JADUAL KADAR HARGA KERJA-KERJA SIVIL

CONTENTS

NO. DESCRIPTION PAGE NO.

1 BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS BQ2-1 - BQ2-2

2 BILL NO. 3 - EARTHWORKS BQ3-1 - BQ3-2

3 BILL NO. 4 - DRAINAGE WORKS BQ4-1

4 BILL NO. 5 - PAVEMENT WORKS (NOT APPLICABLE) -

5 BILL NO. 6 - ROAD FURNITURE BQ6-1 - BQ6-2

6 BILL NO. 7 – GEOTECHNICAL WORKS BQ7-1

7 BILL NO. 8 STRUCTURE

8.1A - PILING WORKS (NOT APPLICABLE) -

8.1B - SUBSTRUCTURE BQ8.1B-1 - BQ8.1B-2

8.1C - SUPERSTRUCTURE (NOT APPLICABLE) -

8.1D - MISCELLANEOUS WORK BQ8.1D-1

8 BIL NO. 9 - TRAFFIC MANAGEMENT AND CONTROL BQ9-1 - BQ9-2

9 BILL NO. 10 - ENVIRONMENTAL PROTECTION WORKS BQ10-1 - BQ10-3

10 BILL NO. 11 - ROUTINE MAINTENANCE WORKS BQ11-1 - BQ11-3

Addenda No.2
Page 1/1 19-02-2008
BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

2.1 SITE CLEARANCE

2.1.1 Upgrading of existing road

a) General site clearance ha. 2,200.00

2.1.2 Construction of new road

a) Bushes ha. 2,000.00

b) Paddy Plantation ha. 2,500.00

c) Swampy Land ha. 2,700.00

2.2 DEMOLITION AND REMOVAL FROM SITE OF ALL BUILDINGS AND


EXISTING STRUCTURES

2.2.1 Buildings

a) Brickwork buildings
i) Single storey
Plan area : less than 100m 2 m2 25.00
100 - 200m2 m2 25.00
exceeding 200m 2 m2 25.00

ii) Double storey


-Plan area : less than 100m 2 m2 30.00

b) Concrete buildings
i) Single storey
Plan area : less than 100m 2 m2 40.00

c) Timber buildings
i) Single storey
Plan area : less than 100m 2 m2 15.00
100 - 200m2 m2 15.00
* Haulage subject to negotiation

2.2.2 Other Structures

a) Fences m 5.00

b) Pipe Culverts 600 mm diameter m 50.00


Pipe Culverts 750 mm diameter m 50.00
Pipe Culverts 900 mm diameter m 50.00
Box Culverts 1200x1200 mm m 70.00

c) Surface lined drains ( irrespective of size ) m 10.00

d) Guardrails m 10.00

Addenda No. 2
BQ 2 - 1/2 19-02-2008
BILL NO. 2 - SITE CLEARANCE AND DEMOLITION WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

e) Inlet / outlet structures No 350.00

f) Stall No 100.00

g) Bus shelter (3m) No 1,000.00

h) Road kerb m 5.00

i) Gabion m2 25.00

j) Mark, cut, break up and remove existing pavement including disposal off
site to Contractor's dump site. m2 6.00

2.3 DISMANTLE AND SEND TO STORE FOR REUSE AS DIRECTED BY


S.O/P.D*.

a) Guardrails m 8.00

b) Sign Board No 115.00

Addenda No. 2
BQ 2 - 2/2 19-02-2008
BILL NO. 3 - EARTHWORKS

ITEM UNIT Rate


DESCRIPTION OF WORKS
NO. (RM)

