You are on page 1of 41

Project Name : FIT OUT FOR PODIUM AT QATAR PETROLEUM DISTRICT

Package No. : 2 Contract No. : GC18108100


Contractor Prj. No. : MJ-175 Form No. : P07-F14/ Rev. 0/ Jul. 2018
Client: Consultant: Contractor:

DOCUMENT SUBMITTAL FORM


Submittal Type : Submittal No. : QPD-9-E19-0041 Rev.: 1
- Technical Submittals - Procedures - Calculation Submittal Date : 29-Oct-22
- PQP / ITP - PQD - Others Expected Response Date : 5-Nov-22
- Test Reports - Method Statement No. of Sets:

- Design Data - Schedule / Reports a.) Hardcopy 0 Size: A4


- Certificates - HSE b.) E-copy PDF Type:
Discipline:
- Civil / Structural - Mechanical - Electrical - Architect - Others
Description of Documents:
METHOD STATEMENT FOR TESTING AND COMMISSIONING OF CROWN LIGHTING SYSTEM

(For code-2 to code-10 approval)

Submitted for :

- IFC : Issued for comment - IFA : Issued for Approval - IFI : Issued For Information - RET : Issued For Retention

- CAN : Issued For Cancellation


Prepared by: Reviewed by: (Contractors Proj. Coordinator or QA/QC) Recommended for Submission by: (Contractors PM)

Mirza Hassan Premkumar D


Name / Sign / Date Name / Sign / Date Name / Sign / Date

USE COMMENT SHEET (P07-F64)


Submittal Status :
10 - Approved (Resubmission not required) 3 - Not Approved (Incorporate comments and resubmit - work
shall not proceed)
1 - Approved without Comments (Resubmission required -
work may proceed) 6 - For Information Only
2 - Approved with Comments (Incorporate comments and 11 - Cancellation Accepted
resubmit - work may proceed subject to incorporation of comments)

Reviewed by: Approved by: Client Rep. Endorsement (when required):

Name / Signature Name / Signature Name / Signature

AEB Discipline Lead AEB - PM/APM/QM/PL


Designation Date Designation Date Designation Date

Note : Approval or comments made to this submittal does not relieve the Contractor from their responsibilities. The assessment is to review the general conformance and compliance of the submittals to the contract and
specification requirements.

MG TN #21014
Document Submittal Form AEB - Quality Forms 1 of 1 Form No.: P07-F14 / Rev. 0 / Jul. 2018
Project Name : FIT OUT FOR PODIUM AT QATAR PETROLEUM DISTRICT
Package No. : 2 Contract No. : GC18108100
Contractor Prj. No. : MJ-175 Form No. : P07-F14/ Rev. 0/ Jul. 2018
Client: Consultant: Contractor:

DOCUMENT SUBMITTAL FORM


Submittal Type : Submittal No. : QPD-9-E19-0041 Rev.: 0
- Technical Submittals - Procedures - Calculation Submittal Date :02/08/2022
- PQP / ITP - PQD - Others Expected Response Date : 14/08/2022
- Test Reports - Method Statement No. of Sets:

- Design Data - Schedule / Reports a.) Hardcopy 0 Size: A4


- Certificates - HSE b.) E-copy PDF Type:
Discipline:
- Civil / Structural - Mechanical - Electrical - Architect - Others
Description of Documents:
METHOD STATEMENT FOR TESTING AND COMMISSIONING OF CROWN LIGHTING SYSTEM

Submitted for :

- IFC : Issued for comment - IFA : Issued for Approval - IFI : Issued For Information - RET : Issued For Retention

- CAN : Issued For Cancellation


Prepared by: Reviewed by: (Contractors Proj. Coordinator or QA/QC) Recommended for Submission by: (Contractors PM)

Mirza Hassan Premkumar D


Name / Sign / Date Name / Sign / Date Name / Sign / Date

USE COMMENT SHEET (P07-F64)


Submittal Status :
10 - Approved (Resubmission not required) 3 - Not Approved (Incorporate comments and resubmit - work
shall not proceed)
1 - Approved without Comments (Resubmission required -
work may proceed) 6 - For Information Only
2 - Approved with Comments (Incorporate comments and 11 - Cancellation Accepted
resubmit - work may proceed subject to incorporation of comments)

Reviewed by: Approved by: Client Rep. Endorsement (when required):

Name / Signature Name / Signature Name / Signature

AEB Discipline Lead AEB - PM/APM/QM/PL


Designation Date Designation Date Designation Date

Note : Approval or comments made to this submittal does not relieve the Contractor from their responsibilities. The assessment is to review the general conformance and compliance of the submittals to the contract and
specification requirements.

MG TN #21014
Document Submittal Form AEB - Quality Forms 1 of 1 Form No.: P07-F14 / Rev. 0 / Jul. 2018
Project Name: Fit Out for Podium at QPD

Package No.: Package 3

Contract No.: GC18108100

COMMENT DISPOSITION FORM (CDF)


Qatar Petroleum District - METHOD STATEMENT FOR TESTING AND
Title: Reviewing Dept.: Arab Engineering Bureau (QRC)
COMMISSIONING OF CROWN LIGHTING SYSTEM
Doc. No.: QPD-9-E19-0041 Rev.: 0 Disposition Dept.: Medgulf Construction Company W.L.L.
Review Date: 17/10/2022 Disposition Date: 29/10/2022
Status 10,2,3,
S. No. Comments Dispositions (Contractor) Status/Remarks
6, 1 and 11.

Elec:
1. 2
Provide name and contact details of each designated NOTED & COMPLIED; please refer Section-
responsible persons. 10.1, Page# 19.

HSE: section 2: HSE objective is missing. Method The document structure is laid with reference
statements are document that detail exactly how to carry to previously approved (code-10) templates
out work safely. which do not have “HSE Objective” but the
Contractor to incorporate the HSE objective. whole document (including Risk Assessment)
is drawn considering the same and in
compliance with HSE Plan. However, since
2. 2 only now this ‘new’ section is been requested,
it is incorporated for this document and all
future new submissions (if any). Hence -

NOTED & COMPLIED; please refer Section-


2.1, Page# 3.

Document Reference: QPD-9-K19-0021 Rev. 0 Page 1 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD

Package No.: Package 2

Contract No.: GC18108100

HSE section 3: Contractor need to incorporate


following references :
QatarEnergy lifesaving rules, NOTED & COMPLIED; please refer
3. 2
Workers welfare standards edition-2, Section-3, Page# 3.
Labour Laws,
Worker Rights Booklet 2009,
HSE section 5.3 : Contractor to ensure
NOTED & COMPLIED; please refer
4. 2 electrician/operatives should wear the electric shock
Section-5.3, Page# 6.
proof gloves during any live testing & commission work.

Document Reference: QPD-9-K19-0041 Rev. 0 Page 2 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD

Package No.: Package 2

Contract No.: GC18108100

HSE Section 5.6: Contractor to incorporate below point


in sequence at the action in the event of fire.
 Raise the manual siren alarm by activating.
 Inform to the Immediate supervisor.
 The type/nature of fire (e.g., Electrical, paper,
wood, fuel).
 Other Information-Company name, the location
where incident occurred and your name and
contact Number.
 Only try to fight the fire if you feel it is safe to
do so.
NOTED & COMPLIED; please refer
5. 2  Evacuation should be prompt and calm, with
Section-5.6, Page# 7.
everyone making their way to the designated
assembly point.
 Do not stop to collect your personal belongings.
 Do not use lift. Go down by nearest staircase.
 Close the door behind you.
 Get to the Assembly Point.
 Await further instructions. A roll call shall be
taken to ensure all workers are present.
 Work Activity shall resume only after obtaining
permission from AEB, MCFM and QE and
revalidation of Permit.
HSE Section 5.6: Scaffolding supervisor is not
authorized to inspect the scaffolding. Scaffolding NOTED & COMPLIED; please refer
6. 2
inspection should be done by authorized third party Section-5.7, Page# 8.
trained scaffolding inspector.

