METHOD STATEMENT FOR PRECOMMISSIONING AND COMMISSIONING OF LIGHTING CONTROL SYSTEM
(Package-2)
Submitted for :
- IFC : Issued for comment - IFA : Issued for Approval - IFI : Issued For Information - RET : Issued For Retention
Note : Approval or comments made to this submittal does not relieve the Contractor from their responsibilities. The assessment is to review the general conformance and compliance of the submittals to the contract and
specification requirements.
MG TN # 16655
Document Submittal Form
AEB - Quality Forms 1 of 1 Form No.: P07-F14 / Rev. 0 / Jul. 2018
10-11-2020
10-11-2020
19-11-2020
11-11-2020
Project Name: Fit Out for Podium at QPD
Document Reference: QPD-9-E19-0035 Rev.0 Page 1 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
HSE – HIRA Compliance of control measures as stated on HIRA. Close Noted & Complied; please refer to the
9 6 monitoring of on the activity to identify any hidden hazards. Pre-Task attached Risk Assessment at Section
briefing shall be develop prior to commence activity 22_”Attachments”.
Document Reference: QPD-9-E19-0035 Rev.0 Page 2 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
14 2
Comply, Lux Level set point will be
Brief “setting a desired Lux Level. as per Lighting Control Philosophy
document QPD-9-TS-E-0002-1.
Elec.: - “The installations of the control system components Noted & Comply; Project team
15 2 are the responsibility of Medgulf”. documents are already approved part of
Submit the training certificates of the dedicated Project Team. PQD submission.
Noted & Comply, Field testing and
witnessing will be as per QP instruction
complying with Project Specification,
Elec.: - Witnessing the field testing will be as per QP Approved LCS Philosophy and Approved
16 2
instruction.
GUI submittal.
(Also refer Section7.8_”Witness
Demonstrations/ Completion”)
QP COMMENTS:
1. Technical Submittal for Lighting Control System Operations Noted & Comply, Lighting Control System
Philosophy for Package-2 shall be submitted first (as similarly operation philosophy is submitted for
17 2 done in other Packages) and this MS for T & C of Lighting review and approval. Please refer to
Control System (LCS) shall be updated and coordinated document QPD-9-TS-E-0002-1. This MS is
accordingly with the said approved Technical Submittal. rewritten considering the same
Document Reference: QPD-9-E19-0035 Rev.0 Page 3 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
2. Pre-Commissioning to include also the works related to Noted & Comply, refer to the revised
18 2 interfacing of LCS to Central Battery System and Blinds Control Pre-commissioning, Section7.1_”Pre-
System. Commissioning”).
3. LCS operation and testing on Normal, Fire Alarm and Comply, LCS operation and testing with
Emergency Scenarios included operation timings as per LCS different scenarios and timings is
19 2
Operations Philosophy shall be clearly defined and included in
this MS. included. Please refer Section 7.6 & 7.7
Document Reference: QPD-9-E19-0035 Rev.0 Page 4 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
Project Name: Fit Out for Podium at QPD
Document Status: 10 = Approved 2 = Approved with Comments (Incorporate comments 3 = Not Approved (Incorporate comments and
(Resubmission not and resubmit - work may proceed subject to resubmit - work shall not proceed)
required) incorporation of comments)
6 = For Information 1 = Approved without Comments (Resubmission 11 = Cancellation Accepted
Only required - work may proceed)
Note 1: A unique CDF serial number will be allocated with document initial submission; subsequent revisions will be reflected in CDF revisions (applicable at least by QRC and QP)
Note 2: Originator - QP/ QRC
Note 3: Please encode separate number for each CDF in the footer with revision number
Document Reference: QPD-9-E19-0035 Rev.0 Page 5 of 5 Form No.: P07-F64, Rev.0, Date: Jul.2018
CONTRACT NO.: GC18105500
DOCUMENT TITLE:
PO Box 1148, DOHA QATAR PO Box 3603, Al Manara Tower, 1st Floor
www.medgulfconstruction
www.aeb-qatar.com
Table of Contents
1. PURPOSE .............................................................................................................. 3
2. SCOPE& OBJECTIVE ........................................................................................... 3
3. REFERENCE ......................................................................................................... 3
4. ABBREVIATIONS .................................................................................................. 4
5. HEALTH & SAFETY HAZARDS: ........................................................................... 5
6. RESPONSIBILITY ................................................................................................. 8
7. PROCEDURE .......................................................................................................11
