You are on page 1of 12

JEMBATAN EMPANANG

KENCANA GROUP - SSWE


( CIVIL WORK )
BOQ

1 24 Oct 22 For Tender


0 14 Jun 22 For Tender
REV. DATE DESCRIPTION PREPARED BY CHECKED BY APPROVED BY
PROJECT : PROJECT OWNER :

JEMBATAN EMPANANG KENCANA GROUP -


SSWE KENCANA GROUP - SSWE
PROJECT ID :
REV.
QUANTITY SURVEYOR AND COST
ESTIMATOR 0139/VOQ/INF-QS/JKTO/10/22 1
REKAP HARGA
KENCANA GROUP - SSWE
harus diisi nama kontraktor

NO BANGUNAN JML NAMA KONTRAKTOR


HARGA TOTAL

JEMBATAN EMPANANG
1 Jembatan Empanang C45 (Struktur Bawah) 1 - -
2 Jembatan Girder Komposit 24M (Struktur Bawah) 1 - -
3 Jembatan Beton 10M H 8M Tanah Mineral 1 - -

Total -
(ROUNDED) -

Printed On 12/27/2022
2/12
Prepared by QS
REKAP HARGA BERDASARKAN HARGA MATERIAL DAN UPAH
KENCANA GROUP - SSWE
harus diisi -

NAMA KONTRAKTOR
NO ITEM SAT
HARGA VOL TOTAL BOBOT

MATERIAL
1 Batu Belah M³ 575.52 -
2 Angkur Ø 16 mm, L = 250 mm Bh 48.00 -
3 Besi Beton £ Ø 12 mm Kg 9,801.15 -
4 Besi Beton > D 12 mm Kg 47,166.78 -
5 Beton Site mix K-125 M³ 10.02 -
6 Beton Site mix K-225 M³ - -
7 Beton Site mix K-300 M³ 265.15 -
8 Cat Genteng Matex Kg 45.95 -
9 Cerucuk Kayu Gelam D10cm 4m Ttk 548.00 -
10 Cerucuk Kayu Gelam D15cm 4m Ttk 346.00 -
11 Elastomeric 450 x 350 x 30 mm Bh 6.00 -
12 Geotextile Woven 50kN M² 2,846.26 -
13 Ijuk Kg 178.55 -
14 Kawat Beton/Bendrat Kg 1,077.14 -
15 Kawat Gabion 2m x 1m x 0.5m Ø-3mm Set 232.00 -
16 Kayu Bekisting Papan 2/20 - 4 m Btg 46.86 -
17 Kayu Bekisting Balok 4/6 - 4 m Btg 449.13 -
18 Kayu Bekisting Balok 6/12 - 4 m Kelas II Btg 42.39 -
19 Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 232.87 -
20 Kayu Galam Ø 7 cm - 6 m Ttk 374.87 -
21 Kayu Galam Ø 3 cm - 4 m Ttk 299.89 -
22 Mobilisasi & Demobilisasi Ls 1.00 -
23 Paku 2" Kg 15.98 -
24 Paku 3" Kg 19.45 -
25 Paku 4" Kg 12.09 -
26 Pasir Beton/Cor M³ 126.37 -
27 Pasir Urug M³ 57.82 -
28 Pasir Pasang M³ 3.46 -
29 PDA Test Ttk 4.00 -
30 Plastik Cor M² 491.50 -
31 Plat > 8 mm Kg 284.86 -
32 Pipa Galvanis Ø 1" - 6 m Btg 4.00 -
33 Pipa PVC Merk Wavin 2" D - 4 m Btg 172.80 -
34 Pipa Drain PVC AW 2" Btg 7.00 -
35 Protokol Kesehatan Ls 1.00 -
36 Rubber Sheet 15x15, t=2 cm Pcs 42.00 -
37 Semen PC Type 1 @ 50 Kg Zak 1,262.78 -
38 SHE Ls 1.00 -
39 Site Management and Establishment Costs Ls 1.00 -
40 Split M³ 238.72 -
41 Triplek 9 mm Lbr 118.00 -
42 Wing nut, steel cone & tie rod Bh 279.20 -
43 Wiremesh M8 M² 540.65 -
Material Utama
Material Pendukung -
Total Material -

