You are on page 1of 7

The area of the plot is 802.

2 sqm and plinth area proposed construction in STILLT is


460.17m2, GF 563.97m2, F.F 563.97m2, S.F 563.97m2, T.F 563.97m2

The estimate is prepared based on prevailing local market and PWD rates.
Contract labour rates are adopted for finished items of works. A brief specification
report certificate is also here with enclosed.

The estimate includes provision for the Electrification of the entire building
with Concealed Wiring, Water Supply and Sanitary arrangements, installation of
0.50HP Electric Motor, Architectural finishing of the building etc., the estimate also
includes reasonable provision for the contingencies and petty supervision charges.

(RUPEES TWO CRORE TEN THOUSAND ONLY)


The Estimated Cost of Construction work out to Rs. 2,00,10,000)

(2)

SPECIFICATION REPORT

FOUNDATIONS: The foundation for all columns will be taken to a depth of 1.50m
and to size of 1.20m x 1.20m. The foundation concrete shall be of 1:5:10 mix, using
40mm and down graded hard broken granite metal other than granite to size of 1.20m
x 1.20m and to a thickness of 0.15m. Above that RCC 1: 1 ½ :3 for column footing of
size 1.20m x 1.20m with a thickness of 0.15m at free end and 0.38 at column end will
be laid. There will be flooring itself. The sides of trenches are to be filled with
excavated earth. The size of the column to be adopted is 0.23m x 0.30m using RCC 1:
1 ½: 3mix
BASEMENT: The walls in basement are to be constructed with Brick Masonry in
cement mortar 1:8 to a width of 0.23m and a height of 0.60m. The basement is to be
filled with carted earth collected from outside and is to be well compacted and
consolidated. There will be a continuous Plinth beam of size 0.23m x 0.30m using
RCC 1: 1 ½: 3mix
SUPERSTRUCTURE: The walls in Ground Floor and shall be raised to a height of
3.00m above the basement and above the slab and to a thickness of 0.23m using Brick
Masonry in cement mortar 1:8 using 2nd class table moulded country bricks. There
will be a continuous lintel beam alround to a thickness of 0.10m and to a width of
0.23m RCC 1: 1 ½:3mix. There will be a continuous ‘T’ beams of size 0.23m x 0.30m
using RCC1:1 ½ :3mix.
SUNSHADE: Reinforced cement concrete1: 1 ½ :3 mix, using 20mm and down
graded hard broken granite metal is to be adopted. The thickness at the support is
0.75m from the face of wall.
ROOFING: The Roofing will be with RCC 1:1 ½: 3mix using 20mm and
downgraded hard broken granite metal. The thickness of slab is 0.11cm and the
reinforcing steel shall not be less than 0.12% of grass sectional area and should be in
accordance with the Engineer’s design details.
FLOORING: Vitrified tile flooring over 100mm thick cement concrete 1:5:10 bed in
Ground floor.
PLASTERING: Both external and internal walls are to be plastered with cement
mortar 1:5 - 12mm thick. The Ceiling will be plastered with cement mortar 1:3-12mm
thick
WOOD WORK: All the wood work is to be carried out using well seasoned
Country wood and the sizes are as per the detailed drawings and specifications.
PAINTING WALLS: Two coats with best white cement over plastered surface of
walls and ceiling.
PAINTING WOOD WORK: Two coats with best synthetic enamel paint over a
primary coat of white lead.
ELECTRIFICATION: The Electrification will be Concealed type and number of
points will be as per actual requirements.
WATER SUPPLY: Bore well, 0.50 HP Electric Motor.
SANITARY ARRANGEMENTS: Septic tank along with soak pit. The entire work
is to be executed in accordance with Andhra Pradesh detailed standards specification
and other standard specifications

(3)

NAME OF WORK: the Estimate for the Construction of onsite STIILT+


Ground+3Floor

DETAILED MEASUEMENTS SHEET AND ABSTRACT SHEET

S.NO DESCRIPTION OF WORK NOS. MEASUREMENTS IN


METERES
LEN BRE DEP CON

1 2 3 4 5 6 7
1. Earth work excavation in foundation with an initial lead 10m and an initial lift of
2m, for foundation.

