PRESIDENT’S OFFICE
REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT
PROPOSED DISPENSARY
PROJECT AREA
TANZANIA MAINLAND
MATERIALS
A SUBSTRUCTURE -PROVISIONAL
2 Foundation Walls
6'' Cement & Sand Block 1,232 No
3
Sand 4M
Cement -50kgs 21 Bags
B. SUPERSTRUCTURE
2 Roof Covering
2
28G IT resincoated sheet 120 M
Hips - 28 G 3 PC'S
Roofing Nails 10 Box
TO COLLECTION C/F
E. CEILING
Gypsum board -12mm thick 23 PC'S
Plain Cornice 42 PC'S
Gypsum Screw 1'' 800pcs/box 3 Box
Screw 1.25'' 800pcs/box 1 Box
Gypsum powder 5 Bags
Fibre tape 2 Pcs
Treated softwood Timber 2'' X 2'' 1,047 FT
Nails 4'' 11 Kgs
Nails 3'' 13 Kgs
PVC ceiling with its fittings - 40 Pc's
SUB-TOTAL FOR CEILING
F. DOOR
1 45mm thick Pannelled door shutter
900 x 2100mm high 7 PC'S
3 IronMongeries B/F
Mortice lock Three lever - ref: union 7 No
Brass hinges - 100mm 10.5 Pairs
Barrel bolt - 150mm 2 No
SUB-TOTAL FOR DOORS
G. WINDOWS
1 Supply and fix Aluminium Windows 2mm thick frem
with fibre glass, Mosquitor gauze and its
ironmongeries
1200 X 1500mm high 8 PC'S
900 X 600mm high 3 PC'S
2 Supply and fix 4mm thick flat bar grill painted red-
oxide
1200 x 1500mm high 8 PC'S
900 x 600 mm high 3 PC'S
SUB-TOTAL FOR WINDOWS
H. FINISHING
1 Floor finishing
3
Sand 5M
Cement-50kgs 32 Bags
600 x 600Non slippery Porcelain floor tiles (1.46
44 Box
Sqm/Box)
Skirting (600 mm long; 25No/Box) 6 Box
Grout 2 Packet
Spacer 2 Packet
2 Wall Finishing
3
Sand 12 M
Cement-50kgs 73 Bags
White cement - 50kg 4 Bags
Gypsum powder 5 Bags
Sand paper (msasa) No.120 0.5 Roll
200 X 300 Wall tiles to toilets full height 35 Box
(0.96Sqm/Box)
Grout 3 Packet
Spacer 1 Packet
SUB-TOTAL FOR FINISHING
J. ELECTRICAL INSTALLATION
1 Single flourescent fiiting, approved philips or equal 7 No
A. SUBSTRUCTURE -PROVISIONAL
B. SUPERSTRUCTURE
D. CEILING
E. DOOR
F. WINDOWS
G. FINISHING
J. ELECTRICAL INSTALLATION
Kufunga mbao
4 Pembezoni mwa jamvi
5 Pembezoni mwa nguzo
6 Kuondoa mbao
Kumwaga zege
7 Chini kwenye msingi wa tofali
8 Chini kwenye msingi wa nguzo
9 katika nguzo ya awali
10 kwenye jamvi
Mawe
12 Upangaji wa mawe na utandazaji wa DPM
13 Umwagiliaji wa maji
Jumla ndogo msingi wa jengo
D. Milango
1 Kufitisha fremu za milango
2 Kufitisha shata za milango pamoja na vitasa
3 Upakaji wa Varnishi katika milango na fremu
E. Umaliziaji (Finishing)
Upigaji wa lipu pamoja na kutengeneza koplo:
1 Nje ya jengo
2 Ndani ya jengo
Sakafu
3 Uwekaji wa sakafu ya kupokea vigae (beds)
4 Uwekaji wa vigae pamoja na grauti katika sakafu (floor tiles) -
Dali:
6 Ufungaji wa mbao za dali (Brandering)
7 Uwekaji wa dali na mikanda ya gypsum
8 Uwekaji wa dali ya pvc kuzunguka nyumba kwa nje
H.
