METHOD STATEMENT
for
Rev. 01
Prepared by:
Gilbert A. Neptuno
Senior Site Manager
Thang Long Fire Co.
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
TABLE OF CONTENTS
page no.
1.0.Purpose......................................................................................................................3
2.0.Definitions ................................................................................................................3
2.1 Party..................................................................................................................3
2.2 Scope of Works ................................................................................................3
3.0 Specific Standards ...................................................................................................3
3.1 References & Standards..................................................................................3
4.0 Materials ..................................................................................................................4
5.0 Material Handling, Storage and Delivery .............................................................6
6.0 Preparation Works ..................................................................................................7
7.0 Work Flow Chart ....................................................................................................8
8.0 Construction Method..............................................................................................9
9.0 Quality Control......................................................................................................40
9.1 Preparation Works.........................................................................................40
9.2 Installation......................................................................................................42
9.3 Inspection........................................................................................................42
9.4 Handover After Installation..........................................................................42
9.5 Lists of Testing & Commissioning Tasks.....................................................42
10.0 Safety Plan............................................................................................................44
11.0 Appendix...............................................................................................................45
Page 2 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
1.0 Purpose
The objective is to describe the installation of Plumbing & Drainage System associated
with installation of internal pipes to ensure compliance with contract requirements,
approved shop drawing, combine and coordinated all services and structural penetration
shop drawings, material, specification and quality control.
2.0 Definitions
This Method Statement describes the work execution on the installation of pipes for
plumbing system and piping works.
2.1 Party
All M & E works (Plumbing & Drainage System) for Basement 01 & 02, Master
Ground Floor, Podium and V2 & V3 Tower will be carried out by Thang Long Fire Co.
Ltd.
This procedure establishes the instructions for the preparation and control of Inspection
and Test Plan (ITP) for field construction activities and notification to Owner’s project
management for their selected inspection point in a timely manner. The method
statement is applied to the installation of water supply pipe and sanitation equipment for
Sunrise City Project – Plot V.
Materials Standard
uPVC pipe for Soil, Waste, Vent and Drain
SS 213 & SS 272
System
PPR pipe for Cold and Hot Water Pipe System DIN 8077/8078
Cast Iron Pipe for Soil, Waste & Drain at
ASTM A74
Basement high level and transfer floor
4.0 Materials
Page 3 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
In addition, all materials have been tested and delivered with good quality and
assurance of “Top Quality in the Market” policy.
The first uPVC and HDPE pipes systems could have good performance in the field
of application as:
Drinking water, industrial process water, domestic / industrial waste water
treatment, drain water / waste water discharge, well drilling, agriculture irrigation,
aquaculture, electrical and telecom.
Aquatherm is a pipe system with many applications due to its special characteristics
and versatility.
Potable water pipe networks: for cold and hot water installations for residential
buildings, hospitals, hotels, office and school buildings etc. house connections,
boiler connections, water distribution, riser and water point connection.
This pipe system is applied in all fields of new installation, repair and
renovation.
According to DIN 1988 T2 all installation parts coming directly in contact with
potable water are commodity goods according to the Law of Food and Commodity
Goods.
All piping system and fittings system have UV stabilizer to bridge transport and
installation times. Maximum storage time in the open air is 6 months.
Page 4 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
For the application in open air Aquatherm offers composite pipes with UV-
protective layer made from polyethylene, which excludes damages caused by
sunlight.
The sound insulation qualities of the PPR Pipe system, related to water flow and
hydraulic shock within a building, provide a sound proofing effect on noise
transmission.
This pipe system complies with the requirements of the fire classification B2 DIN
4102 (normal inflammable). Compared to natural products like wood, cork or wool.
Aquatherm don’t produce any gas toxicity. To avoid fire and smoke transmission
aquatherm advises the use of fire retardant seals and the fire resistance period is the
minimum period in minutes.
PP-R pipe is connected with the welding method used in welding and electricity to
heat with. This material is applicable to both cold & hot water supply piping, fitting
for down feed line and distribution line system.
Page 5 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
This purpose is to provide instruction for the control and receipt of material,
equipment and supplies purchased, furnished or controlled by Thang Long for
Sunrise City Plot V Project.
5.2 SCOPE
5.3 RESPONSIBILITY
b) The Subcontractor shall place items in the storage areas to which they are
assigned.
c) The Subcontractor shall record each item on the material stock inventory report
and shall be submitted to KEC for monitoring.
5.4 GENERAL
5.6 RECEIVING
STORAGE
a) Storage Area
Page 6 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
3. KEC engineer shall perform the periodic inspection for storage area every
week.