Column footings 72 1.20 1.20 1.50 155.52m3

@ Rs.1500.00/10 cu.M Rs.233280.00


2. C.C. Levelling Course in 1:5:10 using 20mm size O.T.G.metal including cost and
conveyance of all material and labour charges.

Column footings 72 1.20 1.20 0.15 15.54m3

@ Rs.3000.00/ cu.M Rs.46500.00

3. Reinforced cement concrete 1:1 ½ :3 using 20mm H.B.G metal and also using 60kg
of steel per cum of concrete including cost and conveyance of all material labour
charges.

Column footings (Rectangular) 72 1.20 1.20 0.15 19.77m3


Column footings (Trapezoidal) 72 X0.35 (1.202 + 0.38 X 0.45 + 4 X 0.802) 20.76m3
--------

Columns 72 0.23 0.30 12.34 61.29m3


----------
106.32m3
------------
@ Rs.16,000.00/cu.M Rs.1701150.00

4. RCC 1: 1 ½ : 3 for plinth beam alround including cost of necessary steel and labour
charges.

Walls alround 1 420.12 0.23 0.30 28.05m3

@ Rs.16,000.00/cu.M Rs.436200.00

(4)

5. Basement filling with Local sand for the basement including cost and conveyance
of all material and labour charges, pudling and consolidation charges.

Volume of Basement 1 41.91 24.00 0.90 905.25m3


Deduct (-)
Basement walls 1 168.12 0.23 0.90 (-) 34.8m3
----------
870.45m3
------------
@ Rs.700.00/cu.M Rs.609315.00

6. Brick Masonry in Cement Mortar 1:8 in superstructure in Stilt +G. F, +FF, S.F
using 1nd class table moulded country bricks.

Basement walls 1 77.42 0.23 0.90 16.02m3


Superstructure walls 3 77.42 0.23 5.14 274.57m3
Internal walls 3 240.0 0.10 2.75 198.0m3
Parapet walls 1 77.42 0.10 1.00 7.74m3
------------
498.33m3

Deduct (-)

Doors-D 36 1.00 0.23 2.00 16.56m3


Doors D 2 12 0.75 0.23 2.00 4.14m3
Windows –W 36 1.20 0.23 1.20 11.92m3
Windows –WK 6 1.20 0.23 1.00 1.52m3
Ventilator – V 12 0.90 0.23 0.60 1.49m3
----------
35.63m3
---------
Nett Qty 462.70m³
@ Rs.6000.00/cu.M Rs.27, 76,200.00

7. Supply and fixing of best Country wood doors and with Paneled shutters and
Including cost of all materials like holdfasts, tower bolts and hinges and including
cost of labour charges.

Doors D 36 1.00 - 2.00 72.00m2


Doors D2 12 0.75 - 2.00 18.00m2
----------
90.00m
@ Rs.6500.00/ Sq.M Rs.5, 85,000.00

(5)

8. Supply and fixing of teak wood glazed windows including cost conveyance of all
Material and labour charges.

Windows W 36 1.37 1.37 67.56m3


Windows WK 6 1.20 1.00 7.20m3
Ventilator – V 12 0.90 0.60 6.48m3
----------
81.24m2
---------
@ Rs.6000.00 sq.M Rs. 4, 87,440.00

9. RCC 1: 1 ½ :3 using 20mm and down graded hard broken crushed metal for
Sunshades alround cost of necessary steel and centering charges
Sunshades in 40 67.54 0.75 - 2026.20m2

@ Rs.800.00/ sq.M Rs16,20,960.00

10. Reinforced cement concrete 1:2:4 using 20mm metal and also using 60kg of steel
per cum of concrete for Lintel beams alround including cost of necessary steel and
centering and labour charges.

