fire Drills Steps
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 8 of 25
Safety boots
Safety Helmet
High Visibility Vest
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 9 of 25
Safety Gloves
Electric shock proof gloves (while working on live during T&C)
Safety Glasses
Ear Plugs
Dust Mask
Full Body Harness
6. RESPONSIBILITY
Project Manager- is overall responsible for the successful initiation, planning, execution,
monitoring, controlling and closure of a project as per the approved schedule and contractual
requirements and make sure they control risk and minimize uncertainty. Also, he will
maintain the planning progress and coordination of works with Main Contractor.
Testing & Commissioning manager (MG) - is the overall responsible for the
implementation of this procedure and ensure that the team of Engineers, and other related
staff are aware of this procedure , all resources , manpower; material and equipment are
available to carry out the testing and Commissioning as planned, without any delay. And
implement the Lock -out / Tag-Out procedure when required.
To ensure that all commissioning activities are carried out in liaison with supplier / vendor to
the satisfaction of QRC/ QatarEnergy.
Raising non-conformance or corrective action and adhere to safety procedure.
Carry out a punch list walk down and liquidate punch list items as required.
HSE Manager- will report to Medgulf Project Manager and will be responsible for: -
o Provide guidelines to the Construction Department (team involved for T&C) on safety
related matters.
o Ensure the development and implementation at site SAFETY related activities; assist the
management in all SAFETY related matters and manages the SAFETY Organization at
site.
o Ensure that the SAFETY Plan/Procedures are distributed to all concerned and supplying
the necessary information.
o Managing the incident/accident investigation as per procedure and maintaining records of
the site Safety Statistics.
o Issuing SAFETY meetings programme and organizing meetings. Ensure the teams are
briefed prior to start activities mentioned in this document and the related risks and
necessary mitigations are in place.
o Managing First-Aid and health care organization and facilities at site.
o Liaise with Project Manager and Const. Manager for implementation of SAFETY
Plan/Procedures etc.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 10 of 25
o Ensure that the Project SAFETY objectives are met through implementation of
Procedures and technical activities.
Commissioning Engineer - To ensure that all commissioning activities are carried out in
liaison with system specialist to the satisfaction of MG / AEB-QRC/ QATARENERGY. Raising
non-conformance or corrective action and adhere to safety procedure. Carry out a punch list
walk down and liquidate punch list items as required
Project Engineer/ Site Engineer- is responsible for the day to day activities on site, for
materials, approved drawings, approved method statement, testing & commissioning and
allocation of departmental resources to work areas on Site. He is also responsible to ensure
adequate equipment for shifting of materials and other related works are in place prior to the
starting of work. The Project Engineer will report to the Project Manager.
Supervisor / Foreman – will be directly responsible for the day-to-day works on site as per
instructions of the Project Engineer / Site Engineer and provide proper documentation to his
workers so they can proceed with tasks and handling the technicians, or any other staff
assign to his area.
QA/QC Manager – Manage and control quality inspection activities, ensuring that all
inspection and testing efficiently executed in accordance with standard specifications,
approved engineering drawings and ITPs; ensures results data/records are properly
documented and maintained.
QA/QC Engineer – will oversee all the quality requirements and quality control measures for
the Project in coordination with the Project Engineer as outlined in the Approved Project
Quality Plan
QA/QC Inspector - will check the quality requirements and quality control measures for the
Project in coordination with the QA/QC Engineer as outlined in the Approved Project Quality
Plan
Safety Officer – will be responsible for the Health and Safety aspects on site as per the
Mains Contractor Safety requirements.
Specialist (Techno-Q) Project/ Cx Manager – coordinates with the Contractor and
manages the testing procedure at site.
Specialist (Techno-Q) Project Engineer/ Commissioning Engineer - is responsible for
pre-commissioning, testing and commissioning.
AEB-QRC/ QE Representative - Advise punch list items. Witness of testing & verification
carried out during commissioning.
Third Party (GST) – will be witnessing the Testing & Commissioning activity. GST being
qualified and experienced independent testing and commissioning third party, hired by MG
shall be witnessing & reporting of the testing and commissioning activities.
Refer Prequalification for Third Party Testing & Commissioning (GST), Doc.ref. no. QPD-9-
PQD-MG-0072
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 11 of 25
7.1 Pre-Commissioning:
Prior to beginning the commissioning activities, it shall be insured that:
Check that all relevant QA/QC IRs are available, i.e., Installation of lights & modules, Cable
Testing and Panel termination IRs, as applicable.