UPAH
1 Bekisting Backwall M² 58.06 -
2 Bekisting Badan Abutment M² 138.67 -
3 Bekisting Dinding Multiplek M² 522.13 -
4 Bekisting Kepala Abutment M² 50.66 -
5 Bekisting Menerus M² 114.07 -
6 Bekisting Plat Injak M² 16.20 -
7 Bekisting Plat Lantai M² 37.49 -
8 Bekisting Pilecap M² 52.69 -
9 Bekisting Setempat Multiplek M² 99.51 -
10 Bekisting Stopper M² 3.33 -
11 Bekisting Wingwall M² 205.26 -
12 Erection Struktur Baja Kg 81,636.49 -
13 Galian Tanah M³ 224.76 -
14 Galian Struktur M³ 263.29 -
15 Lantai Kerja M³ 9.55 -
16 Mobilisasi Tiang Pancang Jemb. C45 Ls by kebun
17 Mobilisasi Tiang Pancang Jemb. Girder Komposit 24M Ls by kebun
18 Pasangan Beronjong M³ 232.00 -
19 Pemotongan Tiang Pancang Ttk 62.00 -
20 Pengelasan Tiang Pancang Ttk 41.00 -
21 Pemancangan Tiang Pancang M' 536.00 -
22 Pengecatan Kanstin M² 91.89 -
23 Pekerjaan Geotekstile M² 2,710.72 -
24 Pekerjaan Pipa Galvanis Ø 1" Btg 4.00 -
25 Pekerjaan Baja Plat > 8 mm (Fabrikasi/Erection) Kg 271.30 -
26 Pekerjaan Timbunan M³ 306.58 -
27 Pekerjaan Timbunan Trase Jalan M³ 2,775.36 -
28 Pondasi Cerucuk Kayu D10cm L 4m Ttk 548.00 -
29 Pondasi Cerucuk Kayu D15cm L 4m Ttk 346.00 -
30 Pembesian £ dia. 12 mm Kg 8,825.76 -
31 Pembesian > dia. 12 mm (Deformed) Kg 44,048.31 -
32 Pembesian £ dia. 12 mm (Tanpa Kawat Beton) Kg 346.14 -
33 Pembesian > dia. 12 mm (Tanpa Kawat Beton) Kg 872.44 -
34 Pembesian Wiremesh M8-Single Layer M2 491.50 -
35 Pengecoran (K-300) M³ 252.52 -
36 Pengecoran (K 225) M³ - -
37 Pengecoran (K 175) Bentang > 6 M M³ 70.13 -
38 Pengecoran 1:3:5 + 60% Batu Mangga M³ 456.53 -
39 Peresapan 1M2/Ttk Ttk 739.00 -
40 Plesteran 1:2 + Acian M 2
153.68 -
41 Steiger Bentang > 6 M M2 37.49 -
42 Handling Material Baja Kg 81,636.49 -
43 Urug Pasir M³ 52.56 -
44 Urugan Tanah & Pemadatan M³ 124.75 -
Upah Utama
Upah Pendukung -
Total Upah -

TOTAL -

Printed On 12/27/2022
3/12
Prepared by QS
ANALISA SATUAN PEKERJAAN
KENCANA GROUP - SSWE
harus diisi -

VOL ESTIMASI OWNER


EST
NO URAIAN PEKERJAAN SAT
SAT. BAHAN BAHAN SAT. UPAH UPAH JUMLAH EST VOL

PEKERJAAN TANAH & PONDASI


Galian Tanah M³ 1.00 - - - 1.00
Galian Struktur M³ 1.00 - - - 1.00
Mobilisasi Tiang Pancang Jemb. C45 Ls 1.00 by kebun 1.00
Mobilisasi Tiang Pancang Jemb. Girder Komposit 24M Ls 1.00 by kebun 1.00
Pekerjaan Timbunan M³ 1.20 - - - 1.20
Pekerjaan Timbunan Trase Jalan M³ 1.20 - - - 1.20
Urugan Tanah & Pemadatan M³ 1.00 - - - 1.00
Pemotongan Tiang Pancang Ttk 1.00 - - - 1.00
Pengelasan Tiang Pancang Ttk 1.00 - - - 1.00
Pekerjaan Geotekstile M² 1.00 - - - - 1.00
Geotextile Woven 50kN M² 1.05 - - 1.05
Pondasi Cerucuk Kayu D10cm L 4m Ttk 1.00 - - - - 1.00
Cerucuk Kayu Gelam D10cm 4m Btg 1.00 - - 1.00
Pondasi Cerucuk Kayu D15cm L 4m Ttk 1.00 - - - - 1.00
Cerucuk Kayu Gelam D15cm 4m Btg 1.00 - - 1.00
Besi Beton £ Ø 12 mm Kg 0.49 - - 0.49
Peresapan 1M2/Ttk Ttk 1.00 - - - - 1.00
Ijuk Kg 0.20 - - 0.20
Pipa PVC Merk Wavin 2" D - 4 m Btg 0.15 - - 0.15
Urug Pasir M³ 1.00 - - - - 1.00
Pasir Urug M³ 1.10 - - 1.10
Pasangan Beronjong M³ 1.00 - - - - 1.00
TiBatu Belah M³ 1.30 - - 1.30
Kawat Gabion 2m x 1m x 0.5m Ø-3mm Set 1.00 - - 1.00
Pemancangan Tiang Pancang M' 1.00 - - - 1.00