Mifumo ya maji safi na taka (Water Supply and Sewage system)
MAJUMUISHO (SUMMARY)
Shs
A. Msingi wa Jengo (Sub-structure)
D. Milango
E. Umaliziaji (Finishing)
ANGALIZO:
Fundi anatakiwa kujaza hii fomu kwa kupitia mchoro wa jengo husika
230
230
230
1 1
860
1950 4080 3870 3640
1090
1090
W2
1430
900
900
150
2 2
W1 2
1200
2550
1950 3 PRINCIPAL
SHOWER
1050
1050
230
900
900
8 D2 BEDROOM
W2
3600
1200
3 2 1 W1
150
3 3
860
600
600
1950 D1
900
230
150
4 4
KITCHEN 1700 900 1660
1350
1050
1050
CORRIDOR
900
900
D1 D1
2400
900
X2 9 X2 6 150 230
1 2 3 2070 900 900 3870
W2 3 2 1
150
150
150
5 5
D1
7960
7960
D1
900
900
D1
900
900
1580
6
150 X1 6
980
W1 SITTING
3960
3980
3980
5 BEDROOM 2 VERRANDAH
1200
1 1
X1
3080
3 2 1
3270
3270
1200
3310
W1
2100mm high,
1580
230mm thick
1130
230 painted block wall 230 150 230
6030 2740 3640 1130
250
230
230
230
7 7
W1 W1
6260 980 1200 2030 1200 1580 880
250
GROUND PLAN 1990 4270
14150
1090
2 2
1050
1050
3 3
600
600
4 4
1050
1050
X2 X2
5 5
7960
7960
900
900
6 X1 6
X1
3270
3270
2100mm high,
230mm thick
painted block wall
7 7
1990 4270 2930 1130 2700
14150
ROOF PLAN
A B C D E F G
SCALE: 1:100
Building Section
Policy and Planning Department
Approved No. Description Date Client
STAFF QUARTER
PRESIDENT'S OFFICE, REGIONAL ADMINISTRATION
Ministry of Health, Community Developent, Roof Plan
Gender, Elderly and Children AND LOCAL GOVERNMENT Project number 2017 / 05 / 02
University of Dodoma
College of Humanities and Social Science 11th Project
Date 24 APRIL 2018 A102
Building,
P. O. Box 743, PROPOSED STANDARD DESIGN FOR A DISPENSARY Drawn by DCNM
40478 DODOMA Checked by DCNM Scale 1: 100
C D E F G
50x50mm ceiling joists
50x150mm tie beams
26°
500
500
500
500
1500
3000
2500
2500
2500
BEDROOM 1 SITTING VERANDAH
1000
50mm total thickness floor 50mm total thickness floor
finish including 1:3 cement finish including 1:3 cement
G.F screed & floor finish screed & floor finish
150 100
150 100
230
230
230
690 690 690 690
10mm thick Porcelain floor tiles on
40mm sand-cement backing on
SECTION X1:X1
100mm thick plain concrete slab on
150mm thick hardcore on well compacted back fill
SCALE: 1:50
Building Section
Policy and Planning Department
Approved No. Description Date Client
STAFF QUARTER
PRESIDENT'S OFFICE, REGIONAL ADMINISTRATION
Ministry of Health, Community Developent, Section X1:X1
Gender, Elderly and Children AND LOCAL GOVERNMENT Project number 2017 / 05 / 02
University of Dodoma
College of Humanities and Social Science 11th Project
Date 24 APRIL 2018 A103
Building,
P. O. Box 743, PROPOSED STANDARD DESIGN FOR A DISPENSARY Drawn by DCNM
40478 DODOMA Checked by DCNM Scale 1:50
7 6 5 4 3 2 1 G F E D C B A
FRONT ELEVATION RIGHT SIDE ELEVATION
1 2 3 4 5 6 7 A B C D E F G
REAR ELEVATION LEFT SIDE ELEVATION
ELEVATIONS
SCALE: 1:100
Building Section