RPL/ Punch list Category A items are addressed, cleared, completed, corrected and
approved by QatarEnergy/QRC before starting the pre-commissioning activities.
Inspect visually the external and internal, where applicable, parts of panels, controllers,
modules, devices, lighting fixtures, wiring, etc.
Ensure all installation are complying to the approved, by QRC, technical and construction
submittals (MARs, MIRs, IRs, shop drawings, approved installation details, Schematic
diagram etc.) related to this activity
Ensure and verify that tagging is applied as per approved tagging system in the project.
Ensure tagging materials as per approved submittals
Ensure cables and wiring are installed, terminated and labelled safely with no defect.
Labelling shall be as per approved labelling system
Ensure termination to final lighting fixtures shall be as per Kahramaa regulation, QCS
requirements, project specification, MIRs, IRs and shop drawings
Check fixation for the light fitting is complete and the alignments are done properly.
Ensure that the grounding/earthing of the lights are properly connected to the earthing
system.
Ensure all warning labels and circuits tags are provided.
All light fittings should be installed and powered UP.
Console, all the light fitting and Stick D3 controller etc. should be powered ON with
240±6%VAC (and/ or rating as per the equipment name plate and approved schedules).
7.2 Commissioning:
Pre-commissioning activity for fixtures and cable are completed and related inspection
requests are approved.
All approved documents of Method Statement for Testing & Commissioning, ITP, Checklist,
and relevant approved drawings (schematic and layouts) shall be available for the test.
After PRC and prior to Commissioning commencement, check that Mechanical Completion
Certificate (MCC) and Punch list details must be complied as per the T&C plan. MCC
approval from QRC/QatarEnergy must be obtained prior Commissioning activities.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 12 of 25
Punch list Category A items are addressed, cleared, completed, corrected and approved by
QatarEnergy/QRC before starting the commissioning activities.
The MCI light fixtures must be addressed using the addressing tool which is shown below.
MCI 7150203
The addressed fixtures should be patched in the ESA pro application which is used to configure
the Stick D3 controller. All the fixtures are patched in the universe 1, which can control 512
channels.
After the patching the fixtures are divided into three zones and the fixtures covering the zones are
grouped together in the ESA pro application.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 13 of 25
The next step in the commissioning is the creating the Pre-set , these pre-set can be defined in
the ESAPRO application
FIXTURE
S.NO CONTROL FROM RGBW PERCENTAGE
CONSOLE
Zone 1 -Blue 100 %.
1 Preset 1 Zone 2 - Green-100 %,Blue 74 %,
Zone 3 -Blue 100 %.
Zone 1 -Blue 100 %, with the stimulation
effect
Zone 2 - Green-100 %,Blue 74 %,with the
2 Preset 2
stimulation effect
Zone 3 -Blue 100 %.with the stimulation
effect
Zone 1 - Red 80 %
3 Preset 3 Zone 2 - White 100 %
Zone 3 - Red 80 %
Zone 1 - OFF
4 Preset 4 Zone 2 - OFF
Zone 3 - OFF
Zone 1 - White- 100 %
5 Preset-5 Zone 2 - White 100 %
Zone 3 - White 100 %
The programmed configuration is written in stick D3 controller with the help of USB interface cable .
The images of the write menu are shown for your reference.
Before writing the configuration, make sure that memory Sd card is installed in the Stick D3 controller, the
programmed database is stored in the SD memory card.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 15 of 25
7.3 Third Party Interface Testing (SIT - System Integration/ Interface Test):
RS232 Triggering It is possible to start scenes using the input ports (contact closure)
included on the 2x10pin Extension Socket. To activate a port, a brief contact of at least 1/25
second must be established between the ports (1...8) and the ground (GND). Note: 1. A
scene must be assigned to a port in the software,
The scene will not be switched off when the switch is released.
1) Pre-requisite
Prior to start of Site Acceptance Test (SAT) activities, the following activities to be completed.
Commissioning activities (Functional and Interface tests) has been successfully completed
and documented in relevant dossiers.
Relevant training has been conducted.
All relevant operational/ functional tests have been conducted.
2) SAT
SAT shall be performed for duration of 72 hours (3 days).
Since operation of these lights at night timings but the controllers is operational 24/7, SAT
hours shall be considered observing the operation of the lights for 8 hours per 3 days
duration.
The commissioning results will be recorded on project agreed format and offered to
AEB/QatarEnergy for witnessing/acceptance.
An Inspection Request attached with the PRC IR, test reports and later with the MCC will be
raised by MG to QRC, to enable co-ordination/sign off of Crown Lighting system testing with
the Client representatives.