PEKERJAAN KONSTRUKSI BETON


Bekisting Dinding Multiplek M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.06 - - 0.06
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.22 - - 0.22
Bekisting Setempat Multiplek M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.35 - - 0.35
Kayu Bekisting Balok 4/6 - 4 m Btg 2.67 - - 2.67
Paku 2" Kg 0.08 - - 0.08
Bekisting Plat Lantai M² 1.00 - - - - 1.00
Kayu Bekisting Papan 2/20 - 4 m Btg 1.25 - - 1.25
Kayu Bekisting Balok 4/6 - 4 m Btg 2.50 - - 2.50
Paku 2" Kg 0.08 - - 0.08
Bekisting Menerus M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.17 - - 0.17
Kayu Bekisting Balok 4/6 - 4 m Btg 0.79 - - 0.79
Paku 2" Kg 0.05 - - 0.05
Bekisting Pilecap M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.12 - - 0.12
Kayu Bekisting Balok 6/12 - 4 m Kelas II Btg 0.08 - - 0.08
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.29 - - 0.29
Bekisting Backwall M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.06 - - 0.06
Kayu Bekisting Balok 6/12 - 4 m Kelas II Btg 0.08 - - 0.08
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.22 - - 0.22
Bekisting Badan Abutment M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.06 - - 0.06
Kayu Bekisting Balok 6/12 - 4 m Kelas II Btg 0.08 - - 0.08
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.22 - - 0.22
Bekisting Kepala Abutment M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.06 - - 0.06
Kayu Bekisting Balok 6/12 - 4 m Kelas II Btg 0.08 - - 0.08
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.22 - - 0.22
Bekisting Plat Injak M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.06 - - 0.06
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.22 - - 0.22
Bekisting Stopper M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.06 - - 0.06
Kayu Bekisting Balok 6/12 - 4 m Kelas II Btg 0.08 - - 0.08
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.22 - - 0.22
Bekisting Wingwall M² 1.00 - - - - 1.00
Triplek 9 mm Lbr 0.06 - - 0.06
Kayu Bekisting Balok 6/12 - 4 m Kelas II Btg 0.08 - - 0.08
Wing nut, steel cone & tie rod Bh 0.27 - - 0.27
Kayu Bekisting Balok 5/7 - 4 m Kelas II Btg 0.22 - - 0.22
Pengecoran (K 175) Bentang > 6 M M³ 1.00 - - - - 1.00
Semen PC Type 1 @ 50 Kg Zak 6.60 - - 6.60
Pasir Beton/Cor M³ 0.50 - - 0.50
Split M³ 0.80 - - 0.80
Pengecoran (K-300) M³ 1.00 - - - - 1.00
Beton Site mix K-300 M³ 1.05 - - 1.05
Pengecoran (K 225) M³ 1.00 - - - - 1.00
Beton Site mix K-225 M³ 1.05 - - 1.05
Pengecoran 1:3:5 + 60% Batu Mangga M³ 1.00 - - - 1.00
Pengecoran 1:3:5 + 60% Batu Mangga M³ 1.00 - - 1.000
Urugan Tanah & Pemadatan M³ 0.21 - - 0.210
Semen PC Type 1 @ 50 Kg Zak 1.70 - - 1.696
Split M³ 0.40 - - 0.400
Pasir Beton/Cor M³ 0.20 - - 0.200
Batu Belah M³ 0.60 - - 0.600
Steiger Bentang > 6 M M² 1.00 - - - - 1.00
Kayu Galam Ø 7 cm - 6 m Btg 10.00 - - 10.00
Paku 4" Kg 0.32 - - 0.32
Kayu Galam Ø 3 cm - 4 m Btg 8.00 - - 8.00
Paku 3" Kg 0.52 - - 0.52
Lantai Kerja M³ 1.00 - - - - 1.00
Beton Site mix K-125 M³ 1.05 - - 1.05
Pembesian £ dia. 12 mm Kg 1.00 - - - - 1.00
Besi Beton £ Ø 12 mm Kg 1.05 - - 1.05
Kawat Beton/Bendrat Kg 0.02 - - 0.02
Pembesian > dia. 12 mm (Deformed) Kg 1.00 - - - - 1.00
Besi Beton > D 12 mm Kg 1.05 - - 1.05
Kawat Beton/Bendrat Kg 0.02 - - 0.02
Pembesian £ dia. 12 mm (Tanpa Kawat Beton) Kg 1.00 - - - - 1.00
Besi Beton £ Ø 12 mm Kg 1.05 - - 1.05
Pembesian > dia. 12 mm (Tanpa Kawat Beton) Kg 1.00 - - - - 1.00
Besi Beton > D 12 mm Kg 1.05 - - 1.05
Pembesian Wiremesh M8-Single Layer M2 1.00 - - - - 1.00
Wiremesh M8 M2 1.10 - - 1.10
Kawat Beton/Bendrat Kg 0.04 - - 0.04

PEKERJAAN PASANGAN
Plesteran 1:2 + Acian M² 1.00 - - - - 1.00
Semen PC Type 1 @ 50 Kg Zak 0.17 - - 0.17
Pasir Pasang M³ 0.02 - - 0.02

PEKERJAAN KONSTRUKSI BAJA


Erection Struktur Baja Kg 1.00 - - - 1.00
Pekerjaan Baja Plat > 8 mm (Fabrikasi/Erection) Kg 1.00 - - - - 1.00
Plat > 8 mm Kg 1.05 - - 1.05
Pekerjaan Pipa Galvanis Ø 1" Btg 1.00 - - - - 1.00
Pipa Galvanis Ø 1" - 6 m Btg 1.00 - - 1.00
Handling Material Baja Kg 1.00 - - - 1.00

PEKERJAAN PENGECATAN & PENGIRIMAN


Pengecatan kanstin M2 1.00 - - - - 1.00
Cat Genteng Matex Kg 0.50 - - 0.50

Printed On 12/27/2022
4/12
Prepared by QS
BILL OF QUANTITY
PROYEK : JEMBATAN EMPANANG C45 (STRUKTUR BAWAH)
LOKASI : EMPANANG - SSWE
HARGA : Rp -
KONTRAKTOR :
harus diisi -
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT. VOL VOL SATUAN HARGA
Estimasi Kontraktor Rp. Rp.

