Professional Documents
Culture Documents
Facility Layout Eqpt & Piping PDF
Facility Layout Eqpt & Piping PDF
Equipment and Piping arrangements During the planning stages, the Piping
cannot be segregated to have different Engineer could meet with simple ideas
approaches since the requirements of that can effect substantial cost savings. Let
equipment and piping layout design often us take a practical example to it.
overlap. In a chemical process industry, a waste
Equipment is arranged in the process heat boiler had to be installed at the
flow sequence in plan and elevation and exhaust of a diesel engine to recover the
piping is laid to effect the process flow. It waste heat. The job was awarded to a
is very appropriate to say that the Consulting Engineering organization on a
Equipment and Piping layout design is an turnkey basis. The design activities took
ART and not a SCIENCE. There is not a the following sequence.
single formula available for the design of The process group worked out the
Equipment and Piping layout. The required parameters, did the process
equipment layout design can be as rational design of the heat exchanger and issued
as the mathematics of fluid flow but with Process Data Sheet (PDS) to the
the language of projective geometry. Fabricated Equipment Group (FEG), who
Mathematics is abstract; geometry is did the mechanical design and issued the
visual. All engineering courses have drawing to the Piping Group. Piping
mathematics; few have the subject of Group located the heat exchanger and
projective geometry but none has layout designed the inlet piping and also did the
design. However, systematic methods and flexibility analysis of the same piping as it
procedures can be developed from is subjected to high temperature. To save
engineering principles, specifications, the equipment, an anchor was placed near
practical engineering knowhow, and just the inlet nozzle with an expansion bellow.
SIMPLE COMMON SENSE. All this The data of the anchor loading was passed
should be coupled with the capacity to on the Structural Group, who designed a
visualize the arrangement of equipment braced structure to take care of this. The
and piping three dimensionally. The total cost became prohibitive. At this
design must take constructibility, point, a suggestion was made to turn the
economics, safety, quality and operation waste heat boiler upside down and thus
into account. All these should be achieved eliminating the heavy structure. The final
within the shortest schedule and will design turned out to be simple, cost
demonstrate the technical capacity along effective and occupied less space. (Refer
with creative talent and common sense Fig. 1.1a, 1.1b)
approach to problem solving. Although the
tools to achieve these goals have changed
from pencil and paper to computer
graphics, the responsibilities of the Piping
Engineer remains the same.
operating levels and lifting beam for the required for personal facilities. These are
agitators. Utility equipment is normally worked out in co-ordination with
housed together for operating Electrical, Instrument and Civil/Structural
convenience. Process compressors under groups.
one roof are a frequent requirement.
Pumps in a row can facilitate better rack 2.2.4 GUIDELINES – PROJECT
layout, cable arrangement and ENGINEERING SPECIFICATION (PES)
maintenance accessibility GENERAL EGINEERING
c) Functional equipment grouping SPECIFICATION (GES)
Cost of alloy steel/stainless steel piping Layout guidelines for major
initiates a compact arrangement of equipment are based on minimum distance
equipment. Bolting condensers on top of required between various types of
distillation column as a part of the same, equipment to meet the insurance
stacking heat exchangers one above the regulations. They are designed to help
other are some examples. Reactors are prevent major catastrophes, especially
arranged in a row, which need crane or when highly inflammable chemicals are
trolley for removing equipment internals involved. These guidelines, while useful,
and for material handling. Equipment often include ambiguous entries such as
containing acids or toxic materials is “provide spacing based on access for
grouped and located within a paved and operation and maintenance”, “as
curbed area which will have the facility to required”, and “not applicable” etc. Hence
drain out the effluent to the treatment plant following these guidelines only could still
or for neutralizing it. The building sizes in result in crowded plant if not handled
an outdoor plant include the MCC room, carefully. The solution is to study each
control room, laboratories and space
piece of equipment to determine the needs for the minimum distances between
of operation and maintenance. This, foundations, escape routes etc and issued
however, is an extremely time consuming as guidelines under General Engineering
activity, and is quite possible to be Specification (GES) for plant layout.
overlooked or not accounted for certain Some of the published data in this respect
specific need. As a result, plant layout are
becomes a subjective topic, left to an a) PIP Standsrds.
experienced Piping Engineer/Layout b) SABIC Standards.
Designer. c) OISD Standards.