3.1 STRIPPING OF TOPSOIL

3.1.1 Stripping topsoil average depth 150mm and dispose to Contractor's dump
site as approved by the S.O/P.D*. m2 1.00

3.1.2 Stripping topsoil average depth 150mm and stockpile for reuse. m2 0.90

3.2 EXCAVATE, LOAD, HAUL AND DEPOSIT TO FORM EMBANKMENT

3.2.1 Common excavation in cuttings or in bulk to embankment. m3 3.50

3.2.2 Excavation of hard material in cuttings or in bulk to embankment. m3 8.50

3.2.3 Rock excavation by open blasting to embankment. m3 15.00

3.2.4 Rock excavation by control blasting to embankment. m3 20.00

3.2.5 Excavation foundation, trenches, culvert, drainage, etc. in any material


except rock to any depth
m3 6.50

3.3 EXCAVATE, LOAD, HAUL AND DISPOSE

3.3.1 Common excavation in cuttings or in bulk and dispose to Contractor's dump


site as approved by S.O/P.D*. (within 10km) m3 6.50

3.3.2 Excavation of hard material in cuttings or in bulk and dispose to


Contractor's dump site as approved by S.O/P.D*. (within 10km) m3 15.00

3.3.3 Rock excavation by open blasting and dispose to Contractor's dump site as
approved by S.O./P.D*. m3 20.00

3.3.4 Rock excavation by control blasting and dispose to Contractor's dump site
as approved by S.O./P.D*. m3 30.00

3.4 EXCAVATE UNSUITABLE MATERIAL, LOAD, HAUL AND DISPOSE

3.4.1 Excavate unsuitable material below embankments, below culverts or below


formation in cuttings as shown in drawing or as per specification as
approved by S.O/P.D* and dispose to Contractor's dump site.
m3 8.00

Addenda No.2
BQ 3 - 1/2 19-02-2008
BILL NO. 3 - EARTHWORKS

ITEM UNIT Rate


DESCRIPTION OF WORKS
NO. (RM)

3.5 SPREAD, GRADE AND COMPACT TO FORM EMBANKMENT

3.5.1 Suitable material from common excavation to form embankment. m3 2.00

3.5.2 Suitable hard material from excavation to form embankment. m3 2.50

3.6 TURFING AND HYDROSEEDING

3.6.1 Spot turfing. m2 2.80

3.6.2 Close turfing. m2 3.50

3.6.3 Hydroseeding. m2 2.50

3.6.4 Hydroseeding with fibromat or equivalent. m2 4.00

3.7 FIELD DENSITY TEST

3.7.1 Carry out compaction test to verify the degree of compaction by using sand
replacement method or other approved method by S.O/P.D*. No 20.00

Addenda No.2
BQ 3 - 2/2 19-02-2008
BILL NO 4 - DRAINAGE WORKS

ITEM RATE
DESCRIPTION OF WORKS UNIT
NO. (RM)

4.1 CULVERT

4.1.1 Pipe Culverts

Supply and lay precast reinforced concrete pipe culvert including


jointing. Spigot Collar

a) Single 600mm diameter Class X m 150.00 98.00


Single 675mm diameter Class X m 163.00 108.00
Single 750mm diameter Class X m 181.00 121.00
Single 900mm diameter Class X m 229.00 161.00
Single 1050mm diameter Class X m 275.00 196.00
Single 1200mm diameter Class X m 334.00 240.00
Single 1500mm diameter Class X m 465.00 446.00
Single 1800mm diameter Class X m - 580.00

b) Single 600mm diameter Class Y m 153.00 105.00


Single 675mm diameter Class Y m 170.00 114.00
Single 750mm diameter Class Y m 189.00 129.00
Single 900mm diameter Class Y m 245.00 177.00
Single 1050mm diameter Class Y m 300.00 220.00
Single 1200mm diameter Class Y m 360.00 265.00
Single 1500mm diameter Class Y m 490.00 471.00
Single 1800mm diameter Class Y m - 634.00

c) Single 600mm diameter Class Z m 160.00 110.00


Single 675mm diameter Class Z m 178.00 122.00
Single 750mm diameter Class Z m 203.00 142.00
Single 900mm diameter Class Z m 260.00 192.00
Single 1050mm diameter Class Z 318.00 238.00
Single 1200mm diameter Class Z m 384.00 289.00
Single 1500mm diameter Class Z m 538.00 518.00
Single 1800mm diameter Class Z m - 700.00

4.1.2 Precast Box Culvert

Supply and lay box culvert and flat lid including joint.

i) 1200mm x 1200mm size box culvert. m 546.00

ii) 1500mm x 1500mm size box culvert. m 746.00

iii) 1800mm x 1800mm size box culvert. m 934.00

Addenda No.2
BQ 4 - 1/1 19-02-2008
BILL NO. 6 - ROAD FURNITURE

ITEM RATE
DESCRIPTION OF WORKS UNIT
NO. (RM)