00 PEKERJAAN PERSIAPAN -
Mobilisasi & Demobilisasi Ls 1.00 1.00 - -
Mob
Mobilisasi Tiang Pancang Jemb. C45 Ls by kebun
Site Management and Establishment Costs Ls 1.00 1.00 - -
Protokol Kesehatan Ls 1.00 1.00 - -
SHE Ls 1.00 1.00 - -
10 PEKERJAAN PENGUJIAN -
PDA Test Ttk 4.00 4.00 - -
20 PEKERJAAN TANAH & GEOSINTETIK -
21 Abutment A1 -
Pekerjaan Galian -
GalGalian Struktur M³ 42.21 42.21 - -
Pekerjaan Backfill Include Pemadatan -
Pe Pekerjaan Timbunan M³ 87.84 87.84 - -
Timbunan Material Granular -
UruUrug Pasir M³ 14.96 14.96 - -
Pekerjaan Geotekstile -
PekPekerjaan Geotekstile M² 288.84 288.84 - -
PekPemasangan Geotekstile Timbunan Jalan M² 399.00 399.00 - -
Pekerjaan Timbunan Trase Jalan -
PekPekerjaan Timbunan Trase Jalan M³ 660.80 660.80 - -
22 Abutment A2 -
Pekerjaan Galian -
GalGalian Struktur M³ 113.28 113.28 - -
Pekerjaan Backfill Include Pemadatan -
Pe Pekerjaan Timbunan M³ 87.84 87.84 - -
Timbunan Material Granular -
UruUrug Pasir M³ 14.96 14.96 - -
Pekerjaan Geotekstile -
PekPekerjaan Geotekstile M² 288.84 288.84 - -
PekPemasangan Geotekstile Timbunan Jalan M² 399.00 399.00 - -
Pekerjaan Timbunan Trase Jalan -
PekPekerjaan Timbunan Trase Jalan M³ 660.80 660.80 - -
30 PEKERJAAN LINING BETON -
31 Pasangan Beronjong -
Pasangan Beronjong -
r Pasangan Beronjong M³ 232.00 232.00 - -
Pekerjaan Geotekstile M² 417.60 417.60 - -
32 Lining Beton A1 -
Concrete Lining -
Plastik Cor M² 170.93 170.93 - -
Bekisting Menerus M² 0.96 0.96 - -
Pe Pembesian Wiremesh M6-1Layer M² 170.93 170.93 - -
Pengecoran (K 175) Bentang > 6 M M³ 17.09 17.09 - -
Peresapan 1M2/Ttk ttk 171.00 171.00 - -
Pem
Dowel Ø8 - 200 mm Kg 39.90 39.90 - -
Retaining Wall -
Pondasi Cerucuk Kayu D10cm L 4m Ttk 134.00 134.00 - -
Galian Tanah M³ 26.78 26.78 - -