5.7 MARKING
The subcontractor shall ensure that material delivered to site are neatly arranged,
packed and labeled as per item against the packing list or receipt from the
manufacturer.
5.8 METHODS
a) All items shall be stored in such a manner as to permit ready access for
inspection and maintenance without excessive handling in order to minimize risk
or damage.
b) Items stacked for storage shall be arranged so that the racks, cribbing or crates
are bearing the full weight without distortion of the item.
1. For site inspection, Thang Long Engineer shall prepare the Request for Inspection
and notify to the Engineer not less than one working day in advance for required
hold and witness point.
3. Thang Long Engineer shall follow up the inspection activities in accordance with the
“ITP”.
4. Upon completion of the work operation, the responsible Thang Long Engineer shall
review item covered by the applicable ITP to assure that the work has been
completed satisfactorily and that the ITP and all supplementary documentation is
attached and submitted to the Engineer.
5. Thang Long shall request the Engineer for visual check on site, to witness how the
PPR, uPVC and C.I. pipe are cut, heated and cooled, joined together.
Page 7 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
1. Materials
2. Shop Drawing
3. Method Statement
Rejected
Engineer's/Consultant’s Comments
Approved
Rejected
Inspection
8.0 Construction Method
Approved
Inspection
Approved
1. Pipe insulation (where applicable)
2. Pipe penetration seals
3. Fire stopping –FS One (Hiltii Brand)
4. Pipe system cleaning & flushing
Rejected
Inspection
Approved
1. Installation of equipment
2. Final connection to equipment, valves
and accessories
- Push the end of the pipe up to the welding depth into the welding tool.
Page 8 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
- After the stipulated heating times, quickly remove pipe and fitting from the
welding tool (See table 1)
- Join them immediately until the marked welding depth is covered by the
PP-R bead from the fitting.
- Before starting the fusion, check if the aluminum-PP- composite layer has
been completely remove.
- All used devices and tools must have reached the necessary operating
temperature of 260 deg. C.
Page 9 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
2) Weld in saddles
- Weld in saddles are available for pipe outer diameter of 40, 50, 63, 75,
90, 110, 125, 160, 200 and 250 mm. The maximum sensor well
diameter is specified in the following Table. 2
Page 10 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
- Drill through the pipe wall at the intended outlet point by using the
drill.
- Insert the heating tool on the concave side of the weld-in saddle tool
into the hole drilled in the pipe wall until the tool is completely in
contact with the outer wall of the pipe.
- Fusing the weld-in saddle with the pipe the outer surface and the pipe
inner wall connection reaches highest stability.
- The welding device/saddle welding tool must have reached the required
operating temperature of 260 deg. C
- Insert the heating tool on the concave side of the weld-in saddle tool
into the hole drilled in the pipe wall until the tool is completely in
contact with the outer wall of the pipe. Next the weld-in saddle tool is
inserted in to the heating sleeve until the saddle surface is up against
the convex side of the welding tool. The heating time of the elements is
generally 30 sec.
- Insert the weld-in saddle in to the heated drilled hole. Pressed and wait
for 15 sec. Wait for 10 mins. to cool before exposed to full loading.
Page 11 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 12 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 13 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
3) Butt Welding
Pipes and fittings are fused, as explained below by butt welding (pipe
dimension 160, 200, and 250 mm)
- Plastic pipes are aligned and fixed by means of the clamping elements.
- Push the pipes onto the heating place with a defined adjusting pressure.
- When heating time has expired, divide the machine slide, remove heating
element quickly and joint the pipes (by putting both parts of the slide
together).
Page 14 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
4) Repair
- In addition to this the offers the possibility of the pipe repair stick.
Page 15 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
a) Exposed pipes
Page 16 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 17 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
- After layout has been established, mark the pipe route on the brick wall
with two marked lines according to installed pipe size (follow Table 3).
Page 18 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 19 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Preparation works
The construction drawings have been approved and allowed work at the Sunrise
City.
The PP-R pipes and accessories have been reviewed and authorized for
construction at the Sunrise City Project site.
Location, the installation area has been checked and permitted by the responsible
authority.
The worker use heat welding machine has been training, inspected and certified
for welding pipe PP-R.
Welders will be tested and trained in the site. Welders through the test will be
given certificates for welding pipe PP-R at the site.
The necessary tool and equipments for connection, installations have been
prepared and checked (pipe cutter, the head, the welding machines, drilling
machines, hand tools ...). Appliances this device must be checked and sealed test
period 3 months / time).
Sanitary tools for cleaning surface connection such as (wiper, sandpaper ...).
When performing on the finishing floor to improve plastic covering and
plywood 10mm.