Document Reference: QPD-9-K19-0041 Rev. 0 Page 3 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD

Package No.: Package 2

Contract No.: GC18108100

HSE : Since the client brand name has changed. So,


NOTED & COMPLIED; logo replaced
7. 2 contractor to replace the QP name with new brand
where applicable.
name as QatarEnergy in whole documents.
HSE Section 5.7: Lifting equipment third party
NOTED & COMPLIED; point removed as
8. 2 certificate for what purpose. if it is not required then
it is not applicable for this MS.
Irrelevant thing should be remove from MS.
HSE section 5.7: Contractor to add electric gloves in NOTED & COMPLIED; please refer
9. 2
task related PPE. Section-5.7, Page# 9.
HSE section 6: Contractor to incorporate the HSE NOTED & COMPLIED; please refer
10. 2
manager responsibilities. Section-6, Page# 9.
HSE HIRA: Contractor to incorporate the Covid-19 NOTED & COMPLIED; please refer
11. 2 hazard and precautions in HIRA. Section 22, Risk Assessment, Sl.no. 1 as
updated by MG HSE Manager.
QAQC: Contractor to submit testing and commissioning ITP,
NOTED & COMPLIED; T&C ITP already
12. 6 Checklist & sample reports for review and approval prior to
code-10 (Doc. Ref.# QPD-9-E25-0031-1).
commence the work.
QAQC: Section.6 NOTED & COMPLIED; please refer
13. 2 Include QAQC Manager roles and responsibilities. Section-6, Page# 10.
QAQC: Contractor to ensure & Include prior to Testing and NOTED & ALREADY COMPLIED; please
14. 2 commissioning all MCC/Punch list comments shall be cleared refer Section-7.1, Page# 11 and Section-
and accepted by QP/QRC. 7.2, Page# 11 & 12.

Iftekhar Antuley – HSE inspector, QRC


Reviewer Name: Rameez Saifullah-DLE-QRC Signature: Date: 15/10/2022

Shibu Georgev – PM, QRC


Approver Name: Signature: Date: Select date.
Jett Irish De Guzman – APM / Coordinator, QRC

Document Reference: QPD-9-K19-0041 Rev. 0 Page 4 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD

Package No.: Package 2

Contract No.: GC18108100

Dispositioner Name: Contractor Representative Signature: Date: 29/10/2022

Document Status: 10 = Approved 2 = Approved with Comments (Incorporate comments 3 = Not Approved (Incorporate comments and
(Resubmission not and resubmit - work may proceed subject to resubmit - work shall not proceed)
required) incorporation of comments)
6 = For Information 1 = Approved without Comments (Resubmission 11 = Cancellation Accepted
Only required - work may proceed)

Note 1: A unique CDF serial number will be allocated with document initial submission; subsequent revisions will be reflected in CDF revisions (applicable at least by QRC and QP)
Note 2: Originator - QP/ QRC
Note 3: Please encode separate number for each CDF in the footer with revision number

Document Reference: QPD-9-K19-0041 Rev. 0 Page 5 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
CONTRACT REF.: GC18108100

CONTRACT TITLE: - FIT OUT FOR PODIUM AT QPD

DOCUMENT TITLE :
METHOD STATEMENT FOR TESTING AND COMMISSIONING OF
CROWN LIGHTING SYSTEM

QRC:
CONTRACTOR :

ARAB ENGINEERING BUREAU


MEDGULF CONSTRUCTION COMPANY WLL
PO Box 1148, DOHA QATAR
PO Box 3603, Al Manara Tower, 1st Floor
Office: 44068888 / Fax: 44477868
Office: 44463000 / Fax: 44433586
www.aeb-qatar.com
www.medgulfconstruction.com

29/10/2022 1 Issued For Final Approval AT HS PD

02/08/2022 0 Issued For Comments AT HS PD


Date Rev Description Prepared Checked Approved Appd. Q.P.

Document No. QPD-9-E19-0041 Page: 1 of 23


Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 2 of 25

Contents
1. PURPOSE: ............................................................................................................................................. 3
2. SCOPE& OBJECTIVE ........................................................................................................................... 3
3. REFERENCES ....................................................................................................................................... 3
4. ABBREVIATIONS .................................................................................................................................. 4
5. HEALTH & SAFETY HAZARDS: ........................................................................................................... 5
6. RESPONSIBILITY ................................................................................................................................. 9
7. PROCEDURE / METHOD TO BE EMPLOYED .................................................................................. 11
7.1 Pre-Commissioning: ................................................................................................................ 11
7.2 Commissioning: ....................................................................................................................... 11
7.3 Third Party Interface Testing (SIT - System Integration/ Interface Test):........................... 15
7.4 SITE ACCEPTANCE / OPERATIONAL & PERFORMANCE TEST (SAT) .............................. 16
7.5 Witness Demonstrations/ Completion ................................................................................... 16
8. WORK PERMIT ................................................................................................................................... 19
9. WORKING HOURS .............................................................................................................................. 19
10. MANPOWER ........................................................................................................................................ 19
11. LOGISTICS .......................................................................................................................................... 21
12. MATERIAL REQUIREMENT ............................................................................................................... 21
13. PLANT & EQUIPMENT REQUIREMENT ............................................................................................ 21
14. COLOR CODING ................................................................................................................................. 21
15. HOUSE KEEPING................................................................................................................................ 21
16. SCAFFOLDING (where necessary) ................................................................................................... 22
17. QC APPROVAL AND OTHER DOCUMENTARY REQUIREMENTS ................................................. 22
18. SUPPORTING DOCUMENT ................................................................................................................ 22
19. DISTRIBUTION .................................................................................................................................... 22
20. OTHER INFORMATION ...................................................................................................................... 23
21. MAIN CONTRACTORS SAFETY ENGINEERS APPROVAL ............................................................. 23
22. ATTACHMENTS .................................................................................................................................. 23
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 3 of 25

1. PURPOSE:
This Method Statement covers the Testing and Commissioning procedure of the Crown Lighting
within the QPD Project (roof levels of Tower 1 to 9 and Tower 10) to insure proper operation of all
components of the systems and their compliance with project requirements & specifications.

2. SCOPE& OBJECTIVE
This Method Statement is applicable for Testing & Commissioning of Crown Lighting System
(CLS) in Fit Out works for Package 2 at QPD Project (under Appendix-F, several modifications
Item# 7). The scope of this document is to provide the implementation of the commissioning
process regarding specific system being commissioned. Commissioning includes performance
testing to demonstrate that CLS and accessories meet the contract performance of the system
installation per manufacturer’s recommendation, industry accepted standard and project
specification.
2.1 HSE Objective:
The HSE objective is to deploy standard procedures in ensuring no harm befalls anyone
during the T&C of the system.