The client representative of the end user will be invited to witness the field testing. The
representative will select the points to be demonstrated and the results shall be stored in
accordance with the prescriptions.
Witnessing the field testing will be as per QatarEnergy instruction in compliance with Project
Specification, T&C Plan, approved T&C MS and ITP.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 17 of 25
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 18 of 25
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 19 of 25
8. WORK PERMIT
Permit to Work (PTW) is required prior to start of any work activities within the project. MG PTW
procedures approved by AEB and QATARENERGY will be adopted for all internal works without
interference to FM services and ongoing client operations.
MG PTW Authorized Person shall be the only person who shall approve the Permit to Work
(PTW). If any activity that requires an interface is to be undertaken, a MCFM Permit to Work shall
be processed as required.
Reference shall be made to this Method statement and Risk assessment in the PTW. MSDS of all
Hazardous materials shall be attached with the PTW for ready reference.
9. WORKING HOURS
Site working hours shall be followed as instructed by Main Contractor site timings. Statutory
Regulations shall be strictly followed in summer for the working hours.
10. MANPOWER
11. LOGISTICS
List of Test Equipment/ Tools required for Pre-Commissioning & Commissioning of LCS Systems
are as follows.
Laptop – programmed with Software to commission, Check light Levels, Troubleshooting
Screwdriver – for Termination.
Digital Multi-Meter - Check continuity, measure voltage.
Lux meter – Check lux levels
NOTE: Ensure all instruments having latest and valid calibration certificate and the same shall be
available onsite for verification by the supervision team and also the same shall be attached with
corresponding T&C IRs.
All personnel should wear at all time safety shoes, Goggles, Helmet and Coverall.
All power tools are subject to inspection prior to bring at site, with attach update inspection
tag/sticker and color coding as per approved HSE Plan (Ref no. QPD-9-04-0007). Power tools
must be inspected by competent/certified person and attach inspection tag with color coding as per
approved HSE plan required.
Working Areas will be kept clean by disposing the waste materials at the designated areas. At the
end of days’ work, installation supervisor will ensure that the debris are disposed of.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 22 of 25
All scaffolding and ladders required for providing access to the workplace shall be erected and
inspected in accordance with the requirements. Prior to use scaffolding, must be visually checked
for any defects and be certified and tagged by scaffold inspector (approved by QATARENERGY).
Only approved and certified scaffold erector is authorized to erect and dismantle mobile
scaffolding.
19. DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action
Project Manager
Project Engineer
T&C Manager
Site Engineers / T&C Engineers
Safety Engineer
QA/QC Engineer /Inspector
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 23 of 25
The work shall be inspected in accordance to the inspection & testing plan and inspection
checklists. Results of inspection & testing shall be recorded on the inspection checklist forms.
22. ATTACHMENTS
Risk Assessment
Schematic Diagram (for reference)
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 24 of 25
Consequen
Risk rating
Likelihood
Consequence
Hazard Who or what
Likelihood
Sl. Description task
Rating
description might be Control measures
no. step/Activity
and effect harmed?
1 Area Preparation - Injuries due to Site workers, 3 2 6(Moderate) -Deploy only the inducted 3 1 3(Low)
malfunction foreman/engineer staff/workers/Operator/Driver at
with safety , patient, public site.
guards Testing/ -STARRT/ RAMS discussed to all
- Misuse due to commissioning workers prior to works
lack of team commencing.
competency. -Obtain infection control permit
-Dust. before construction begins.
-Damaged of -Isolate working area.
previous mat. -Complete all critical barriers or
-Slip, Trip & implement control cube
Fall method before construction
- COVID-19 begins.
pandemic - All personnel involved in T/C
mitigation activity shall be fully vaccinated
and shall present a green
“EHTERAZ”. Masks shall be
worn all the time and use of
sanitizer/soap to clean hands, as
per guidelines by MOPH.
-
2 Testing and commissioning of Slip, trip & fall, Site workers, 3 2 6 -Obtain infection control permit 3 1 3
Light Fixtures & controllers. Materials fall foreman/engineer (Moderate) before installation/removal of (Low)
from height, , patient, public existing services as per ICRA class
Floor damaged, IV.
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM
6 Work at height Fall from the Site workers, 3 3 9 -Obtain work at height PTW 3 1 3 (Low)
height workers foreman/engineer (Moderate) before start of work.
and materials, -Safe, secured and inspected work
Untrained platform shall be in place at work
personnel area.
engaging on -Ladders shall be provided for
work at height access and egress.
