BILL OF QUANTITIES

REHABILITATION WORKS ON THE LIKODRA BRIDGE

CONSTRUCTION WORKS Quantity of


Item Item description Unit price Amount in RSD
works
Unit

I ) PRELIMINARY WORKS
1 Site preparation and organization_x000D_
-site application (registration)
-power supply connector
-transportation of containers and equipment
_x000D_
-security service (60 days)

Calculation lump sum lump 1.00 0.00


2

Setting temporary scaffold for accepting the


installations from the bridge on the upstream
side. Scaffold is placed next to the existing
bridge cantilever, but in a way that does not
interfere with formwork for the new
cantilever girders. The width of the floor of
scaffolding to 1.0m. Length as of the entire
bridge. The average height of the scaffolding
5.5m.
Calculation per 1 m3 of erected and
dismantled scaffolding.
1x5.5x30=165m3 m3 165.00 0.00
3 Erecting and dismantling operational pipe
scaffolding beneath the bridge carriageway
structure. Scaffolding width about 12m,
average height of 5.5 m. Floor of the
scaffolding must be set 1.5m from the bottom
edge of the structure. The floor is to be
moved under the bridge, as required, and
under the cantilever of walkways to be
demolished, floor must be set for reception
of rubble from the structure. Final
calculation according to the actual quantity of
placed and dismantled scaffolding.
Calculation per 1 m3 of erected and
dismantled scaffolding.

Calculation per 1 m3 of erected and


dismantled scaffolding.

12x32.5x5.5=2145m3
m3 2,145.00 0.00
4 - Relocation of the installations during the
works,
- Setup of installations in the new ducts on
the bridge
lump 1.00 0.00
Total I: 0.00
II) DISMANTLING, REMOVAL AND DEMOLITION WORKS
1 Removing the entire pavement structure
from the bridge and between the wings. The
composition of the pavement structure is not
known, except for the thickness of asphalt ~
6cm. The lower layer is removed by hand to
avoid damaging the concrete deck.
The price includes loading and transportation
of materials to the landfill determined by the
Employer. Transportation calculated for up to
5 km.

Calculation per m2
7.0*37.0=259.00 м2
m2 259.00 0.00
2 Removal of the existing stone curbs 18x24
along the bridge and wing walls.
The price includes: loading, transportation
and unloading at a place determined by the
Employer. Transportation calculated for up to
5 km.

Calculation per m
37.05+36.45=73.50 m
m 73.50 0.00
3 Manual removal by chiselling the friable
concrete from concrete decks after removing
pavement surface. Quantity assumed 25% of
the uncovered (removed) area.

Calculation per m2
7.0*(26.30+0.7*2)*0.25=29.09 m2
m2 29.09 0.00
4 Removing railings for pedestrians by cutting
on the left and right sides of the bridge. The
lower part of concreted column of railing is
removed together with the walkways
cantilever concrete which is to be
demolished.The price includes: loading,
transportation and unloading at a place
determined by the Employer. Transportation
calculated for up to 5 km.

Calculation per m
37.05+36.45=73.50 m
m 73.50 0.00
5 Removing of concrete structure of footpaths
together with the final asphalt layer up to 3
cm, between the curbs to the end of the
cantilever overhang, from the bridge and
wings by demolition. The structure of
walkways is made of concrete, assumed to be
non-reinforced.
The price includes loading and transportation
of debris to the landfill determined by the
Employer. Calculated distances up to 5 km.
Scaffolding for the reception of rubble is paid
separately.

Calculation per m 3
0.38*73.5=27.93 m3
m3 27.93 0.00
6 Removal by demolition of reinforced
concrete of cantilever culverts of footpaths
on the bridge and wings using pickhammers.
The existing reinforcement of the cantilever
shall be cut.
The price includes loading and transportation
of debris to the landfill determined by the
Employer. Calculated distances up to 5 km.
Scaffolding for the reception of rubble is paid
separately.

Calculation per m 3
0.034*73.5=2.50 m3
m3 2.50 0.00
7 Removal of mortar and the surface layer of
concrete on the bottom and lateral sides of
the bridge deck, pillars and wing walls, where
the concrete is contaminated, cracked or
fallen off, to a sound concrete.
Quantity ratio has been assumed. Demolition
is carried out by mechanical means, water jet
or sand blasting according to possibilities and
methodology of the Contractor. Take care not
to damage the reinforcement of the deck.
The price includes: setting out the location,
notching with a saw, removing mortar and
poor concrete by chiselling, water jet or
sandblasting.

Calculation per m2
removal of mortar:
m2 30.00 0.00
removal of concrete to 2cm:
m2 30.00 0.00
removal of concrete 2-4cm:
m2 30.00 0.00
removal of concrete 4-6cm:
m2 25.00 0.00
8 Disassembly of the lining, supports and
installation at the upstream side of the
bridge. Installation shall be temporarily
supported with additional scaffold which is
paid separately. Existing installations: 1 pipe
with an unknown type of installation.

Calculation lump sum


lump 1.00 0.00
9 Dismantling of existing phone cable brackets
on the upstream side of the bridge and under
the bridge. Installation is temporarily
supported by auxiliary scaffold which is
calculated separately.
After completion, the cable will be put
through the pipes for installations in the
walkway.

Calculation lump sum


lump 1.00 0.00
10 Collection of debris that fell from the
structure, loading and transportation to the
landfill determined by the Employer.
Transporting distance to 5 km.

Calculation lump sum


lump 1.00 0.00
Total II: 0.00
III) EARTHWORKS
1 Excavation of soil material on the pavement
behind pillars after the removal of asphalt for
the purpose of execution of concrete floating
slab 70% mechanical and 30% manual. After
the excavation, conduct planning of the
trench bottom with accuracy of ± 1.5 cm.
Excavation is made by the methodology of
the Contractor, fully in accordance with the
supervisory engineer and applicable
regulations regarding safety at work. The
calculation is done according to the actually
excavated quantities under measures
specified in the design.
The price includes all labour, machinery,
loading and transportation of soil to the
landfill determined by the Employer.
Transporting distance to 5km.

Calculation per m 3
(1.895+0.213)*6.6*2=27.83 m3
m3 27.83 0.00
2 A combined mechanical and manual loading
of the existing material behind the pillar S1
(broken stone that was urgently laid over
after the flood) including loading into a
vehicle and haulage to a temporary dump site
within the site. The deposited material will be
used for backfilling of eroded right slope and
the area behind the pillar S1 between the
wing walls. Calculation per m 3 of material
disposed.

Calculation per m 3
0.38*73.5=27.93 m3
m3 27.93 0.00
3 Excavation of soil material for investigation pit
near the pillar S1. Exploratory pits will be
excavated along the longitudinal edge of the
foundation of pillar S1 on the side towards
the river, in the length of the footing and the
required width and depth which will be
determined on site. Excavation works to be
done together with earthworks on the
arrangement of the riverbed. During the
excavation the presence of supervisory
engineer is required, as well as constructive
designer and a geologist to conduct a a
report on the surveyed state of the
foundation of pillar and of the ground under
the foundation.
The price includes mechanical and manual
excavation of exploration pits, visiting by the
constructive designer and geologists to the
site and the preparation of reports on the
review where further action on the required
intervention will be determined. Excavated
material shall be used for backfilling provided
in the works for regulation of the river bed,
the excess shall be loaded and taken to a
landfill determined by the Employer.
Transporting distance to 5km.

Calculation lump sum


lump 1.00 0.00
4 Filling and compacting base layer d=15 cm
and wedge of gravel to compaction Ms =
30MPa below the concrete floating slab over
the previously levelled layer._x000D_
Unit price includes all necessary work,
material, machinery and transportation of the
material required._x000D_

Calculation per m 3
(1.895+0.213)*6.6*2=27.83 m3
m3 27.83 0.00
Total III: 0.00
IV) PREPARATORY WORKS FOR CONCRETING
1 Sand blasting of the upper surface of the
deck after the demolition of part of
cantilevers, face surfaces of the slab behind
the abutments after excavation for floating
slab and the upper surface on the wing walls,
as well as the underside of the cantilevers, all
visible sides of longitudinal and cross beams
after the removal of footpaths. Sand blasting
must be carried out under a protective
curtain and screen._x000D_
Sandblasting is done after manual removing
of friable concrete from the surface to be
repaired._x000D_

Calculation per m2
243.21+165.26+46.15+10.37+1.32=466.31 m2
m2 466.31 0.00
2 Fine pick hammering of the top surface of
concrete deck by garreting.

Calculation per m2
surface from the drawings
m2 243.88 0.00
3 Coating the deck using connection for old and
new concrete.

Calculation per m2

surface from the drawings


m2 243.88 0.00
4 Drilling holes Ø 25 using impact drill with
length of 5cm and 20cm on the top side of
the deck. The price includes exhausting of
holes, injection of Sikagard 31/41 (or another
of the same characteristics) and placing
anchors. Anchors are calculated
separately._x000D_

Calculation per pcs


l=20 cm
pcs 212.00 0.00
l=5 cm
pcs 689.00 0.00
Total IV: 0.00
V) CONCRETE AND REINFORCED CONCRETE WORKS
Concrete works to be performed by the Contractor's methodology, fully in accordance with the supervisory
engineer and applicable regulations for this type of work._x000D_
Unit price in addition to the above includes all preparatory works, formwork execution with all the necessary
work and material in its assembly and disassembly with included transportation, as well as all other work, tools
and materials necessary for the works._x000D_

1 Concreting onsite of cantilever culverts,


cornices of footpaths on the bridge and wing
walls, using concrete class MB 30, V6, M150.
The price includes the appropriate formwork
and scaffolding.

Calculation per m 3
0.39*(36.57+36.89)=28.65 m3
m3 28.65 0.00
2 Concreting onsite of additional carriageway
slab on the bridge on the part of walkways
and pavement using concrete class MB 30,
V6, M150. First cast concrete on one side and
then the other with conduction of the traffic
flow on the other carriageway lane. The exact
amounts will be determined on the spot
together with the supervisory authorities.

Calculation per m 3
surface from the drawings, 1.1422*27.78=31.7
m3 31.73 0.00
3 Concreting using fine-grained concrete MB30,
V6, M150 of structure ending parts including
the construction of wing walls after the
demolition of friable concrete. The quantity
has been estimated.

Calculation per m 3
m3 1.00 0.00
4 Concreting of the floating slab d = 20cm
onsite using concrete MB30.

Calculation per m 3
surface from the drawings, 33.354*0.20=6.67
m3
m3 6.67 0.00
Total V: 0.00
VI) REPARATION OF CONCRETE SURFACES
1 Reparation of concrete surfaces on the deck
from the top side after removing the
pavement surface and demolition of
walkways. The price of the repaired surface
inputs: protection of corroded rebars using
rebar protective means. Sandblasting is
calculated in the part for concrete works.
Replacement of rebar parts or adding grid is
paid separately.
The quantity for reparation has been
assumed. The final quantities are determined
based on actually measured and repaired
surface.
Calculation per meter of protected
reinforcement.