3. REFERENCES
 Contract Documents, Scope of Work Appendix F Several modifications, Item# 7, Package 2
Electrical specification (QPD-9-A14-2000)
 QATARENERGY safety Regulations QP-REG-S-001, Corporate Quality Standards QP-REG-Q-
003 & QP-STD-Q-004
 QatarEnergy lifesaving rules; QATARENERGY Code of Practice for Life Saving rules (NEW)
(QP-SOF-COP-21)
 Workers welfare standards edition-2
 Labour Laws; Qatar Law No.14 of the Year 2004 – The Labor Law, and the ministerial decisions
issued (No.14 of 2004, and its amendment)
 Worker Rights Booklet 2009
 Approved For Construction (AFC) Drawings
 Approved Shop Drawing
 Approved Material Submittal for lighting type- L01F, L01W, L02F, L02W, L03F, L03W (roof light)
(QPD-9-MAR-E-0444-2)
 Specialist Contractor for Commissioning of the system (Pre-Qualification for Techno-Q Light
Fitting Supplier) – Prequalification Document (QPD-9-PQD-E-0134-1)
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 4 of 25

 Manufacturer's Standard installation and testing recommendations


 Kahramaa regulations 2016 - Electrical Wiring Regulation
 Qatar Construction Specification 2014
 OHSAS 18001:2007and ISO 14001:2004.
 Approved Project HSE Plan (Ref no. QPD-9-04-0007-11)
 Approved Emergency Response & Disaster plan (Ref no. QPD-9-04-0003-5)
 Approved Project Quality Plan (Ref no. QPD-9-04-0006-2)
 Prequalification for Third Party Testing & Commissioning (GST) (Ref no. QPD-9-PQD-MG-0072-
 Testing and Commissioning plan (Ref no. QPD-9-04-0016-2)
 Method Statement for Installation of Crown Lighting System (Ref. no.: QPD-9-E19-0047-0)
 Method Statement for the Pre Commissioning and Commissioning of Lighting control system.
(Package 2) (ref.no.: QPD-9-E19-0035-1)
 Inspection and Test Plan for Testing and Commissioning of Crown Lighting System (Ref. no.:
QPD-9-E25-0031-1)
 Document Transmittals - Approved for Construction drawings
 Technical Submittal for Crown Lighting Report (ref. no.: QPD-9-TS-E-0007-0)

Note: Revision reference numbers of the above mentioned documents are subject to frequent
change (resubmission), and hence latest revision shall be cross checked from the document
register.

4. ABBREVIATIONS
AEB Arab Engineering Bureau
AFC Approved for Construction
FM Facility Management
MG Medgulf (Main Contractor)
Client QatarEnergy
Supplier/ Vendor Gulf Lights
Specialist Subcontractor for Commissioning Techno-Q

HSE Health Safety & Environment


HIRA Hazard Identification and Risk
Assessment
SIMOPs Simultaneous operations
IR Inspection Request
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 5 of 25

RPL Request for Punch List


PRC Pre-Commissioning
MCC Mechanical Completion Certificate
COM Commissioning (Cx)
FT Functional Test
SIT System Integration/ Interface Test
SAT Site Acceptance (Operational &
Performance) Test
T&C Testing & Commissioning
MS Method Statement
PPE Personal Protective Equipment
QA/QC Quality Assurance / Quality Control
Client QatarEnergy
KM KAHRAMAA
QPD Qatar Petroleum District
QRC Qatar Registered Consultant
ITP Inspection and Test Plan
RA Risk Assessment
RAMS Risk Assessment Method Statement
LOTO Lock-out/Tag-out
TBT Tool Box Talk
SD Shop drawing
ICD Interface Control Document
CLS Crown Lighting System
LCS Lighting Control System
TP Third Party

5. HEALTH & SAFETY HAZARDS:

5.1 HEALTH AND SAFETY KNOWLEDGE DISSEMINATION

 HSE Site Safety Inductions


Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 6 of 25

 Pre-task briefing, Toolbox talk (TBT) and Risk assessment matrix (RAMS) to be briefed /
communicated to the workforce prior to commencement of the activity
 Safety toolbox talks
 Environmental toolbox talks
 HSE training records / Toolbox attendance register
 Internal Safety Awareness courses
 HSE Bulletin / HSE Site Notice Boards
 HSE Personnel site instructions
 Site Engineers, Site Supervisors and Site Foreman will ensure safe work method is adopted.
 Emergency Procedure: All running machines shall be switched off before leaving the site.

5.2 Work Pre-Commencement Mandatory HSE Activity

 To obtain necessary PTW (Permit to Work), prior to commence activity.


 Appropriate trainings should be conducted by site Supervisor/Foreman. Daily activities
briefing to be conducted prior to start work.
 Discuss RA with work crew.
 Carry out toolbox talks before start of each working day or new task Ensure only trained /
certified personnel are assigned on the job
 Pre-task briefing, TBT and RAMS to be briefed / communicated to workforce prior to
commencement of the activity

5.3 Mandatory PPE

All project personnel, subcontractors and visitors shall be required to wear as a minimum the
following PPE:
 Safety boots (with steel toecaps and insoles)
 Safety helmets
 Eye protection
 Ear plugs / Earmuff
 High visibility vest
 Full body harness as per QATARENERGY standard (for height more than 1.8m)

Compulsory PPE for labour in addition to the above:

 Gloves; electrician/operatives should wear the electric shock proof gloves during any live
testing & commission works
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 7 of 25

 Face Masks
 Ear defenders, if working near to the equipment.

5.4 Emergency Procedure

Client / Consultants-approved Site Emergency Procedure shall be followed by the contractor


during the execution of this work.

5.5 Pre-Emergency Planning and Awareness

 Emergency procedures to be communicated to all assigned employees for this scope of work
before commencement of activity.
 All communications to be documented and made available for the client whenever requested
 Copies of emergency procedure to be kept at site for and available for reference at any point
during the work

5.6 Actions in the Event of a Fire

• Raise the manual siren alarm by activating.

• Inform to the immediate supervisor.

• Report the type/nature of fire (e.g., Electrical, paper, wood, fuel).

• Report other Information-Company name, the location where incident occurred and your
name and contact Number.

• Only try to fight the fire if you feel it is safe to do so.

• Evacuation should be prompt and calm, with everyone making their way to the designated
assembly point.

• Do not stop to collect your personal belongings.

• Do not use lift; Go down by nearest staircase

• Close the door behind you.

• Get to the Assembly Point.

• Await further instructions. A roll call shall be taken to ensure all workers are present.

• Work Activity shall resume only after obtaining permission from AEB, MCFM and QE and
revalidation of Permit.

Follow the client / consultants approved Fire Emergency Procedure and Fire Drills Steps
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 8 of 25

5.7 General Safety Guidelines

 Ensure only trained / certified personnel are assigned on the job


 Scaffold to be used must be tagged and inspected by an authorized third party trained
scaffolding inspector prior to usage.
 Ensure LOTO procedure is observed before conducting the multi meter test on the
equipment and to obtain necessary permit as required.
 Make sure all employees are Safety Inducted before they can work on site.
 Nominated competent manpower shall be required a mandatory competent training such as
electrician, scaffolder installer and inspector, working at heights operatives etc. QatarEnergy
approved 3rd party certifications shall be submitted and secure approval.
 Make sure employees take the right equipment with them on visits. Check they have been
trained and know how to use it.
 Keep available, records of hazards on particular sites. Make sure all relevant people are
notified.
 Make sure a supply of the right equipment is available.
 Helmets, Safety boots, Safety goggles, High visibility vests, face masks, overalls should be
appropriate and in good condition.
 Consider the risks of manual handling before going to the site and look at the materials being
used or stored.
 Adequate Illumination shall be set up at the work area and ensure the required Lux available
as per QCS 2014 during night shift, and at the dark areas required during daytime.
 Ensure Ventilation system shall be provided capable of maintaining an acceptable quality of
air inside the buildings.
 Ensure strict implementation of housekeeping, shall be improved during the course of the
activity. Any materials stacked in the site shall neither obstruct the emergency evacuation
route nor the access to the FE’s and hose reel.
 Trained, Competent and authorized Supervision present always to ensure workers are
performing their duties safely.

