8 DAY'S CYCLE ACTIVITIES FOR ALLUMINIUM SHUTTERING WORKS

FOR A FLOOR PLATE OF 1000 SQ.MTS OF ALLUMINIUM SHUTTERING


D1 D2 D3 D4 D5 D6 D7 D8
ACTIVITY M A M A M A M A M A M A M A M A
Cleaning, Marking & Inking line
Shifting of wall Rebar
Installation of wall Rebar
M & E installation for Wall
Shifting of Lower Bracket
Dismantle,Shift & Erect of External wall Formwork
Dismantle & Shift Internal Wall formwork*
Erect (shuttering) internal wall formwork*
Dismantle & Shift Slab formwork
Erect (shuttering) slab formwork
Shifting of Beam, slab Rebar
Installation of slab/beam Rebar
Levelling & Alignment
Dismantle & Shift Kicker, Sunken
Installation of Kicker, Sunken formwork
M & E installation for Slab
Inspection
Pouring Concrete
Minimum Number of Carpenters 100
Minimum Number of Helpers 33
Minimum Number of Fitter 83
*Wall formwork includes all Al-Form panels excluding Slab panels.
1) Erection of Scaffolding (day= -8 )
2) Shifting of Rebar from steel yard to site (day= -8)
M= MORNING SESSION
A= AFTERNOON SESSION
D= DAY