Calculation per m of protected reinforcement

m 30.00 0.00
2 Reparation of concrete surfaces using repair
mortar up to 3 cm on the deck from below,
from the side, on the pillars, wing walls,
longitudinal and cross beams. The price of
the repaired surface inputs: setting out the
location, notching using saw, removal of low
quality concrete by chiselling, sandblasting
using quartz sand and surface coating with
mortar for connecting and protecting the
reinforcement and placing the repair mortar.
Replacement of rebar parts or adding grid is
calculated separately. Scaffolding is
calculated separately for the deck also.
The final quantities are determined based on
actually measured and repaired surface.
pillars and wings = up to 6m2
bottom slab = up to 8 m2
lateral surface = up to 8m2
longitudinal, cross girders = up to 11m2

Calculation per m2
m2 33.00 0.00
3 Grouting cracks on the lateral sides of the
deck.
Calculation of 1 m' of grouted crack shall
include all the necessary materials,
preparation of cracks and injecting epoxy
resins. Scaffolding is separately calculated.

Calculation per m
m 5.00 0.00
Total VI: 0.00
VII) REINFORCEMENT WORKS
1 Supply and installation of rebars A400/500-2,
MA 500/560, for all elements of the bridge:
additional carriageway slab = 6000 kg
walkway on the bridge and the wings = 2200
kg
floating slab = 750 kg
Calculation per kg of reinforcement
embedded fully according to the regulations
for the reinforcement work.

Calculation per kg
kg 8,950.00 0.00
Total VII: 0.00
VIII) ОTHER WORKS
1 Procurement and waterproofing performance
on the deck and cantilever made of SBS -
elastomer bitumen tapes in a single layer. The
quantity includes overlap in the middle, min
10 cm.

Calculation per m2

m2 244.43 0.00
2 Supply and installation of precast concrete
curb s on the layer of cement mortar of the
concrete class MB 40 and resistance to frost
min M-150. The pricef inputs sealing joints
with cement mortar 1: 3.

Calculation per m
37.05+36.45= 73.5 m
m 73.50 0.00
3 Procurement and installation of bituminous
sealing strips along the concrete curbs before
concreting paths and paving.

Calculation per m
TEBM 10/10
m 73.50 0.00
TEBM 10/30
m 73.50 0.00
4 Setting PVC pipes 110mm in diameter in
pedestrian paths on the bridge and wings
used for installations.

Calculation per m

73.5x3=220.5 m
m 220.50 0.00
5 Supply and installation of guard rail on the
bridge and wings, type SUPER-RAIL H2-W4-B
(containment level H2, the area of operation
W4, the degree of severity of impact B)
production by Unipromet Cacak or
equivalent.

Calculation per m

36.8+36.7=73.5 m
m 73.50 0.00
6 Paving the road surface on the bridge
structure above the floating slab using
asphalt concrete AB 11 2x4 = 8 cm thick.

Calculation per m2
m2 257.57 0.00
7 Execution of asphalt expansion joints AD-30,
width of 30 cm of dilatation bed (dilatation ±
15mm) of manufacturers Product BG
Engineering or the like, at the ends of the
bridge roadway. The price includes
mechanical cutting of asphalt and asphalt
excavating using pickhammer, cleaning joints
width of 31cm, all necessary primers and
materials according to the manufacturer's
instructions. The price includes installation
and removing the protective board placed
over dilatation holes and over the
waterproofing at the stage of paving. After
cleaning the riverbed make sure to set the
appropriate galvanized sheet.
Fully to the technical drawings. Bed depth d =
8 cm on the pavement.

Calculation per m

7.0x2=14.0 m
m 14.00 0.00
8 Protective coating of old concrete surfaces
after repairs of columns, wings and the
bottom slab with protective coating Sikagard
680-S. Scaffolding is calculated separately.

Calculation per m2

154.72+165.26+46.15+72.07+97.16+10.24+8
3.06+40.5=669.7 m2
m2 669.70 0.00
9 Trial load of the bridge. The price includes
preparation, work on the structure, data and
reporting processing.

Calculation lump sum


lump 1.00 0.00
10 Procurement and installation of benchmarks
for surveying the bridge.

Calculation per piece


pcs 6.00 0.00
11 As-built design

Calculation lump sum


pcs 1.00 0.00
Total VIII: 0.00
TOTAL WORKS: 0.00
RIVERBED REGULATION

Item Description Quantity Unit price Total


Unit
5. BILL OF QUANTITITES

I - PRELIMINARY WORKS
1 Formation and security of construction site -
providing space for the site at the approved
location (extra working and sanitary facilities
on construction sites, machinery parking
space and warehouse for equipment and
fuel) restoring the area to its original state
after completion. Item covers execution and
maintenance of guardrails for preventing
access to the site by unauthorized persons
and the protection of workers from falling
down in the working pit or open excavation.
The Contractor is responsible for all damages
caused by non-compliance with prescribed
environmental protection measures and
measures of safety and health at work.
Calculation per complete executed item.
Charged after mutual signing of the final
measurement of works.

lump 1.00 0.00


2 Deforestation of shrubs and other vegetation
from the river slopes along regulation route,
the bandwidth is 12 m. Cut vegetation is to
be loaded into a vehicle and transported to
the landfill determined by the Supervisory
engineer. Calculation per m2 of deforested
surface.

m2 1,440.00 0.00
3 Ensuring access by using existing and forming
temporary roads and work area including
restoring the area to its original state. The
Contractor shall form internal roads for the
delivery of materials and equipment and
internal transport, in accordance with the
regulations of safety and health at work. The
working area width must be at least 3.5m on
both sides of the river. Calculation per
complete executed item.

lump 1.00 0.00


4 The application of envisaged measures of
traffic safety in the contact zone of roads to
access to the site with classified roads (4
locations) - registration, formation, marking
and maintenance of temporary vertical
signals and road markings in the contact
zone. Preventing removal of material to the
public road by enforcement of vehicle control
when exiting to public road. Calculation per
complete executed item.

lump 1.00 0.00


5 Geodetic setting out of elements of the
deigned regulated riverbed on the ground,
maintenance of benchmarks and geodetic
control of the works performed during the
execution. Calculation per m' of the route for
which the Supervisory engineer has certified
Measurement books sheet.

m 60.00 0.00
TOTAL I: 0.00
II - EARTHWORKS
1 Combined mechanical manual loading of
waste, humus, branches and other unsuitable
material for installation with loading into
vehicle and transportation to the landfill
determined by the supervisory engineer. The
price includes the cost of depositing if the
same are charged. Calculation per m3 of
disposed unsuitable materials.

m3 70.00 0.00
2 Combined mechanical manual loading of the
remains of existing regulated riverbed
(broken stone and concrete blocks) including
loading into a vehicle and haulage to a
temporary dump site within the site. The
deposited material shall be used for
backfilling eroded right slope. Calculation per
m3 of deposited material.

m3 50.00 0.00
3 Execution and maintainance of coffer dam for
enabling work in dry. Coffer dam shall occupy
a maximum of 1/3 of the width of the
riverbed to ensure the throughput of the
same, as required in the Opinion regarding
issuing water requirements procedure by PE
"Srbijavode" VPC "Sava-Danube" Belgrade.
Item includes provision of borrow pits,
loading, transportation and installation of
materials in coffer dam as well as works on
removing a quandary. Calculation per set of
the works of construction and the removal of
the cofferdam.

lump 1.00 0.00


4 Mechanical excavation of soil III and IV
category at the bottom of the riverbed to
create stabilization thresholds and foundation
bottom of stone lining of left slope including
loading into the vehicle. Excavation partially
under water. Calculation per m3 of excavated
material in a wild state.

stabilization thresholds: 35m x 1,00m x


1,50m= 52,50 m3
52.50
left slope foundation bottom: 55m x 0,80m x
1,20m= 52,80 m3
52.80
Total item II.4.:
m3 105.30 0.00
5 Mechanical excavation of soil III and IV
category at the bottom of the riverbed to
create stabilization thresholds and foundation
bottom of stone lining of left slope including
loading into the vehicle. Excavation partially
under water. Calculation per m3 of excavated
material in a wild state.

stabilization thresholds: 35m x 1,00m x


1,50m= 52,50 m3
52.50
right slope foundation bottom: 60m x 1,00m
x 1,50m= 90 m3
90.00
Total Item II.5.: m3 142.50 0.00
6 Mechanical excavation of soil III category
from slopes for execution of stone lining and
concrete girders including loading into a
vehicle. Excavation in dry to the accuracy of ±
5cm. The quantity taken from the statement
of the quantity of earthworks. Calculation per
m3 of excavated material in a wild state.

1207,73-70-50-105,30-142,50-6,4=833,53 m3

m3 833.53 0.00
7 Mechanical excavation of soil III category at
the bottom of the riverbed for for execution
of foundation bottom of stone lining behind
the bridge pier of the right bank in bays
length of 1m. Excavation is performed
manually because of the impact on bridge
pier foundation. Excavation to be done
carefully in layers. Installation of stone in the
bottom takes place immediately after the
excavation, before the start of the next bay
length of 1m excavation. Excavation partially
under water. Calculation per m3 of excavated
material in a wild state.

8m x 0,80m x 1,00м= 6,4 m3


m3 6.40 0.00
8 Transportation of excavated material
specified in Items II.4. and II.6. and II.7. from
left to the right bank and unloading to a
temporary landfill. Item includes preparation
of the landfill and spreading material at the
landfill. Calculation per m3 of deposited
material.

m3 938.83 0.00
9 Formation of the right slope by mechanical
installation of soil material specified in Items
II.2. and II.4.-II.7. The material is installed in
layers thickness of 30 cm with optimal
humidification and compaction by crossings
of bulldozer and tapperfoot roller to the
degree of compaction of Cd = 95% at Proctor
standard procedure. The quantity taken from
the statement of the quantity of earthworks.
Calculation per m3 of embedded and
compacted material.

m3 967.12 0.00
10 Procurement, transportation and installation
of a natural mixture of gravel in the base
layer under the stone lining and concrete
beams. Embedding is done manually, by fine
plannning to the accuracy of ± 1cm and
compactionusing vibro plate to compaction
modulus Mc = 50 MN/m2. Calculation per m3
of gravel embedded.

m3 70.00 0.00
TOTAL II: 0.00
III - QUARRY STONE WORKS
1 Execution of stabilization thresholds. 2
thresholds are executed: at the entrance and
at the exit of the regulated sections of the
riverbed in the area of the bridge. The
threshold is made of coarse quarry stone d =
60cm and concrete, combined mechanically
(80%) and manually (20%). The space
between the pieces of broken stones is filled
with concrete. The top layer thickness of
30cm is executed using concrete MB30, class
VDP 4. Smooth visible concrete surface and
execute it in longitudinal decline of 2.5 ‰.
The unit price includes the consumption of
concrete: 0.7m3/ m' of threshold.
Dimensions of threshold by graphic
enclosure. Calculation per m3 of finished
threshold.

m3 105.00 0.00
2 Execution of foundation bottom of slope
stone lining on regulated riverbed section in
the bridge zone. Foundation bottom is carried
out using the same methodology as for
stabilization threshold, according to the detail
in the graphics attached. Calculation per m3
of finished foundation bottom.