7.1. PRE-COMMISSIONING ........................................................................................11
7.2. COMMISSIONING ................................................................................................12
7.3. Prerequisites to procedure .................................................................................13
7.4. Pre-Start Checks procedure ...............................................................................14
7.5. Commissioning Test Procedure .........................................................................15
7.6. Third Party Interface Testing ..............................................................................17
7.7. Operation & Integration Testing .........................................................................19
7.8. SITE ACCEPTANCE / OPERATIONAL & PERFORMANCE TEST (SAT) ...........21
7.9. Witness Demonstrations/ Completion ...............................................................21
8. WORK PERMIT ....................................................................................................24
9. WORKING HOURS ...............................................................................................24
10. MANPOWER.........................................................................................................25
11. LOGISTICS ...........................................................................................................25
12. MATERIAL REQUIREMENT .................................................................................25
13. PLANT & EQUIPMENT REQUIREMENT ..............................................................25
14. COLOR CODING ..................................................................................................26
15. HOUSE KEEPING ................................................................................................26
16. SCAFFOLDING (where necessary) .....................................................................26
17. QC APPROVAL AND OTHER DOCUMENTARY REQUIREMENTS ....................27
18. SUPPORTING DOCUMENT .................................................................................27
19. DISTRIBUTION .....................................................................................................27
20. OTHER INFORMATION ........................................................................................27
21. MAIN CONTRACTORS SAFETY ENGINEERS APPROVAL ...............................28
22. ATTACHMENTS ...................................................................................................28
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 3 of 28
1. PURPOSE
The purpose of this Method Statement for Testing & Commissioning of Lighting
Control System (LCS) is to define the systematic manner of proceeding with
activities such that the result will be in accordance with the prevalent
Regulations in the State of Qatar within the Contract Requirements.
2. SCOPE& OBJECTIVE
3. REFERENCE
Note: Revision reference numbers of the above mentioned documents are subject to
frequent change (resubmission), and hence latest revision shall be cross checked
from the document register.
4. ABBREVIATIONS
IR Inspection Request
PRC Pre-Commissioning
COM Commissioning
FT Functional Test
Performance) Test
MS Method Statement
KM KAHRAMAA
RA Risk Assessment
LOTO Lock-out/Tag-out
SD Shop drawing
TP Third Party
Consider the risks of manual handling before going to the site and look at
the materials being used or stored.
Adequate Illumination shall be set up at the work area and ensure the
required Lux available as per QCS 2014 during night shift, and at the dark
areas required during daytime.
6. RESPONSIBILITY
Project Manager- is overall responsible for the successful initiation,
planning, execution, monitoring, controlling and closure of a project as per
the approved schedule and contractual requirements and make sure they
control risk and minimize uncertainty. Also, he will maintain the planning
progress and coordination of works with Main Contractor.
Commissioning Engineer - To ensure that all commissioning activities
are carried out in liaison with system specialist to the satisfaction of MG /
AEB-QRC/ QP. Raising non-conformance or corrective action and adhere
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 9 of 28
to safety procedure. Carry out a punch list walk down and liquidate punch
list items as required
Project Engineer/ Site Engineer- is responsible for the day to day
activities on site, for materials, approved drawings, approved method
statement, testing & commissioning and allocation of departmental
resources to work areas on Site. He is also responsible to ensure
adequate equipment for shifting of materials and other related works are in
place prior to the starting of work. The Project Engineer will report to the
Project Manager.