Printed On 12/27/2022
5/12
Prepared by QS
Bekisting Dinding Multiplek M² 37.42 37.42 - -
Pengecoran 1:3:5 + 60% Batu Mangga M³ 45.19 45.19 - -
Peresapan 1M2/Ttk ttk 45.00 45.00 - -
33 Lining Beton A2 -
Concrete Lining -
Plastik Cor M² 170.93 170.93 - -
Bekisting Menerus M² 0.96 0.96 - -
Pe Pembesian Wiremesh M6-1Layer M² 170.93 170.93 - -
Pengecoran (K 175) Bentang > 6 M M³ 17.09 17.09 - -
Peresapan 1M2/Ttk ttk 171.00 171.00 - -
Pem
Dowel Ø8 - 200 mm Kg 39.90 39.90 - -
Retaining Wall -
Pondasi Cerucuk Kayu D10cm L 4m Ttk 134.00 134.00 - -
Galian Tanah M³ 26.78 26.78 - -
Bekisting Dinding Multiplek M² 37.42 37.42 - -
Pengecoran 1:3:5 + 60% Batu Mangga t10cm M³ 45.19 45.19 - -
Peresapan 1M2/Ttk ttk 45.00 45.00 - -
40 PEKERJAAN STRUKTUR BAWAH JEMBATAN -
41 Abutment A1 -
Tiang Pancang Beton Square pile 30x30, L10 m Ttk 21.00 21.00 -
Pe Pemotongan Tiang Pancang Ttk 21.00 21.00 - -
PenPengelasan Tiang Pancang Ttk 21.00 21.00 - -
Pe Pemancangan Tiang Pancang M' 210.00 210.00 - -
Urug Pasir M³ 1.89 1.89 - -
Lantai Kerja M³ 1.89 1.89 - -
Bekisting -
Bekisting Pilecap M² 16.47 16.47 - -
Bekisting Badan Abutment M² 57.02 57.02 - -
Bekisting Kepala Abutment M² 16.93 16.93 - -
Bekisting Backwall M² 13.33 13.33 - -
Bekisting Stopper M² 1.67 1.67 - -
Bekisting Wingwall M² 81.01 81.01 - -
Bekisting Plat Injak M² 4.50 4.50 - -
Pembesian -
Pem
Pembesian Pilecap Kg 2,404.02 2,404.02 - -
Pem
Pembesian Badan Abutment Kg 4,497.48 4,497.48 - -
Pem
Pembesian Kepala Abutment Kg 656.79 656.79 - -
Pem
Pembesian Backwall Kg 621.06 621.06 - -
Pem
Pembesian Stopper Kg 51.05 51.05 - -
Pem
Pembesian Wingwall Kg 2,543.04 2,543.04 - -
Pem
Pembesian Plat Injak Kg 786.06 786.06 - -
Pengecoran K-300 -
Pe Pengecoran Pilecap M³ 17.01 17.01 - -
Pe Pengecoran Badan Abutment M³ 21.23 21.23 - -
Pe Pengecoran Kepala Abutment M³ 6.60 6.60 - -
Pe Pengecoran Backwall M³ 2.17 2.17 - -
Pe Pengecoran Stopper M³ 0.30 0.30 - -
Pe Pengecoran Wingwall M³ 11.77 11.77 - -
Pe Peresapan 1M2/Ttk Ttk 30.00 30.00 - -
Pe Pengecoran Plat Injak M³ 3.98 3.98 - -
Angkur Plat Injak -
PekPipa Galvanis ᴓ 1" Btg 1.00 1.00 - -
Pem
Angkur ᴓ 19 mm Kg 12.42 12.42 - -
Pem
Besi Beton Ø 10 mm Kg 26.07 26.07 - -
Rubber Sheet 15x15, t=2 cm Pcs 12.00 12.00 - -
42 Abutment A2 -
Tiang Pancang Beton Square pile 30x30, L6 m Ttk 21.00 21.00 -
Pe Pemotongan Tiang Pancang Ttk 21.00 21.00 - -
Pe Pemancangan Tiang Pancang M' 126.00 126.00 - -

Printed On 12/27/2022
6/12
Prepared by QS
Urug Pasir M³ 1.80 1.80 - -
Lantai Kerja M³ 1.80 1.80 - -
Bekisting -
Bekisting Pilecap M² 16.20 16.20 - -
Bekisting Badan Abutment M² 17.58 17.58 - -
Bekisting Kepala Abutment M² 16.10 16.10 - -
Bekisting Backwall M² 14.05 14.05 - -
Bekisting Stopper M² 1.67 1.67 - -
Bekisting Wingwall M² 76.92 76.92 - -
Bekisting Plat Injak M² 4.50 4.50 - -
Pembesian -
Pem
Pembesian Pilecap Kg 1,805.18 1,805.18 - -
Pem
Pembesian Badan Abutment Kg 4,134.59 4,134.59 - -
Pem
Pembesian Kepala Abutment Kg 615.49 615.49 - -
Pem
Pembesian Backwall Kg 627.96 627.96 - -
Pem
Pembesian Stopper Kg 51.05 51.05 - -
Pem
Pembesian Wingwall Kg 3,141.13 3,141.13 - -
Pem
Pembesian Plat Injak Kg 786.06 786.06 - -
Pengecoran K-300 -
Pe Pengecoran Pilecap M³ 16.20 16.20 - -
Pe Pengecoran Badan Abutment M³ 17.58 17.58 - -
Pe Pengecoran Kepala Abutment M³ 6.75 6.75 - -
Pe Pengecoran Backwall M³ 2.18 2.18 - -
Pe Pengecoran Stopper M³ 0.30 0.30 - -
Pe Pengecoran Wingwall M³ 10.82 10.82 - -
Pe Peresapan 1M2/Ttk Ttk 33.00 33.00 - -
Pe Pengecoran Plat Injak M³ 3.98 3.98 - -
Angkur Plat Injak -
PekPipa Galvanis ᴓ 1" Btg 1.00 1.00 - -
Pem
Angkur ᴓ 19 mm Kg 12.42 12.42 - -
Pem
Besi Beton Ø 10 mm Kg 26.07 26.07 - -
Rubber Sheet 15x15, t=2 cm Pcs 12.00 12.00 - -
50 PEKERJAAN KONSTRUKSI STRUKTUR ATAS JEMBATAN -
51 PEKERJAAN KONSTRUKSI BAJA JEMBATAN -
Konstruksi Baja Jembatan 45 Meter -
r Handling Material Baja Kg 52,705.49 52,705.49 - -
r Erection Struktur Baja Kg 52,705.49 52,705.49 - -
52 LANTAI JEMBATAN -
Pekerjaan Lantai Jembatan 45 Meter -
Bekisting Menerus M² 29.54 29.54 - -
Pembesian > dia. 12 mm (Deformed) Kg 8,832.21 8,832.21 - -
Pengecoran (K-300) M³ 28.86 28.86 - -
Pekerjaan Kanstin & Deck Drain -
Bekisting Menerus M² 45.97 45.97 - -
Pembesian £ dia. 12 mm Kg 1,145.16 1,145.16 - -
Pengecoran (K-300) Include Fin. Expose u/ cansteen M³ 3.99 3.99 - -
Pipa Drain PVC AW 2" Btg 5.00 5.00 - -
Pengecatan kanstin M² 44.37 44.37 - -

TOTAL -

Note = Volume di atas hanya sebagai panduan, kontraktor harus tetap menghitung ulang

Printed On 12/27/2022
7/12
Prepared by QS
BILL OF QUANTITY
PROYEK : JEMBATAN GIRDER KOMPOSIT 24M (STRUKTUR BAWAH)
LOKASI : EMPANANG - SSWE
HARGA : Rp -
KONTRAKTOR :
harus diisi
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT. VOL VOL SATUAN HARGA
Estimasi Kontraktor Rp. Rp.