m3 142.80 0.00
3 Execution of stone lining of the left bank
using quarry stone size d = 25-30cm. The
lining is performed on a base layer of gravel d
= 10cm. The stone that is built in must meet
the attest requirements to water absorption
(SRPS B.B8.010) and resistance to frost (SRPS
B.B8.002). Stone is built 100% by hand,
queuing on the prepared gravel base with
pretreatment of edges. Construction without
garreting. The top side of the lining is sealed
with cement mortar in scale of 1:3 with
grouting joints. Calculation per m3 of finished
stone lining.

m3 75.00 0.00
4 Execution of stone lining on the right bank
using quarry stone of size d = 30-50cm. The
lining is performed on a base layer of gravel d
= 10cm and is placed into concrete MB25,
VDP Class 3, 15cm thick. Concrete is not
included in the price-calculated in Item IV.2.
The stone that is built in must meet the
attest requirements to water absorption
(SRPS B.B8.010) and resistance to frost (SRPS
B.B8.002). The stone is hand-built 80%, by
queuing on the prepared gravel base with
pretreatment of edges. Construction without
garreting. The top side of the lining is sealed
with cement mortar in scale of 1:3 with
grouting joints. Calculation per m3 of finished
stone lining.

m3 200.00 0.00
TOTAL III:
0.00
IV - CONCRETE WORKS
1 Procurement, transportation and casting of
concrete MB 30, class VDP 3 water resistance
according to SRPS U.M1.015/1998 and Class
M-150 according to the resistance of
concrete to frost SRPS U.M1.016:1992.
Concrete is incorporated into the terminal
and dividing beam covering. Procurement
and installation of the formwork to be
included in the price. Calculation per m3 of
concrete cast.

terminal and dividing beam of the right slope:


0,5m x 0,8m x 85m= 34 m3
32.00
terminal and dividing beam of the right slope:
0,3m x 0,5m x 70m= 10,50 m3
9.38
Total Item IV.1.:
m3 41.38 0.00
2 Procurement, transportation and casting of
concrete MB 30, class VDP 3 water resistance
according to SRPS U.M1.015/1998 and Class
M-150 according to the resistance of
concrete to frost SRPS U.M1.016:1992.
Concrete is incorporated as a base thickness
of d=15cm of the right slope lining.
Procurement and installation of the formwork
to be included in the price. Calculation per
m3 of concrete cast.

m3 60.00 0.00
TOTAL IV: 0.00
V - REINFORCEMENT WORKS
1 Procurement, transportation, cutting,
bending and assembly of ribbed
reinforcement A 400/500-2 in the upper part
of the stabilization thresholds, foundation
bottom and terminal and dividing beams of
lining. Constructive longitudinal
reinforcement Ø14 RA, RA Ø8 stirrup. The
quantity increased by 2.5% due to the large
number of overlaps on extensions of
constructive reinforcement. Calculation per
kg of embedded reinforcement.

4070,97kg x1,025=4172,74 kg
kg 4,172.74 0.00
TOTAL V: 0.00
VI - ОTHER WORKS
1 Pumping water during execution of works.
The contractor is required to get familiar with
river section, design and hydrology before
bidding for this Item. Subsequent work on
this Item will not be acknowledged, because
the quantity depends on the applied
methodology and organization of the
Contractor itself. Calculated and paid per
complete performed works.

lump 1.00 0.00


2 Supply, transportation and installation of
nonwoven geotextile surface mass of 200
gr/m2 that meets SRPS EN 13252. Geotextile
is installed under gravel base of the left slope
lining. Calculation of quantities shall include
overlaps. Calculation per m2 of built-in
geotextile.

m2 210.00 0.00
3 Supply, transportation and installation of
drainage pipe ("weephole") nominal
diameter DN 75 mm. The pipe is coated with
filter protection and set according to the
detail in the graphics attached. Calculation
per m' of embedded pipes.

30 drainage pipes length of 2,3м


m' 69.00 0.00
4 Preparation of as built design. The Contractor
is required to survey elevation and
positioning of the executed structure and to
elaborate as-built design in 4 copies.

pcs 1.00 0.00


TOTAL VI: 0.00
SUMMARY
I - PRELIMINARY WORKS 0.00
II - EARTHWORKS 0.00
III - QUARRY STONE WORKS 0.00
IV - CONCRETE WORKS 0.00
V - REINFORCEMENT WORKS 0.00
VI - OTHER WORKS 0.00
TOTAL FROM I TO VI: 0.00
BILL OF QUANTITIES
ROAD OVERLAPPING
BRIDGE OVER THE LIKODRA ON THE STATE ROAD IIA rank, number 137, км 0+203.00

No. Item description Quantity of Unit price Amount in RSD


works
Unit
I) ROAD OVERLAPPING WORKS
1 Setting out the aligment with maintaining
benchmarks during the construction works.
Settting out must be visible with clear
markings and must be preserved until the
final handing over of the structure. The
Contractor is obliged to carry out a detailed
survey of the site before commencement of
the works, and, in case there are deviations
from the design documentation, to align
them with theEmployer, otherwise the
Employer is not obliged to reimburse the
costs arising as a result of any discrepancy
between the designed and the situation on
the spot.

m1 136.80 0.00
2 Demolition of existing pavement on the site
of execution of new pavement from km
0+166.33 to km 0+246.62 (bridge is not an
issue) with a thickness of 25-30 cm and
haulage to the landfill.

m3 86.10 0.00
3 Preparation of construction joints for the
continuation of paving.
At the beginning and the end of the section.

m 16.00 0.00
4 Paving road surface using asphalt concrete AB
11s d = 5 cm.
m2 289.00 0.00
5 Paving road surface using BNS 22 sсА d=8 cm
m2 289.00 0.00
6 Executing a layer of crushed stone material
0/31.5 mm thickness of about 15-17 cm with
compaction to the required density.

m3 56.50 0.00
7 Planning and rolling of subrade.
m2 289.00 0.00
Arranging of slopes and shoulders. The price
8 includes also topsoiling.
lump 1.00 0.00
TOTAL WORKS: 0.00
BILL OF QUANTITIES FOR THE MAIN DESIGN ON TRAFFIC SIGNS AND EQUIPMENT
ON THE ROAD 137 AT THE BRIDGE OVER THE RIVER LIKODRA

Item ITEM DESCRIPTION QUANTITY UNIT PRICE TOTAL


no.
UNIT
1 TRAFFIC SIGNS
1.1. Supply of standard traffic signs (SRPS Z.S2.300)

Round diameter of 600 mm (class 2) pcs 2.00 0.00


Installation of standard traffic signs
Mounting traffic signs on placed supports pcs 2.00 0.00
OVERALL 1.1. 0.00
The price of a standard traffic sign includes: procurement and delivery, transportation to place of installation, all the
elements for fixing to the supports (reinforcement, clamps, bolts, cuffs, etc.), mounting the sign on embedded
support, as well as the quality control according to SRPS Z.S2 .300.

1.2. Procurement of non-standard traffic signs - without supports

III-58 (Likodra) (rectangle sides100х800 mm)


(class 2)
pcs. 2.00 0.00
Placing non-standard traffic signs

Mounting the signs on embedded supports


pcs. 2.00 0.00
OVERALL 1.2.
0.00
The price of non-standard traffic sign includes: fabrication and delivery, transportation to place of installation,
assembly and quality control according to SRPS Z.S2.300.
Procurement of traffic signs supports
1.3.
Single Column pipe supports in length of
2,800 mm
pcs 2.00 0.00
Single-column pipe supports in length of
3.000 mm
pcs 4.00 0.00
Placing traffic signs supports

Procurement of concrete "MB-15" for footing


to place sign posts
pcs 6.00 0.00
Mounting of traffic signs supports
pcs 6.00 0.00
OVERALL 1.3. 0.00
The price of single-pipe supports includes procurement, delivery and transportation to the place of installation, site
preparation and execution of foundation, installation and leveling, the price of accessories for connections between
the elements of the supports, crossbars in foundation, filling holes, compaction and shoulder planning, and the
price of seals against rain and quality control of the materials.

TOTAL 1. 0.00
2 PAVEMENT MARKINGS

2.1. Marking longitudinal line - SRPS U.S4.222,223,224,231

Dividing line
m2 9.00 0.00
Edge line
m2 18.00 0.00
Material for execution of pavement markings
Procurement of colours (0.65 kg / m2),
thinner (0.065 kg / m2) and glass beads
(0.195 kg / m2) m2 27.00 0.00
The price of works on carrying out road markings shall be calculated according to the coloured element or per m2
of painted surface. Price includes measuring on the site, cleaning and degreasing of pavement, procurement of
colour, painting and quality control of used materials and executed works based on SRPS U.S2.240.
TOTAL 2. 0.00
3 TRAFFIC EQUIPMENT

3.1. Guardrail

Continuous portion of the guardrail ЈО/2.00,


N2-W5 m 60.00 0.00
Continuous portion of the guardrail
ЈDО/2.00, H1-W5
m 16.00 0.00

Continuous portion of the guardrail SUPER


RAIL/1.33, H2-W4
m 112.00 0.00

Transitional structure with H1 to H2 length


12m
pcs. 4.00 0.00

Oblique endings in places of guardrail


interruptions length of 12m
pcs. 6.00 0.00

Reflectors in pressure shroud of railings


red/white
pcs. 13.00 0.00
OVERALL 3.1. 0.00
The price of guardrail includes procurement, supply and transportation to place of installation, preparing the site,
placing the poles to the shoulder, or anchoring to concrete base, fixing elements of guardrail, setting up the final
parts, setting retro reflective lights and quality control of the materials used.

TOTAL 3.
0.00

4 TEMPORARY TRAFFIC
SIGNALS

Supply and installation of temporary traffic


signals fully in accordance with the
specification. Temporary traffic signals remain
in the possession of the Contractor after
completion of the works.
lump 1.00 0.00
TOTAL 4. 0.00
TOTAL TRAFFIC SIGNALS AND EQUIPMENT 0.00
TOTAL LIKODRA
1 BRIDGE REHABILITATION 0.00

2 RIVERBED REGULATION 0.00

3 ROAD OVERLAPPING 0.00

4 TRAFFIC SIGNALISATION 0.00


TOTAL 0.00
BILL OF QUANTITIES
REHABILITATION WORKS ON THE DUMACA BRIDGE

No. Item description Quantity of Unit price Amount


Unit Works in RSD
CONSTRUCTION WORKS
Note:
Cleaning operations of end slopes, embankment
slopes and works on lining using crushed stone have
been calculated in the river regulation part.