For executing the major projects, d) OSHA Standards
certain guidelines specific to the layout of General guide lines for equipment
the equipment covered therein will be minimum spacing could be as given in the
drawn. These are used under the title Table. Companies dealing in Layout
Project Engineering Specification (PES). design also develop their own standards to
meet these guidelines.
Certain Consulting Engineering companies
dealing in layout also establish guideline
2.2.3. Air coolers can be placed over the for sprinklers above the pumps. This type
pipe rack while those at the ground will of layout is the most economical and
increase the ground coverage. When thousands of petrochemical plants are built
pumps are lined up under the pipe rack all over the world using this principle.
with central access and air coolers placed
above, the insurance requirement may ask
When pumps are placed outside the rack In a building, mobile platforms can
that will increase the distance between the be used extensively but it is not practicable
pipe rack and process equipment resulting outdoors. Hence permanent local
in additional pipe length. This platforms are more common in outdoor
arrangement is shown in Fig. 2.2.3. plants. Mobile cranes can be used in
The one sided arrangement as outdoor for maintenance. In indoor, tube
shown in Fig. 2.2.4 and 2.2.5 are more pulling area for exchangers is to be built
expensive, since only one side of the area in. Building will be costly if this facility is
is used to locate the process equipments. to be included. Or else, the exchanger will
However, if only a narrow area is have to be shifted to workshop for
available and or if expansion is to be taken cleaning which again will need more time
up in future, these arrangements give and hence cost. Removal of large vessels,
optimum solution. glass lined kettles etc., will need space
The control room and furnaces are above or below and also access aisle to
placed outside the main process area, outside with adequate clearance. Lifting
keeping the required safe distances. beams and/or HOT/EOT cranes located
Auxiliary pipe rack is required to run with negligible initial cost can make
cables to control room and piping from substantial savings in future maintenance
furnace to process area. Safety distance cost.
and maximum allowable length of transfer Typical in house vertical
line influence the furnace location. arrangement is shown in Fig. 2.2.6.
The basic principle to be
remembered while locating equipments in
all these cases is to eliminate, combine
and minimize structures to achieve cost
savings.
enter and leave on three sides of the plant. influences the width of the rack. The
Fig. 2.3.5 shows a ‘U’ or ‘C’ – shaped arrangements adopted are:
yard. Lines can enter and leave at all four a) Single column rack ‘T’ type
sides of the plant. Fig.2.3.6 shows a b) Double column rack with a single tier
combination of the ‘L’ and ‘T’ – shaped (Goal Post).
yard. Lines enter and leave similar to that c) Double column rack with a double tier
shown in Fig. 2.3.2. Fig. 2.3.7 shows
complex yard piping for a very large plant. These are illustrated in Fig. 2.3.8.
This layout can be considered as a
combination of many simpler yard piping
arrangements.
Of course, the configuration of pipe
rack is not determined while doing the
plant layout. The arrangement results from
an overall plant layout, site conditions,
client requirements and above all plant
economy.
The pipelines on the rack are classified
as process lines, relief line headers and
utility lines. The rack should
accommodate the electrical and instrument
cable trays as well. The width of the pipe
rack is estimated without the preparation
of a line routing diagram as
W = (f x n x s) + A + B
Where
f = Safety factor
= 1.5 if pipes are counted from the PFD
= 1.2 if pipes are counted from P & ID.
n = Number of lines in the densest area
up to the size of 450NB
s = 300mm (estimated average spacing)
=225mm(if lines are smaller than
250NB)
A = Additional width for
(1) Lines larger than 450 NB Depending upon the type of plant the rack
(2) For instrument cable tray/duct could be of steel, concrete or a
(3) For electrical cable tray combination of both. The spacing between
B = Future provision the bent/column of the pipe rack is
= 20% of (f x n x s) + A normally 5 to 6 meters. Wide spacing is
Normally pipe rack width is limited to 6M. necessary at road crossings or where
If the width worked out thus is more, then loading and access space are needed. The
the arrangement to be done in multiple headroom clearance also depends upon
layers. The space requirements of the type of crossings.
equipment along with the access below
The headroom normally provided is as are mainly used to run large diameter
below: piping such as off-site piping. Another
Sr. Description Head room way to run the yard piping is in open
No. (mm) trenches with the arrangement same as that
1. Clear headroom under 2200 of a single tier rack. The road crossings are
Structures/pipe lines done by culverts. Water logging in the
inside operating area. trenches and draining of the same are
2. Head room over rail 7000 major problems to be handled in this case.
(from top of rails)
3. Clear headroom above 7000
crest of road for crane
movement.