6.1 SIGNBOARDS

6.1.1 Destination Signboard

Destination sign type high intensity retroreflective sheeting inclusive of posts,


footing and frames as specified and shown in the drawing.
a) 2 No 825.00
1-2m
b) 2 - 3 m2 No 1,375.00
c) 3 - 4 m2 No 1,925.00
d) 2 No 2,750.00
4-6m
e) 2 No 3,850.00
6-8m
f) 2 No 4,950.00
8 - 10 m
g) 10 - 12 m2 No 6,050.00
h) 12 - 14 m2 No 7,150.00
i) 2 No 8,250.00
14 - 16 m
j) 2 No 9,900.00
16 - 20 m

6.1.2 Warning and Regulatory Traffic signs

Warning and Regulatory sign type high intensity retroreflective sheeting


inclusive of posts, footing and frames as specified and shown in the drawing.
a) Type RP.1 - RP.12 No 350.00
b) Type RM.1a - RM.4 No 350.00
c) Type WD.1 - WD.4 No 350.00
d) Type WD.8 - WD.38b No 350.00
e) Type WD.40 - WD.43 No 350.00

6.2 TRAFFIC BARRIER

6.2.1 Guardrails
a) Single mounted corrugated steel beam guardrail inclusive of delineators.
ii) 1.95m post spacing m 180.00

b) Guardrail Ends
i) Type 1 No 135.00
ii) Type 2 No 756.00
iii) Type 3 No 773.00

6.3 ROAD MARKING

6.3.1 Hot-applied superimposed reflectorised thermoplastic road markings

3mm thick hot-applied superimposed reflectorised thermoplastic road markings


White Yellow
with 20% glassbead as specified in BS 3262 and in the drawing.
a) Type 1 - Continuity line m 2.70 3.00
b) Type 2 - Give way line m 3.60 4.00
c) Type 3 - Centre line/lane line m 1.80 2.00
d) Type 4 m 1.80 2.00
e) Type 5 m 1.80 2.00
f) Type 6 - Edge line m 2.70 3.00
g) Type 7 - Stop line m 5.40 6.00
h) Type 10 m 1.80 2.00
i) Type 12 m 1.80 2.00
j) Type 13 - Stop line with pedestrian crossing m 1.80 2.00
2
k) Type 14 (Yellow box marking) m 18.00 20.00
l) Chevron marking m2 18.00 20.00
m) Transverse bar m2 18.00 20.00

Addenda No. 2
BQ 6 - 1/2 19-02-2008
BILL NO. 6 - ROAD FURNITURE

ITEM RATE
DESCRIPTION OF WORKS UNIT
NO. (RM)

6.3.2 Directional Arrow for roads in urban area

a) Single Straight No 65.00


b) Single turning No 65.00
c) Double headed No 75.00

6.3.3 Directional Arrow for roads in rural area

a) Single Straight No 65.00


b) Single turning No 65.00
c) Double headed No 75.00

6.4 KILOMETRE POST

Kilometre post inclusive of all necessary works at location and details as


shown in the drawing or as directed by the S.O/P.D*
a) Type A No 350.00
b) Type B No 140.00

6.5 CONCRETE KERB

a) Cast-in-situ concrete kerb including jointing, excavation, backfilling,


bedding and disposal of surplus materials as shown in the drawing or as
directed by the S.O/P.D* all in accordance with Sub-Section 6.4 of the
standard specification.
i) Type SM1 m 31.10
ii) Type SM2 m 34.70
iii) Semi mountable kerb (Type VIII) m 33.70

b) Precast concrete kerb including jointing, excavation, backfilling, bedding


and disposal of surplus materials as shown in the drawing or as directed
by the S.O/P.D* all in accordance with Sub-Section 6.4 of the standard
specification.
i) Type SM1 m 30.00
ii) Type SM2 m 35.00

6.6 DELINEATORS

6.6.1 Delineator post

Delineator post as shown in the drawing. No 65.00

6.6.2 Retroreflective Raised Pavement Marker (Road Stud)

Retroreflective Raised Pavement Marker as shown in the drawing. No 35.00

6.6.3 Flexible post

Flexible post as shown in the drawing. No 160.00

6.7 RIGHT OF WAY MARKER

Right of Way marker as shown in the drawing. No 73.00

Addenda No. 2
BQ 6 - 2/2 19-02-2008
BILL NO. 7 – GEOTECHNICAL WORKS

ITEM RATE
DESCRIPTION OF WORK UNIT
NO. (RM)

