Notes:
During testing all cables and wiring must be completely disconnected from any equipment.
Screens shall be checked as common conductors.
Insulation test:
1. Between signal wires
2. Each core to ground
Continuity/point to wire check (with low voltage tester)
Check correct installation of cable glands
Check cable identification tags
Check that cables, wiring, ducting, trays and fittings are complete and secured
Isolation test-shield/armoring to ground
Remarks:
C:\RB_Forms\RB26K15.DOT\ www.red-bag.com