4. Clear headroom above 6000
crest of road for truck
movement.
5. Clear headroom above 4500
crest of road between
process units.
A typical arrangement of yard piping is
illustrated in Fig. 2.3.9.
placed on the top level of the pipe rack. be located along the external face of the
The line that requires the largest expansion column or on the centerline of the same.
loop leg must be located on the outside. If hydrocarbons are prevalent in the
The loop shall be arranged with the plant, it is a common practice to fireproof
portion of the loop getting elevated from the columns just below the lower support
0
the rack level by two 90 elbows.This will rack support beam. If air coolers or any
allow the straight run of other lines on the other equipment is located above the pipe
rack, the fireproofing is extended up to the
equipment support beams (see Fig.
2.3.14). Fireproofing is done on the rack
columns by covering these by Plain
Cement Concrete (PCC).
the process equipments away. arranging the same on the piping. Process
(Refer Fig. 2.3.16) isolation valves should be readily
accessible, the valve-stem centerline being
at an elevation of 1200 - 1500 mm from
the operating level. If at elevated level,
they can have chain operators. Valves
located at low or high locations can have
extended stems to reach the access aisles.
One thing must be ensured that the stem
will not be oriented below horizontal
level. (Fig. 2.3.18)
Fig 2.3.20
Fig 2.3.19
Fig 2.3.21a
d) Isolation valves for level gauges and more than the valve inlet size.
pressure gauges shall be made accessible. ii) The inlet nozzle can be
Access and space for the removal of level reinforced.
controllers temperature probes d) The inlet line for liquid service shall
,conductivity probes,bottom flanges of the never run dry. Formation of bubble at inlet
control values etc shall be provided. All shall be avoided.
primary and secondary indicators of e) Supporting arrangement shall be such
pressure, temperature, flow, level, that the piping should not vibrate while the
positioners etc. should be visible from the valve is discharging.
operating area. f) Gas/Vapour discharge line should be
e) Rotameter shall be placed on vertical kept atleast 3M above the nearby platform.
line and the inlet should be from the g) Liquid discharge line shall be routed to
bottom of the instrument. facilitate draining the system.
f) Thermowell shall be located on the pipe h) A weep hole shall be provided for the
line of required size. Instrument hook-up vapour discharge line.
drawing shall be referred for the
requirement. 2.3.7 RUPTURE DISC PIPING
g) Enough operating and maintenance a) Rupture Disc shall be installed
access shall be considered while locating at the direct vicinity of the system to be
any instrument. protected.
b) Discharge piping should be kept
2.3.6 SAFETY VALVE PIPING as short as possible to ensure safe
Safety valve is defined as automatic discharge of the fluid.
pressure relieving device actuated by the c) If rupture disc is of graphite,
static pressure upstream of the valve and trap shall be installed downstream to
characterized by full opening pop action. It collect the broken pieces.
is used for gas or vapour service. d) It will be ideal to integrate the
Relief valve is defined as an automatic rupture disc into vertical lines with flow
pressure retieving device actuated by the from the bottom.
static pressure upstream of the valve
which opens further with the increase in 2.3.8 MISCELLANEOUS
pressure over the opening pressure. It is Space requirement of HVAC ducting,
used primarily for liquid service. where applicable, shall be integrated into
Safety Relief Valve is an automatic the layout at the stage of development.
pressure actuated relieving device suitable The equipment for these will be housed
for use either as Safety Valve or Relief separately and should include in the
Valve depending on application. overall plot plan. The dimensional
a) SRV shall be installed in upright requirements of ladders, stairways,
position and directly attached to piping trenches, platforms etc. are to be
system or equipment to be protected. considered while making equipment
b) Depending on the service the system arrangement and planning access to valves
can be open discharge or closed discharge. and instruments.
c) The installation should be such as to
keep the piping force to the minimum. To
reduce the force/stress in the inlet line;
i) The inlet line should be kept
Fig. 2.3.24
the edge of the yard, with orifice flanges d)Has adequate maintenance access
near a rack column for access, with a provided?
portable ladder. Orifice runs after pumps e)How to evacuate in case of emergency?
can be located near supporting column at f)Has safe fire fighting access provided?
2.5 m level. Control valves are usually g)Standard practices where applicable has
located near rack columns for convenience been adopted?
in supporting. h)Is the piping arrangement aesthetic ?