Required Personal Protective Equipment for the Tasks

Task related PPE for specific activities:

 Safety boots
 Safety Helmet
 High Visibility Vest
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 9 of 25

 Safety Gloves
 Electric shock proof gloves (while working on live during T&C)
 Safety Glasses
 Ear Plugs
 Dust Mask
 Full Body Harness

6. RESPONSIBILITY
 Project Manager- is overall responsible for the successful initiation, planning, execution,
monitoring, controlling and closure of a project as per the approved schedule and contractual
requirements and make sure they control risk and minimize uncertainty. Also, he will
maintain the planning progress and coordination of works with Main Contractor.
 Testing & Commissioning manager (MG) - is the overall responsible for the
implementation of this procedure and ensure that the team of Engineers, and other related
staff are aware of this procedure , all resources , manpower; material and equipment are
available to carry out the testing and Commissioning as planned, without any delay. And
implement the Lock -out / Tag-Out procedure when required.
To ensure that all commissioning activities are carried out in liaison with supplier / vendor to
the satisfaction of QRC/ QatarEnergy.
Raising non-conformance or corrective action and adhere to safety procedure.
Carry out a punch list walk down and liquidate punch list items as required.
 HSE Manager- will report to Medgulf Project Manager and will be responsible for: -
o Provide guidelines to the Construction Department (team involved for T&C) on safety
related matters.
o Ensure the development and implementation at site SAFETY related activities; assist the
management in all SAFETY related matters and manages the SAFETY Organization at
site.
o Ensure that the SAFETY Plan/Procedures are distributed to all concerned and supplying
the necessary information.
o Managing the incident/accident investigation as per procedure and maintaining records of
the site Safety Statistics.
o Issuing SAFETY meetings programme and organizing meetings. Ensure the teams are
briefed prior to start activities mentioned in this document and the related risks and
necessary mitigations are in place.
o Managing First-Aid and health care organization and facilities at site.
o Liaise with Project Manager and Const. Manager for implementation of SAFETY
Plan/Procedures etc.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 10 of 25

o Ensure that the Project SAFETY objectives are met through implementation of
Procedures and technical activities.
 Commissioning Engineer - To ensure that all commissioning activities are carried out in
liaison with system specialist to the satisfaction of MG / AEB-QRC/ QATARENERGY. Raising
non-conformance or corrective action and adhere to safety procedure. Carry out a punch list
walk down and liquidate punch list items as required
 Project Engineer/ Site Engineer- is responsible for the day to day activities on site, for
materials, approved drawings, approved method statement, testing & commissioning and
allocation of departmental resources to work areas on Site. He is also responsible to ensure
adequate equipment for shifting of materials and other related works are in place prior to the
starting of work. The Project Engineer will report to the Project Manager.
 Supervisor / Foreman – will be directly responsible for the day-to-day works on site as per
instructions of the Project Engineer / Site Engineer and provide proper documentation to his
workers so they can proceed with tasks and handling the technicians, or any other staff
assign to his area.
 QA/QC Manager – Manage and control quality inspection activities, ensuring that all
inspection and testing efficiently executed in accordance with standard specifications,
approved engineering drawings and ITPs; ensures results data/records are properly
documented and maintained.
 QA/QC Engineer – will oversee all the quality requirements and quality control measures for
the Project in coordination with the Project Engineer as outlined in the Approved Project
Quality Plan
 QA/QC Inspector - will check the quality requirements and quality control measures for the
Project in coordination with the QA/QC Engineer as outlined in the Approved Project Quality
Plan
 Safety Officer – will be responsible for the Health and Safety aspects on site as per the
Mains Contractor Safety requirements.
 Specialist (Techno-Q) Project/ Cx Manager – coordinates with the Contractor and
manages the testing procedure at site.
 Specialist (Techno-Q) Project Engineer/ Commissioning Engineer - is responsible for
pre-commissioning, testing and commissioning.
 AEB-QRC/ QE Representative - Advise punch list items. Witness of testing & verification
carried out during commissioning.
 Third Party (GST) – will be witnessing the Testing & Commissioning activity. GST being
qualified and experienced independent testing and commissioning third party, hired by MG
shall be witnessing & reporting of the testing and commissioning activities.
Refer Prequalification for Third Party Testing & Commissioning (GST), Doc.ref. no. QPD-9-
PQD-MG-0072
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 11 of 25

7. PROCEDURE / METHOD TO BE EMPLOYED

7.1 Pre-Commissioning:
Prior to beginning the commissioning activities, it shall be insured that:
 Check that all relevant QA/QC IRs are available, i.e., Installation of lights & modules, Cable
Testing and Panel termination IRs, as applicable.
 RPL/ Punch list Category A items are addressed, cleared, completed, corrected and
approved by QatarEnergy/QRC before starting the pre-commissioning activities.
 Inspect visually the external and internal, where applicable, parts of panels, controllers,
modules, devices, lighting fixtures, wiring, etc.
 Ensure all installation are complying to the approved, by QRC, technical and construction
submittals (MARs, MIRs, IRs, shop drawings, approved installation details, Schematic
diagram etc.) related to this activity
 Ensure and verify that tagging is applied as per approved tagging system in the project.
Ensure tagging materials as per approved submittals
 Ensure cables and wiring are installed, terminated and labelled safely with no defect.
Labelling shall be as per approved labelling system
 Ensure termination to final lighting fixtures shall be as per Kahramaa regulation, QCS
requirements, project specification, MIRs, IRs and shop drawings
 Check fixation for the light fitting is complete and the alignments are done properly.
 Ensure that the grounding/earthing of the lights are properly connected to the earthing
system.
 Ensure all warning labels and circuits tags are provided.
 All light fittings should be installed and powered UP.
 Console, all the light fitting and Stick D3 controller etc. should be powered ON with
240±6%VAC (and/ or rating as per the equipment name plate and approved schedules).

7.2 Commissioning:

 Pre-commissioning activity for fixtures and cable are completed and related inspection
requests are approved.
 All approved documents of Method Statement for Testing & Commissioning, ITP, Checklist,
and relevant approved drawings (schematic and layouts) shall be available for the test.
 After PRC and prior to Commissioning commencement, check that Mechanical Completion
Certificate (MCC) and Punch list details must be complied as per the T&C plan. MCC
approval from QRC/QatarEnergy must be obtained prior Commissioning activities.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 12 of 25

 Punch list Category A items are addressed, cleared, completed, corrected and approved by
QatarEnergy/QRC before starting the commissioning activities.

7.2.1 Programming the StickD3 controller

Addressing of the light fixture:

The MCI light fixtures must be addressed using the addressing tool which is shown below.

MCI 7150203

The addressed fixtures should be patched in the ESA pro application which is used to configure
the Stick D3 controller. All the fixtures are patched in the universe 1, which can control 512
channels.

The patching of the fixtures in the application is shown below.

After the patching the fixtures are divided into three zones and the fixtures covering the zones are
grouped together in the ESA pro application.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 13 of 25

The zone mapping is shown below for your reference

The next step in the commissioning is the creating the Pre-set , these pre-set can be defined in
the ESAPRO application

The pre-set is defined as follows

FIXTURE
S.NO CONTROL FROM RGBW PERCENTAGE
CONSOLE
Zone 1 -Blue 100 %.
1 Preset 1 Zone 2 - Green-100 %,Blue 74 %,
Zone 3 -Blue 100 %.
Zone 1 -Blue 100 %, with the stimulation
effect
Zone 2 - Green-100 %,Blue 74 %,with the
2 Preset 2
stimulation effect
Zone 3 -Blue 100 %.with the stimulation
effect
Zone 1 - Red 80 %
3 Preset 3 Zone 2 - White 100 %
Zone 3 - Red 80 %
Zone 1 - OFF
4 Preset 4 Zone 2 - OFF
Zone 3 - OFF
Zone 1 - White- 100 %
5 Preset-5 Zone 2 - White 100 %
Zone 3 - White 100 %

The Images of the defined pre-set are mentioned below


Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 14 of 25

The programmed configuration is written in stick D3 controller with the help of USB interface cable .