I ) PRELIMINARY WORKS
Site preparation and organization
-site application (registration)
-power supply connector
1
-transportation of containers and equipment
-security service (60 days)
lump 1.00 0.00
Placement of traffic signs and traffic lights for
conducting alternating one-way traffic, according
to the design of traffic signs.
The regulation of any restrictions and interruption
of traffic shall be included in the unit price.
The position of traffic lights and traffic signs is
2 changed during the works (changing traffic
carriageway).

lump 1.00 0.00


Installation of temporary scaffolding for the
installation Ø100mm on the upstream side of the
structure. Scaffolding is set only on a part of the
3 arch. Calculation per 1 piece of erected and
dismantled scaffolding.

lump 1.00 0.00


Erecting and dismantling operational tubular
scaffolding beneath the arch structure. Scaffolding
width 13m, average height of 3 m. Floor is set on
the whole surface of the scaffold. On the sides the
scaffold is required to be equipped with full
railings min 50cm high to prevent the fall of
debris in the river. Final calculation according to
the actual quantity of placed and dismantled
4 scaffolding. Calculation per 1 m3 of erected and
dismantled scaffolding.
Floor = 10x13 = 130m2
Scaffolding = 13x3x10 = 390m3

m3 390.00 0.00
Setting up the necessary guard rail made from
tubular profiles between pavement and areas of
work during one-way traffic and the flow of both-
way traffic. Calculation per running meter of
5 installed guard rails and dismantled guard rails for
each phase of the traffic.

m' 20.00 0.00


Total I:
0.00
II) DISMANTLING, REMOVAL AND DEMOLITION WORKS
Removing the plants, shrubs and stumps from
slopes of end slopes and bank under the bridge.
6
lump 1.00 0.00
Removing the entire asphalt pavement of the
bridge from the end of the stairs to the end of the
pillar and along the wing walls in width of 1.2m.
Total estimated thickness of asphalt up to 15 cm.
The price includes loading and transportation of
materials to the landfill determined by the
7 Employer. Transportation calculated for up to 5
km.
8.2x14.8+2.5x1.2x4=133.36m2

m2 133.36 0.00
Removal of the existing stone curbs 18x20 along
the bridge and wing walls.
The price includes: loading, transportation and
unloading at a place determined by the Employer.
8 Transportation calculated for up to 5 km.
19.7x2=39.4m'

m' 39.40 0.00


Manual removal by chiselling the friable concrete
from concrete decks after removing pavement
surface. Quantity assumed 25% of the uncovered
9 (removed) area.
1.3x14.8x2x0.25=9.62m2

m2 9.62 0.00
Removing railings for pedestrians by cutting on the
left and right sides of the bridge. The price
includes: loading, transportation and unloading at
a place determined by the Employer.
10 Transportation calculated for up to 5 km.

m' 39.40 0.00


Removal by the demolition of the concrete
structure of footpaths, cantilevers and parts of
reinforced concrete slab and wings from the
bridge and wings. The dimensions and structure of
pedestrian paths due to the lack of design
documentation have been assumed.
The price includes loading and transportation of
11 debris to the landfill determined by the Employer.
The calculated distance to 5 km.
(0.17x0.82+0.3x0.16)x19.7x2
+0.13x0.25x2.5x4=7.71m3

m3 7.71 0.00
Demolition of the remaining parts of the wall from
1/2 bricks on the lateral sides of the bridge. The
price includes loading and transportation of debris
to the landfill determined by the Employer. The
12 calculated distance to 5. Calculation per 1m2 of
the demolished wall.

m2 20.70 0.00
Demolition of parts of the pillars of stone in order
to form niches for supporting reinforced concrete
protective screens (walls) of the arch. The depth of
the niche 30cm and width 20cm of supporting
13 height.
0.2x0.3x3.7x4=0.89m3

m3 0.89 0.00
Dismantling of girders and installation on the
upstream side of the bridge. Installation is
14 temporarily supported by auxiliary scaffold which
is calculated separately.
lump 1.00 0.00
Collection of debris that fell from the structure,
loading and transportation to the landfill
determined by the Employer. Transportation
15 distances up to 5 km.

lump 1.00 0.00


Total II: 0.00
III) EARTHWORKS
Excavation of filled material from the embankment
above the arch next to wing walls after the
removal of asphalt. 70% mechanical and 30%
manual. After the excavation, conduct planning of
the trench bottom with accuracy of ± 1.5 cm.
Excavation is done by Contractor's methodology,
fully in accordance with the supervisory engineer
and the applicable regulations of safety at work.
The calculation according to the actually excavated
quantities under measures specified in the design.
The price includes all labor, machinery, loading
and transportation of soil material to the landfill
16 determined by the Employer. Transportation
distances up to 5km.
0.16x8.2x14.8+(0.6+1)x0.5x0.65x10x2
+1.7x0.23x2.5x4= 33.72m3

m3 33.72 0.00
Filling and compacting base layer of d=10 cm and
wedge of gravel to compaction Ms = 30MPa below
the footpaths next to the wings.
Unit price includes all necessary work, material,
machinery and transportation of the material
required.
17 Calculation per 1 m3 of filled materials.
1.7x0.1x2.6x4+0.2x0.4x2.6x4=2.6m3

m3 2.60 0.00
Total III: 0.00
IV) CONCRETE WORKS
Concrete works to be performed by the
Contractor's methodology, fully in accordance
with the supervisory engineer and applicable
regulations for this type of work.
Unit price in addition to the above includes all
preparatory works, formwork execution with all
the necessary work and material in its assembly
and disassembly with included transportation, as
well as all other work, tools and materials
necessary for the works.

Sand blasting of the upper surface of the deck


after the demolition of the cantilever and the
upper surface of the wing walls after the removal
of footpaths. Sand blasting must be carried out
under a protective curtain and screen.
Sandblasting is done after manual removing of
18 friables from the upper surface of the concrete
slab.
1.3x14.8x2+0.25x2.5x4=40.98m2

m2 40.98 0.00
Coating the concrete surface of deck and pillar
after the demolition using joint for the old and
19 new concrete.
0.3x14.8x2=8.88m2
m2 8.88 0.00
Drilling holes Ø 25 using impact drill with length of
40cm on the upper side of the carriageway slab.
The price includes exhausting of holes, injection of
Sikagard 31/41 (or another of the same
characteristics) and placing anchors. Anchors are
20 calculated separatelly.
(2+2)x2x10/0.2+2.4/0.2x3x2=472 pcs

pcs 472.00 0.00


Drilling holes Ø 25 using impact drill with length of
25cm on the lateral sides of the arch made of
bricks. The price includes exhausting of holes,
injection of Sikagard 31/41 (or another of the
21 same characteristics) and placing anchors. Anchors
are calculated separatelly.
31x2x2=124 kom

pcs 124.00 0.00


Concreting using reinforced concrete on-site of
lateral screens (walls) thickness of 12cm with fine-
grained concrete MB30 with the addition of
plasticizers. For concreting, always use the funnel
in order to prevent segregation. Calculation per 1
22 m3 of concrete placed. Surfaces calculated in
AutoCAD.
16.9x0.12x2=4.06m3

m3 4.60 0.00
Concreting on-site using plain concrete MB 30 of
the embankment filling above the arch and above
the pillars. Calculation per 1 m3 of concrete
23 placed.
(0.58+1.0)x0.5x0.8x10x2=20.8m3

m3 20.80 0.00
Concreting using reinforced concrete 30 MB of the
slab above the arches and pillars in thickness of 16
to 19cm. Calculation per 1 m3 of placed concrete.
24 (0.16x1.3x2+0.19x4)x14.8=17.4m3

m3 17.40 0.00
Leveling layer of repair mortar in thicknesses of up
to 5 cm.
25 0.05x1.3x14.8x2=1.92m3
m3 1.92 0.00
Concreting of footpaths and lateral masks using
concrete MB 30, V6, M-150.
Calculation per 1 m3 of placed concrete.
26 (0.42+0.43)x10+(0.31+0.42)x2.4x2
+0.77x2.5x4=15.92m3
m3 15.92 0.00
Casting a layer of shotcrete or other appropriate
mortar under pressure using method over the
head, to the wall surfaces of the arch on the
bottom side. Layer thickness up to 5cm.
Scaffolding is separatelly calculated.
The price includes:
-setting FIX anchor bolts M12, L = 160mm, 4
pcs/m2 with plates 100x100x5
27 -setting the grid Q 138 separatelly calculated.
Calculation per m2 of treated surface.
6x10.2=61.2m2

m2 61.20 0.00
Total IV:
0.00
V) REPARATION OF CONCRETE SURFACES
Repair of concrete surfaces usin reparation mortar
up to 3 cm on the deck from the bottom and on
the sides after excavation of pavement. The price
of the repaired surface inputs: location setting out,
cutting with a saw, removing low quality concrete
by chiselling, quartz sand blasting and surface
coating using mortar for joints and protection of
reinforcement and placing reparation mortar.
Replacement of reinforcement parts or adding grid
is calculated separately. Scaffolding is separatelly
28 calculated.
The quantity has been estimated.
The final quantities are to be determined based on
actually measured, and repaired surface.

m2 5.00 0.00
Replacing broken smooth reinforcement.
Reinforcement has already been sand blasted. The
price includes needed suspenders and needed min
welding according to BAB. Calculation per piece of
29 reinforcement replaced. Quantity has been
assumed.

pcs 20.00 0.00


Total V:
0.00
VI) REINFORCEMENT WORKS
The reinforcement for all elements of the bridge.
Reinforcement RA B500
Slab = 4397 kg
Footpath = 2955kg
30 Lateral screens = 285 kg

kg 7,637.00 0.00
Total VI: 0.00
VII) STRENGTHENING OF THE STRUCTURE USING FRP- LAMINATE BRIDGE PLATE
Strengthening deckusing strips of SikaCarbo Dur
S2.025/80. In the unit cost of 1 m ' to be also
calculated: the provision of all necessary materials,
preliminary tests, providing the access to the
workplace, preparing concrete surfaces and
removing shotcrete mortar including the eventual
leveling layer and primer, bonding of laminate,
quality control and finishing processing. Access
scaffolding is separate

m' 0.00 0.00


Total VII: 0.00
VIII) OTHER WORKS
Procurement of materials, placing respective
anchors, clouts, mounting installation on the
31 upstream side of the bridge under the cantilever
culvert.
kom 10.00 0.00
Sealing of gerber hinge continuity plate
with sealing mass for joints. Slit width of 3cm and
the depth of 4 cm. Calculation per 1 meter of
sealed hinge.
32 14.8x2x2=59.2m

m' 59.20 0.00


Procurement and waterproofing performance of
the deck and cantilever of the wing walls made of
SBS - with bitumen tape. The quantity calculated
33 also overlapping in the middle.
9.3x14.8=137.64m2

m2 137.64 0.00
Supply and installation of precast concrete curbs
18x12 on the layer of cement mortar with the
concrete class of MB40 and frost resistance min
M-150. The price includes also sealing of joints
with cement mortar 1:3. Calculation per running
34 meter of mounted curb.
19.75x2=39.5m

m' 39.50 0.00


Supply and laying of bituminous sealing strips
along the concrete curbs before paving and only
on the part of the deck. Width of the sealing strip
35 is to 8 cm.
14.8x2=29.6 m'
m' 29.60 0.00

Setting the PVC pipes diameter of 110 mm in the


36 footpaths on the bridge and wings used for
installations.
3x19.75x2=118.5m'
m' 118.50 0.00