Keeping dimensions B and C to the i)Is supporting arrangement adequate and
lowest required levels will minimize the aesthetic ?
length of pipe between rack and process j) Is piping adequately flexible ?
equipment and for connecting equipment
on opposite sides of rack. The dimensions 3.0 TYPICAL ANALYSIS
D and E at not more than the required yard
height will reduce the vertical pipe runs. With the general principles and
However, the distance E is kept 1 to 1.5 m requirements as described above, we will
to have a proper erection and maintenance analyze the layout and piping design of
access and depends on the size of the pipe specific equipment deployed in
at the lower tier. chemical/petrochemical process plants.
Based on the suction and discharge drive or stroke adjustments is used. The
arrangement the type of pumps available alternating action of reciprocating pumps
are produces pulsation in flow. The extent and
(a) end suction top discharge frequency of pulsation depends on the
(b) top suction top discharge number of cylinders in parallel and
(c) side suction side discharge. whether they are single or double acting.
Due to pulsating operations, these pumps
The end suction top discharge pump has are bulky, but are considered for very low
vertically split casing and the end suction flow applications. The pumps could be
end discharge pump has horizontally split single acting with single piston plunger
casing. Vertically split casing has good with very high pulsating flow. The
maintenance access. They are normally the variation in cylinder arrangements gives
back pull out design, which facilitates the single, duplex, triplex and quadruplex
removal of impeller without affecting the pumps. The diaphragm pumps are
piping connections. Pumps will be compact and deliver precise quantities of
mounted on a base plate with the motor, fluid.
keeping the motor shaft and pump shaft The positive displacements pumps are not
carefully aligned. This base plate will be suitable for pumping slurry and are not
grouted on to a concrete foundation. The suitable for abrasive services.
size of this foundation will be
approximately 500 x 1500 mm or can vary 3.1.1. EQUIPMENT LAYOUT
up to 2500 mm long in case of large
pumps. The design of equipment and piping
Large capacity water pumps usually have configuration affect the energy used and
horizontally split casing. Inlet and outlet capital cost of pumps. Hence, economy of
are horizontal at right angles to the pump piping and structures along with ease of
shaft. Suction piping should be short and operation and maintenance are the
straight with one or two expansion joints. principal aim while arranging the pumps.
Inline pumps are compact and mounted Pumps are placed close to process vessels.
along the pipeline even overhead. Large Number of pumps should be lined up and
inline pumps may need separate support. aesthetically well arranged. Pumps are
Vertical shaft pumps occupy less area but
needs head room for removal.
The positive displacement pumps can be
rotary or reciprocating type. The rotary
pumps work with forced volume
displacement and can deliver constant
pulsation free flow against higher head
than the centrifugal pumps. The layout and
piping design do not differ from that of
centrifugal pumps.
Reciprocating pumps are used where very
high head is needed for a low flow. Here
the discharge cannot be throttled to obtain
capacity control as in the case of Fig. 3.1.1a
centrifugal pumps. Instead, variable speed
Fig. 3.1.1b
arranged under the pipe rack in a refinery
or an outdoor process plant, keeping motor
end towards the access space and
suction/discharge faces towards the Fig. 3.1.3
process vessels (Refer Fig. 3.1.1). Single
pump should have access all around, a For safety and operators' convenience,
minimum of 900mm. When space is pumps for tanks containing
restricted, or the pumps are small, two inflammable/corrosive liquids should be
pumps can be placed on common located outside the dykes. (Refer
foundations with the orientation of the Fig.3.1.3)
motor terminal modified if required.
(Refer Fig. 3.1.2) 3.1.2 PIPING ARRANGEMENT
The primary goal in piping
arrangement is to satisfy the performance
and the flexibility requirements. Suction
piping should be designed without loops
or pockets. The eccentric reducers are
placed close to the suction nozzle either
FSU or FSD depending on the line
configuration (Refer Fig. 3.1.4). These
lines shall be drainable near the pumps.
The suction line is generally one or two
sizes larger than the pump suction nozzle
for centrifugal pumps. NPSH requirement
has to be checked while locating the
pumps and routing the suction lines.