7.1 SOFT GROUND IMPROVEMENT

7.1.1 SOFT GROUND REPLACEMENT / STABILITY

7.1.1.1 Non-woven geotextile as separator. m2 4.50

7.1.1.2 High strength woven geotextile (200kN) m2 20.00

7.1.2 PREFABRICATED VERTICAL DRAINS

7.1.2.1 1.3m c/c square grids prefabricated vertical drains. m 2.00

7.2 INSTRUMENTATION

7.2.1 Supply and install surface settlement marker. No 150.00

7.2.2 Supply and install settlement plate. No 900.00

7.3 RETAINING WALL

7.3.1 REINFORCED SOIL WALLS

7.3.1.1 Supply and installation of wall component including reinforcing tendons,


anchor blocks, joint fillers, cushion pads, fasterners and inclusive of cast-in-
situ wall panels as per specification and drawings. m2 250.00

7.3.1.2 350mm x 150mm cast-in-situ mass concrete grade 20 levelling pad. m 30.00

7.3.2 RUBBLE RETAINING WALLS

7.3.2.1 225mm thick grouted stone pitching including all necessary excavation
works at both inlet and outlet of culverts as show in the drawing. m2 65.00

7.3.2.2 100mm diameter PVC pipe weep holes at 3000mm c/c inclusive of
approved drainage materials around weep holes. m 20.00

7.4 DRAINAGE BLANKET

7.4.1 150mm diameter Perforated UPVC pipe wrapped with geotextile fabric. m 40.00

Addenda No.2
BQ7 - 1/1 19-02-2008
BILL NO. 8 STRUCTURE

ITEM RATE
DESCRIPTION UNIT
NO. (RM)

8.1B SUBSTRUCTURE

8.1B.1 300mm thick PVC Coated Wire Mesh Gabion mattress forming slopes and
berms as shown in the Drawing. m2 60.00

8.1B.2 G.I handrailing and 300mm thk x 1000mm width grouted stone pitching steps
at abutment for inspection purposes as shown in the Drawing. m 150.00

8.1B.3 1.0m x 1.0m x 1.0m PVC coated wire mesh rock filled gabion. No 200.00

8.1B.4 200mm thick permeable layer comprising of 20mm - 40mm crushed stones.
m2 15.00

8.1B.5 Two layers of bituminous coating on buried surface of abutment and


wingwalls. m2 15.00

8.1B.6 In- situ Reinforced Concrete


i) 50mm thick Grade 15/20 lean concrete m2 8.50
ii) Concrete grade 20/20. m3 190.00
iii) Concrete grade 30/20. m3 230.00
iv) Concrete Grade 40 m3 250.00

8.1B.7 Formwork
i) Class F1 for buried surfaces. m2 32.00
ii) Class F2 for exposed surfaces. m2 35.00
iii) Class F3 m2 40.00
iv) Permanent formwork at soffit of deck slab m2 55.00

8.1B.8 High Yield Steel Reinforcement


i) 10mm diameter. t 3,500.00
ii) 12mm diameter. t 3,440.00
iii) 16mm to 32mm diameter. t 3,370.00

8.1B.9 Mild Steel Reinforcement


i) 10mm diameter. t 3,470.00
ii) 12mm diameter. t 3,420.00

8.1B.10 Fabric Reinforcement


i) Steel Fabric Reinforcement B603 m2 18.00
ii) Steel Fabric Reinforcement B785 m2 26.00
iii) Steel Fabric Reinforcement BRC A 10 m2 30.00

8.1B.11 75mm Diameter UPVC pipe wrapped with filter cloth m 10.00

8.1B.12 100mm Diameter PVC porous pipe wrapped around with filter cloth m 50.00

Addenda No.2
BQ 8.1B - 1/3 19-02-2008
BILL NO. 8 STRUCTURE

ITEM RATE
DESCRIPTION UNIT
NO. (RM)

8.1B.13 150mm dia. Perforated UPVC pipe wrapped with geotextile fabric. m 40.00

8.1B.14 20mm dia ms dowel bars galvanised for expansiopn joint No 25.00

8.1B.15 Joint sealer at 50m interval m 2.80

Addenda No.2
BQ 8.1B - 2/3 19-02-2008
BILL NO. 8 STRUCTURE

ITEM RATE
DESCRIPTION UNIT
NO. (RM)

8.1D MISCELLANEOUS WORKS

8.1D.1 Expansion Joints

8.1D.1.1 Form Expansion joints as shown in the Drawings at:


i) Deck Slabs m 120.00
ii) Parapets m 120.00
iii) Approach slabs m 90.00

8.1D.2 Brass Plaque

8.1D.2.1 Install brass plaque as shown in the Drawing. No 1,000.00

8.1D.3 Dowel Bar

8.1D.3.1 Supply and install 25mm diameter high yield steel galvanised dowel bars,
450mm long with rubber dowel caps as per details. No 35.00