The images of the write menu are shown for your reference.

Before writing the configuration, make sure that memory Sd card is installed in the Stick D3 controller, the
programmed database is stored in the SD memory card.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 15 of 25

7.3 Third Party Interface Testing (SIT - System Integration/ Interface Test):

 Ensure standalone/functional tests completed prior to the Interface/ Integration testing.

RS232 SERIAL INTERFACE PORT for Delmatic (LCS) Interface


 Make a cable using the 3 pins : TX, RX and G (GND) Set the RS232 parameters to :
9600bds 8 bits, no Parity, 2 Stop bits Messages should be hexadecimal not decimal (ie. 1 =
01, 255 = ff etc.) - To play a scene, send 4 bytes : 1 x y 255 - To stop a scene, send 4 bytes :
2 x y 255 - To pause a scene, send 4 bytes : 3 x y 255 - To release a pause, send 4 bytes : 4
x y 255 - To reset a scene, send 4 bytes : 5 x y 255 When (y)=0, (x) can be set between 0
and 255 -to stop scene 145, send the command: 2 145 0 255 When (y)=1, (x) can be set
between 0 and 243 to trigger scenes 256-499 -to play scene 300, send the command: 1 44 1
255

 Dry Contact Port Triggering


Network Control TCP Triggering - The controller works with the official IR remote control,
however there is no receiver. A 36 kHz infra-red receiver can be connected, such as the
TSOP34836 by Vishay Semiconductors. Farnell ref: 4913127. This can be attached to the 20
pin connector. It is a good idea to add a resistor and capacitor to suppress power supply
disturbance. A relay can be connected between the RELAY and GND sockets of the 20 pin
extension socket. This is an open drain output that allows current to flow only when the
controller is on. It can be used to turn off other equipment such as lighting drivers. Infra-Red
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 16 of 25

RS232 Triggering It is possible to start scenes using the input ports (contact closure)
included on the 2x10pin Extension Socket. To activate a port, a brief contact of at least 1/25
second must be established between the ports (1...8) and the ground (GND). Note: 1. A
scene must be assigned to a port in the software,
 The scene will not be switched off when the switch is released.

7.4 SITE ACCEPTANCE / OPERATIONAL & PERFORMANCE TEST (SAT)

1) Pre-requisite
Prior to start of Site Acceptance Test (SAT) activities, the following activities to be completed.
 Commissioning activities (Functional and Interface tests) has been successfully completed
and documented in relevant dossiers.
 Relevant training has been conducted.
 All relevant operational/ functional tests have been conducted.
2) SAT
SAT shall be performed for duration of 72 hours (3 days).

 Since operation of these lights at night timings but the controllers is operational 24/7, SAT
hours shall be considered observing the operation of the lights for 8 hours per 3 days
duration.

7.5 Witness Demonstrations/ Completion

 The commissioning results will be recorded on project agreed format and offered to
AEB/QatarEnergy for witnessing/acceptance.
 An Inspection Request attached with the PRC IR, test reports and later with the MCC will be
raised by MG to QRC, to enable co-ordination/sign off of Crown Lighting system testing with
the Client representatives.
 The client representative of the end user will be invited to witness the field testing. The
representative will select the points to be demonstrated and the results shall be stored in
accordance with the prescriptions.
 Witnessing the field testing will be as per QatarEnergy instruction in compliance with Project
Specification, T&C Plan, approved T&C MS and ITP.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 17 of 25
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 18 of 25
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 19 of 25

8. WORK PERMIT

Permit to Work (PTW) is required prior to start of any work activities within the project. MG PTW
procedures approved by AEB and QATARENERGY will be adopted for all internal works without
interference to FM services and ongoing client operations.

MG PTW Authorized Person shall be the only person who shall approve the Permit to Work
(PTW). If any activity that requires an interface is to be undertaken, a MCFM Permit to Work shall
be processed as required.

Reference shall be made to this Method statement and Risk assessment in the PTW. MSDS of all
Hazardous materials shall be attached with the PTW for ready reference.

9. WORKING HOURS

Site working hours shall be followed as instructed by Main Contractor site timings. Statutory
Regulations shall be strictly followed in summer for the working hours.

10. MANPOWER

Staff will consist of:


 Electrical Site Engineer
 Commissioning Engineer
 Electrical Supervisor / Foreman
 Safety Officer
 QA/QC Engineer
 QA/QC Inspector
 Certified Scaffold inspector and erector/dismantling

Labor force will consist of:


 Electricians
 Electrical Helper
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 20 of 25

10.1 Name & Contact Details of Key Personnel

Reference Name Organization Designation Contact Details

Manufacturer RAÚL Groupo MCI Telecommunications Phone: +34 660 55 44 32


ESCOBAR Engineering/
E-mail: raul.escobar@movistar.es
GARCÍA Programmer

Supplier SAIFUR Gulf Lights Project Manager Phone: +974-5520 0145


RAHMAN E-mail: saif@gulflights.com
T&C AZEEMUDDEN TechnoQ Support Engineer (T&C) Phone: +974-5514 5108
Supervision TAJUDDIN E-mail: Azeemudden@technoq.com
Interface PRAVEEN VAS Delmatic Project Engineer Phone: +974-7776 3270
Specialist E-mail: siteeng@delmaticarabia.ae
Main MIRZA ABDUL Medgulf Electrical Engineer Phone: +974-7073 6936
Contractor WAJID BAIG (Engg, Construction and E-mail:
T&C) mohamed.buhari@medgulfconstruction.
com
Main MOHAMED Medgulf MEP Construction Phone: +974-7049 8651
Contractor BUHARI Manager E-mail:
mirza.baig@medgulfconstruction.com
Main HASSAN Medgulf MEP Commissioning Phone: +974-3041 9046
Contractor SHAIK Manager E-mail:
hassan.ali@medgulfconstruction.com
NOTE: Refer corresponding Operation & Maintenance Manual for further details.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 21 of 25

11. LOGISTICS

Logistics will be carried out as per the Approved logistic plan.

12. MATERIAL REQUIREMENT

As per project specification, approved shop drawings and material submittals.

13. PLANT & EQUIPMENT REQUIREMENT

List of Test Equipment/ Tools required for Pre-Commissioning & Commissioning of LCS Systems
are as follows.
 Laptop – programmed with Software to commission, Check light Levels, Troubleshooting
 Screwdriver – for Termination.
 Digital Multi-Meter - Check continuity, measure voltage.
 Lux meter – Check lux levels

NOTE: Ensure all instruments having latest and valid calibration certificate and the same shall be
available onsite for verification by the supervision team and also the same shall be attached with
corresponding T&C IRs.

All personnel should wear at all time safety shoes, Goggles, Helmet and Coverall.

Also when required:


 Eye & Ear protectors
 Protective Gloves (Electrical shock proof gloves while working live during T&C)
 Protective Clothing (i.e. Coveralls)

14. COLOR CODING

All power tools are subject to inspection prior to bring at site, with attach update inspection
tag/sticker and color coding as per approved HSE Plan (Ref no. QPD-9-04-0007). Power tools
must be inspected by competent/certified person and attach inspection tag with color coding as per
approved HSE plan required.

15. HOUSE KEEPING

Working Areas will be kept clean by disposing the waste materials at the designated areas. At the
end of days’ work, installation supervisor will ensure that the debris are disposed of.
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 22 of 25

16. SCAFFOLDING (WHERE NECESSARY)

All scaffolding and ladders required for providing access to the workplace shall be erected and
inspected in accordance with the requirements. Prior to use scaffolding, must be visually checked
for any defects and be certified and tagged by scaffold inspector (approved by QATARENERGY).
Only approved and certified scaffold erector is authorized to erect and dismantle mobile
scaffolding.