Supervisor / Foreman – will be directly responsible for the day-to-day
works on site as per instructions of the Project Engineer / Site Engineer
and provide proper documentation to his workers so they can proceed with
tasks and handling the technicians, or any other staff assign to his area.
QA/QC Engineer – will oversee all the quality requirements and quality
control measures for the Project in coordination with the Project Engineer
as outlined in the Approved Project Quality Plan
QA/QC Inspector - will check the quality requirements and quality control
measures for the Project in coordination with the QA/QC Engineer as
outlined in the Approved Project Quality Plan
Safety Officer – will be responsible for the Health and Safety aspects on
site as per the Mains Contractor Safety requirements.
LCS Specialist Project Manager – coordinates with the Contractor and
manages the testing procedure at site.
LCS Specialist Project Engineer - is responsible for pre-commissioning,
testing and commissioning.
AEB-QRC/ QP Representative - Advise punch list items. Witness of
testing & verification carried out during commissioning.
Third Party (GST) – will be witnessing the Testing & Commissioning
activity. GST being qualified and experienced independent testing and
commissioning third party, hired by MG shall be witnessing & reporting of
the testing and commissioning activities.
Refer Prequalification for Third Party Testing & Commissioning (GST),
Doc.ref. no. QPD-9-PQD-MG-0072.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 10 of 28
7. PROCEDURE
7.1. PRE-COMMISSIONING
Ensure that all system materials, wiring, supports, lighting fixtures, etc. are
approved through the construction MIRs and IRs
Inspect visually the external and internal, where applicable, parts of panels,
modules, devices, sensors, switches lighting fixtures DALI units, interfaced
emergency lighting modules, wiring, etc.
Ensure all LON devices (DALI Broadcast Module, 1.10 DALI Module, Blind Control
Module, RS 232 AV interface and Touch panels) these units are available, not
defected and installed as per approved submittals.
Ensure all installation are complying to the approved, by QRC, technical and
construction submittals (MARs, MIRs, IRs, shop drawings, electrical room
details, approved installation details, etc.) related to this activity
Ensure and verify that tagging is applied as per approved tagging system in the
project. Ensure tagging materials as per approved submittals
Ensure cables and wiring are installed, terminated and labelled safely with no
defect. Labelling shall be as per approved labelling system
Ensure earthing is provided as per approved submittals, and mockup
installation comments for BCMs and broadcasting modules
Ensure termination to final lighting fixtures shall be as per Kahramaa regulation,
QCS requirements, project specification, MIRs, IRs and shop drawings
Ensure all warning labels and circuits tags are provided.
All light fittings should be installed and powered UP. DALI cable should be
terminated to all DALI Light fittings.
All sensors should be installed. The DALI cable should be terminated to all
Sensors.
Note: The sensors should be connected and addressing should be provided as
mentioned in As-built lighting layout drawings forwarded to Delmatic for
preparing offline program.
7.2. COMMISSIONING
The main objective here is to minimize the risks of injury and damage to personnel
and equipment prior to the running of the Delmatic Lighting Control System.
The following test procedures will be performed during the various stages of
installation, configuration, testing and commissioning of Lighting Control System
Unit Test: All the DALI Broadcast Module, 1.10 DALI Module, Blind Control Module
will be commissioned by pressing the service pin.
Unit Test: The next step would be to check the operation of DALI light fittings
On & OFF.
Unit Test: Sensors will be addressed using the addressing dial present on the
device.
Unit Test: Sensors will be programmed to controller the respective lamps.
Functional Test: Occupancy Operations - Operation of sensors for
occupancy is checked for switching ON/OFF at pre-programmed time delay.
Functional Test: Lux Level Operations - Operation of sensors for lux control
is checked by setting a desired lux level (as per Lighting Control Philosophy
document QPD-9-TS-E-0002)
Lux Level Set Point for QP project is 300-500 lux.