8.1D.4 Protective Coating

i) One layer primer ans two layers of top coat inclusive of surface preparation
to all exposed surfaces of beams, diaphragm and parapets m2 30.00

ii) One layer of primer and two layers of top coat inclusive of surface
preparation to all exposed surfaces of abutments and piers above water. m2 25.00

Addenda No.2
BQ 8.1D - 3/3 19-02-2008
BIL NO.9 - TRAFFIC MANAGEMENT AND CONTROL

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

9.1 TRAFFIC MANAGEMENT TEAM

9.1.1 Appointment of traffic management team as follows :


a) Traffic Safety Officer Registered with OSHA man-mth 3,500.00
b) Supervisor/Foreman man-mth 2,000.00
c) Traffic Controller man-mth 1,000.00

9.2 TEMPORARY ROAD FURNITURES

9.2.1 Supply temporary road furnitures including installation, storage,


maintenance, replacement, shifting within the work area and removal
upon completion of the works as shown in the drawings and /or as
directed by the S.O/P.D*.

a) Precast Movable Reinforced Concrete Barriers or equivalent No 200.00

b) Light Weight Movable Barriers No 120.00

c) Light Weight Movable Barriers with Delineators No 125.00

d) Light Weight Movable Traffic Guidance Cones No 50.00

e) Blinkers including batteries No 80.00

f) Beacon Light including batteries No 350.00

g) Double Sided Reflective String Delineators m 1.50

9.3 TEMPORARY SIGNS

9.3.1 Supply, install in position and maintain all temporary traffic signs of
fluorescent orange prismatic retro-reflective sheeting including all
posts, frames, brackets and everything complete as shown in the
drawing and/or as directed by the S.O/P.D* including shifting at the
end of each stage and removal at the completion of the road works.
a) Not exceeding 1 m2 No 500.00
b) 1 - 2 m2 No 750.00
c) 2 - 3 m2 No 1,250.00
e) More than 4 m2 No 2,000.00

Addenda No.2
BQ 9 - 1/2 19-02-2008
BIL NO.9 - TRAFFIC MANAGEMENT AND CONTROL

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

Warning and Regulatory Traffic signs

9.3.2 Warning and Regulatory sign type high intensity retroreflective


a) Type T.1b No 250.00
b) Type 1.1c No 250.00
c) Type T.4 No 250.00
d) Type T.6 No 250.00
e) Type T.8a No 250.00
f) Type T.8b No 250.00
g) Type T.11m No 250.00
h) Type T.13b No 250.00
i) Type T.14 No 250.00

9.4 TEMPORARY ROAD DIVERSION

9.4.1 Excavate to form earth drain along temporary road. m 2.50

Road Markings

9.4.2 Ordinary road line paint marking as shown in the drawings and or/as
directed by the S.O/P.D* and as specified during the construction
i d
a) 100mm width blackening existing line marking m 1.20
b) New road marking m 1.80

9.5 TRAFFIC MANAGEMENT PLAN AND REPORT

9.5.1 Allow for the preparation and submission of traffic management plan
and method statement for approval upon request by the S.O/P.D*.
Sum 15,000.00

9.5.2 Submission 6 copies of Traffic Management Safety Report once in


every 3 months. Set 180.00
1 set = 6 copies
RM 30.00/copy x 6 copies = RM 180.00

Addenda No.2
BQ 9 - 2/2 19-02-2008
BILL NO. 10 - ENVIRONMENTAL PROTECTION WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

10.1 NON - PHYSICAL WORK

10.1.1 ENVIRONMENTAL MANAGEMENT PLAN (EMP)

10.1.1.1 Provide a full time Environmental Officer throughout contract period man- mth 3,500.00

10.1.2 ENVIRONMENTAL MONITORING, AUDITING AND TRAINING

10.1.2.1 Monitoring Report

Preparation and submission of five (5) copies of monitoring reports for


the following:
i) Monthly for water quality No 400.00
ii) Quarterly for air quality and noise. No 400.00

