PCCP DATA SUMMARY (ROAD PROJECTS)

CAGUIBA 7,238.00 m2 60.00 434,280.00 1,080.30 lm


ACCOMPLISHMENT
DATE Length width Area (m2)
6-Apr 72.00 lm 3.35 241.20
13-Apr 60.00 lm 3.35 201.00
18-Apr 81.00 lm 3.35 271.35
23-Apr 82.50 lm 3.35 276.38
26-Apr 81.00 lm 3.35 271.35
1-May 87.00 lm 3.35 291.45
3-May 65.00 lm 3.35 217.75
7-May 90.00 lm 3.35 301.50
widening 7-May 30.00 lm 0.50 15.00
10-May 91.50 lm 3.35 306.53
11-May 33.00 lm 3.35 110.55
17-May 93.00 lm 3.35 311.55
22-May 100.50 lm 3.35 336.68
26-May 82.00 lm 3.35 274.70
28-May 90.00 lm 3.35 301.50
1-Jun 91.50 lm 3.35 306.53
13-Jun 93.00 lm 3.35 311.55
19-Jun 69.00 lm 3.35 231.15
1,362.00 4,577.70 percent accomplishment 63.25%

SAN RAMON 9,150.00 m2 60.00 549,000.00 1,500.00 lm


ACCOMPLISHMENT
DATE Length width Area (m2)
20-Mar 99.00 lm 3.05 301.95
27-Mar 40.50 lm 3.05 123.53
3-Apr 76.50 lm 3.05 233.33
7-Apr 72.00 lm 3.05 219.60
9-Apr 76.50 lm 3.05 233.33
12-Apr 99.00 lm 3.05 301.95
17-Apr 58.50 lm 3.05 178.43
19-Apr 85.50 lm 3.05 260.78
21-Apr 99.00 lm 3.05 301.95
24-Apr 54.00 lm 3.05 164.70
27-Apr 117.00 lm 3.05 356.85
2-May 121.50 lm 3.05 370.58
4-May 99.00 lm 3.05 301.95
9-May 144.00 lm 3.05 439.20
12-May 68.00 lm 3.05 207.40
16-May 123.00 lm 3.05 375.15
18-May 46.50 lm 3.05 141.83
21-May 112.50 lm 3.05 343.13
23-May 63.00 lm 3.05 192.15
11-Jun 67.50 lm 3.05 205.88
11-Jun 27.00 lm 3.05 82.35
13-Jun 27.00 lm 3.05 82.35
21-Jun 61.50 lm 3.05 187.58
26-Jun 31.50 lm 3.05 96.08
1,869.50 5,701.98 percent accomplishment 62.32%
ILAWOD 8,915.00 m2 60.00 534,900.00 1,330.60 lm
ACCOMPLISHMENT
DATE Length width Area (m2)
16-Apr 58.50 lm 3.35 195.98 Left Side
17-Apr 45.00 lm 3.35 150.75 Left Side
20-Apr 58.50 lm 3.35 195.98 Right Side
25-Apr 117.00 lm 3.35 391.95 Left Side
30-Apr 135.00 lm 3.35 452.25 Right Side
5-May 36.00 lm 3.35 120.60 Left Side
8-May 81.00 lm 3.35 271.35 Left Side
11-May 58.50 lm 3.35 195.98 Right Side
12-May 1.50 lm 3.35 5.03 Right Side
12-May 49.50 lm 3.35 165.83 Left Side
18-May 37.50 lm 3.35 125.63 Right Side
19-May 61.50 lm 3.35 206.03 Left Side
23-May 55.50 lm 3.35 185.93 Right Side
24-May 6.00 lm 3.35 20.10 Right Side
24-May 49.50 lm 3.35 165.83 Right Side
25-May 63.00 lm 3.35 211.05 Right Side
26-May 4.50 lm 3.35 15.08 Right Side
2-Jun 124.50 lm 3.35 417.08 Left Side
4-Jun 72.00 lm 3.35 241.20 Right Side
5-Jun 33.00 lm 3.35 110.55 Right Side
6-Jun 55.50 lm 3.35 185.93 Left Side
9-Jun 28.50 lm 3.35 95.48 Right Side
12-Jun 27.00 lm 3.35 90.45 Right Side
12-Jun 63.00 lm 3.35 211.05 Left Side
13-Jun 31.50 lm 3.35 105.53 Right Side
15-Jun 72.00 lm 3.35 241.20 Left Side
22-Jun 67.50 lm 3.35 226.13 Right Side
22-Jun 54.00 lm 3.35 180.90 Left Side

1,546.50 5,180.78 percent accomplishment 58.11%