Policy and Planning Department
Approved No. Description Date Client
STAFF QUARTER
PRESIDENT'S OFFICE, REGIONAL ADMINISTRATION
Ministry of Health, Community Developent, Elevations
Gender, Elderly and Children AND LOCAL GOVERNMENT Project number 2017 / 05 / 02
University of Dodoma
College of Humanities and Social Science 11th Project
Date 24 APRIL 2018 A105
Building,
P. O. Box 743, PROPOSED STANDARD DESIGN FOR A DISPENSARY Drawn by DCNM
40478 DODOMA Checked by DCNM Scale 1:100
NOTE:
A B C D E F 1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
referred to the structural
engineer
3. Reinforced concrete shall be
of grade 20 with
fcu=25N/mm² at 28 days of
age
4. Main reinforcements shall be
1 1 high tensile steel with fy =
460N/mm²
5. Nominal cover to the
reinforcements:
2 2 a) Foundation 50mm
b) Column 25mm
c) Beam 25mm
d) Slab 25mm
3 3 PROJECT:
PROPOSED REHABILITATION
OF HEALTH CENTRE
4 4
CLIENT:
PRESIDENT'S OFFICE
5 5 REGIONAL ADMINISTRATION
LOCAL GOVERNMENT
MINISTRY OF HEALTH,
COMMUNITY DEVELOPMENT,
6 6 GENDER AND CHILDREN
DRAWING TITLE:
STAFF HOUSE
FOUNDATION LAYOUT
Designed by: Eng. R.A.M
Drawn by: ENG. MKHOTYA
Checked by: Eng. R.A.M
A B C D E F
Approved by:
Date: Scale:
2018
FOUNDATION PLAN Drawing No. Sheet:
STR.101
230 NOTE:
150 1. All dimensions are in mm
unless otherwise specified
+0.450
+0.450 2. All discrepancies shall be
100mm floor slab
100mm floor slab referred to the structural
200mm hardcore engineer
450
200mm hardcore
3. Reinforced concrete shall be
dpm level
of grade 25 with
dpc level dpc level fcu=25N/mm² at 28 days of
Well compacted
age
1000
230
-1.000 460N/mm²
230
Concrete grade 15
Concrete grade 15 5. Nominal cover to the
reinforcements:
230 230 230 a) Foundation 50mm
230 230 230
b) Column 25mm
345 345
345 345 c) Beam 25mm
690 d) Slab 25mm
690
Section B - B Section C - C
PROJECT:
PROPOSED REHABILITATION
OF HEALTH CENTRE
1000
CLIENT:
PRESIDENT'S OFFICE
REGIONAL ADMINISTRATION
6Y16-01-200(B2
230
LOCAL GOVERNMENT
1000
230
MINISTRY OF
250
6Y16-01-200(B1) HEALTH,COMMUNITY
DEVELOPMENT,GENDER,
0mm CONCRETE BLINDING ELDERLY AND CHILDREN
TYPICAL SECTION A-A THROUGH
FOOTING
COLUMN FOOTING F1 -4Nos
1000x1000x250mm
DRAWING TITLE:
STAFF HOUSE PLINTH
BEAM LAYOUT
Designed by: Eng. R.A.M
Drawn by: Eng. R.A.M
Checked by: ENG. A.MKHOTYA
Approved by:
Date: Scale:
2018
Drawing No. Sheet:
STR,102
NOTE:
A B C D E F
1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
referred to the structural
engineer
3. Reinforced concrete shall be
of grade 25 with
fcu=25N/mm² at 28 days of
age
BEAM 01 4. Main reinforcements shall be
1 1
high tensile steel with fy =
460N/mm²
BEAM 02 5. Nominal cover to the
2 2 reinforcements:
a) Foundation 50mm
b) Column 25mm
BEAM 05
BEAM 07
BEAM 08
BEAM 06
c) Beam 25mm
d) Slab 25mm
3 3
PROJECT:
PROPOSED REHABILITATION
BEAM 03