Procurement and installation of bridge steel safety


barriers type H1 according to the detail in the
37 Design, including protection by hot dip galvanizing
procedure and the anchoring in the concrete of
walkways.
m' 39.50 0.00
Procurement of materials, fabrication and erection
of guard rails of pedestrian pathways on the bridge
and wings. The price includes the ACP corrosivity
38 category S4 with painting using epoxy-
polyurethane system. Calculation per 1 kg of
installed guard rails.
kg 830.00 0.00
Scraping of asphalt thickness of up to 4 cm
between the wing walls.
39 5.8x2.5x4=29.0m2

m2 29.00 0.00
Construction of bearing asphalt layer for thickness
equalization of 12cm from BNS. Calculation per
40 1m2 of embedded layer.
0.5x2.5x4=5.0m2
m2 5.00 0.00
Paving the road surface on the bridge using
asphalt concrete AB 11, 2x4 = 8 cm thick.
41 6.6x19.75=130.35m2

m2 130.35 0.00
Grouting joints between the curbs on pedestrian
paths.
42 19.75x2=39.5m

m' 131.26 0.00


Supply and installation of styrofoam panels
weighing 17gr below the edge slab with hinges
and on the lateral sides of the existing concrete
slab in thickness of 3cm. Calculation per 1 m2 of
43 panels placed.
1x14.8x2+0.8x14.8x2=53.28m2

m2 53.28 0.00
Protective coating of old concrete areas after
repairs of pillars, wings and the bottom slab using
protective coating Sikagard 680-S. Scaffolding is
calculated separately. Calculation per m2 of the
44 coated surface.
(0.8x2+10)x39.44+1.7x(11+2x5)x2=
528.9m2

m2 528.90 0.00
Traffic signals after the reconstruction of the
bridge.
45
lump 1.00 0.00
Transferring installations from the temporary
supports into the new ducts of pedestrian paths
46 and shafts in sidewalks.
lump 1.00 0.00
47 As-built Design pcs 1.00 0.00
Total VIII: 0.00
OVERALL WORKS: 0.00
BILL OF QUANTITITES
The Dumaca Riverbed Regulation
No. Item description Quantity of Amount
Unit Works Unit price in RSD
CONSTRUCTION WORKS
NOTE: Quantities of works on bridge end slopes profiling, works on lining end slopes using
stone, part of road embankment out of river regulation and works on lining of road
maintenance channel using stone have been calculated separately
other works have been calculated and presented in the table

I ) PRELIMINARY WORKS
Setting out and surveying the work axis of riverbed
alignment, setting out the envisaged sections and
geodetic monitoring during construction works.
Calculation per 1 running m.

1 m' 100.00 0.00


Complete removing of cross regulating structure
made of stone and twigs upstream from the
bridge, as well as stone and concrete under the
bridge. The stone is deposited directly to the
minor because it can be used for a new stone
pitch.

2 m3 7.00 0.00
Closing water flow in the portion where the works
are performed by executing barrier on upstream
and downstream part of the observed section, for
the purpose of execution of works in the dry.
Selecting the type of barrier and section length
depending on the methodology available to the
Contractor (interruption of the water flow along
the section where works are carried out with the
help of a coffer dam or otherwise). It is
understood that the coffer dam upon completion
of the work is to be removed, and the river bed,
which is not regulated, to be reinstated to its
original condition.
Unit price includes all necessary works and
materials for execution of works in proper quality.
The Contractor is obliged to take all safety
measures.
Calculation per completely carried out work.

3 pcs 1.00 0.00


Clearing the ground, cutting shrubs and low
vegetation in the area which covers the regulation
works.
4 m2 1,500.00 0.00
Total I 0.00
II) EARTHWORKS
Mechanical excavation of the Dumaca riverbed
(minor and small part of major). Item includes
depositing material to a temporary landfill outside
the work area, for later placement in
embankments of riverbed minor and major.
Tabular: 887.28

5 m3 947.00 0.00
Manual excavation of part of soil material under
the bridge which cannot be reached by excavator.

6 m3 20.00 0.00
Filling with soil from the excavation of the area
behind the stone pitch to the designed level. The
material is installed in layers of 30cm. The material
must not contain humus and organic substances.
Item includes loading material from excavation on
a temporary landfill, transportation to the site and
installation in layers. Calculation per m3 of filled
material.
tabular: 41.92

7 m3 41.92 0.00
Levelling of river bed after formation of lining and
laying stone pitch.
8 m2 250.00 0.00
Formation of cross slopes in inclination 1: 1 and 1:
1.5 on the banks in the abutments area and
profiling bridge end slopes.
9 lump 3.00 0.00
Loading and transportation of excess soil from the
temporary landfill to landfill designated by the
Employer. Transporting distances up to 5 km. The
price includes arrangement of the landfill.
Calculation per 1 m3 of hauled material.
887.28-41.92m3

10 m3 880.00 0.00
Total II 0.00
III) WORKS IN GRAVEL AND STONE
Supply, transportation and installation of crushed
stone base layer d = 10 cm beneath the stone
substrate.
Calculation per m3 of built-in material.
11 m3 19.90 0.00
Supply, transportation, installation and formation
of prism of broken stone diameter of 25 to 45 cm.
Lying width of prism is 2m, and slopes in
inclination of 1:1. The price includes formation of
the slope on the front side by rolling, manually
and using grapples.

12 m3 131.18 0.00
Supply, transportation, installation of stone pitch
made of broken stone diameter 15 to 25cm. The
price includes formation of the slope on the front
side in inclination of 1:1 by rolling, manually and
using grapples.

13 m3 296.00 0.00
Manual coating of slopes and shoulders of
riverbed minor using crushed stone 30cm thick in
cement mortar 1:3. Joints are sealed with cement
mortar 1:3, and then grouting is to be executed.
Before sealing with cement mortar joints are to be
washed with water and compressed air. Quality of
stone and work must be in accordance with
applicable regulations for this type of work.
Calculation per m3 of placed coating.
tabular

14 m3 199.67 0.00
Execution of stone foundation in concrete MB30
below the end slope bottoms, parts of riverbed
lining upstream and foundation (bottom) of road
maintenance channel. The foundation dimensions
are 50x80.
(2x3x3.14x0.4+2x6.2x3.14x0.4+4+6+9.8)x
0.5x0.8=23.54m3

15 m3 23.54 0.00
Stone coating d = 30 cm in cement mortar 1:3 of
bridge end slopes, road maintenance channel from
the slopes with the road slope. Joints are sealed
using cement mortar 1:3 and then grouted.
The price includes 10cm layer of gravel.
Calculation per m3 of placed stone.
9.81+37+8+15.2+40.8+19.8+8.9=
139.51m3

16 m3 139.51 0.00
Wall execution using selected broken stone in
cement mortar 1:3 wall thickness at the bottom
1.2 and in the top 0.4m. Joints are sealed using
cement mortar 1:3 and then grouted. Before
sealing with cement mortar joints are to be
washed with water and compressed air. Quality of
stone and work must be in accordance with
applicable regulations for this type of work.
Calculation per m3 of placed coating.
tabular

17 m3 90.27 0.00
Works on execution of cross regulation structure in
the riverbed on the curve near the bridge have
been calculated in the previous items.

18
Total III 0.00
IV) CONCRETE WORKS
Grouting joints on the front side of stone prisms
using fine grain concrete MB 20. The joints are
sealed from the level of water minimun to the
stone lining on the slope.
Calculation per m2 of sealed surface.
(65+71)x1.41=192m2

19 m2 192.00 0.00
Total IV 0.00

V) REINFORCEMENT WORKS
Reinforcement for all elements
kg 0.00 115.00 0.00
Total V 0.00

VI) OTHER WORKS


Final cleaning, landscaping abutments area and
reinstating to their original state the locations used
for temporary storage of materials and work
equipment as auxiliary and sanitary facilities.

20 lump 1.00 0.00


21 As-built Design pcs 1.00 0.00
Total VI 0.00
OVERALL 0.00

BILL OF QUANTITIES
The Dumaca Road Overlapping
I) ROAD OVERLAPPING WORKS
Works on lining shoulders, part of embankment and road maintenance channel using broken stone calculated with
works on the river regulation.
Demolition of entire pavement of asphalt average
thickness of 20 cm, starting from the bridge wing.
The price includes loading and transportation of
materials to the landfill determined by the
Employer. Transportation to be calculated up to 10
1 km.
According to the table

m3 21.90 0.00
Scraping of asphalt average thickness of 5.5 cm for
overlapping to the existing pavement.
2 36.95/67= 0.0552 m average thickness
67x6.6=442.2m
m2 442.00 0.00
Preparation of work joints for paving continuation.
6.6x2 =13.05m
3
m 13.20 0.00
Ecavation of shoulders, part of embankment and
slopes at end slopes 90% mechanically and 10%
manually. The price includes loading and
transportation of material to the landfill
4 designated by the Employer. Transportation to be
calculated up to 10 km.
Tabular

m3 610.80 0.00
Procurement of materials, spreading and
compacting of base layer of gravel or stone debris
in a layer thickness of 10 cm.
5 Tabular.

m3 34.27 0.00
Concreting on-site of reinforced concrete
protective walls (beams) on the shoulders using
concrete MB 30. The price includes also the
corresponding formwork. Calculation per 1 m3 of
6 placed concrete. Quantities according to formwork
schedule.
106.2+18.9+2.88=127.98M3

m3 127.98 0.00
Supply, cutting and assembling the reinforcement.
7
kg 3,594.00 0.00
Procurement of materials, transportation and
installation with compacting of pavement bearing
structure (wedge) of granulate crushed stone 0- 31
8 mm. Calculation per 1 m3 of placed material.

m3 74.90 0.00
Execution of asphalt layer of BNS for levelling.
Calculation per 1 t of placed material.
9 Tabular = 27.31m3x2.4=

t 65.54 0.00
Supply and installation of prefabricated curbstone
18x12 on the layer of cement mortar. The price
includes sealing joints between concrete and
10 curbs. Calculation per 1 meter of built-in curb.
(42+25)x2=134m

m 134.00 0.00
Paving the road surface on the overlapping with
asphalt concrete AB 11 in a single layer of 4cm.
11 67.0x6.6=442.2m2

m2 442.20 0.00
Filling embankment slopes next to concrete walls
12 using soil from the excavation.
m3 5.40 0.00
Procurement and installation of bridge gully S5 or
the like in the pavement. The price includes
placing the arch 87.5 ° and drain pipes l = 1.3m
13 PVC Ø200. Calculation per piece of set of mounted
gullies.
kom 1.00 0.00
Supply and installation of prefabricated reinforced
concrete drain channel on a layer of gravel d =
10cm. The price includes also the supporting
beam at the bottom. Calculation per 1 meter of
14 built-in drain channel.

m 8.00 0.00
Placing PVC pipe diameter of 110 mm in reinforced
concrete walls used for installations.
15 3x67x2=402m

m 402.00 0.00
Procurement of materials, fabrication and erection
of guard rails of pedestrian pathways on the
protective beam along the bridge. The price
includes the ACP corrosivity category S4 with
16 painting using epoxy-polyurethane system.
Calculation per 1 kg of installed guard rails.

kg 292.32 0.00
Supply and installation of bridge steel safety
barriers type H1 according to the detail in the
Design, including protection by hot dip galvanizing
procedure and anchoring in the concrete
walkways.
17 Overlapping of the existing barriers is the
obligation of the Employer.
(42+25)x2=134m

m 134.00 0.00
Landscaping of slopes and shoulders. The price
18 includes also topsoiling.
lump 1.00 0.00
OVERALL WORKS: 0.00
TOTAL DUMACA
1 BRIDGE REHABILITATION 0.00
2 RIVERBED REGULATION 0.00
3 ROAD OVERLAPPING 0.00
TOTAL 0.00
BILL OF QUANTITIES
REHABILITATION WORKS ON THE BRIDGE OVER THE TAMNAVA RIVER

Unit Quantity of
No. Item description Unit price
mere Works
CONSTRUCTION WORKS
Note:

Bill of Quantities does not cover:


- Turning off installation of lighting on the bridge, design and execution of new installations.
- Switching other installations from temporary supports in the ducts in new walkways and in manholes on sidewalks.
- Only water supply pipe is accepted with new girders in the same position.