Delmatic will assign the Lux Set Point for each Multi Sensor for Daylight
harvesting. When the Lux Level measured by the sensor is greater than Lux
Set Point, the DALI light fittings will be dimmed down until OFF (0%). When the
Lux Level measured by the sensor is lower than Lux Set Point, the DALI light
fittings will be Dimmed UP until 100%
Functional Test: Touch Pad Operations - Operation of lights dimming, blinds
and AC is checked from Desk mounted Wireless Touch Pad.
Functional Test: Touch Panel Operations - Operation of lights dimming,
blinds and AC is checked from Wall Mounted Wired Touch Panel.
Unit Test: Router - The Routers are assigned an IP address and
communication for all DALI Broadcast Module, 1.10 DALI Module, Blind Control
Module is verified by running a test to check all modules are ONLINE.
Functional Test: Lightscape GUI Application - Delmatic shall prepare GUI
as per approved GUI submittal after receiving the As-built lighting layout
drawings from Contractor.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 13 of 28
Step 2: Delmatic shall carry out offline programming or mapping of local devices such
as switch, sensor etc. to control appropriate lighting based on information provided in
the As-built lighting layouts.
a). All light fittings should be installed and powered UP. DALI cable should be
terminated to all DALI Light fittings.
b). All sensors, switch interface unit and scene set panel should be installed. The
DALI cable should be terminated to all.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 14 of 28
d). IP Routers should be powered ON with 240VAC and IP LAN network active.
f). LON cable from IP Router to all Lighting Control Modules, Blind Control Modules,
RS232 interface module, Touch Panel should be installed, terminated and tested.
Please install 100ohm resistor in first point (in IP Router) and check in all lighting
control modules that correct resistance value (between 100ohms to 125ohms is
measured).
g). Blind Control Modules should be powered ON with 240VAC and Motors should be
connected to each output port matching the layout drawings showing port references.
h). Touch Panel should be installed, 240VAC power supply to be switched ON. LON
cable should be terminated as shown on lighting layout drawings. The Touch Panel
should be connected to building IP network with unique IP address.
i). Virtual Machine should be installed, and IP address should be assigned by QPD IT.
j). BMS Points list for interface with be shared after completion of standalone LCS
T&C.
k). Fire Alarm 2core cable from FAS should be terminated to Floor controller in IP
Router.
l). Power Supply, LON cable and RS232 cable (from AVS) should be terminated to the
RS232 interface module. AV System interface with LCS will be carried out after
completion of standalone LCS T&C.
Ensure all data and low voltage supply is as per Delmatic specifications.
Ensure all required data and low voltage supply cables are installed between
modules, IP routers or sensors.
Ensure all installed wall or back boxes for control locations are installed and are at
minimum depth suitable for the control devices.
All installed equipment is safe and is in a suitable area to gain access to for
programming.
Main power supply feed relates to the appropriate isolation to relevant module.
All controlled loads are connected to the appropriate module
All data and power cables are connected to all relevant wall/ceiling control panels.
LON & DALI data communication cables are as Delmatic have specified.
The Punch List contains details of the outstanding items (punch items) to be
completed together with information as to who is responsible for clearing the
items, the planned date for clearance and the classification of the items.
Items on the Punch List are categorized as follows:
* Category “A”: A punch list item that will prevent the safe operation of the
equipment and system and plant and may jeopardize personnel or environment.
Such items, as agreed, shall be cleared before the equipment and system and
plant can progress to the next stage of the commissioning and handover phase.
* Category “B”: A punch list item that will not endanger the safe operation of
the equipment and system and plant or personnel and or environment. Such item,
as agreed, can be carried over to the next stage and may be cleared later. These
items shall be repaired, completed or corrected in a timely manner or if approved
by QP may be carried over to the next stage.
a) For DALI Broadcast Switching/Dimming, DALI One ten modules, Blind Control
Module, RS232 interface module
Ensure unit has mains power
Press service Pin of the Unit.
Carry out programming to control circuits by sensors or timer.