OF HEALTH CENTRES
4 4
CLIENT:
5 5 PRESIDENT'S OFFICE
REGIONAL ADMINISTRATION
LOCAL GOVERNMENT
BEAM 04 MINISTRY OF
6 6 HEALTH,COMMUNITY
DEVELOPMENT,GENDER,
ELDERLY AND CHILDREN
DRAWING TITLE:
STAFF HOUSE PLINTH
BEAM LAYOUT
Designed by: Eng. R.A.M
Drawn by: Eng. R.A.M
Checked by: Eng. A. MKHOTYA
A B C D E F
Approved by:
Date: Scale:
2018
FOUNDATION BEAM LAYOUT Drawing No. Sheet:
STR,103
NOTE:
1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
referred to the structural
engineer
3. Reinforced concrete shall be
of grade 25 with
2Y12 fcu=25N/mm² at 28 days of
age
4. Main reinforcements shall be
high tensile steel with fy =
460N/mm²
A
5. Nominal cover to the
reinforcements:
a) Foundation 50mm
A b) Column 25mm
c) Beam 25mm
2Y12 d) Slab 25mm
SECTION B-B PROJECT:
PROPOSED REHABILITATION
OF HEALTH CENTRES
A 2Y12
CLIENT:
PRESIDENT'S OFFICE
A REGIONAL ADMINISTRATION
LOCAL GOVERNMENT
MINISTRY OF
HEALTH,COMMUNITY
230 DEVELOPMENT,GENDER,
ELDERLY AND CHILDREN
2Y12
DRAWING TITLE:
STAFF HOUSE PLINTH BEAM
SECTION A-A DETAILS
Designed by: Eng. R.A.M
Drawn by: Eng. R.A.M
Checked by: Eng. A.MKOTYA
Approved by:
Date: Scale:
2018
Drawing No. Sheet:
STR.104
NOTE:
A B C D E F 1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
referred to the structural
engineer
3. Reinforced concrete shall be
of grade 25 with
fcu=25N/mm² at 28 days of
age
BEAM 01 4. Main reinforcements shall be
1 1 high tensile steel with fy =
460N/mm²
BEAM 02 5. Nominal cover to the
2 2 reinforcements:
BEAM 10 a) Foundation 50mm
b) Column 25mm
BEAM 11
c) Beam 25mm
d) Slab 25mm
BEAM 03
3 3
PROJECT:
BEAM 08
BEAM 07
PROPOSED REHABILITATION
BEAM 04 OF HEALTH CENTRES
4 4
BEAM 09
BEAM 05 CLIENT:
5 5 PRESIDENT'S OFFICE
REGIONAL ADMINISTRATION
LOCAL GOVERNMENT
BEAM 06 MINISTRY OF
6 6 HEALTH,COMMUNITY
DEVELOPMENT,GENDER,
ELDERLY AND CHILDREN
DRAWING TITLE:
STAFF HOUSE RINGBEAM
LAYOUT
Designed by: Eng. R.A.M
Drawn by: Eng. R.A.M
A B C D E F Checked by: Eng. A.MKHOTYA
Approved by:
Date: Scale:
RING BEAM LAYOUT 2018
Drawing No. Sheet:
STR. 105
NOTE:
1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
referred to the structural
engineer
3. Reinforced concrete shall be
2Y12 of grade 25 with
fcu=25N/mm² at 28 days of
age
4. Main reinforcements shall be
B high tensile steel with fy =
460N/mm²
5. Nominal cover to the
reinforcements:
B a) Foundation 50mm
b) Column 25mm
c) Beam 25mm
d) Slab 25mm
2Y12
SECTION B-B PROJECT:
PROPOSED REHABILITATION
OF HEALTH CENTRES
2Y12
CLIENT:
PRESIDENT'S OFFICE
REGIONAL ADMINISTRATION
LOCAL GOVERNMENT
A
MINISTRY OF
HEALTH,COMMUNITY
DEVELOPMENT,GENDER,
A 150 ELDERLY AND CHILDREN
2Y12 DRAWING TITLE:
STAFF HOUSE RING BE
DETAILS
SECTION A-A Designed by: Eng. R.A.M
Drawn by: Eng. R.A.M
Checked by: Eng. A.MKHOTYA
Approved by:
Date: Scale:
2018
Drawing No. Sheet:
STR.106
NOTE:
1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
referred to the structural
engineer
2640 19715 3. Reinforced concrete shall be
of grade 25 with
fcu=25N/mm² at 28 days of
age
4. Main reinforcements shall be
600
high tensile steel with fy =
460N/mm²
1690
10210
6830
OF HEALTH CENTRES
CLIENT:
PRESIDENT'S OFFICE
REGIONAL ADMINISTRATION
LOCAL GOVERNMENT
1690
MINISTRY OF
HEALTH,COMMUNITY
DEVELOPMENT,GENDER,
ELDERLY AND CHILDREN
DRAWING TITLE:
TRUSS LAYOUT
Designed by: Eng. R.A.M
Drawn by: Eng. R.A.M
Checked by: Eng. A.MKHOTYA
Approved by:
Date: Scale:
2018
Drawing No. Sheet:
STR.107
NOTE:
1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
referred to the structural
engineer
3. Reinforced concrete shall be
of grade 25 with
fcu=25N/mm² at 28 days of
age
4. Main reinforcements shall be
high tensile steel with fy =
A
460N/mm²
5. Nominal cover to the
reinforcements:
B a) Foundation 50mm
B
b) Column 25mm
c) Beam 25mm
C d) Slab 25mm
F
PROJECT:
PROPOSED
REHABILITATION OF
D E D C HEALTH CENTRES
CLIENT:
PRESIDENT'S OFFICE
REGIONAL ADMINISTRATION
LOCAL GOVERNMENT
MINISTRY OF
HEALTH,COMMUNITY
SCALE 1:50
DEVELOPMENT,GENDER,
ELDERLY AND CHILDREN
TYPICAL ROOF TRUSS T01 ; 9Nos. DRAWING TITLE:
STAFF HOUSE TRUSS
DETAILS
Designed by: Eng. R.A.M
Drawn by: Eng. R.A.M
Checked by: Eng. A. MKOTYA
Approved by:
Date: Scale:
2018
Drawing No. Sheet:
STR.108
NOTE:
1. All dimensions are in mm
unless otherwise specified
2. All discrepancies shall be
1
150
referred to the structural
engineer
171
2 3. Reinforced concrete shall be
of grade 25 with
fcu=25N/mm² at 28 days of
1825
950
73
140
age
23
37
4
460N/mm²
1290 2420 2640 2420 1290
5. Nominal cover to the
545
545
reinforcements:
TIMBER PLATE(GUSSET)
Nails.
a) Foundation 50mm
50
50
b) Column 25mm
c) Beam 25mm
TYPICAL ROOF TRUSS T01 ; 9Nos. d) Slab 25mm
150
150
50
50
0
15 150 150
PROJECT:
50
15
0
REHABILITATION OF
HEALTH CENTRES
50
150
0 15
15 0 Nails.
50
50
150
50 50
PRESIDENT'S OFFICE
150
150
150
50
150
ROOF TRUSS DETAIL " 2 " MINISTRY OF
HEALTH,COMMUNITY
DEVELOPMENT,GENDER,
TIMBER PLATE(GUSSET) ELDERLY AND CHILDREN
25 25 25 25
50 Nails 50
TIMBER PLATE(GUSSET)
DRAWING TITLE:
150
150
ROOF TRUSS DETAIL " 7 " Nails.
ROOF TRUSS DETAIL " 5 " STAFF HOUSE TRUSS DETAILS AND
CONNECTIONS
50 50
Designed by: Eng. R.A.M
150
Eng. R.A.M
150
50
Drawn by:
15
Eng. A. MKHOTYA
50
Checked by:
50
TIMBER PLATE(GUSSET) 25 25 50
50
50 150
150
Approved by:
15
150
0
0
15
ROOF TRUSS DETAIL " 1 "
ROOF TRUSS DETAIL " 4 " Date: Scale:
ROOF TRUSS DETAIL " 2 " 2018
Drawing No. Sheet:
STR.109
NOTES:
DRAWING DESCRIPTION
FLOOR PLANS
CHECKED CHENGULA
DRAWING NUMBER REVISION
NOTES:
ELECTRICAL SYMBOLS
No. Date Description
Fluorescent light fitting Single tube 1200mm P Water pump F Extract fan
DRAWING DESCRIPTION
ELECTRICAL PLAN
CHECKED CHENGULA
DRAWING NUMBER
REVISION