BEFORE COMMENCEMENT OF WORKS USERS OF INSTALLATIONS SHALL BE INFORMED TO PREPARE DESIGNS OF


INSTALLATION TRANSFERRING UP TO COMPLETION OF REHABILITATION AND TO EXECUTE THEM.

I ) PRELIMINARY WORKS
Site preparation and organization
-site application (registration)
-power supply connector
1 -transportation of containers and equipment
-security service (60 days)
pcs 1.00
Placement of traffic signs and traffic lights for
conducting alternating one-way traffic, according
to the design of traffic signs.
The regulation of any restrictions and interruption
of traffic shall be included in the unit price.
The position of traffic lights and traffic signs is
2 changed during the works (changing traffic
carriageway).

pcs 1.00
Setting up a temporary scaffold for accepting
installations from the bridge on the upstream side.
Scaffolding is placed next to the existing bridge
cantilever but in a way that does not interfere with
the formwork for the new cantilever mounts.
Width of the floor of scaffolding to 1.0m. Length as
the entire bridge. The average height of the
3 scaffolding 3.8m. Calculation per 1 m3 of erected
and dismantled scaffolding.
1x3x42=126m3

m3 126.00
Setting up and dismantling operational tubular
scaffolding under structure of carriageway slab in
the middle span of the bridge. Scaffolding width
13m, average height of 4.4m. Floor of scaffolding
must be positioned 1.5m from the bottom edge of
the structure. Floor is moved under the bridge as
necessary and below cantilever of footpaths that
are demolished the floor should be set for
receiving debris from the structure. Final
4 calculation according to the actual quantity of
placed and dismantled scaffolding. Calculation per
1 m3 of erected and dismantled scaffolding.
4.4x15.3x12=807.84m3

m3 807.84
Setting up the necessary guard rail made from
tubular profiles between pavement and areas of
work during one-way traffic and the flow of both-
way traffic. Calculation per running meter of
5 installed guard rails and dismantled guard rails for
each phase of the traffic.

m' 50.00
Setting up and moving light mobile scaffolding
height up to 1.5 m for works under the bridge in
6 the first and last span.
m3 30.00
Total I:

II) DISMANTLING, REMOVAL AND DEMOLITION WORKS


Removing the plants, shrubs and stumps from
slopes of end slopes and bank under the bridge.
7
lump 1.00
Removing the entire pavement structure from the
bridge and between wings. Pavement structure
includes 10cm of asphalt, stone cubes 10cm and
sand layer d=5cm. Remove sand layer manually
not to damage concrete of pavement structure.
The price includes loading and transportation of
materials to the landfill determined by the
8 Employer. Transportation calculated for up to 5
km.
8x49.80=398.4 m2

m2 398.40
Demolition of existing sidewalks on the
approaches to the bridge on both sides together
with curbs within the limits of operation. The
average width of sidewalk with curb amounts to
9 1.5m, and the assumed average thickness of
25cm.
11.4x4=45.6m'

m' 0.00
Removal of the existing stone curbs 18x20 along
the bridge and wing walls.
The price includes: loading, transportation and
unloading at a place determined by the Employer.
10 Transportation calculated for up to 5 km.
49.8x2=99.6m'

m' 99.60
Manual removal by chiselling the friable concrete
from concrete decks after removing pavement
surface. Quantity assumed 25% of the uncovered
11 (removed) area.
8.4x41.72x0.25=87.61m2
m2 87.61
Removing railings for pedestrians by cutting on the
left and right sides of the bridge. Anchor plates are
removed together with cantilever concrete of
footpaths that is demolished. The price includes:
loading, transportation and unloading at a place
12 determined by the Employer. Transportation
calculated for up to 5 km.

m' 99.60
Removal by the demolition of the concrete
structure of footpaths with asphalt layer to 3cm
between curbs and cantilever culverts. from bridge
and wings. The dimensions and structure of
footpaths is assumed.
The price includes loading and transportation of
13 debris to the landfill determined by the Employer.
The calculated distance to 5 km
0.34x0.84x49.8x2=28.44m3

m3 28.44
Removing by demolition using pickhammers of
reinforced concrete cantilever culvert on footpaths
on the bridge and wings. The existing
reinforcement of cantilever to be cut.
The price includes loading and transportation of
debris to the landfill determined by the Employer.
14 The calculated distance to 5 km. Scale for receiving
debris is paid separately.
(0.18+0.25)x0.5x41.72x2+
(0.18+0.25)x0.5x0.22x4x4=19.13m3

m3 19.13
Removing the existing gullies after removing
pavement from the bridge. Gully outlet is no more
than Ø75 and dimensions and shape of the upper
side beneath the asphalt are not known. The price
includes chiselling of concrete around gully vertical
line from the bottom in-depth 10cm, cutting the
15 vertical, closing the holes with cement mortar and
sealing from the upper side with cement mortar.
Calculation per piece of gully.

pcs 16.00
Dismantling of the existing poles and complete
installation of lighting on the bridge together with
16 steel girders. Poles are deposited directly to the
construction site.
pcs 6.00
Dismantling of coating, girders and installation on
the upstream side of the bridge. Installation is
temporarily supported by auxiliary scaffold which
is calculated separately. Existing installations: 4
optic cables, Telekom
17 - 1 high-voltage cable (20 kV), 1 cable for street
lighting and 1 low voltage cable.

lump 1.00
Dismantling of the existing steel girders,
installation of water supply on the downstream
side of the bridge after concreting cantilever and
acceptance of water supply with new girders.
18 Scaffold is calculated separately. Calculation per
piece of dismantled girder.

pcs 11.00
Collection of debris that fell from the structure,
loading and transportation to the landfill
19 determined by the Employer. Transportation
distances up to 5 km.
lump 1.00
Total II:
III) EARTHWORKS
Excavation of soil material on pavement behind
the pillars after removal of asphalt for the
purposes of execution of concrete floating slab
70% mechanically and 30% manually. After the
excavation, conduct planning of the trench bottom
with accuracy of ± 1.5 cm. Excavation is done by
Contractor's methodology, fully in accordance with
the supervisory engineer and the applicable
regulations of safety at work. The calculation
according to the actually excavated quantities
under measures specified in the design.
20 The price includes all labor, machinery, loading
and transportation of soil material to the landfill
determined by the Employer. Transportation
distances up to 5 km.
(2.8x0.1+0.65x0.6)x8x2=11.24m3

m3 11.24
Filling and compacting base layer of d=15cm and
wedge of gravel to compaction Ms = 30MPa below
the concrete floating slab, under and around the
concrete manhole over previously planned
bottom.
Unit price includes all necessary work, material,
machinery and transportation of the material
21 required.
Calculation per 1 m3 of filled materials.
3x8x0.15x2+1.2x1.5x4+5=19.4m 3

m3 19.40
Total III:
IV) CONCRETE WORKS
Concrete works to be performed by the
Contractor's methodology, fully in accordance
with the supervisory engineer and applicable
regulations for this type of work.
Unit price in addition to the above includes all
preparatory works, formwork execution with all
the necessary work and material in its assembly
and disassembly with included transportation, as
well as all other work, tools and materials
necessary for the works.
Sandblasting the upper surface of the pavement
slab after the demolition of cantilevers, front
surfaces of slab behind the abutments after the
excavation for floating slab, the upper surfaces on
wing walls after the removal of footpaths. Sand
blasting must be carried out under a protective
curtain and screen. Sandblasting to be done after
22 manual removal of friable concrete at the surface
to be repaired.
10x41.72+1.34x4x4=438.64m2

m2 438.64
Pick hammering the top surface of the pavement
concrete slab.
23 350.44-87.61=262.83m2
m2 262.83
Coating the pavement surface of deck using joint
24 for the old and new concrete.
m2 350.44
Drilling holes Ø 25 using impact drill with length of
25 CM on the upper side of the carriageway slab.
The price includes exhausting of holes, injection of
Sikagard 31/41 (or another of the same
characteristics) and placing anchors. Anchors are
25 calculated separately.
2756 pcs

pcs 2,756.00
Welding cross ribbed reinforcement of carriageway
slab Ø12 mm on a free overlap according to BAB.
Calculation per piece of welded reinforcement.
26 = 0 pc

pcs 0.00
Concreting onsite cantilever culvert on the bridge
and wing walls using concrete class MB 30, V6,
M150. The price includes appropriate formwork
and scaffolding. Calculation per 1 m3 of concrete
placed. Surfaces calculated in AutoCAD.
27 0.315x41.72x2+0.21x4x4
+0.45x0.45x0.3x3x2=30.00m3

m3 30.00
Concreting onsite of thickening of deck on the
bridge on the part of pathways and on pavement
using concrete class MB 30, V6, M150. Concrete
first one side then the other with traffic on the
other lane. The exact quantity will be determined
on the spot together with the supervisory
28 engineer. Calculation per 1 m3 of placed concrete.
0.16x4.22x2x41.72+0.254x47.72x2+
0.545x4x4-9x0.007x49.72x2=84.94m 3

m3 84.94
Concreting with fine-grained concrete MB 30, V6,
M150 of parts of structure ends of the wing walls
29 after the demolition and removal of friable
concrete. The quantity is estimated.
m3 1.00
Concreting floating slab d = 20cm onsite using
concrete MB 30.
30 Calculation per 1 m3 of placed concrete.
3x0.2x8x2=4.8m3
m3 4.80
Concreting columns of railings for pedestrians
using concrete MB 30, V6, M150.
Calculation per 1 piece of concreted columns.
In one piece of column calculate 0.07m3 of
31 concrete.
19x2=38 pcs

pcs 38.00
Total IV:
V) REPARATION OF CONCRETE SURFACES
Reparation of concrete surfaces on the deck from
the top side after removal of pavement surface
and demolition of footpaths. The price of the
repaired surface inputs: Protection of corroded
rebars using means for rebar protection.
Sandblasting is included in part with concrete
works. Replacement of reinforcement parts or
adding the grid is paid separately.
The quantity for reparation has been estimated.
The final quantities are to be determined based on
32 actually measured, and repaired surface.
Calculation per meter of protected reinforcement.

