You are on page 1of 4

SR NO

4
8
8
11
17
21
22
23
30
32
PARTICULAR
SPACE FOR EQUIPMENTS(SHARING SITE)
LIGHTING
LIGHTING
PIU/ACDB
TOWER
LIGHTNING PROTECTION
AVITATION LIGHT
CABEL INLET
GSM ANTENNA AZIMUTH(EXISTING)
MW ANTENNA AZIMUTH(EXISTING)
ANNEXURE -2 (PUNCH POINT LIST)

PUNCH POINT
SPACE IS NOT AVAILABLE FOR BTS
NO OF FITTING ≤2
NOT OPERATIONAL
PIU/ACDB NOT INSTALLED,POWER TERMINATIN ,COMMISSIONED
TOWER PAINTING NOT DONE
LA NOT CONNECTED TO EARTH PIT
NOT COMMISSIONED
NOT AVAILABLE FOR POWER AND SIGNAL CABEL
NOT ACCORDING TO RF PLAN
NOT ACCORDING TO PLANE
REMARK
NEW SHELTER REQUIRED
REQUIRE ONE MORE
REQUIRE OPERATION
REQUIRE INSTALLATION,POWER TERMINATION,COMMISSIONING
REQUIRE PAINTING
REQUIRE CONNECTION
REQUIRE COMMISSIONING
REQUIRE CABEL INLET
REQUIRE MODIFICATION
REQUIRE MODIFICATION