Professional Documents
Culture Documents
Reference Rate PDF
Reference Rate PDF
CONTENTS
Addenda No.2
Page 1/1 19-02-2008
BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
2.2.1 Buildings
a) Brickwork buildings
i) Single storey
Plan area : less than 100m 2 m2 25.00
100 - 200m2 m2 25.00
exceeding 200m 2 m2 25.00
b) Concrete buildings
i) Single storey
Plan area : less than 100m 2 m2 40.00
c) Timber buildings
i) Single storey
Plan area : less than 100m 2 m2 15.00
100 - 200m2 m2 15.00
* Haulage subject to negotiation
a) Fences m 5.00
d) Guardrails m 10.00
Addenda No. 2
BQ 2 - 1/2 19-02-2008
BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
f) Stall No 100.00
i) Gabion m2 25.00
j) Mark, cut, break up and remove existing pavement including disposal off
site to Contractor's dump site. m2 6.00
a) Guardrails m 8.00
Addenda No. 2
BQ 2 - 2/2 19-02-2008
BILL NO. 3 - EARTHWORKS
3.1.1 Stripping topsoil average depth 150mm and dispose to Contractor's dump
site as approved by the S.O/P.D*. m2 1.00
3.1.2 Stripping topsoil average depth 150mm and stockpile for reuse. m2 0.90
3.3.3 Rock excavation by open blasting and dispose to Contractor's dump site as
approved by S.O./P.D*. m3 20.00
3.3.4 Rock excavation by control blasting and dispose to Contractor's dump site
as approved by S.O./P.D*. m3 30.00
Addenda No.2
BQ 3 - 1/2 19-02-2008
BILL NO. 3 - EARTHWORKS
3.7.1 Carry out compaction test to verify the degree of compaction by using sand
replacement method or other approved method by S.O/P.D*. No 20.00
Addenda No.2
BQ 3 - 2/2 19-02-2008
BILL NO 4 - DRAINAGE WORKS
ITEM RATE
DESCRIPTION OF WORKS UNIT
NO. (RM)
4.1 CULVERT
Supply and lay box culvert and flat lid including joint.
Addenda No.2
BQ 4 - 1/1 19-02-2008
BILL NO. 6 - ROAD FURNITURE
ITEM RATE
DESCRIPTION OF WORKS UNIT
NO. (RM)
6.1 SIGNBOARDS
6.2.1 Guardrails
a) Single mounted corrugated steel beam guardrail inclusive of delineators.
ii) 1.95m post spacing m 180.00
b) Guardrail Ends
i) Type 1 No 135.00
ii) Type 2 No 756.00
iii) Type 3 No 773.00
Addenda No. 2
BQ 6 - 1/2 19-02-2008
BILL NO. 6 - ROAD FURNITURE
ITEM RATE
DESCRIPTION OF WORKS UNIT
NO. (RM)
6.6 DELINEATORS
Addenda No. 2
BQ 6 - 2/2 19-02-2008
BILL NO. 7 – GEOTECHNICAL WORKS
ITEM RATE
DESCRIPTION OF WORK UNIT
NO. (RM)
7.2 INSTRUMENTATION
7.3.1.2 350mm x 150mm cast-in-situ mass concrete grade 20 levelling pad. m 30.00
7.3.2.1 225mm thick grouted stone pitching including all necessary excavation
works at both inlet and outlet of culverts as show in the drawing. m2 65.00
7.3.2.2 100mm diameter PVC pipe weep holes at 3000mm c/c inclusive of
approved drainage materials around weep holes. m 20.00
7.4.1 150mm diameter Perforated UPVC pipe wrapped with geotextile fabric. m 40.00
Addenda No.2
BQ7 - 1/1 19-02-2008
BILL NO. 8 STRUCTURE
ITEM RATE
DESCRIPTION UNIT
NO. (RM)
8.1B SUBSTRUCTURE
8.1B.1 300mm thick PVC Coated Wire Mesh Gabion mattress forming slopes and
berms as shown in the Drawing. m2 60.00
8.1B.2 G.I handrailing and 300mm thk x 1000mm width grouted stone pitching steps
at abutment for inspection purposes as shown in the Drawing. m 150.00
8.1B.3 1.0m x 1.0m x 1.0m PVC coated wire mesh rock filled gabion. No 200.00
8.1B.4 200mm thick permeable layer comprising of 20mm - 40mm crushed stones.