m' 50.00
Repair of concrete surfaces using reparation
mortar up to 3 cm on the deck from the bottom
side on pillars and wing walls. The price of the
repaired surface inputs: location setting out,
cutting with a saw, removing low quality concrete
by chiselling, quartz sand blasting and surface
coating using mortar for joints and protection of
reinforcement and placing reparation mortar.
Replacement of reinforcement parts or adding grid
is calculated separately. Scaffolding is separately
calculated both for pillars and deck.
The final quantities are to be determined based on
33 actually measured, and repaired surface.
pillars and wings = do 5m2
bottom slab = do 4 m2
lateral areas = do 10m2

m2 19.00
Repair of concrete surfaces using reparation
mortar up to 5 cm on the deck from the bottom
side on pillars and wing walls. The price of the
repaired surface inputs: location setting out,
cutting with a saw, removing low quality concrete
by chiselling, quartz sand blasting and surface
coating using mortar for joints and protection of
reinforcement and placing reparation mortar.
Replacement of reinforcement parts or adding grid
is calculated separately. Scaffolding is separately
calculated both for pillars and deck.
The final quantities are to be determined based on
34 actually measured, and repaired surface..
pillars and wings: to 1m2
bottom slab: to 1 m2

m2 2.00
Grouting of cracks on the sides of the deck.
The calculation of 1 m' of injected crack shall
include all the necessary materials, preparation of
crack and injecting epoxy resins. Scaffolding is
35 calculated separately.
Up to 5 m

m' 5.00
Repair of surfaces from which the shotcrete
mortar had fallen, from surfaces on which the
process of separation and cracking of shotcrete
mortar started.
The price includes:
-mechanical removal of shotcrete mortar which is
separating,
-sandblasting of area without shotcrete mortar,
36 -coating surfaces with reparatory mortar for fine
alignment.
The amount is estimated

m2 25.00
Replacing broken smooth reinforcement.
Reinforcement has already been sand blasted. The
price includes needed suspenders and needed min
welding according to BAB. Calculation per piece of
37 reinforcement replaced. Quantity has been
assumed.

pcs 30.00
Total V:
VI) REINFORCEMENT WORKS
The reinforcement for all elements of the bridge.
Slab= 12342 kg
Footpath on the wing=1047kg
Posts on footpaths=330 kg
38 Floating slab=239kg

kg 13,958.00
Total VI:

VII) STRENGTHENING OF THE STRUCTURE USING FRP- LAMINATE BRIDGE PLATE

Strengthening deck using strips of SikaCarbo Dur


S2.025/80. In the unit cost of 1 m' to be also
calculated: the provision of all necessary materials,
preliminary tests, providing the access to the
workplace, preparing concrete surfaces and
removing shotcrete mortar including the eventual
leveling layer and primer, bonding of laminate,
39 quality control and finishing processing. Access
scaffolding is separate
30x9.5+30x2x8.8x=813m'

m' 0.00
Total VII:

VIII) OTHER WORKS


Procurement and installation of bridge flat gullies
S1 with vertical outlet L = 1.4m. The price includes:
puncturing deck slab thickness of d = 70cm,
complete ACP-degree of corrosivity S4, assembly
and grouting (sealing) of the gullies with mortar
for grouting based on epoxy. Mortar must be
waterproof without shrinkage. Calculation per
40 piece of installed gully.
Payment per piece of placed gully.

pcs 6.00
Procurement of materials, fabrication and
installation of new water supply pipe brackets on
the downstream side of the bridge. Calculation per
1 bracket
The price of bracket includes:
- Cutting the existing casing in width of 10 cm
- procurement of bolts M20 L = 750mm pcs = 2
-procurement of angle L 100x100x10 L = 500 pcs =
41 1
-protective pipe closing and setting up thermal
insulation after removal of the existing brackets

pcs 11.00
Procurement and waterproofing performance of
the deck and cantilever of the wing walls made of
SBS - with bitumen tape. The quantity calculated
also overlapping in the middle. The price includes
42 also rounded edges of cement mortar at parapet
beam on the cantilever.
(8.44+2x(0.25+1.32))x41.48=480.34m 2

m2 480.34
Supply and installation of precast concrete curbs
on the layer of cement mortar with the concrete
class of MB40 and frost resistance min M-150. The
price includes also sealing of joints with cement
43 mortar 1:3. Calculation per running meter of
mounted curb.
49.72x2=99.44m

m' 99.44
Supply and laying of bituminous sealing strips
along the concrete edge beam before paving and
only on the part of the deck. Width of the sealing
44 strip is to 8 cm.
41.48x2=82.96 m'
m' 82.96

Setting the PVC pipes diameter of 110 mm in the


45 footpaths on the bridge and wings used for
installations.
(4+5)x49.48=446m'
m' 446.00
Setting the PVC pipes diameter of 75 mm in the
footpaths used for lighting installations.
46 49.48x2=98.96m'
m' 98.96
Concreting manhole for the installation on
pavement next to the bridge. Calculation per one
piece of performed manhole. The price includes:
excavation of soil = 5.4m3
base and gravel wedge = 4m3
base = 0.1m3 of concrete
MB30 manhole concrete = 1.0M3
47 reinforcement = 40kg
cast cover 60x60 N = 15kn = 1 piece
climbing frames = 2 pcs

pcs 4.00
Manhole 30x30 depth 20 cm on foot paths for
lighting. Calculation per one manhole.
The price includes:
-Setting the drain pipe Ø50 L = 15 cm
48 -Ribbed Ø75 for cable lighting
-Manhole waterproofing 0.3 m2
- Cast cover 35x35 cm 1 piece

pcs 6.00
Sandblasting, ACP and re-erection of the columns
of lighting. The price includes purchase and
installation of anchor plates. Setup and installation
49 of cables is not included in the price.

pcs 6.00
Supply and installation of luminaries of bridge
lighting. Calculation per piece of embedded
50 luminaries. The price includes dismantling of
existing luminaries.
pcs 6.00
Procurement of materials and installation of
seamless round pipes Ø 51mm length of 230 mm
into the concrete guard rails posts for pedestrians.
51 The price includes also ACP. Calculated per 1 kg of
installed pipes.
pcs 76.00
Procurement of materials, fabrication and erection
of guard rails of pedestrian pathways on the bridge
and wings. The price includes the ACP corrosivity
category S4 with painting using epoxy-
52 polyurethane system. Calculation per 1 kg of
installed guard rails.
24x69.74+12x65.82=2464kg

kg 2,464.00
Paving the road surface on the bridge structure
and above floating slabs using asphalt concrete
53 AB 11 thickness 2x4= 8cm.
8x47.48=379.84m2
m2 379.84
Paving the road surface on the bridge pedestrian
paths and on wings using asphalt concrete AB 8
54 thickness of 3.
1.32x49.72x2=131.26m2
m2 131.26
Execution of asphalt expansion joint AD40 +/- on
part of the roadway and pedestrian paths. The
price includes mechanical cutting of asphalt and
extracting asphalt using pickhammer, cleaning
joint in width of 40cm, all necessary primers and
materials according to the manufacturer's
instructions. In addition to this the price shall
include placing and removal of protective board
placed over dilatation hole and waterproofing.
After cleaning the riverbed be sure to set the
appropriate galvanized sheet.
55 Fully in accordance with the technical drawings.
Riverbed depth d = 8cm on pavement and 6 cm on
walkways. Calculation per 1 m' of built-in
expansion joint.
(8.44+1.31x2)x2=22.12m'

m' 22.12
Cleaning of existing end slopes from vegetation,
debris and soil with embedding stone required.
56 The price includes sealing of joints between stone
using cement mortar.
m2 120.00
Protective coating of old concrete areas after
repairs of pillars, wings and the bottom slab using
protective coating Sikagard 680-S. Scaffolding is
calculated separately. Calculation per m2 of the
57 coated surface.
(0.8x2+10)x39.44+1.7x(11+2x5)x2=
528.9m2

m2 528.90
Traffic signals after the reconstruction of the
58 bridge. According to the separate design.
pcs 1.00
Trial bridge load. The price includes preparation,
work on the structure, processing the results and
reports. The bridge is of the system with
continuous slabs and three openings.
59 L= 12+15.8+12
Paid by lump sum.

lump 1.00
60 As-built Design pcs 1.00
Total VIII:
OVERALL BRIDGE REHABILITATION WORKS:

BILL OF QUANTITIES
TAMNAVA RIVERBED REGULATION
Quantity of
NO Item description Unit price
Unit Works
CONSTRUCTION WORKS
NOTE:
I ) PRELIMINARY WORKS
Setting out and surveying the work axis of riverbed
alignment, setting out the envisaged sections and
geodetic monitoring during construction works.
Calculation per 1 running m.

1 m' 120.00
Removing the stone lining on parts that have not
been destroyed and that interfere with the newly
designed profile of regulation. Lining is deposited
directly to the minor because it can be used for a
new liner.

2 m3 30.00
Removing the stone rockfill that has been pitched
along medium pillar on the left bank. The stone is
removed to the newly designed elevation of
shoulder of minor riverbed and it is placed
upstream to the existing stone pitch.
1.5x3x2=9m3

3 m3 9.00
Closing water flow in the portion where the works
are performed by executing barrier on upstream
and downstream part of the observed section, for
the purpose of execution of works in the dry.
Selecting the type of barrier and section length
depending on the methodology available to the
Contractor (interruption of the water flow along
the section where works are carried out with the
help of a coffer dam from soil material or
otherwise). It is understood that the coffer dam
upon completion of the work is to be removed,
and the river bed, which is not regulated, to be
reinstated to its original condition.
Unit price includes all necessary works and
materials for execution of works in proper quality.
The Contractor is obliged to take all safety
measures.
Calculation per completely carried out work.

4 pcs 1.00
Clearing the ground, cutting shrubs and low
vegetation in the area which covers the riverbed.

5 m2 1,500.00
Dismantling bracket of pipeline downstream from
the bridge.
6 lump 1.00
Total I

II) EARTHWORKS
Formation of riverbed between the profiles 3 and
4 downstream excavation to 0.5m and removing
slid stone. The stone is disposed to a temporary
landfill outside the work zone.
0.5x 3.7x0.5x10=9.25m3

7 m2 9.25
Mechanical excavation of the Tamnava riverbed
(minor and small part of major). Item includes
depositing material to a temporary landfill outside
the work area, for later placement in
embankments of riverbed minor and major.
1863.32-55=1808

8 m3 608.00
Mechanical and manual excavation of soil for road
maintenance channel on the left bank.
(2.55+0.75)x0.5x0.9x34=50.49m3
9 m3 50.49
Filling with soil from the excavation of the area
behind the stone pitch on the left bank from the
riverbed excavation to the designed level. The
material is installed in layers of 30cm. The material
must not contain humus and organic substances.
Item includes loading material from excavation on
a temporary landfill, transportation to the site and
installation in layers. Calculation per m3 of filled
material.