00 PEKERJAAN PERSIAPAN -
Mob
Mobilisasi Tiang Pancang Jemb. Girder Komposit 24M Ls by kebun
20 PEKERJAAN TANAH & GEOSINTETIK -
21 Abutment A1 -
Pekerjaan Galian -
GalGalian Struktur M³ 53.90 53.90 - -
Pekerjaan Backfill Include Pemadatan M³ -
Pe Pekerjaan Timbunan M³ 39.90 39.90 - -
Timbunan Material Granular -
UruUrug Pasir M³ 4.73 4.73 - -
Pekerjaan Geotekstile -
PekPekerjaan Geotekstile M² 129.72 129.72 - -
PekPemasangan Geotekstile Timbunan Jalan M² 329.00 329.00 - -
Pekerjaan Timbunan Trase Jalan -
PekPekerjaan Timbunan Trase Jalan M³ 495.60 495.60 - -
22 Abutment A2 -
Pekerjaan Galian -
GalGalian Struktur M³ 53.90 53.90 - -
Pekerjaan Backfill Include Pemadatan M³ -
Pe Pekerjaan Timbunan M³ 39.90 39.90 - -
Timbunan Material Granular -
UruUrug Pasir M³ 4.73 4.73 - -
Pekerjaan Geotekstile -
PekPekerjaan Geotekstile M² 129.72 129.72 - -
PekPemasangan Geotekstile Timbunan Jalan M² 329.00 329.00 - -
Pekerjaan Timbunan Trase Jalan -
PekPekerjaan Timbunan Trase Jalan M³ 495.60 495.60 - -
30 PEKERJAAN LINING BETON -
31 Lining Beton A1 -
Concrete Lining -
Plastik Cor M² 74.82 74.82 - -
Bekisting Menerus M² 0.86 0.86 - -
Pe Pembesian Wiremesh M6-1Layer M² 74.82 74.82 - -
Pengecoran (K 175) Bentang > 6 M M³ 7.48 7.48 - -
Peresapan 1M2/Ttk ttk 75.00 75.00 - -
Pem
Dowel Ø8 - 200 mm Kg 41.48 41.48 - -
Retaining Wall -
Pondasi Cerucuk Kayu D10cm L 4m Ttk 140.00 140.00 - -
Galian Tanah M³ 27.84 27.84 - -
Bekisting Dinding Multiplek M² 38.91 38.91 - -
Pengecoran 1:3:5 + 60% Batu Mangga M³ 46.98 46.98 - -
Peresapan 1M2/Ttk ttk 47.00 47.00 - -
32 Lining Beton A2 -
Concrete Lining -
Plastik Cor M² 74.82 74.82 - -
Bekisting Menerus M² 0.86 0.86 - -
Pe Pembesian Wiremesh M6-1Layer M² 74.82 74.82 - -
Pengecoran (K 175) Bentang > 6 M M³ 7.48 7.48 - -

Printed On 12/27/2022
8/12
Prepared by QS
Peresapan 1M2/Ttk ttk 75.00 75.00 - -
Pem
Dowel Ø8 - 200 mm Kg 41.48 41.48 - -
Retaining Wall -
Pondasi Cerucuk Kayu D10cm L 4m Ttk 140.00 140.00 - -
Galian Tanah M³ 27.84 27.84 - -
Bekisting Dinding Multiplek M² 38.91 38.91 - -
Pengecoran 1:3:5 + 60% Batu Mangga t10cm M³ 46.98 46.98 - -
Peresapan 1M2/Ttk ttk 47.00 47.00 - -