17. QC APPROVAL AND OTHER DOCUMENTARY REQUIREMENTS


 Material approval Request (MAR)
 Approved Shop Drawings (SD)
 Approved Schematic Drawings
 Approved T&C Inspection Test Plan (ITP)
 Approved T&C Method Statement, Risk Assessment & HSE Plan

18. SUPPORTING DOCUMENT

This MST to be read in conjunction with the below referenced documents:


 Approved Shop Drawings and Project Specification.
 Project Quality Plan
 Project HSE Plan
 Scope of Work Appendix A
 Interface Register Appendix A
 ITP for Testing and Commissioning of Crown Lighting System (Ref no. QPD-9-E25-0031)

19. DISTRIBUTION

Copies of this MS will be circulated to the following for Information & action
 Project Manager
 Project Engineer
 T&C Manager
 Site Engineers / T&C Engineers
 Safety Engineer
 QA/QC Engineer /Inspector
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 23 of 25

20. OTHER INFORMATION

The work shall be inspected in accordance to the inspection & testing plan and inspection
checklists. Results of inspection & testing shall be recorded on the inspection checklist forms.

21. MAIN CONTRACTORS SAFETY ENGINEERS APPROVAL


 Risk mitigation measures as identified in the attached Risk Assessments to be inspected at
regular intervals for Activity duration as identified in the approved Health & Safety Manual
 Work Permit shall be obtained from prior to start the work and endorsed as per permit
requirements.

22. ATTACHMENTS
 Risk Assessment
 Schematic Diagram (for reference)
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
Rev.: 1
COMMISSIONING OF CROWN LIGHTING SYSTEM
Date : 29/10/2022
Page: 24 of 25

APPX-1: RISK ASSESSMENT


QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

Task Risk Initial Risk Controls Residual risk

Consequen

Risk rating
Likelihood
Consequence
Hazard Who or what

Likelihood
Sl. Description task

Rating
description might be Control measures
no. step/Activity
and effect harmed?

1 Area Preparation - Injuries due to Site workers, 3 2 6(Moderate) -Deploy only the inducted 3 1 3(Low)
malfunction foreman/engineer staff/workers/Operator/Driver at
with safety , patient, public site.
guards Testing/ -STARRT/ RAMS discussed to all
- Misuse due to commissioning workers prior to works
lack of team commencing.
competency. -Obtain infection control permit
-Dust. before construction begins.
-Damaged of -Isolate working area.
previous mat. -Complete all critical barriers or
-Slip, Trip & implement control cube
Fall method before construction
- COVID-19 begins.
pandemic - All personnel involved in T/C
mitigation activity shall be fully vaccinated
and shall present a green
“EHTERAZ”. Masks shall be
worn all the time and use of
sanitizer/soap to clean hands, as
per guidelines by MOPH.
-
2 Testing and commissioning of Slip, trip & fall, Site workers, 3 2 6 -Obtain infection control permit 3 1 3
Light Fixtures & controllers. Materials fall foreman/engineer (Moderate) before installation/removal of (Low)
from height, , patient, public existing services as per ICRA class
Floor damaged, IV.
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

Musculoskeletal -Obtain hot work permit if


disorder, required.
Slip, Trip and -Isolate the working area and
Fall, provide warning poster to prevent
Noise pollution, unauthorized personal.
Dust, -Provide brief about MS/RA
Damaged of among the workers with related
existing mat, foreman. .
Electrocution, -To ensure that workers are trained
Fires & Burns, for same work.
-All workers are must be internal
trained for manual handling.
-Do not remove barriers from
work area until
completed project is thoroughly
cleaned by the
housekeeping team.
-Vacuum work area with HEPA
filtered vacuum.
-Remove barrier materials
carefully to minimize
spreading of dirt and debris
associated with
construction.
-Use battery operated hand &
Power Tool to reduce the noise.
-Use appropriate PPE such hard
hat, hand gloves, safety glass, ear
plugs, dust mask etc.
-Supervisor must be present full-
time near workplace.
3 Use of aluminum ladders Slip, trip and Site workers, 3 2 6 -Ladders must be inspected by
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

fall from height foreman/engineer (Moderate) competent personal and color


, patient, public coded.
-Provide brief about safe use of
ladder prior to use.
check all four stepladder feet are
in contact with the ground and the
steps are level;
-Only carry light materials and
tools;
 don’t overreach;
 don’t stand and work on
the top three steps
(including a step forming
the very top of the
stepladder) unless there is
a suitable handhold;
-Ensure any locking devices are
engaged;
-Try to position the stepladder to
face the work activity and not side
on.
-Try to avoid work that imposes a
side loading, such as side-on
drilling through solid materials (eg
bricks or concrete);
-Where side-on loadings cannot be
avoided, you should prevent the
steps from tipping over, eg by
tying the steps. Otherwise, use a
more suitable
type of access equipment;
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

-Maintain three points of contact at


the working position. This means
two
feet and one hand, or when both
hands.
4 Use of electrical/electronic - Misuse due to Site workers, 4 2 8 -All tools must be inspected by 4 1 4 (Low)
tools lack of foreman/engineer (Moderate) competent person and colour
competency , patient, public coded.
- Use battery operated hand &
Power Tool to reduce the noise.
- Shall be used by experienced
person only. Closed supervisory
monitoring is required.
- Manufacturer manual shall be
made available in store for
reference.
- Periodic training and awareness
program on usage of power tools
shall be conducted.
-Wear the required and suitable
PPE eye, face, and ear protection -
Do not operate tool in an explosive
or flammable atmosphere.
-Provide fire extinguisher at the
work area if necessary.
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

6 Work at height Fall from the Site workers, 3 3 9 -Obtain work at height PTW 3 1 3 (Low)
height workers foreman/engineer (Moderate) before start of work.
and materials, -Safe, secured and inspected work
Untrained platform shall be in place at work
personnel area.
engaging on -Ladders shall be provided for
work at height access and egress.
Unsafe work -All workers should have work at
platform height training and valid card.
Use damaged -Full body harness should be
harness. inspected and colour coded and
free from defect and damaged.
-Full body harness is a must use
while working at height.
-Supervisor should be all time
present for monitor the work.
-Provide exclusion zones with
suitable signs to prevent
unauthorized access.
-Objects should not be thrown
from the top
-Follow three (3) point contact
while ascending or descending the
ladder
-Install a suitable lifeline / railing
for the operatives for safe
anchorage of the safety harness.
-Suitable PPEs shall be used.
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

7 Manual Handling Slip, Trip and Site workers, 4 2 8 -Ensure that workers and foreman 4 1 4 (Low)
Fall. foreman (Moderate) are internally trained for manual
Hand and leg handling.
injuries. -Use proper manual handling
Abrasion, process for storage and handling to
Fracture avoid falling on leg or back pain
Fall of and musculoskeletal disorder.
materials. -Barricade the formwork area and
Lifting of heavy prevent unauthorized entry if
component may falling or collapse possibilities.
cause back pain/ -Workers should follow proper
musculoskeletal manual handling methods.
disorders. -Minimise manual handling and
wherever possible use mechanical
means
8 Personal attire - Loose clothing Site workers, 4 2 8(Moderate) - Avoid loose clothing. 4 1 4(Low
may lead to foreman/engineer - Avoid wearing loose items and
traps -Jewelry or , patient, public rings, necklaces, bracelets, long
ornaments may chains and long hair.
be caught/
trapped to lead
injuries.