10 m3 44.00
Backfilling of road maintenance channel on the
left bank and sewer trench on the right bank
upstream from the bridge with soil from
excavation.
11 m3 80.00
Formation of cross slopes in inclination 1: 1.5 on
the banks in the abutments area and profiling
bridge end slopes.
12 lump 2.00
Loading and transportation of excess soil from the
temporary landfill to landfill designated by the
Employer. Transporting distances up to 5 km. The
price includes arrangement of the landfill.
Calculation per 1 m3 of hauled material.
(608+50.49)-44-80=534.5m3

13 m3 534.50
Backfilling of the channel on cross regulation
structure between sections 10 and 11 which is
formed along the left bank. The channel is
backfilled with crushed stone from the temporary
landfill to the upper level of the existing
regulation.

14 m3 6.00

Total II

III) WORKS IN GRAVEL AND STONE


Supply, transportation and installation of base
layer d=10cm thick from gravel material beneath
the substrate of concrete on the bottom, slope and
shoulder of riverbed minor.
Calculation per m3 of built-in material.
15 m3 34.00
Supply, transportation, installation and formation
of prism of broken stone diameter of 25 to 45 cm.
Lying width of prism is 2m, and slopes in
inclination of 1:1. The price includes formation of
the slope on the front side by rolling, manually
and using g

16 m3 100.00
Supply, transportation, installation of stone pitch
made of broken stone diameter 25 to 45cm. The
price includes formation of the slope on the front
side in inclination of 1:1 by rolling, manually and
using grapples.

17 m3 295.00
Manual coating of slopes and shoulders of
riverbed minor and slopes beneath the bridge (on
the bank) using crushed stone 30cm thick in
cement mortar 1:3. Joints are sealed with cement
mortar 1:3, and then grouting is to be executed.
Before sealing with cement mortar joints are to be
washed with water and compressed air. Quality of
stone and work must be in accordance with
applicable regulations for this type of work.
Calculation per m3 of placed coating.

18 m3 187.00
Loading, transportation, installation and formation
of of stone pitch of broken stone15 to 25 to
protect the existing sewer pipes, on the bottom of
the river, downstream from the bridge. After
formation of structure slopes roll the surface
manually or using grapples. Stone is taken from
the temporary landfill made of previously removed
stone.
Calculation per m3 of placed coating.
(1.5x0.5+1x3.1x0.5)x6.5=14.95m3

19 m3 14.95
Stone coating d = 30 cm in cement mortar 1:3 of
major cross slopes (embankments near
abutments) on the right and left bank. Joints are
sealed in cement mortar 1:3 and then grouted.
The price includes gravel layer of 10cm.
Calculation per m3 of embedded stone.
(23.1x1.2x4)x0.2+0.5x0.5x 12x4=34.54m3

20 m3 34.54
Execution of stone foundation in concrete MB30
on parts of stone lining under the bridge and lining
of major cross slopes. The foundation dimensions
are 50x50.
0.5x0.5x11.5x4=11.40m3

21 m3 11.40
Formation of road maintenance channel on the
left and right bank. The channel is trapezoidal
formed using stone d = 20cm sealed, then grouted
with cement mortar 1:3. The price includes base
layer of gravel d=10cm. Calculation per 1 meter of
constructed channel.
in 1 meter of Channel belongs. Excavation is
separately calculated.
Gravel = 0.33m3
Stone = 0.52m3
L = 35x2 = 70m '

22 m' 70.00
Total III
IV) CONCRETE WORKS
Grouting joints on the front side of stone prisms
using fine grain concrete MB 20. The joints are
sealed from the level of water minimum to the
stone lining on the slope.
Calculation per m2 of sealed surface.
1x2x50=100m

23 m2 100.00
Concreting wit plain concrete MB 30 of the
supporting foundations of road maintenance
channel on the layer of gravel. The foundations are
formed on the shoulders of regulation.

24 m3 4.00

Total IV
V) REINFORCEMENT WORKS
Reinforcement for all the elements
25 kg 0.00

Total V

VI) OTHER WORKS


Final cleaning, landscaping abutments area and
reinstating to their original state the locations used
for temporary storage of materials and work
equipment as auxiliary and sanitary facilities.

26 lump 1.00
As-built Design
27 pcs 1.00
Total VI
OVERALL
ROAD OVERLAPPING
BRIDGE OVER THE TAMNAVA RIVER IN TOWN STREET IN KOCELJEVA

Quantity of
NO Item description Unit price
Works
Unit
I) ROAD OVERLAPPING WORKS
Demolition of existing pavement on the
approaches to the bridge on both sides along with
curbs on the side in the limits of overlapping. The
average width of the sidewalk with curb is 1.5m,
and the assumed average thickness of 25 cm.
The price includes loading and transportation of
materials to the landfill determined by the
1 Employer. Transportation to be calculated up to 5
km.
11.4x4=45.6m'

m' 45.60
Scraping of asphalt thickness of 4 cm for
overlapping to the existing pavement at 3 m from
limiting of overlapping to the existing level.
2 7.36x3x2=44.16m2

m2 44.16
Preparation of work joints for paving continuation.
7.89+7.26 =15.15m
3
m 15.15
Demolition of entire pavement of asphalt average
thickness of 43cm in length of 8.45m on one bank
and 8.10m on the other bank starting from the
bridge wings. The composition of structure to be
removed is not known.
The price includes loading and transportation of
materials to the landfill determined by the
4 Employer. Transportation to be calculated up to 5
km.
7.8x(8.45+8.10)=129.09 m2

m2 129.09
Procurement of materials, transportation and
installation with compacting of pavement bearing
structure and base under the pedestrian paths of
granulate crushed stone 0- 31 mm. Calculation per
5 1 m3 of placed material.
7.67+33.87=41.54m3

m3 41.54
Execution of asphalt layer of BNS average
thickness of 10 cm in part behind pillars and
6 beside wing walls.
m2 128.41
Supply and installation of prefabricated reinforced
concrete curbs 18x24. Calculation per 1 meter of
built-in curb.
7 m 40.93
Paving the road surface on the overlapping with
asphalt concrete AB 11 in two layers 2x4cm.
8
m2 175.71
Concreting using plain concrete MB30 of the
sidewalk on overlapping. Concrete thickness
9 d=10cm.
m3 5.40
Paving the pavement surface on the footpaths
with asphalt concrete AB 8 average thickness of 3
10 cm.
m2 54.03
Landscaping of slopes and shoulders. The price
11 includes also topsoiling.
lump 1.00
Traffic signals after the reconstruction of the
12 bridge. According to the separate design.
lump 1.00
OVERALL WORKS:
BILL OF QUANTITIES FOR TRAFFIC SIGNS AND EQUIPMENT

Quantity of
NO Item description Unit price
Works
Unit
I PERMANENT TRAFFIC SIGNALS
1) ELEMENTS OF VERTICAL SIGNS

1.1 Notice signs


III-58 "Tamnava" (rectangular sides 1100 x
800mm) - class II
pcs 2.00
1.2 Traffic signs posts
Single-column pipe posts length of 4000 mm pcs 4.00
2) PAVEMENT MARKING ELEMENTS
2.1 Longitudinal, cross lines and other markings - SRPS U. S4. 222 do 234
Uninterrupted dividing line, d=0.15 m m2 6.00
Ordinary dashed (5.0 + 5.0) line, d = 0.15mm m2 5.50
Guiding line (1.0+1.0), d=0.12 m m2 4.00
TOTAL I
II TEMPORARY TRAFFIC SIGNALS
Supply and installation of temporary traffic signals
fully in accordance with the specification. lump 1.00
Temporary traffic signals remain in the possession
TOTAL II
of the Contractor after completion of the works.
OVERALL I + II
SUMMARY OF WORKS
1 BRIDGE REHABILITATION
2 REGULATION OF THE TAMNAVA RIVERBED
3 ROAD OVERLAPPING
4 TRAFFIC SIGNS
OVERALL
MNAVA RIVER
Amount
in RSD

ns.
d in manholes on sidewalks.

O PREPARE DESIGNS OF
E THEM.

0.00

0.00

0.00
0.00

0.00

0.00
0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00
0.00
0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00
0.00
0.00

0.00
0.00

0.00

0.00

0.00
0.00
0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00

0.00
0.00
0.00
0.00

Amount
in RSD

0.00

0.00

0.00
0.00

0.00

0.00
0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00
0.00

0.00
0.00
0.00

0.00

0.00

0.00

0.00

0.00

0.00
0.00
0.00

N KOCELJEVA

Amount
in RSD
0.00

0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00
0.00
IPMENT

Amount
in RSD

0.00

0.00

0.00
0.00
0.00
0.00

0.00
0.00

0.00

0.00
0.00
0.00
0.00
0.00
PRICED BILL OF QUANTITIES - MONTAGE OF THE SIGNBOARDS
Scetch of signboard and method statement for montage
attached

No DESCRIPTION UoM Quantity

I PREPARATORY WORKS
1

Mounting and dismounting of the metal pipe scaffold, fully


according to standing regulations and PP measures. The
scaffold shall be structurally stable, and properly grounded.
Working platforms made of 5cm boards shall be placed at
2.00m of height. From the exterior, 5cm boards shall be
placed vertically as guards. The scaffold shall be used
throughout the montage of the signboard and untill concrete
foundation reaches70% of its load bearing capacity.Same
scaffold is to be used for mantage of all signboards.
Calculated per m2 of vertical
projection of the assembled scaffold. m2 10.00
TOTAL

II EARTH WORKS
Manual excavation of 3rd category soil for signboard
foundations. The excavation shall be executed and levelled
according to the design and provided elevation points. The
sides shall be clean and verticaly cut and the bottom levelled.
Excavated soil shall be wheelbarrowed, poured and the
terrain levelled or loaded onto a lorry and transported to the
town landfill. Calculated per m3 of soil, measured in
autochthonous state.

m3 1.50
TOTAL

III CONCRETE WORKS


Manufacture of the unreinforced concrete foundation mark
MB20;Hight of fuondation is 80cm and other two dimensions
90x60cm. Concrete should be poured over the gravel layer
thickness 10cm The top surface shall be floated and the
concrete shall be cured according the regulations. Unit price
shall consider gravel layr and all neccessary formwork
Calculated per m3 of foundation.

m3 1.30
TOTAL

IV MONTAGE WORKS
Installation of steel plates for marking of donor.Table is
rectangular in shape, dimensions and materialization
according to the sketch , mounted on a steel substructure
consisting of steel profiles 80x80x4mm , and metal sheet d =
1mm . The total height of the table is 4m, of which 80cm is
anchored into the concrete, and the lower angle of table is
at a height of 2.2m above ground level. Calculated per peace
of installed signboard

kom 3.00
TOTAL

TOTAL MONTAGE OF SIGNBOARDS WORK


Unit Price TOTAL RSD

0.00
0.00

0.00
0.00

0.00
0.00
0.00
0.00

0.00
TOTAL SUMMARY
FOR REHABILITATION WORKS ON THREE BRIDGES

In Krupanj, Koceljeva and Sabac Municipalities

I REHABILITATION WORKS ON THE LIKODRA BRIDGE


II REHABILITATION WORKS ON THE DUMACA BRIDGE
III REHABILITATION WORKS ON THE BRIDGE OVER THE TAMNAVA RIVER
IV MONTAGE OF THE SIGNBOARDS
TOTAL
0.00
0.00
0.00
0.00
0.00