The wall conceal tube must mark the location and request to the responsible
authority for inspection before cutting.
Installing the rack position was marked. The racks must be zinc galvanized after
processing and testing.
Inspection works.
Page 20 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 21 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
A kind of bar hanger, rack must have approved, the location, size according to the
construction drawings approved specification, the blow bolt must be fitted and
drilling accuracy and make sure. The bar hanger, rack distance is not higher more
than the distance specified in the drawing specification. The bar hanger, rack must
be straight, bolt must be screwed and correct position. Rack should be cut drilling,
and improved before being zinc galvanized. The hole shot stopper must be round,
deep and clean. When drilling or working on a high level scaffolding must be used.
3. The general rule of space and edge distance requirement for mechanically
expanded anchors as followings:
B) Threaded Rod
Page 22 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
U BOLT
Page 23 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Specifications /Standards:
a) Cutting of pipe
Page 24 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Zero point
Stopper
Swell layer by Adhesive
Marking (0.1-0.2mm) Marking
- Ensure pipes are in correct diameter, approval material prior to start works.
Plain ends shall be inspected with special attention, as these ends are the
most susceptible to damage.
- Pipes shall not be rolled or skidded against other pipe materials. Make sure
that the pipes are free from debris and other foreign materials.
- Mark the measured length on the pipe by permanent marker pen. Cut the pipe
using a power saw or a PVC cutter. Be sure to cut the pipe squarely.
Page 25 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
- Chamfer the corners and remove all burrs by reamer, file or sand paper, clean
away dust, dirt and oils with a clean rug before applying adhesive.
- Before jointing, insert the pipe into the joint socket and confirm that the
length from zero point to the end of pipe is 1/3 to 2/3 of actual socket length.
The tube must be checked, as hygiene, dry cleaning connection, if performed on the
finishing floor must have plastic cover, plywood to avoid dust.
a) Polished top, tube edge, cleaning the surface of contact
between the tube and accessories with sandpaper smooth.
Page 26 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
c) Using a palm-tree has quick glue paste on the tube top marked and inside face
of accessory.
Page 27 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
c) Pipe installation
1) Exposed pipe
Page 28 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
2) Concealed pipes
Note: See shop drawing details for
various pipe outlet heights as per
san. fixtures supplier
recommendation.
Page 29 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
30~20 mm thk
Page 30 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
30~20 mm thk.
The pipe tested after each phase or part of the pipeline and before the pipeline
are be hidden backing up.
Hydrostatic drainage system test for each section by dividing the system
horizontally (estimated per 3 floors)
Fitting the test plug on the mounting block top of a pipe tested.
Testing is done by filling of clean water into the pipes up to the highest level.
Mark and check the water level after the period stipulated within 24 hours.
Check and record the water level after 24 hours, inform to the consultants, client
will check and sign on the inspection report if no detected leakage.
Page 31 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
A) P-TYPE CLAMP
Page 32 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
UR50 125 5” 10 12 32 48
UR60 150 6” 10 12 32 48
UR80 200 8” 10 12 32 48
UR100 250 10” 10 12 50 48
UR120 300 12” 16.1 16 50 75
a) Cutting of Pipe
- All cutting must be done in warehouse or in designated areas of each floor. All
cutting must not be done at work area.
- Pipe shall be cut by power hacksaw, circular cutting machine with abrasive
wheel, hand hacksaw or square end sawing vice only.
b) Coupling Joint
Page 33 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
- Push the supplied complete connector on to the pipe end right up to the
middle spacing ring of the seal.
- Install the next pipe or formed part flush with the spacing ring and fold
back the turned over half of the collar.
Page 34 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
- Alternatively tighten the two clamping screw uniformly and hard tight.
The guiding and threaded plates of the clamp must come together parallel
to avoid any deformations.
- Push the supplied complete connector on to the pipe end right up to the
middle spacing ring of the seal.
- Push the pipe end from the other end into the connector.
-
- Firmly tighten the hexagon socket screw with a socket spanner, hard
ratchet or impact screwdriver, if possible to the point where the two
clamping jaws come together.
Page 35 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 36 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 37 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Grade
ANSI B18.2.2 ¼” ~ 1” 2 or 5
BS 916 ¼” ~ 1” 2 or 5
AS/NZA 2451 ¼” ~ 1” 2 or 5
TC Bolt
Shear Stud
Page 38 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Page 39 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
b) Material.
- uPVC & PPR Pipes
- Latch
- Soft material for opening.
c) Line marking
- Use ruling pen marking 2 points for center line of cutting line: 1
point at higher level and 1 point at lower level.
- Use line marking tool in making center line for pipes.