After control system components have been configured and initialization the system
will require testing of program that has been uploaded. The programming is generally
in accordance with the LCS Philosophy document and may possibly be adapted on
site to meet the end user requirements where possible.
The general tasks to be executed within programming are typically as follows but may
include site specific requirements.
The lights are then switched ON/OFF from the BMS PC. Visual verification is
carried out either on floor or LCS GUI to confirm that lights are switched
ON/OFF.
Once the fire signal (cable close) is received from FA at IP Router all the
lighting control modules within the IP Router are switched ON to 100%.
After reset of Fire signal (open cable), the lights will switch OFF based on
occupancy once sensor triggers occupancy.
AVS will send Lights Five Scenes and Blinds Five Scenes for control of lighting
and Blinds as indicated in the LCS philosophy document.
Once the operation of Lights and Blinds from AV Touch panel is confirmed, this
recorded in the checklist and witnessing is carried out by Consultant & Client.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 18 of 28
Emergency Lighting
LCS is interfaced with CBS through interface module supplied and tested by
CBS Supplier.
During Normal operation, emergency lights along with Normal lights are Controlled by
local devices such as sensors, central PC.
Emergency lights are switched ON during normal power failure. The Normal failure is
simulated by switching OFF Normal Power Supply to verify switching ON of
emergency lights.
Upon return of Normal power supply, the lights will switch OFF based on occupancy
once sensor triggers occupancy.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 19 of 28
The operation and Testing from the workstation is briefly explained as below.
For comprehensive information, refer to Lighting Control Philosophy document.
The corresponding feedback of the below checks shall be verified on screen and
in the field.
A. Office Rooms
The Lights in the office rooms are controlled through multi-sensors that
switches/dims lights based on occupancy, touch pad commands, daylight
harvesting (for rooms near façade).
The testing is carried out by ensuring all lights in the rooms being switched OFF
after elapse of pre-configured time delay.
After upload of the program on the lighting control module, blind control
module the T&C engineer awaits to ensure all the lights are switched OFF.
The T&C engineer enters the room to trigger occupancy. Lights are turned ON to
100%.
The T&C engineer then tests the Lights operation ON/OFF/Dimming presets
through the Touch Pad.
The operation of blinds UP/DOWN and preset positions are tested through the
Touch pad.
Daylight harvesting is tested by initially assigning the lux set point at dusk. The
lights are dimmed to arrive at desk lux level of 500-700lux. The lux value
measured at multi-sensor is assigned the set point. Daylight harvesting is tested
for desk lux value of 500-700lux and confirmed.
The testing is carried out by ensuring all lights in the rooms being switched OFF
after elapse of pre-configured time delay.
After upload of the program on the lighting control module, T&C engineer
awaits to ensure all the lights are switched OFF.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 20 of 28
The T&C engineer enters the room to trigger occupancy. Lights are turned ON to
100%.
C. Meeting Rooms.
The Lights in the rooms are controlled similar to Office Rooms. Additionally in
certain rooms, AV touch pad is used for control of lighting through Five Scenes
and control of blinds for UP/DOWN and 3 preset positions.
The interface with LCS & AVS is through Delmatic RS232 interface module
installed in AV Rack.
D. Corridor.
The testing is carried out by ensuring all lights in the corridor being switched
OFF after elapse of pre-configured time delay.
After upload of the program on the lighting control module, T&C engineer
awaits to ensure all the lights are switched OFF.
The T&C engineer enters the area to trigger occupancy. Lights are turned ON to
100%.
E. Lift Lobby.
The testing is carried out by ensuring all lights in the lift lobby being switched
OFF after elapse of pre-configured time delay. Certain lighting control channel is
retained at dimmed level for security purpose.
After upload of the program on the lighting control module, T&C engineer
awaits to ensure all the lights are switched OFF or dimmed.
The T&C engineer enters the area to trigger occupancy. Lights are turned ON to
100%.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 21 of 28
7.8.1. Pre-requisite
Prior to start of Site Acceptance Test (SAT) activities, the following activities to
be completed.