Accordingly saturated liquid, steam
condensate and vacuum conditions need
elevated suction vessels. The horizontal
Fig. 3.1.2 runs should be kept minimum in all
suction piping. The thermal expansion
requirement should be taken care of in
such a way that the pump nozzles are not
loaded. The suction as well as the
discharge piping shall be supported
adequate enough not to impose excess
FIG. 3.1.4a
FIG. 3.1.4b
The following alterations can be suggested b) Angular nozzle can save one or two
in order to achieve an optimum piping bends in the pipeline. The maximum angle
arrangement. Consent from the process from the vertical centre line can be about
0
group is required to ensure that these will 30 . (Refer Fig. 3.3.4)
not affect the thermal design of the
exchanger. The cost increase in
modification can be more than offset by
the cost effective piping. These factors
influence the decision on piping routing as
well.
a) Elbow nozzle permits lowering of heat
exchanger to grade to have better
accessibility to valves and instruments.
(Refer Fig. 3.3.3)
Fig. 3.3.4a
FIG.3.3.4b
heat loss and/or avoid use of thicker shell ii) If high pressure fluid flows on the tube
insulation. side, only tubes, tube sheets, channels and
covers have to be designed for high
pressure. This reduces shell side thickness result in easier tube bundle removal and
and the cost. cleaning.
iii) Corrosive liquid should pass through v) Shell side volume is much more than
the tube so that only the tubes and the the tube side and hence vaporization or
channels have to be made of corrosion condensation of free flowing fluid is more
resistant material. effective in shell.
iv) If one medium is dirty and the other is
clean, passing clean through the shell will
vi) When hazardous chemicals are water through the operating floors with the
cooled, the water is passed through the manholes located at accessible levels.
shell. The tube leakage will contaminate Space for utility manifolds and process
the cooling water. On the other hand, the inlet manifolds, if required, shall be
shell leakage can vent process material to provided for in the layout.
the atmosphere.
Simplifying the flow path to improve the 3.4.3 Storage vessels and tanks can be in
piping design is illustrated in Fig. 3.3.5. two categories:
a) Intermediate storage, generally located
3.4 Process And Storage Vessels adjacent to process units or buildings.
The basic set of information required and
for the equipment and piping arrangement b) Feed chemical, solvent or product
for the process and storage vessel does not tanks remotely located, the area being
differ from those of other equipment. identified as tank farm with its dyking
Design methods and conceptual details and acid proofing requirements.
also differ very little. The process vessels
can be classified, based on their function, These tanks are conical roof
as follows: atmospheric storage tanks to store bulk
chemicals. If the storage demands high
3.4.1 a) Surge volume to hold liquid for pressure, these are designed as horizontal
a specific length of time and bullets or spheres. The relevant statutory
b) Liquid-vapor separation, or requirements govern the layout of these
separation of immiscible liquids storage tanks. These aspects are already
with different specific gravities. covered in the ‘Development of Plot Plan’.
This category include reflux drums,
surge drums, process liquid collection 3.4.4 PIPING ARRANGEMENT
drums, drums for additives, decanters, The piping associated with these
steam flash and condensate collection vessels is simple. Economy of piping and
drums; caustics and acids holding drums access to valves and instruments depend
etc. These could be horizontal or vertical. on well-oriented nozzles. The nozzle and
support orientation can be evaluated as
3.4.2 Drums are with internals, often below. (Refer Fig. 3.4.1)
agitators, for mixing operations. These can a) Inlet/outlet nozzles
be simple reactors with agitators of Vapor/liquid inlet is placed on top at
required type or with cooling/heating one end. Bottom inlet is also possible but
coils, limpet or jacket. The material of with a standpipe. Outlet is placed at the
construction can vary from carbon steel, bottom on the other end. The bottom inlet
stainless steel and glass lined. These is provided in case of large diameter
reactors are normally vertical. piping to save pipe and fittings. In some
These vessels are located in a process cases, the inlet and outlet are centrally
flow sequence. The area required around located. The vapor outlet in this case shall
reactors is much more compared to other be diametrically opposite to liquid inlet.
process vessels.
The manual loading of these, if b) Vents and Drains
required, also shall be facilitated. Hence Vent nozzles are located at the top and
these reactors will be located passing drain at the bottom of the other end.
bellows or hoses. Such equipments are envisaged and detailed in the P&I
centrifuges, filters, dryers etc. In all these Diagrams.
cases, interaction with the manufacturers The structural arrangement for support
of equipment will always yield positive also contributes a considerable part in the
results. economy of installation. Certain
While detailing the layout and piping, it economical arrangement of support is
should always be borne in mind that this illustrated in Fig. 3.4.2 to 3.4.5, which are
should achieve the best performance as self-explanatory.
Fig. 3.4.4
*********