- Offset from center to right and left of center line 30mm.
- Mark 2 lines for trench of pipe (Lines No.2, No.3)
- Base on reference level, mark high level and low level of trench.
Page 40 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
d) Cutting wall.
- Check cutting machine and other equipments.
- Cut brick wall follow to line mark No.2, 3, 4, 5.
- Chip brick wall inside marking area.
- Clean area before continuing the works.
Page 41 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
2. INSTALLATION:
- Cut the pipe as per approved dimension and with shop drawing.
- Install the pipe inside the wall.
- Use spring wind tape to check and adjust dimension as per shop
drawing dimension.
- Use latchs to fix the pipe to the wall.
(refer to below figure)
- Install soft blocks at the end of pipe to make opening after civil
contractor render the wall.
(refer to below figure)
3. INSPECTION:
a. Dimensions:
- Distance from existing wall (or reference groove) to center of
pipe: at high level and low level point.
- Check level of soft block for above opening.
- Check level of soft block for below opening.
b. Visual check:
- Solidify of pipe fixing.
- Seal pipes to ensure that binder can’t filled inside the pipe when
plastering.
c. Other requirements:
- Inside the pipe must be cleaned before installation.
- To ensure don’t have crippling strain of G.I pipe after fixing.
Test Method and Test Plan, Test Record Forms, Inspection Forms
1. Test Method
Scope of Testing
Page 42 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
Cold and Hot water pipe Pipe leakage test ( by The pressure drop shall
water,100 psi 2 hours) not drop more than 5%
Not less than 12.5 bar or one (See specs. Section
and a half times the maximum 13.3)
pressure whichever is greater.
(See specs. Section 13.3)
Soil, Waste, Vent and Water filling test ( by water ) Water level will not
Drainage pipe (Fill with water to top of change.
highest part of install area, 24
hours )
- Two (2) water pressure gauges shall be installed at the test point of the pipe for
monitoring the test pressure in the pipe. Range of pressure gauge shall be follow
as,
b) 0 bar ~ 15 bar: Hot Water Supply system, Plumbing and Sanitary Fixtures,
Water Supply system.
Step 2 - Use the Manual hand pump to increase the pressure to the final test
pressure required by checking on the pressure gauges.
The test duration is at least (24) hours, the pressure drop shall not drop more
than 5% (See specs. Section 13.3)
Page 43 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
-Water filling test shall be applied to Soil, Waste, Vent and drainage pipe.
-Water filling test shall be done for floor by floor after pipe installation is finish.
- Before water filling test, all bends, changes in direction, ends of runs and all other
openings should be plugged or capped with test plugs or tests caps.
- Isolate each floor or section being tested by inserting tests plugs through test tees
installed in the stacks.
- Once the stack is filled with water to 2000 mm, an inspector makes a visual
inspection of the section being tested to check for leaks.
- Record the interval between pipe edge and water surface and water level shall be
marked on pipe surface. 24 hours or longer later, check interval change by visual
check. The change water level shall not be approved.
- Once the system has been successfully tested, it should be drained and the next
section should be prepared for test.
- Testing of drainage system shall be carried out in sections by dividing the system
horizontally. Each section shall comprise pipe works and fittings for three (3)
floors required for testing.
Test reports shall be prepared and filed. Copies of test reports shall be submitted as
required. See Appendix for ITP Form – Cold and Hot Water Pipe – Hydraulic Leak
Test and Soil/Waste/Vent/Drainage Pipe – Leakage Test (Water filling).
Thang Long shall carry out its works in the safest manner possible. Job hazard analyses
shall be prepared and approved prior to setting out with specific tasks to perform. The
health of the workers shall be a paramount concern of the Company.
Safety Measures
General
Safety shall be in first priority during construction, safety staff shall be present on
site at all times to supervise and to remind workers to observe safety requirements.
Stop work order shall enforce once it does not meet the safety requirement.
Page 44 of 45
METHOD STATEMENT
THANH LONG FIRE for Plumbing and Drainage SUNRISE CITY
CO. LTD. Piping Installation Works PLOT V PROJECT
The labor force doing the installation work shall have undergone safety orientation
and shall have been familiarized with the procedures related to their work
Safety shall be strictly observed. All safety equipment such as clothes, shoes,
helmet, gloves, safety belt will be provided and regularly check during construction.
Kumho Engineer shall inspect all Sub-contractor’s tools prior to be use on site.
Kumho Engineer shall be present for all the safety site inspection.
Equipment intended for use shall have been inspected and tagged “Safe for Use”.
Installed hangers and supports should be inspected first and be approved before
installation of pipe.
11.0 Appendix