Unsafe work -All workers should have work at
platform height training and valid card.
Use damaged -Full body harness should be
harness. inspected and colour coded and
free from defect and damaged.
-Full body harness is a must use
while working at height.
-Supervisor should be all time
present for monitor the work.
-Provide exclusion zones with
suitable signs to prevent
unauthorized access.
-Objects should not be thrown
from the top
-Follow three (3) point contact
while ascending or descending the
ladder
-Install a suitable lifeline / railing
for the operatives for safe
anchorage of the safety harness.
-Suitable PPEs shall be used.
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM
7 Manual Handling Slip, Trip and Site workers, 4 2 8 -Ensure that workers and foreman 4 1 4 (Low)
Fall. foreman (Moderate) are internally trained for manual
Hand and leg handling.
injuries. -Use proper manual handling
Abrasion, process for storage and handling to
Fracture avoid falling on leg or back pain
Fall of and musculoskeletal disorder.
materials. -Barricade the formwork area and
Lifting of heavy prevent unauthorized entry if
component may falling or collapse possibilities.
cause back pain/ -Workers should follow proper
musculoskeletal manual handling methods.
disorders. -Minimise manual handling and
wherever possible use mechanical
means
8 Personal attire - Loose clothing Site workers, 4 2 8(Moderate) - Avoid loose clothing. 4 1 4(Low
may lead to foreman/engineer - Avoid wearing loose items and
traps -Jewelry or , patient, public rings, necklaces, bracelets, long
ornaments may chains and long hair.
be caught/
trapped to lead
injuries.
9 Electric tools -Electric shock Site workers, 4 3 12(High) -Extension cables shall be 4 1 4(Low)
-Punctures and foreman/engineer checked, and color coded
cuts due to , patient, public periodically by competent person,
damaged drill industrial sockets and extension
bits boards shall be used for extension.
Suitable ELCBs shall be fitted at a
distribution points.
-Standard drill bit shall be issued
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM
and used.
-To ensure that electrical
connection taken only from
approved DB.
10 Human concerns and site - Harm to Site workers, 3 3 9 -only competent person shall use 3 1 3 (Low)
discipline person and foreman/engineer (Moderate) the power tools.
property , patient, public - Proper and enough trainings shall
be provided to workers. -
Person who are using power tools
shall be given frequent intervals.
- Persons who are using the power
tools in open environment shall be
provided with energy supplements.
- Persons using the power tools
shall concentrate on the respective
job and avoid conversation and
breaks by keeping the machinery
in on condition.
- Person who temper, manipulate
the tools and safety guards and
violate the safe working
procedures shall be treated
seriously and disciplinary action
shall be taken.
11 Demobilization of manpower Slip, trip and Site workers, 3 2 6 -Wet mop with disinfectant. 3 1 3 (Low)
fall. foreman/engineer (Moderate) Remove barrier materials carefully
Poor , patient, public to minimize
housekeeping. spreading of dirt and debris
Poor posture, associated with
Musculoskeletal construction.
disorder. -Use appropriate PPE’s
-To ensure that all workers are
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM
5-9 Moderate Specific monitoring or procedures required, management responsibility must be specified.
Organization should consider what can be done to manage the risk & aspect to prevent any negative Outcomes.
1 -4 Low Manage through routine procedures. Organization can proceed with these activities as planned.
PH HT
QTY: 09 Nos. QTY: 09 Nos. QTY: 09 Nos. QTY: 09 Nos. QTY: 09 Nos.
T6
T9
TYPE - L 02F TYPE - L 02F TYPE - L 02F TYPE - L 02F TYPE - L 02F
QTY L 01W: 02 Nos. QTY L 01W: 02 Nos. QTY L 01W: 02 Nos. QTY L 01W: 02 Nos. QTY L 01W: 02 Nos.
QTY L 01F: 06 Nos. QTY L 01F: 06 Nos. QTY L 01F: 06 Nos. QTY: 08 Nos. QTY L 01F: 06 Nos. QTY: 08 Nos. QTY L 01F: 06 Nos. QTY: 08 Nos.
LEGEND T7
T8
TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F
SYMBOL SYMBOL
CODE (SCHEMATIC) (LAYOUT) DESCRIPTION T5
QTY: 07 Nos. QTY: 07 Nos.