9 Electric tools -Electric shock Site workers, 4 3 12(High) -Extension cables shall be 4 1 4(Low)
-Punctures and foreman/engineer checked, and color coded
cuts due to , patient, public periodically by competent person,
damaged drill industrial sockets and extension
bits boards shall be used for extension.
Suitable ELCBs shall be fitted at a
distribution points.
-Standard drill bit shall be issued
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

and used.
-To ensure that electrical
connection taken only from
approved DB.
10 Human concerns and site - Harm to Site workers, 3 3 9 -only competent person shall use 3 1 3 (Low)
discipline person and foreman/engineer (Moderate) the power tools.
property , patient, public - Proper and enough trainings shall
be provided to workers. -
Person who are using power tools
shall be given frequent intervals.
- Persons who are using the power
tools in open environment shall be
provided with energy supplements.
- Persons using the power tools
shall concentrate on the respective
job and avoid conversation and
breaks by keeping the machinery
in on condition.
- Person who temper, manipulate
the tools and safety guards and
violate the safe working
procedures shall be treated
seriously and disciplinary action
shall be taken.
11 Demobilization of manpower Slip, trip and Site workers, 3 2 6 -Wet mop with disinfectant. 3 1 3 (Low)
fall. foreman/engineer (Moderate) Remove barrier materials carefully
Poor , patient, public to minimize
housekeeping. spreading of dirt and debris
Poor posture, associated with
Musculoskeletal construction.
disorder. -Use appropriate PPE’s
-To ensure that all workers are
QPD – TESTING & COMMISSIONING OF CROWN LIGHTING
SYSTEM

JOB HAZARD ANALYSIS

internal trained for manual


handling.
-Removed all materials after the
job completion.
-To ensure that good housekeeping
done before leaving the working
place.
-All kind of electrical connection
disconnected proper and removed
from working place.
Risk score Ranking What to do
17 - 25 Extremely High Immediate attention and action required. Organizations should consider whether they should eliminate or modify these
activities
10 – 16 High Action plan required, senior management attention needed
Application of proactive risk/ impact management strategies to reduce the risk & impact is advised.

5-9 Moderate Specific monitoring or procedures required, management responsibility must be specified.
Organization should consider what can be done to manage the risk & aspect to prevent any negative Outcomes.

1 -4 Low Manage through routine procedures. Organization can proceed with these activities as planned.

SN Reviewed by: Position / Ref Indicator Sign

1 Site HSE Manager


JHA Team Leader Authorization: Ref Indicator: Sign:
JHA Approval {Permit Authority/Asset Ref Indicator: Sign:
Holder):
Document Title : Doc No. QPD-9-E19-0041
METHOD STATEMENT FOR TESTING AND
COMMISSIONING OF CROWN LIGHTING SYSTEM Rev.: 1
Date : 29/10/2022
Page: 25 of 25

APPX-2: SCHEMATIC DIAGRAM (for reference)


TOWER-1 TOWER-2 TOWER-3 TOWER-4 TOWER-5
1
EC

PH HT

QTY: 09 Nos. QTY: 09 Nos. QTY: 09 Nos. QTY: 09 Nos. QTY: 09 Nos.
T6

T9
TYPE - L 02F TYPE - L 02F TYPE - L 02F TYPE - L 02F TYPE - L 02F
QTY L 01W: 02 Nos. QTY L 01W: 02 Nos. QTY L 01W: 02 Nos. QTY L 01W: 02 Nos. QTY L 01W: 02 Nos.
QTY L 01F: 06 Nos. QTY L 01F: 06 Nos. QTY L 01F: 06 Nos. QTY: 08 Nos. QTY L 01F: 06 Nos. QTY: 08 Nos. QTY L 01F: 06 Nos. QTY: 08 Nos.

LEGEND T7
T8
TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F
SYMBOL SYMBOL
CODE (SCHEMATIC) (LAYOUT) DESCRIPTION T5
QTY: 07 Nos. QTY: 07 Nos.

T1

TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 01W TYPE - L 01W TYPE - L 02F
L01F T4

PK T2
T3

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F

L01W

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F

L02F

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F

L02W
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F

EXTENSION EXTENSION EXTENSION EXTENSION EXTENSION


CABLE (5 CABLE (5 CABLE (5 CABLE (5 CABLE (5
POLES) POLES) POLES) POLES) POLES)
TYPICAL TYPICAL TYPICAL TYPICAL TYPICAL
(REF: (REF: (REF: (REF: (REF:
M030581) M030581) M030581) M030581) M030581)
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F L08

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F

POWER CABLE POWER CABLE POWER CABLE POWER CABLE POWER CABLE L09W
(5 POLES) (5 POLES) (5 POLES) (5 POLES) (5 POLES)
FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP
(REF: (REF: (REF: (REF: (REF:
M030580) M030580) M030580) M030580) M030580)

Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE
(REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE LCP
FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB
(DB.T1.16.02/Y1) (DB.T1.16.02/B1) (DB.T1.16.02/R1) (DB.T2.19.02/R12) (DB.T2.19.02/Y12) (DB.T2.19.02/B12) (DB.T3.22.02/B1) (DB.T3.22.02/R1) (DB.T3.22.02/Y1) (DB.T4.25.02/B1) (DB.T4.25.02/Y1) (DB.T4.25.02/R1) (DB.T5.28.02/B1) (DB.T5.28.02/Y2) (DB.T5.28.02/Y1) IPR IPR
3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F
(REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154)
RS232 RS232
3x1.5 MM² H07RN-F (REF: M030154)

BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224)
Elect.: Code 02
To comply with rev-0 comments.
6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 Endorsement to be provided by the specialist. 15.05.2022
DMX DMX DMX DMX DMX
AMPLIFIER AMPLIFIER AMPLIFIER AMPLIFIER AMPLIFIER
6 - OUTPUTS 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM
(MODEL: 3091211) DB.T2.19.01/R7
(MODEL: 3091211) (T2-19-01)
DB.T3.22.02/B12
(MODEL: 3091211) (T3-22-01)
DB.T4.25.02/B12
(MODEL: 3091211) (T4-25-01)
DB.T5.28.02/B9
(MODEL: 3091211) (T5-28-04)
DB.T1.16.01/B4 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
13A UNSPUR OUTLET OUTLET OUTLET OUTLET
240V 240V 240V 240V 240V
OUTLET
BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224)

LON CABLE LON CABLE LON CABLE LON CABLE LON CABLE
BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP)

T1.16.01 LCP.T1.16.02.1 LCP.T1.16.02.2 LCP.T1.16.02.3 T2.19.01 LCP.T2.19.02.1 LCP.T2.19.02.2 LCP.T2.19.02.3 T3.22.01 LCP.T3.22.02.1 LCP.T3.22.02.2 LCP.T3.22.02.3 T4.25.01 LCP.T4.25.02.1 LCP.T4.25.02.2 LCP.T4.25.02.3 T5.28.01 LCP.T5.28.02.1 LCP.T5.28.02.2 LCP.T5.28.02.3
240V 240V 240V 240V 240V
IPR RS232 DB.T1.16.01/B4 IPR RS232 DB.T2.19.01/R7 IPR RS232 DB.T3.22.02/B12 IPR RS232 DB.T4.25.02/B12 IPR RS232 DB.T5.28.02/B9
IP ROUTER AT IP ROUTER AT IP ROUTER AT IP ROUTER AT IP ROUTER AT
EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm: EL Rm:
TELECOM ROOM T1-16-03 T1-16-03 T1-16-03 TELECOM ROOM T2-19-01 T2-19-01 T2-19-01 TELECOM ROOM T3-22-01 T3-22-01 T3-22-01 TELECOM ROOM T4-25-01 T4-25-01 T4-25-01 TELECOM ROOM T5-28-04 T5-28-04 T5-28-04
T1-16-05
RS 232 CABLE T2-19-06 RS 232 CABLE T3-22-07 RS 232 CABLE T4-25-06 RS 232 CABLE T5-28-06 RS 232 CABLE