10.1.2.2 Environmental Audit

i) To submit 5 copies of monthly monitoring report. No 400.00

ii) Conduct quarterly audit and submit five (5) copies of Audit reports
as specified. No 2,000.00

iii) Conduct closure audit once project is deemed completed. No 4,000.00

10.1.2.3 Training
Conduct environmental training on site for JKR personnel once a
year. No 2,500.00

10.1.2.4 Air Quality Monitoring

To conduct quarterly air quality monitoring for Total Suspended


Particulates (TSP) for 24-hour period including wind velocity and the
direction as directed by S.O/P.D*. No 1,150.00

10.1.2.5 Noise Monitoring

To conduct quarterly noise monitoring (12 hours ave.) inc. Leq, L10
and L90 as directed by S.O/P.D*. No 550.00

10.1.2.6 Water Quality Monitoring

i) To conduct monthly river water quality monitoring for the following


parameters: Turbidity,pH, Total Suspended Solids (TSS),
Biochemical Oxygen Demand (BOD), Chemical Oxygen Demand
(COD), Dissolved Oxygen (DO), Oil & Grease, E. Coli and
Ammoniacal Nitrogen or as directed by S.O/P.D*. No 330.00

Addenda No.2
BQ 10 - 1/3 19-02-2008
BILL NO. 10 - ENVIRONMENTAL PROTECTION WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

ii) To conduct monthly water quality monitoring of the effluent


discharge at accommodation area for the following parameters:
pH, Total Suspended Solids (TSS), Oil & Grease, E. Coli and
Ammoniacal Nitrogen or as directed by S.O/P.D*. No 275.00

iii) To conduct monthly water quality monitoring at discharge outlet of


silt trap for Total Suspended Solid (TSS) or as directed by
S.O/P.D*. No 80.00

10.2 PHYSICAL WORK

10.2.1 DUST AND MUD CONTROL

10.2.1.1 Water Browser Truck

Browser truck including operator, pumping of water, water tank and


other necessary equipment needed to carry out water spraying along
haul/access road on site, existing roads and near settlements as
directed by the S.O/P.D*. No 50,000.00

10.2.1.2 Tyre Washing Facilities

Portable water jet including operator, water tank and other necessary
equipment needed to carry out cleaning of vehicle tyres at various
exits from the worksites as directed by the S.O/P.D*. No 2,100.00

10.2.1.3 Wash Trough

Wash trough including excavation, backfill and disposal of surplus


materials, formwork, reinforcement, hardcore and placement of
aggregate layer including maintenance as shown in the drawing and
as directed by the S.O./P.D*. No 15,000.00

10.2.2 SEDIMENT CONTROL

10.2.2.1 Silt fence

i) 1.0m High silt fence including non-woven geotextile and wooden


post with dimension as shown in the drawing or as directed by the
S.O./P.D*. m 17.00

ii) Maintenance of silt fence. m 9.00

Addenda No.2
BQ 10 - 2/3 19-02-2008
BILL NO. 10 - ENVIRONMENTAL PROTECTION WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

10.2.2.2 Silt Trap and Sediment Basin

i) Gabion cage with rock fill and geotextile including excavation,


jointing, backfilling and disposal of surplus materials as shown in
the drawing and as directed by the S.O./P.D* to suit site condition.

a) 1.0m x 1.0m x 1.0m gabion. No 200.00


b) Sand bedding for silt traps. m3 40.00
c) Stone filling. m3 55.00

ii) Maintenance of and including desilting, repair and replacement of


damaged/worn parts and materials as per specification.
a) Silt Trap No 2,000.00
b) Sediment basin No 295.00

10.2.3 TOPSOIL PROTECTION

10.2.3.1 Provision of plastic sheeting to cover topsoil stockpile for turfing and
landscaping m2 14.00

10.2.4 FUEL SPILLAGE MANAGEMENT

10.2.4.1 Containment Bund for Bulk Fuel Tank

Impervious concrete base to contain 110% volume of stored fuel


including grease trap to prevent spilled fuel overflow into natural
streams and demolish the same and cart away debris upon
completion of the project. No 10,000.00

10.2.5 WASTE MANAGEMENT

10.2.5.1 Scheduled Waste Disposal

i) Construction of storage shed to store scheduled wastes while


awaiting disposal. No. 7,500.00

ii) Transport and disposal of scheduled waste to prescribed premises. Sum 10,000.00

10.2.5.2 Grease Trap

Provision and maintenance of grease traps at kitchen areas, kongsi


and workshop. No 100.00

Addenda No.2
BQ 10 - 3/3 19-02-2008
BILL NO. 11 - ROUTINE MAINTENANCE WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