T1
TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F
L01F T4
PK T2
T3
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F
L01W
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F
L02F
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F
L02W
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F
POWER CABLE POWER CABLE POWER CABLE POWER CABLE POWER CABLE L09W
(5 POLES) (5 POLES) (5 POLES) (5 POLES) (5 POLES)
FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP
(REF: (REF: (REF: (REF: (REF:
M030580) M030580) M030580) M030580) M030580)
Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE
(REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE LCP
FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB
(DB.T1.16.02/Y1) (DB.T1.16.02/B1) (DB.T1.16.02/R1) (DB.T2.19.02/R12) (DB.T2.19.02/Y12) (DB.T2.19.02/B12) (DB.T3.22.02/B1) (DB.T3.22.02/R1) (DB.T3.22.02/Y1) (DB.T4.25.02/B1) (DB.T4.25.02/Y1) (DB.T4.25.02/R1) (DB.T5.28.02/B1) (DB.T5.28.02/Y2) (DB.T5.28.02/Y1) IPR IPR
3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F
(REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154)
RS232 RS232
3x1.5 MM² H07RN-F (REF: M030154)
BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224)
Elect.: Code 02
To comply with rev-0 comments.
6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 Endorsement to be provided by the specialist. 15.05.2022
DMX DMX DMX DMX DMX
AMPLIFIER AMPLIFIER AMPLIFIER AMPLIFIER AMPLIFIER
6 - OUTPUTS 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM
(MODEL: 3091211) DB.T2.19.01/R7
(MODEL: 3091211) (T2-19-01)
DB.T3.22.02/B12
(MODEL: 3091211) (T3-22-01)
DB.T4.25.02/B12
(MODEL: 3091211) (T4-25-01)
DB.T5.28.02/B9
(MODEL: 3091211) (T5-28-04)
DB.T1.16.01/B4 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
13A UNSPUR OUTLET OUTLET OUTLET OUTLET
240V 240V 240V 240V 240V
OUTLET
BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224)
LON CABLE LON CABLE LON CABLE LON CABLE LON CABLE
BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP)
T1.16.01 LCP.T1.16.02.1 LCP.T1.16.02.2 LCP.T1.16.02.3 T2.19.01 LCP.T2.19.02.1 LCP.T2.19.02.2 LCP.T2.19.02.3 T3.22.01 LCP.T3.22.02.1 LCP.T3.22.02.2 LCP.T3.22.02.3 T4.25.01 LCP.T4.25.02.1 LCP.T4.25.02.2 LCP.T4.25.02.3 T5.28.01 LCP.T5.28.02.1 LCP.T5.28.02.2 LCP.T5.28.02.3
240V 240V 240V 240V 240V
IPR RS232 DB.T1.16.01/B4 IPR RS232 DB.T2.19.01/R7 IPR RS232 DB.T3.22.02/B12 IPR RS232 DB.T4.25.02/B12 IPR RS232 DB.T5.28.02/B9
IP ROUTER AT IP ROUTER AT IP ROUTER AT IP ROUTER AT IP ROUTER AT
EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm:
TELECOM ROOM T1-16-03 T1-16-03 T1-16-03 TELECOM ROOM T2-19-01 T2-19-01 T2-19-01 TELECOM ROOM T3-22-01 T3-22-01 T3-22-01 TELECOM ROOM T4-25-01 T4-25-01 T4-25-01 TELECOM ROOM T5-28-04 T5-28-04 T5-28-04
T1-16-05
RS 232 CABLE T2-19-06 RS 232 CABLE T3-22-07 RS 232 CABLE T4-25-06 RS 232 CABLE T5-28-06 RS 232 CABLE
DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4
DB.T1.16.01/B4
(MODEL: 7150612/C02) (T1-16-03)
DB.T2.19.01/R7
(MODEL: 7150612/C02) (T2-19-01)
DB.T3.22.02/B12
(MODEL: 7150612/C02) (T3-22-01)
DB.T4.25.02/B12
(MODEL: 7150612/C02) (T4-25-01)
DB.T5.28.02/B9
(MODEL: 7150612/C02) (T5-28-04)
13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V
QTY: 15 Nos.
TYPE - L 01F TYPE - L 01F TYPE - L 02F
QTY L 02W: 02 Nos.
QTY: 09 Nos. QTY L 02F: 07 Nos.
TYPE - L 08
TYPE - L 02F TYPE - L 01F TYPE - L 02F TYPE - L 01F TYPE - L 02F
QTY L 01W: 02 Nos.
QTY L 01F: 06 Nos. QTY: 08 Nos. QTY: 08 Nos.
TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F
QTY L 02W: 02 Nos.