EXISTING EXISTING EXISTING EXISTING EXISTING

DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4

CONTROLLER @ELEC ROOM


CONTROLLER @ELEC ROOM
CONTROLLER @ELEC ROOM
CONTROLLER @ELEC ROOM
CONTROLLER @ELEC ROOM

DB.T1.16.01/B4
(MODEL: 7150612/C02) (T1-16-03)
DB.T2.19.01/R7
(MODEL: 7150612/C02) (T2-19-01)
DB.T3.22.02/B12
(MODEL: 7150612/C02) (T3-22-01)
DB.T4.25.02/B12
(MODEL: 7150612/C02) (T4-25-01)
DB.T5.28.02/B9
(MODEL: 7150612/C02) (T5-28-04)
13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V

TOWER-6 TOWER-7 TOWER-8 TOWER-9 TOWER-10 (HT)

QTY: 10 Nos. QTY: 10 Nos. QTY: 10 Nos.

QTY: 15 Nos.
TYPE - L 01F TYPE - L 01F TYPE - L 02F
QTY L 02W: 02 Nos.
QTY: 09 Nos. QTY L 02F: 07 Nos.

TYPE - L 08

TYPE - L 02F TYPE - L 01F TYPE - L 02F TYPE - L 01F TYPE - L 02F
QTY L 01W: 02 Nos.
QTY L 01F: 06 Nos. QTY: 08 Nos. QTY: 08 Nos.

TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02F
QTY L 02W: 02 Nos.
QTY: 07 Nos. QTY: 07 Nos. QTY: 07 Nos. QTY L 02F: 05 Nos.

TYPE - L 08

TYPE - L 01W TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F

QTY: 16 Nos.

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 08 TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 08 TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F

QTY: 03 Nos.

TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 02F TYPE - L 02F

EXTENSION QTY: 16 Nos. EXTENSION EXTENSION EXTENSION EXTENSION


CABLE (5 CABLE (5 CABLE (5 CABLE (5 CABLE (5
POLES) POLES) POLES) POLES) POLES)
TYPICAL TYPICAL TYPICAL TYPICAL TYPICAL
(REF: (REF: (REF: (REF: (REF:
M030581) M030581) M030581) M030581) M030581)
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 08 TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 02F TYPE - L 02F

EXTENSION
CABLE (5
POLES)
TYPICAL
(REF:
M030584)
TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 08 TYPE - L 09W TYPE - L 01F TYPE - L 01F TYPE - L 01W TYPE - L 02W TYPE - L 01F TYPE - L 01W TYPE - L 02F TYPE - L 02F TYPE - L 02F

POWER CABLE POWER CABLE POWER CABLE POWER CABLE POWER CABLE
(5 POLES) (5 POLES) (5 POLES) (5 POLES) (5 POLES)
FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP FEMALE - TYP
(REF: (REF: (REF: (REF: (REF:
M030580) M030580) M030580) M030580) M030580)

Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE Y TUBE
(REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE (REF: M030584) POWER CABLE
FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB FROM DB
(DB.T6.31.01/R10) (DB.T6.31.01/Y10) (DB.T6.31.01/B10) (DB.T7.46.01/Y8) (DB.T7.46.01/B8) (DB.T7.46.01/Y4) (DB.T7.46.01/B7) (DB.T7.46.01/B3) (DB.T8.29.01/B10) (DB.T8.29.01/Y10) (DB.T8.29.01/R10) (DB.T9.26.01/Y5) (DB.T9.26.01/R5) (DB.T9.26.01/B4) (DB.HT.25.02/B12) (DB.HT.25.02/Y12)
3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F 3x1.5 MM² H07RN-F
(REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154) (REF: M030154)

AEB HEADQUARTERS:
BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable P.O. Box 1148 Doha, Qatar Tel +974 406 88 88 Fax +974 447 78 68
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) Email aeb@aeb-qatar.com Web www.aeb-qatar.com
OTHER BRANCHES:
MUSCAT * KUALA LUMPUR * MANILA
6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1

DMX DMX DMX DMX DMX


AMPLIFIER AMPLIFIER AMPLIFIER AMPLIFIER AMPLIFIER
6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM 6 - OUTPUTS @ELEC ROOM

DB.T6.31.01/R9
(MODEL: 3091211) (T6-31-01)
DB.T7.46.01/R8
(MODEL: 3091211) (T7-46-06)
DB.T8.29.01/B6
(MODEL: 3091211) (T8-29-03)
DB.T9.26.01/R10
(MODEL: 3091211) (T9-26-02)
DB.HT.25.02/R12
(MODEL: 3091211) (HT-25-04)
13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V
BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable BELDEN 3105A cable
(REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224) (REF: M030224)

LON CABLE LON CABLE LON CABLE LON CABLE LON CABLE
BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP) BELDEN 2C UTP 7701NH (TYP)

T6.31.01 LCP.T6.31.02.1 LCP.T6.31.02.2 LCP.T6.31.02.3 LCP.T6.31.02.4 T7.46.01 LCP.T7.46.01.1 T8.29.01 LCP.T8.29.01.1 LCP.T8.29.02.1 LCP.T8.29.02.2 LCP.T8.29.02.3 T9.26.01 LCP.T9.26.02.1 LCP.T9.26.02.2 LCP.T9.26.02.3 HT.25.01 LCP.HT.25.01 LCP.HT.25.02.01 LCP.HT.25.02.02 LCP.HT.25.E01
240V 240V 240V 240V 240V
IPR RS232 DB.T6.31.01/R9 IPR RS232 DB.T7.46.01/R8 IPR RS232 DB.T8.29.01/B6 IPR RS232 DB.T9.26.01/R10 IPR RS232 DB.HT.25.02/R12
IP ROUTER AT EL Rm: EL Rm: EL Rm: EL Rm: IP ROUTER AT EL Rm: IP ROUTER AT EL Rm: EL Rm: EL Rm: EL Rm: IP ROUTER AT EL Rm: EL Rm: EL Rm: IP ROUTER AT EL Rm: EL Rm: EL Rm: EL Rm:
TELECOM ROOM T6-31-01 T6-31-01 T6-31-01 T6-31-01 TELECOM ROOM T7-46-06 TELECOM ROOM T8-29-03 T8-29-03 T8-29-03 T8-29-03 TELECOM ROOM T9-26-02 T9-26-02 T9-26-02 TELECOM ROOM HT-25-04 HT-25-04 HT-25-04 HT-25-04
T6-31-04 RS 232 CABLE T7-46-03
RS 232 CABLE T8-29-01
RS 232 CABLE T9-26-07
RS 232 CABLE HT-25-01
RS 232 CABLE

EXISTING EXISTING EXISTING EXISTING EXISTING

DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4 DMX SEE NOTE # 4

CONTROLLER @ELEC ROOM


CONTROLLER @ELEC ROOM
CONTROLLER @ELEC ROOM
CONTROLLER @ELEC ROOM
CONTROLLER @ELEC ROOM

DB.T6.31.01/R9
(MODEL: 7150612/C02) (T6-31-01)
DB.T7.46.01/R8
(MODEL: 7150612/C02) (T7-46-06)
DB.T8.29.01/B6
(MODEL: 7150612/C02) (T8-29-03)
DB.T9.26.01/R10
(MODEL: 7150612/C02) (T9-26-02)
DB.HT.25.02/R12
(MODEL: 7150612/C02) (HT-25-04)
13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR 13A UNSPUR
OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V OUTLET 240V

You might also like