40 PEKERJAAN STRUKTUR BAWAH JEMBATAN -


43 Abutment A1 -
Tiang Pancang Beton Square pile 30x30, L10 m Ttk 10.00 10.00 -
Pe Pemotongan Tiang Pancang Ttk 10.00 10.00 - -
PenPengelasan Tiang Pancang Ttk 10.00 10.00 - -
Pe Pemancangan Tiang Pancang M' 100.00 100.00 - -
Urug Pasir M³ 1.10 1.10 - -
Lantai Kerja M³ 1.10 1.10 - -
Bekisting -
Bekisting Pilecap M² 10.01 10.01 - -
Bekisting Badan Abutment M² 32.04 32.04 - -
Bekisting Kepala Abutment M² 8.82 8.82 - -
Bekisting Backwall M² 15.34 15.34 - -
Bekisting Wingwall M² 23.67 23.67 - -
Bekisting Plat Injak M² 3.60 3.60 - -
Pembesian -
Pem
Pembesian Pilecap Kg 1,197.12 1,197.12 - -
Pem
Pembesian Badan Abutment Kg 1,183.50 1,183.50 - -
Pem
Pembesian Kepala Abutment Kg 546.16 546.16 - -
Pem
Pembesian Backwall Kg 444.35 444.35 - -
Pem
Pembesian Wingwall Kg 1,304.44 1,304.44 - -
Pem
Pembesian Plat Injak Kg 637.60 637.60 - -
Pengecoran K-300 -
PenPengecoran Pilecap M³ 7.72 7.72 - -
PenPengecoran Badan Abutment M³ 10.42 10.42 - -
PenPengecoran Kepala Abutment M³ 4.19 4.19 - -
PenPengecoran Backwall M³ 2.23 2.23 - -
PenPengecoran Wingwall M³ 6.43 6.43 - -
PenPengecoran Plat Injak M³ 3.15 3.15 - -
Angkur Plat Injak -
PekPipa Galvanis ᴓ 1" Btg 1.00 1.00 - -
Pem
Angkur ᴓ 19 mm Kg 9.32 9.32 - -
Pem
Besi Beton Ø 10 mm Kg 19.55 19.55 - -
Rubber Sheet 15x15, t=2 cm Pcs 9.00 9.00 - -
43 Abutment A2 -
Tiang Pancang Beton Square pile 30x30, L10 m Ttk 10.00 10.00 -
Pe Pemotongan Tiang Pancang Ttk 10.00 10.00 - -
PenPengelasan Tiang Pancang Ttk 10.00 10.00 - -
Pe Pemancangan Tiang Pancang M' 100.00 100.00 - -
Urug Pasir M³ 1.10 1.10 - -
Lantai Kerja M³ 1.10 1.10 - -
Bekisting -
Bekisting Pilecap M² 10.01 10.01 - -
Bekisting Badan Abutment M² 32.04 32.04 - -
Bekisting Kepala Abutment M² 8.82 8.82 - -
Bekisting Backwall M² 15.34 15.34 - -
Bekisting Wingwall M² 23.67 23.67 - -
Bekisting Plat Injak M² 3.60 3.60 - -
Pembesian -

Printed On 12/27/2022
9/12
Prepared by QS
Pem
Pembesian Pilecap Kg 1,197.12 1,197.12 - -
Pem
Pembesian Badan Abutment Kg 1,183.50 1,183.50 - -
Pem
Pembesian Kepala Abutment Kg 546.16 546.16 - -
Pem
Pembesian Backwall Kg 444.35 444.35 - -
Pem
Pembesian Wingwall Kg 1,304.44 1,304.44 - -
Pem
Pembesian Plat Injak Kg 637.60 637.60 - -
Pengecoran K-300 -
PenPengecoran Pilecap M³ 7.72 7.72 - -
PenPengecoran Badan Abutment M³ 10.42 10.42 - -
PenPengecoran Kepala Abutment M³ 4.19 4.19 - -
PenPengecoran Backwall M³ 2.23 2.23 - -
PenPengecoran Wingwall M³ 6.43 6.43 - -
PenPengecoran Plat Injak M³ 3.15 3.15 - -
Angkur Plat Injak -
PekPipa Galvanis ᴓ 1" Btg 1.00 1.00 - -
Pem
Angkur ᴓ 19 mm Kg 9.32 9.32 - -
Pem
Besi Beton Ø 10 mm Kg 19.55 19.55 - -
Rubber Sheet 15x15, t=2 cm Pcs 9.00 9.00 - -
50 PEKERJAAN KONSTRUKSI STRUKTUR ATAS JEMBATAN -
51 PEKERJAAN KONSTRUKSI BAJA JEMBATAN -
Konstruksi Baja Jembatan 24 Meter -
r Handling Material Baja Kg 28,931.00 28,931.00 - -
r Erection Struktur Baja Kg 28,931.00 28,931.00 - -
52 LANTAI JEMBATAN -
Pekerjaan Lantai Jembatan 24 Meter M³ 17.44 17.44 -
Bekisting Menerus M² 11.40 11.40 - -
Pembesian £ dia. 12 mm Kg 5,099.07 5,099.07 - -
Pengecoran (K-300) M³ 25.86 25.86 - -
Pekerjaan Kanstin & Deck Drain M³ 4.69 4.69 -
Bekisting Menerus M² 23.52 23.52 - -
Pembesian £ dia. 12 mm Kg 612.89 612.89 - -
Pengecoran (K-300) Include Fin. Expose u/ cansteen M³ 4.69 4.69 - -
Pipa Drain PVC AW 2" Btg 2.00 2.00 - -
Pengecatan kanstin M² 30.72 30.72 - -

TOTAL -

Note = Volume di atas hanya sebagai panduan, kontraktor harus tetap menghitung ulang

Printed On 12/27/2022
10/12
Prepared by QS
BILL OF QUANTITY
PROYEK : JEMBATAN BETON 10M H = 8.00 M Jenis Tanah : Tanah Mineral - Penge
LOKASI : EMPANANG - SSWE - Bekist
HARGA : Rp -
KONTRAKTOR :
harus diisi
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT. VOL VOL SATUAN HARGA
Estimasi Kontraktor Rp. Rp.