QTY: 07 Nos. QTY: 07 Nos. QTY: 07 Nos. QTY L 02F: 05 Nos.
TYPE - L 08
TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F
QTY: 16 Nos.
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 08 TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 08 TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F
QTY: 03 Nos.
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F TYPE - L 02F
EXTENSION
CABLE (5
POLES)
TYPICAL
(REF:
M030584)
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 08 TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 02F TYPE - L 02F
POWER CABLE POWER CABLE POWER CABLE POWER CABLE POWER CABLE
(5 POLES) (5 POLES) (5 POLES) (5 POLES) (5 POLES)
FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP
(REF: (REF: (REF: (REF: (REF:
M030580) M030580) M030580) M030580) M030580)
Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE
(REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE
FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB
(DB.T6.31.01/R10) (DB.T6.31.01/Y10) (DB.T6.31.01/B10) (DB.T7.46.01/Y8) (DB.T7.46.01/B8) (DB.T7.46.01/Y4) (DB.T7.46.01/B7) (DB.T7.46.01/B3) (DB.T8.29.01/B10) (DB.T8.29.01/Y10) (DB.T8.29.01/R10) (DB.T9.26.01/Y5) (DB.T9.26.01/R5) (DB.T9.26.01/B4) (DB.HT.25.02/B12) (DB.HT.25.02/Y12)
3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F
(REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154)
AEB HEADQUARTERS:
BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable P.O. Box 1148 Doha, Qatar Tel +974 406 88 88 Fax +974 447 78 68
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) Email aeb@aeb-qatar.com Web www.aeb-qatar.com
OTHER BRANCHES:
MUSCAT * KUALA LUMPUR * MANILA
6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1
DB.T6.31.01/R9
(MODEL: 3091211) (T6-31-01)
DB.T7.46.01/R8
(MODEL: 3091211) (T7-46-06)
DB.T8.29.01/B6
(MODEL: 3091211) (T8-29-03)
DB.T9.26.01/R10
(MODEL: 3091211) (T9-26-02)
DB.HT.25.02/R12
(MODEL: 3091211) (HT-25-04)
13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V
BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224)
LON CABLE LON CABLE LON CABLE LON CABLE LON CABLE
BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP)
T6.31.01 LCP.T6.31.02.1 LCP.T6.31.02.2 LCP.T6.31.02.3 LCP.T6.31.02.4 T7.46.01 LCP.T7.46.01.1 T8.29.01 LCP.T8.29.01.1 LCP.T8.29.02.1 LCP.T8.29.02.2 LCP.T8.29.02.3 T9.26.01 LCP.T9.26.02.1 LCP.T9.26.02.2 LCP.T9.26.02.3 HT.25.01 LCP.HT.25.01 LCP.HT.25.02.01 LCP.HT.25.02.02 LCP.HT.25.E01
240V 240V 240V 240V 240V
IPR RS232 DB.T6.31.01/R9 IPR RS232 DB.T7.46.01/R8 IPR RS232 DB.T8.29.01/B6 IPR RS232 DB.T9.26.01/R10 IPR RS232 DB.HT.25.02/R12
IP ROUTER AT EL Rm: EL Rm: EL Rm: EL Rm: IP ROUTER AT EL Rm: IP ROUTER AT EL Rm: EL Rm: EL Rm: EL Rm: IP ROUTER AT EL Rm: EL Rm: EL Rm: IP ROUTER AT EL Rm: EL Rm: EL Rm: EL Rm:
TELECOM ROOM T6-31-01 T6-31-01 T6-31-01 T6-31-01 TELECOM ROOM T7-46-06 TELECOM ROOM T8-29-03 T8-29-03 T8-29-03 T8-29-03 TELECOM ROOM T9-26-02 T9-26-02 T9-26-02 TELECOM ROOM HT-25-04 HT-25-04 HT-25-04 HT-25-04
T6-31-04 RS 232 CABLE T7-46-03
RS 232 CABLE T8-29-01
RS 232 CABLE T9-26-07
RS 232 CABLE HT-25-01
RS 232 CABLE
DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4
DB.T6.31.01/R9
(MODEL: 7150612/C02) (T6-31-01)
DB.T7.46.01/R8
(MODEL: 7150612/C02) (T7-46-06)
DB.T8.29.01/B6
(MODEL: 7150612/C02) (T8-29-03)
DB.T9.26.01/R10
(MODEL: 7150612/C02) (T9-26-02)
DB.HT.25.02/R12
(MODEL: 7150612/C02) (HT-25-04)
13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V