Professional Documents
Culture Documents
Heat load calculation for Main Control Room and Control equipment room (Unit # 1&2) is worked out
based on book “Hand Book of Air Conditioning System Design (AC-11/633) available in Library and
these calculations were cross checked with similar calculations done in.
On detail discussion & analysis, the following loads are considered as significance for
refrigeration requirements.
East wall
75 x 5 m2
(4167 sq.ft)
14 x 5 m2 75 x 14 m2 14 x 5 m2
785 sq. ft Floor ( 11700 sq. ft) (785 sq. Ft)
North wall 35°C South wall
35°C 35°C
75 x 14 m2
Roof ( 11700 sq. ft)
35°C
1a. Through West Wall:
Control Room ( MCR + 1&2 CER) is a construction of Hollow bricks of 230mm with 15mm
cement plastering on either side.
Equivalent temperature Difference ΔTe = 32°F for 20°F Design temperature range
(For weight 37 + 2x6 lbs/ sq. ft)
Correction factor of ΔTe ducts 40°F Design Temperature range in +7°F
= U A ΔTe
= 0.37 x 4167 x 39 = 60129 BTU / hr
= U A ΔTe
= 0.37 x 4167 (104 -72) = 49337.28 Btu / hr
Heat Gain through North and South walls of building due to temperature difference.
Outside temperature = 35°C = 95 °F
= U A ΔTe
= 0.37 x (785 + 785) x (95 °F - 72°F )
= 13360.7 BTU / hr
a. As per table 45, page 97, minimum CFM for person required for air change is 15cfm
(considering application as General Office) & number persons is taken as 20
It is considered air change volume of 17400ft3/hr based on floor area to better evacuation of
Iodine from control room.
3. Occupancy: 20 persons
U-1 U-2
38KVA load 28595 W 22730 W 204860 BTU/hr
48 KV DC load 3293 W 5369 W 59985 W
3 Centrifugal Fans of 7.5 HP 16778 W 57300 BTU/hr
262160 BTU/hr
It is proposed to install 80TR air handling units considering additional loads due to heat through
cooling coil room walls and load due to cooling rate of total volume.