00 PEKERJAAN TANAH & PONDASI -


01 Abutment -
r Pondasi Cerucuk Kayu D15cm L 4m Ttk 234.00 234.00 - -
r Galian Tanah M³ 58.82 58.82 - -
r Urugan Tanah & Pemadatan M³ 14.71 14.71 - -
r Urug Pasir M³ 4.90 4.90 - -
r2 Lantai Kerja M³ 2.45 2.45 - -
r Bekisting Dinding Multiplek M² 195.87 195.87 - -
r Pengecoran 1:3:5 + 60% Batu Mangga M³ 168.26 168.26 - -
Pembesian ###
r Pembes
Besi Beton D 22 mm Kg 91.51 91.51 - -
r Pembes
Besi Beton D 16 mm Kg 644.64 644.64 - -
r Pembes
Besi Beton Ø 12 mm Kg 62.32 62.32 - -
Peresapan ###
r Ijuk Kg 23.40 23.40 - -
r Pipa PVC Merk Wavin 2" D - 4 m Btg 46.80 46.80 - -
r Plesteran 1:2 + Acian M² 58.48 58.48 - -
02 Sayap Jembatan -
r Pondasi Cerucuk Kayu D15cm L 4m Ttk 112.00 112.00 - -
r Galian Tanah M³ 56.70 56.70 - -
r Urugan Tanah & Pemadatan M³ 14.18 14.18 - -
r Urug Pasir M³ 2.40 2.40 - -
r2 Lantai Kerja M³ 1.20 1.20 - -
r Bekisting Dinding Multiplek M² 173.60 173.60 - -
r Pengecoran 1:3:5 + 60% Batu Mangga M³ 103.93 103.93 - -
Pembesian ###
r Pembes
Besi Beton D 16 mm Kg 92.81 92.81 - -
r Pembes
Besi Beton Ø 12 mm Kg 29.83 29.83 - -
Peresapan ###
r Ijuk Kg 7.35 7.35 - -
r Pipa PVC Merk Wavin 2" D - 4 m Btg 14.70 14.70 - -
r Plesteran 1:2 + Acian M² 95.20 95.20 - -

10 PEKERJAAN KONSTRUKSI BETON -


11 Kepala Jembatan (K 175) -
Bekisting Setempat Multiplek M² 27.29 27.29 - -
Pembesian ###
Pembes
Besi Beton D 16 mm Kg 363.42 363.42 - -
Pembes
Besi Beton Ø 12 mm Kg 277.71 277.71 - -
Pengecoran (K 175) Bentang > 6 M M³ 3.68 3.68 - -
12 Plat Beton (K 175) -
Bekisting Plat Lantai M² 37.49 37.49 - -
Pembesian ###
Pembes
Besi Beton Ø 10 mm Kg 899.74 899.74 - -
Pengecoran (K 175) Bentang > 6 M M³ 9.12 9.12 - -
Drainase ###
Pipa PVC Merk Wavin 2" D - 4 m Btg 0.45 0.45 - -
13 Balok Memanjang (K 175) -
Bekisting Setempat Multiplek M² 49.34 49.34 - -

Printed On 12/27/2022
11/12
Prepared by QS
BILL OF QUANTITY
PROYEK : JEMBATAN BETON 10M H = 8.00 M Jenis Tanah : Tanah Mineral - Penge
LOKASI : EMPANANG - SSWE - Bekist
HARGA : Rp -
KONTRAKTOR :
harus diisi
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT. VOL VOL SATUAN HARGA
Estimasi Kontraktor Rp. Rp.

Pembesian ###
Pembes
Besi Beton D 22 mm Kg 1,369.68 1,369.68 - -
Pembes
Besi Beton Ø 12 mm Kg 535.94 535.94 - -
Pengecoran (K 175) Bentang > 6 M M³ 6.68 6.68 - -
14 Balok Pengaku (K 175) -
Bekisting Setempat Multiplek M² 14.40 14.40 - -
Pembesian ###
Pembes
Besi Beton D 16 mm Kg 135.74 135.74 - -
Pembes
Besi Beton Ø 10 mm Kg 108.51 108.51 - -
Pengecoran (K 175) Bentang > 6 M M³ 0.76 0.76 - -
15 Balok Kanstin (K 175) -
Bekisting Setempat Multiplek M² 8.49 8.49 - -
Pembesian ###
Pembes
Besi Beton Ø 10 mm Kg 146.74 146.74 - -
Pengecatan Kanstin M² 16.80 16.80 - -
Pengecoran (K 175) Bentang > 6 M M³ 0.74 0.74 - -
16 Steiger -
Steiger Bentang > 6 M M² 37.49 37.49 - -

20 PEKERJAAN KONSTRUKSI BAJA -


21 Kepala Jembatan -
PekerjPlat 16 mm Kg 271.30 271.30 - -
22 Acesories -
Elastomeric 450 x 350 x 30 mm Bh 6.00 6.00 - -
Angkur Ø 16 mm, L = 250 mm Bh 48.00 48.00 - -

TOTAL BANGUNAN -

Printed On 12/27/2022
12/12
Prepared by QS

You might also like