You are on page 1of 7

ESTIMASI BIAYA

Nama Pekerjaan : Rest Area


Lokasi : Kalijati-Subang
Waktu Pelaksanaan :
PIC :

No Uraian Pekerjaan Volume Sat Harga Satuan Jumlah Keterangan


I Pendahuluan
1 Pengukuran dan bowplang m' -
II Gali dan buang tanah
1 Gali tanah m -
2 Timbun sertu m -
III Pondasi tapak
1 Lantai kerja m3 -
2 Pasir urug, t = 5 cm
3 Plastik cor m2 -
4 Begisting m2 -
5 Besi beton kg -
6 Cor beton m3 -
IV Sloop 15/20
1 Plastik cor m2 -
2 Begisting m2 -
3 Besi beton kg -
4 Cor beton m3 -
5 Finishing m2 -
Kolom Praktis 15/15
1 Plastik cor m2
2 Begisting m2
3 Besi beton d 10 mm kg
4 Besi beton d 8 mm kg
5 Cor beton m3
6 Finishing m2
V Ring balk
1 Begisting m2 -
2 Besi beton kg -
3 Cor beton m3 -
4 Finishing m2 -
VI Lantai
1 Sertu, t = 15 cm -
2 Pemadatan pake stamper m3 -
3 Pasir urug, t = 5 cm m3 -
4 Plastik cor m2 -
5 Wiremesh d8 - 150 m2 -
6 Begsting m2 -
7 Cor Beton, t = 10 cm m3 -
8 Keramik lantai m2 -
VII Dinding
1 Pasangan batu ringan m2 -
2 Plester dan acian m2 -
3 Cat dinding Interior m2 -
4 Cat dinding eksterior m2 -
VIII Pekerjaan Struktur
1 Kolom Utama -
- Begisting m2 -
- Besi beton d 12 mm kg -
- Besi beton d 10 mm kg -
- Cor beton m3 -
- Plester dan acian m2 -
2 Kolom praktis 15x15 cm -
- Begisting m2 -
- Besi beton d 10 mm kg -
- Ring besi beton d 8 mm kg -
- Cor beton m3 -
- Plester dan acian m2 -
3 Kolom WF 300x150x6,5x9 - 3 m kg -
4 Balok WF 300x150x6,5x9 - 3 m kg -
5 Over stek WF kg -
6 Pelat t = 12mm kg -
7 Shear connector d10 - 300 m2 -
8 Baut angkur d 3/4" - 700 pcs -
9 Baut HTB d 3/4" pcs -
10 Meni zinchromate m2 -
IX Kamar mandi
1 Pasangan batu ringan m2 -
4 Plester dan acian m2 -
5 Keramik dinding m2 -
6 Keramik lantai m2 -
7 Lis keramik -
8 Pintu fiber, t = 2100, l = 800 unit -
9 Floor drain unit -
10 Closet unit -
11 Kran air unit -
12 Pipa m -
X Sanitasi
1 Safeti tank unit -
2 Pipa m -
XI Pekerjaan atap
1 Rafter/span kg -
2 Gording kg -
3 Nok atap m2 -
4 Genteng m2 -
5 Talang air m' -
6 Lis plang m' -
XII Pekerjaan plafond
1 Rangka hollow -
2 Plafond GRC m2 -
3 Cat plafond m2 -
4 Lis plafond m' -
XIII Pekerjaan pintu dan jendela
1 Kusen pintu unit -
2 Kusen jendela unit -
3 Pintu utama unit -
4 Jendela unit -
XIII Pekerjaan elektrikal
1 Kabel listik rol -
2 Stop kontak unit -
3 Saklar tunggal unit -
4 Saklar double unit -
Sewa alat
Trasnportasi -
Ereksen

-
Estimasi Biaya -
PPH
PPN
Total Estimasi Biaya

Subang, ………………………

Dibuat oleh Diperiksa

(……………………………………………….) (……………………………………………….)
DAFTAR SATUAN HARGA UPAH
KABUPATEN SUBANG
TAHUN 2017

No Uraian Pekerjaan Wilayah I Wilayah II Wilayah III Wilayah IV Satuan


I Perencana dan pengawas konstruksi
1 Pembuat gambar 200,000 200,000 200,000 200,000 Oh / 8 Jam
2 Pembuat RAB 175,000 175,000 175,000 175,000 Oh / 8 Jam
3 Pengawas 150,000 150,000 150,000 150,000 Oh / 8 Jam
4 Surveyor 100,000 100,000 100,000 100,000 Oh / 8 Jam
5 Estimator 125,000 125,000 125,000 125,000 Oh / 8 Jam
6 Tim penyusun HPS 125,000 125,000 125,000 125,000 Orang