The commissioning results will be recorded on project agreed format and offered to
AEB/QP for witnessing/acceptance.
An Inspection Request attached with the Pre-com check sheets and later with the
Completion IR will be raised by MG to QRC, to enable co-ordination/sign off of
Lighting Control System testing with the Client representatives.
The client representative of the end user will be invited to witness the field testing. The
representative will select 5% of the random links to be demonstrated and the results
shall be stored in accordance with the prescriptions.
Witnessing the field testing will be as per QP instruction in compliance with Project
Specification, T&C Plan, approved LCS Philosophy and approved GUI submittal.
Refer to checklist below for recording of each test (this is just a sample, however
please refer to T&C ITP (Ref.no. QPD-9-E25-0026) for detailed checklists and
sequence of test stages);
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 24 of 28
8. WORK PERMIT
Permit to Work (PTW) is required prior to start of any work activities within the
project. Shapoorji Pallonji internal PTW procedures approved by AEB and QP
will be adopted for all internal works without interference to SNCL services.
MG PTW Authorized Person shall be the only person who shall approve the
Permit to Work (PTW). If any activity that requires an interface is to be
undertaken, a SNCL Permit to Work shall be processed as required.
Reference shall be made to this Method statement and Risk assessment in the
PTW. MSDS of all Hazardous materials shall be attached with the PTW for
ready reference.
General Works ✓
Work at Height ✓
Hot Works X
Confined Space X
Lifting Operations X
9. WORKING HOURS
10. MANPOWER
Designation Available
Electricians
Electrical Helper
11. LOGISTICS
NOTE: Ensure all instruments having latest and valid calibration certificate
and the same shall be available onsite for verification by the supervision
team and also the same shall be attached with corresponding T&C IRs.
All personnel should wear at all time safety shoes, Goggles, Helmet and
Coverall.
Also when required:
Eye & Ear protectors
Protective Gloves
Protective Clothing (i.e. Coveralls)
All power tools are subject to inspection prior to bring at site, with attach update
inspection tag/sticker and color coding as per approved HSE Plan (Ref no.
QPD1B-9-04-0002 Rev 002). Power tools must be inspected by
competent/certified person and attach inspection tag with color coding as per
approved HSE plan required.
Working Areas will be kept clean by disposing the waste materials at the
designated areas. At the end of days’ work, installation supervisor will ensure
that the debris are disposed of.
All scaffolding and ladders required for providing access to the workplace
shall be erected and inspected in accordance with the requirements. Prior
to use scaffolding, must be visually checked for any defects and be
certified and tagged by scaffold inspector (approved by QP). Only
approved and certified scaffold erector is authorized to erect and
dismantle mobile scaffolding.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 27 of 28
19. DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action
Project Manager
Project Engineer
T&C Manager
Site Engineers / T&C Engineers
Safety Engineer
QA/QC Engineer /Inspector
The work shall be inspected in accordance to the inspection & testing plan and
inspection checklists. Results of inspection & testing shall be recorded on the
inspection checklist forms.