m2 15.00
8.1B.7 Formwork
i) Class F1 for buried surfaces. m2 32.00
ii) Class F2 for exposed surfaces. m2 35.00
iii) Class F3 m2 40.00
iv) Permanent formwork at soffit of deck slab m2 55.00
8.1B.11 75mm Diameter UPVC pipe wrapped with filter cloth m 10.00
8.1B.12 100mm Diameter PVC porous pipe wrapped around with filter cloth m 50.00
Addenda No.2
BQ 8.1B - 1/3 19-02-2008
BILL NO. 8 STRUCTURE
ITEM RATE
DESCRIPTION UNIT
NO. (RM)
8.1B.13 150mm dia. Perforated UPVC pipe wrapped with geotextile fabric. m 40.00
8.1B.14 20mm dia ms dowel bars galvanised for expansiopn joint No 25.00
Addenda No.2
BQ 8.1B - 2/3 19-02-2008
BILL NO. 8 STRUCTURE
ITEM RATE
DESCRIPTION UNIT
NO. (RM)
8.1D.3.1 Supply and install 25mm diameter high yield steel galvanised dowel bars,
450mm long with rubber dowel caps as per details. No 35.00
i) One layer primer ans two layers of top coat inclusive of surface preparation
to all exposed surfaces of beams, diaphragm and parapets m2 30.00
ii) One layer of primer and two layers of top coat inclusive of surface
preparation to all exposed surfaces of abutments and piers above water. m2 25.00
Addenda No.2
BQ 8.1D - 3/3 19-02-2008
BIL NO.9 - TRAFFIC MANAGEMENT AND CONTROL
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
9.3.1 Supply, install in position and maintain all temporary traffic signs of
fluorescent orange prismatic retro-reflective sheeting including all
posts, frames, brackets and everything complete as shown in the
drawing and/or as directed by the S.O/P.D* including shifting at the
end of each stage and removal at the completion of the road works.
a) Not exceeding 1 m2 No 500.00
b) 1 - 2 m2 No 750.00
c) 2 - 3 m2 No 1,250.00
e) More than 4 m2 No 2,000.00
Addenda No.2
BQ 9 - 1/2 19-02-2008
BIL NO.9 - TRAFFIC MANAGEMENT AND CONTROL
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
Road Markings
9.4.2 Ordinary road line paint marking as shown in the drawings and or/as
directed by the S.O/P.D* and as specified during the construction
i d
a) 100mm width blackening existing line marking m 1.20
b) New road marking m 1.80
9.5.1 Allow for the preparation and submission of traffic management plan
and method statement for approval upon request by the S.O/P.D*.
Sum 15,000.00
Addenda No.2
BQ 9 - 2/2 19-02-2008
BILL NO. 10 - ENVIRONMENTAL PROTECTION WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
10.1.1.1 Provide a full time Environmental Officer throughout contract period man- mth 3,500.00
ii) Conduct quarterly audit and submit five (5) copies of Audit reports
as specified. No 2,000.00
10.1.2.3 Training
Conduct environmental training on site for JKR personnel once a
year. No 2,500.00
To conduct quarterly noise monitoring (12 hours ave.) inc. Leq, L10
and L90 as directed by S.O/P.D*. No 550.00
Addenda No.2
BQ 10 - 1/3 19-02-2008
BILL NO. 10 - ENVIRONMENTAL PROTECTION WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
Portable water jet including operator, water tank and other necessary
equipment needed to carry out cleaning of vehicle tyres at various
exits from the worksites as directed by the S.O/P.D*. No 2,100.00
Addenda No.2
BQ 10 - 2/3 19-02-2008
BILL NO. 10 - ENVIRONMENTAL PROTECTION WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
10.2.3.1 Provision of plastic sheeting to cover topsoil stockpile for turfing and
landscaping m2 14.00
ii) Transport and disposal of scheduled waste to prescribed premises. Sum 10,000.00
Addenda No.2
BQ 10 - 3/3 19-02-2008
BILL NO. 11 - ROUTINE MAINTENANCE WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
The frequency of cutting shall be carried out once a month: mth 776.00
a) Road shoulder
b) Slope area
c) Berm drain, interceptor drain and all other types of drain on slopes
d) Median
Addenda No.2
BQ 11 - 1/3 19-02-2008
BILL NO. 11 - ROUTINE MAINTENANCE WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
Addenda No.2
BQ 11 - 2/3 19-02-2008
BILL NO. 11 - ROUTINE MAINTENANCE WORKS
ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)
11.1.6 Drainage
a) The works shall comprise of cleaning and desilting works and shall
be carried out 4 cycles/year cycle 1,039.00
i) Debris in lined drains
ii) Debris in unlined drains
iii) Debris in sumps
iv) Debris in culverts
a) Litter collection and disposal and shall be carried out as and when
required.
b) Removal and disposal of loose material and debris as and when
required.
c) Removal and disposal of carcass as and when required.
Addenda No.2
BQ 11 - 3/3 19-02-2008