II Upah kerja
1 Drafmant 125,000 125,000 125,000 125,000 Oh / 8 Jam
2 Juru gambar 200,000 200,000 200,000 200,000 Oh / 8 Jam
3 Juru Ukur 150,000 150,000 150,000 150,000 Oh / 8 Jam
4 Kepala tukang 115,500 115,500 115,500 115,500 Oh / 8 Jam
5 Kepala tukang batu 115,500 115,500 115,500 115,500 Oh / 8 Jam
6 Kepala tukang besi beton 115,500 115,500 115,500 115,500 Oh / 8 Jam
7 Kepala tukang besi profil 115,500 115,500 115,500 115,500 Oh / 8 Jam
8 Kepala tukang cat/plestur 115,500 115,500 115,500 115,500 Oh / 8 Jam
9 Kepala tukang kayu 115,500 115,500 115,500 115,500 Oh / 8 Jam
10 Mandor 112,700 112,700 112,700 112,700 Oh / 8 Jam
11 Mekanik 115,500 115,500 115,500 115,500 Oh / 8 Jam
12 Operator 115,500 115,500 115,500 115,500 Oh / 8 Jam
13 Operator alat berat 115,500 115,500 115,500 115,500 Oh / 8 Jam
14 Operator semi terlatih 105,800 105,800 105,800 105,800 Oh / 8 Jam
15 Pekerja (terampil) 105,800 105,800 105,800 105,800 Oh / 8 Jam
16 Pekerja/tukang gali 96,500 96,500 96,500 96,500 Oh / 8 Jam
17 Pekerja setengah terampil 100,100 100,100 100,100 100,100 Oh / 8 Jam
18 Pembantu juru ukur & operator / mekanik alat berat 104,100 104,100 104,100 104,100 Oh / 8 Jam
19 Pembantu mekanik 104,100 104,100 104,100 104,100 Oh / 8 Jam
20 Pembantu operator 104,100 104,100 104,100 104,100 Oh / 8 Jam
21 Pembantu sopir 104,100 104,100 104,100 104,100 Oh / 8 Jam
22 Penjaga malam 100,000 100,000 100,000 100,000 Oh / 8 Jam
23 Sopir/ supir truk 109,800 109,800 109,800 109,800 Oh / 8 Jam
24 Tukang (terampil) 109,800 109,800 109,800 109,800 Oh / 8 Jam
25 Tukang batu (terampil) 109,800 109,800 109,800 109,800 Oh / 8 Jam
26 Tukang batu setengah terampil 105,800 105,800 105,800 105,800 Oh / 8 Jam
27 Tukang besi beton (terampil) 109,800 109,800 109,800 109,800 Oh / 8 Jam
28 Tukang besi beton setengah terampil 105,800 105,800 105,800 105,800 Oh / 8 Jam
29 Tukang besi profil (terampil) 109,800 109,800 109,800 109,800 Oh / 8 Jam
30 Tukang besi profil setengah terampil 105,800 105,800 105,800 105,800 Oh / 8 Jam
31 Tukang cat /pelitur (terampil) 109,800 109,800 109,800 109,800 Oh / 8 Jam
32 Tukang cat /pelitur setengah terampil 105,800 105,800 105,800 105,800 Oh / 8 Jam
33 Tukang gali 96,500 96,500 96,500 96,500 Oh / 8 Jam
34 Tukang kayu (terampil) 109,800 109,800 109,800 109,800 Oh / 8 Jam
35 Tukang kayu setengah terampil 105,800 105,800 105,800 105,800 Oh / 8 Jam
36 Tukang penganyam bronjong 109,800 109,800 109,800 109,800 Oh / 8 Jam
37 Tukang pipa 109,800 109,800 109,800 109,800 Oh / 8 Jam
38 Tukang pipa setengah terampil 105,800 105,800 105,800 105,800 Oh / 8 Jam
DAFTAR SATUAN HARGA BAHAN
KABUPATEN SUBANG
2017

No Uraian Pekerjaan Wilayah I Wilayah II Wilayah III


1 Adukan beton redy mix K 175 1,551,000 1,551,000 1,551,000
2 Adukan beton redy mix K 225 2,000,000 2,000,000 2,000,000
4 Adukan beton redy mix K 300 2,006,200 2,006,200 2,006,200
5 Adukan beton redy mix K 350 2,104,900 2,104,900 2,104,900
6 Agregat halus 466,600 489,200 486,000
7 Agregat kasar 436,300 448,900 501,400
Wilayah IV Sat Keterangan
1,551,000 m3
2,000,000 m3
Tanpa pompa & selang
2,006,200 m3
2,104,900 m3
492,100 m3
534,200 m3
Menghitung Kebutuhan Cat dinding
- Luas dinding / luas 1 liter
- Standar pemakaian cat (10-12)m2/liter setiap pelapisan
Contoh :
Ruangan ukuran 3x4x3m
1 Luas dinding 42 m2
2 Kebutuhan cat 3.5 liter

Artinya
1x pelapisan butuh 3.5 liter
2x pelapisan butuh 7 liter
1 kaleng cat 2,5 liter
1 kaleng cat 5 liter
1 pail cat 20 liter