Document Title: Doc No. QPD-9-E19-0035
METHOD STATEMENT FOR PRE-
COMMISSIONING AND COMMISSIONING OF Rev.: 1
LIGHTING CONTROL SYSTEM Date : 09/10/2021
Page: 28 of 28
22. ATTACHMENTS
Risk Assessment
INTER– DEPARTMENTAL PROCEDURE -OPERATIONS
1 Slight injury or Slight Damage Slight Effect Slight Effect Low Risk
health effects (<QR35000)
Minor injury or Slight Damage
2 health effects (between QR35000 Minor Effect Minor Effect
and 350,000)
JHA No: Revision No: 0 Area: Cluster at QPD Job Location: QPD Date: 07/10/2021
Job Ref (Project No/Work Order No): Hazardous Area Classification: Zone 0 Zone 1 Zone 2 Non-Hazardous
INTER– DEPARTMENTAL PROCEDURE -OPERATIONS
Job Description: Risk Assessment for Testing & Commissioning of Lighting Control System Permit Type & No:
Risk
Residual
Rating
Sl. Risk
Task / operation Hazards Before Control Measures Rating Action by
No. Mitigation
01 Site Preparation & 1. Live or De-energized 4XC=M 1. Mandatory property protection action must 2XA=L Supervision
Pre- existing facility be completed as part of STARRT Card by
Commissioning 2. Insufficient / Incorrect process CM /
Activities Information 2. Obtain correct PTW. Engineer /
3. Unsafe working practice 3. Communicate RA to work crew. Supervisor /
Foreman
4. Incorrect use of tools / test 4. Carry out toolbox talks before start of each
equipment working day or new task Ensure only HSE Advice
5. Unsafe site condition trained / certified personnel are assigned on & Coverage
6. Inexperienced testing and the job By Safety
commissioning personnel Personnel
5. Pre-task briefing, TBT and RAMS to be
7. Poor communication
briefed / communicated to workforce prior
between work parties
to commencement of the activity
6. All operatives, including vendors for testing
and commissioning shall attend Medgulf
site induction prior to entering the site.
7. All testing and commissioning tasks should
be carried out by trained, authorized and
competent personnel only.
8. Ensure the testing and commissioning
instruments are functioning and in good
condition.
INTER– DEPARTMENTAL PROCEDURE -OPERATIONS
4 Management of 1. Uncontrolled access to test 4XC=M 1. Erect physical barriers and implement 2XA=L Supervision
Test Area area controls to prevent unauthorized access to by
2. Unauthorized entry into test area CM /
test area Engineer /
2. Ensure all post-test activities are carried out Supervisor /
3. Untrained persons
interacting with test by authorized/qualified persons Foreman
equipment 3. Ensure the LOTO system is fully HSE Advice
4. LOTO system not implemented throughout – until all activities & Coverage
implemented or followed and tests have been concluded and the area By Safety
5. Risk Assessment not made safe and vacated after the Personnel
communicated or complied
commissioning activities
with
6. Lack of supervision 4. Ensure all signage, warning tapes and other
safety equipments are kept in place
throughout the test period. Upon
INTER– DEPARTMENTAL PROCEDURE -OPERATIONS
9 Post-Test / Post- 1. LOTO procedure not 4XC=M 1. Make sure the LOTO procedure is observed 2XA=L Supervision
2. Ensure all post–commissioning repair by
INTER– DEPARTMENTAL PROCEDURE -OPERATIONS
10 Working Around 1. High Voltage 4XC=M 1. All workforce are to attend MG LOTO 2XA=L Supervision
Live Energy by
2. Access to energized area Training and provided with training
During T&C CM /
Activities not controlled identification Engineer /
3. Unauthorized entry into Supervisor /
2. Ensure the reviewed Risk Assessment is Foreman
energized area
communicated to all system specialist/
4. Working too close to live HSE Advice
cables or equipment vendor, and contractor persons before & Coverage
By Safety
5. No SiMOPs coordination commencing work in this area.
Personnel
INTER– DEPARTMENTAL PROCEDURE -OPERATIONS
12 Housekeeping 1. Poor Housekeeping 2XB=M 1. Ensure work area is clean and unwanted / 2XA=L Supervision
2. No waste segregation discarded tools / equipment disposed of by
properly. CM /
3. Infrequent cleaning or Engineer /
waste disposal 2. Ensure the walkway and emergency exits Supervisor /
4. Improper disposal are free at all times. Foreman
5. Poor stacking 3. Housekeeping to be done on daily basis HSE Advice
after all installation activities & Coverage
4. Housekeeping should be carried out at By Safety
Personnel
regular intervals throughout the work
activities
5. Industrial disposal bins for different wastes
should be marked clearly and used correctly
6. Wastes should be segregated and disposed
of in respective designated waste collector /
bin