11.1 ROUTINE MAINTENANCE ACTIVITIES DURING CONSTRUCTION


PERIOD

11.1.1 Maintain The Existing Road

The Contractor shall provide all labour, equipments, tools material,


transport and whatever necessary to maintain the existing road which
shall comprise of all the works stated below : km mth 2,451.00

a) To Repair Pavement Surface

The works shall comprise of:


i) Patching of potholes
ii) Sealing of surface cracks
iii) Reinstate edge deterioration of back filled trenches
iv) Treatment to stripping of aggregate
v) Treatment for rutting
vi) Treatment to deterioration of concrete pavement
vii) Repair to concrete pavement joints
viii) Repair to paving blocks and slabs

b) To Maintain Road Shoulder

The works shall comprise of:


i) Re-grading and clearing of vegetation
ii) Topping up of shoulder with suitable filling material
iii) Filling irregularities in unsealed shoulders
iv) Filling pavement/shoulder level differences

11.1.2 Grass Cutting

The frequency of cutting shall be carried out once a month: mth 776.00
a) Road shoulder
b) Slope area
c) Berm drain, interceptor drain and all other types of drain on slopes
d) Median

Repair Slopes and Embankments

a) The works shall comprise of maintaining all slopes and


embankments as described below: km mth 28,921.00
i) Repair to erosion slopesnd embankments
ii) Repairs to failure slopes and embankments

Addenda No.2
BQ 11 - 1/3 19-02-2008
BILL NO. 11 - ROUTINE MAINTENANCE WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

11.1.3 Road Furnitures

a) The works shall comprise of cleaning works and shall be carried


out 4 cycles/year cycle 815.00
i) Cleaning of guardrails and barriers
ii) Cleaning of signages and posts
iii) Cleaning of kilometer post and delineator post
iv) Cleaning of traffic signal aspects

b) The works shall comprise of repainting works and shall be carried


out 2 years/cycle cycle 1,169.00
i) Repainting of guardrails and barriers
ii) Repainting of sign posts and traffic signal posts
iii) Repainting of delineator posts and kilometer posts
iv) Repainting of road kerbs

11.1.4 Bridges and Culverts

a) The works shall comprise of cleaning works and shall be carried


out 4 cycles/year cycle 1,248.00
i) Cleaning of expansion joints
ii) Cleaning of weep holes
iii) Cleaning of parapets
iv) Cleaning of bearing shelves
v) Cleaning of grafiti and markings
vi) Cleaning of waterway or culvert opening and bridge
carriageway
vii) Cleaning and removal of vegetation
viii) Cleaning, lubricating and greasing operation for steel bearings

b) The works shall comprise of repainting works and shall be carried


out 1 year/cycle cycle 2,973.00
i) Repainting of Concrete Parapets/ Railings
ii) Repainting of Steel Railings

11.1.5 Roadline Marking

Repaint roadline marking when faded m2 8.60

Addenda No.2
BQ 11 - 2/3 19-02-2008
BILL NO. 11 - ROUTINE MAINTENANCE WORKS

ITEM Rate
DESCRIPTION OF WORKS UNIT
NO. (RM)

11.1.6 Drainage

a) The works shall comprise of cleaning and desilting works and shall
be carried out 4 cycles/year cycle 1,039.00
i) Debris in lined drains
ii) Debris in unlined drains
iii) Debris in sumps
iv) Debris in culverts

b) The works shall comprise of minor repair as follows:

i) Repair to damaged drains m 60.70


ii) Repair to damaged sumps No 224.00
iii) Repair to misaligned unlined drains m 94.40
iv) Reseat mis-seated covers No 42.50
v) Repair to damaged covers No 33.20

11.1.7 Landscaping km mth 14.50

The works shall comprise of maintaining all landscaped area including


trees, shrubs/bushes as described below:
a) Watering at every alternate day
b) Cutting and trimming and shall be carried out once a month.
c) Weeding, fertilising, insect pest and disease control, pruning and
mulching and shall be carried out once a month.

11.1.8 Litter Collection and Disposal of Minor Obstruction/Debris Sum 16,277.00

a) Litter collection and disposal and shall be carried out as and when
required.
b) Removal and disposal of loose material and debris as and when
required.
c) Removal and disposal of carcass as and when required.

Addenda No.2
BQ 11 - 3/3 19-02-2008