Lintel Beams in 9 77.47 0.23 0.10 160.92m3


In Internal walls in 9 240 0.10 0.10 216.0m3
----------
376.92m3
---------
@ Rs.15,000.00/m3 Rs.56,53,800.00

11. Reinforced cement concrete 1:2:4 using 20mm metal and also using 60kg of steel
per cum of concrete for Roof slab alround including cost of necessary steel and
centering and labour charges..

Roof slab in 5 10.52 17.47 918.92m2


Deduction staircase area 5 2.40 3.06 36.72m2
----------------
955.64m2

@ Rs.18,000.00/10 sq.M Rs. 17, 20,152.00

(6)

12. Reinforced cement concrete 1:2:4 using 20mm metal and also using 60kg of steel
per cum of concrete for ‘T’ beams alround including cost of necessary steel and
centering and labour charges.

T Beams 5 317.42 0.23 0.45 164.26m3

@ Rs.18,000.00/Cu.M Rs. 29,56,760.00

13 Flooring the rooms with vitrified tiles flooring of 20mm thick with vitrified tiles
over C.C .1:6:10 of 100mm including cost of necessary steel and labour charges.

Plinth area in 5 10.52 17.47 - 918.91m2


Deduct (-)

Walls area 5 77.45 0.23 - (-) 53.44m2


in Cross walls Long walls 5 240 0.10 - (-) 72.00m2
-------------
185.60m2
------------
Nett Qty 733.31m³
@ Rs.12000.00/ 10 sq.M Rs.26399160.00

14. Ceiling – Plastering with Cement mortar 1:3-12.50mm thick vide ref item No.
(12)

734..48m2
Add for Sunshades 56.31m2
Deduct (-)
Walls area 22.02m2
-----------
768.77m2
----------
@ Rs.2000.00/10 sq.M Rs.461262.00

15. Plastering the walls in C.M 1:5 of 20mm thick including cost and conveyance of
all material and labour charges.
External Walls in 8 77.47 - 3.00 1859.28m2
Internal walls in 8 240 - 3.00 5760.00m2
Parapet walls in 2 77.47 - 0.90 154.94m2
-------------
7774.22m2

Deduct (-) Door’s area & 90.00 m2


Windows area 81.49 m2
--------------
171.49m2
--------------
Net Area 7774.22m2 @ Rs.1600.00/10 Sq.M. Rs.3731256

(7)

16. Painting walls two coats with best white cem including cost of all materials like
brushes, waste cloth putty etc., and including cost of labour charges.
Plastering area 5869.40m²
Ceiling area 735.12m²
------------
6604.00m²
------------
@ Rs 600.00/10 Sq.M Rs.1188720.00

17. Painting wood work two coats with best synthetic enamel paint over a painting
coat of white lead including cost of all materials like brushes, waste cloth, putty etc.,
and labour charges.

Door’s area 2.25 X120.00m2 270.00m2


Windows area 2.50 X125.00m2 312.50m
------------
582.50m2
------------
@ RS.2000.00/10m2 Rs.349500.00

Total Rs.2,4557,495.00

L.S. Provision has been made for following items.


19. For the Architectural finishing of the building Rs. 5, 00,000.00
20. For the Electrification of the entire building Rs. 20, 00,000.00
21. For the Water supply and sanitary arrangements Rs. 20, 00,000.00
22. For the Construction of Cooking Plat form &shelves Rs. 10 00,000.00
23. For the Construction of septic tank and water tank Rs. 5, 00,000.00
24. For the Installation of 0.50HP Electric Motor Rs. 2,00,000.00
27. For the Compound wall Rs. 3, 00,000.00
28. For the Compound wall gate 2nos Rs. 100,000.00
29. For the Contingencies and petty supervision charges Rs. 1,00,000.00

-- ------------------
Rs,3,12,57,495.00
--------------------
(RUPEES THREE CRORE TWELVE LAKSH FIFTY-SEVEN
THOUSAND FOUR HUNDRED AND NINETY-FIVE ONLY)
The Estimated Cost of Construction work out to Rs. 3,12,57,495.00)