DAFTAR HARGA SATUAN MATERIAL

URAIAN / NAMA / JENIS BARANG HRG SATUAN KET

A MATERIAL SEMEN
1 Semen PC / 50 kg, 73,550.00 /zak
2 Semen Putih 40 kg 58,840.00 /zak
3 Semen warna (semen naat) 13,700.00 /Kg
B MATERIAL MORTAR UTAMA (MU)
1 Plester premium (MU 100) 77,000.00 /zak 40Kg
2 Plester trasraam (MU 101) 90,000.00 /zak 40Kg
3 Acian plesteran / beton expose (MU 200) 171,000.00 /zak 40Kg
4 Acian plesteran (MU 250) 158,000.00 /zak 40Kg
5 Acian profil (MU 260) 188,500.00 /zak 25Kg
6 Acian putih (MU 270) Perekat keramik area lembab 153,000.00 /zak 25Kg
7 Finish plester (MU 290) 97,000.00 /zak 40Kg
8 Pasangan bata (MU 300) 60,000.00 /zak 40Kg
9 Pasangan & plesteran bata (MU 301) 62,500.00 /zak 50Kg
10 Perekat bata ringan (MU 380) 158,500.00 /zak 40Kg
11 Perekat keramik dinding (MU 400) 136,000.00 /zak 25Kg
12 Pengisi naad keramik (MU 408) 12,500.00 /Kg
13 Perata lantai (MU 440) 62,000.00 /zak 40Kg
14 Perata lantai premium (MU 445) 165,000.00 /zak 40Kg
15 Perekat keramik lantai (MU450) 195,000.00 /zak 40Kg
16 Perekat keramik daerah basah (MU 460) 428,500.00 /zak 25Kg
17 Perekat keramik diatas keramik (MU 480) 253,000.00 /zak 25Kg
18 Multi Purpose Tile Adhesive (MU 485) 1,100,000.00 /40Kg set
19 Fast Setting Tile Adhesive (MU 490) 352,000.00 /zak 25Kg
20 Perekat mortar & beton / Bonding Agent (MU L-500) 263,500.00 / 2Kg
21 Pelapis kedap air (MU 600) 1,060,000.00 /30Kg set
22 Floor Hardener (MU 700) 137,500.00 /zak 25Kg
23 Non shrink grout (MU 800) 158,000.00 /zak 40Kg
24 Perbaikan permukaan beton (MU 830) 257,000.00 /zak 40Kg
25 Pengisi celah beton / Finish Coat Repair (MU 840) 320,000.00 / 25Kg set

C BETON READY MIX


1 MORTAR M3 750,000.00
2 Beton mutu B-0 M3 718,750.00
3 Beton mutu K-125 M3 736,000.00
4 Beton mutu K-150 M3 759,000.00
5 Beton mutu K-175 M3 782,000.00
6 Beton mutu K-200 M3 805,000.00
7 Beton mutu K-225 M3 822,250.00
8 Beton mutu K-250 M3 856,750.00
9 Beton mutu K-275 M3 891,250.00
10 Beton mutu K-300 M3 937,250.00
11 Beton mutu K-350 M3 971,750.00
12 Tambahan biaya untuk lama pembongkaran
13 - 0,5 jam s/d 1 jam truk/mixer 100,000.00
14 - 1 jam s/d 2 jam truk/mixer 250,000.00
15 - 2 jam s/d 3 jam truk/mixer 400,000.00
16 Harga sewa Concrete Pump (lebih dari 8 jam, Rp. 500.000/jam) 8 jam/hari 3,000,000.00

D MATERIAL PASIR, BATU & BATA


1 Pasir beton 192,800.00 /M3
2 Pasir extra beton 192,800.00 /M3
3 Pasir Pasang 183,700.00 /M3
4 Pasir Urug 134,900.00 /M3
5 Sirtu 166,400.00 /M3
6 Batu pecah / Split ukuran 1-2 cm 204,500.00 /M3
7 Batu pecah / Split ukuran 2-3 cm 191,800.00 /M3
8 Koral beton 162,400.00 /M3
9 Batu kali belah 170,500.00 /M3
10 Batu Gamping/ Limeston3 250,750.00 /M3
11 Makadam / batu pecah 5-7 cm 162,400.00 /M3
12 Abu batu 5 mm 231,084.00 /M3
13 Sreening 5-13 mm 230,834.00 /M3
14 Batu bata uk. 5 x 11 x 23 cm (ukuran besar) 650.00 /bh
15 Batu bata uk. 4 x 9.5 x 20 cm (ukuran kecil) 500.00 /bh
16 Batu bata ringan (ex Hebel), 10x19x60 cm 866,666.67 /M3
17 10,400.00 /bh
18 Batu bata ringan (ex Hebel), 7x19x60 cm 866,666.67 /M3

Harga Satuan Material - 1


19 5,824.00 /bh
20 Batu bata ringan (ex Broco), 10x19x60 cm 839,400.00 /M3
21 8,058.24 /bh
22 Batu bata ringan (ex Broco), 7x19x60 cm 839,000.00 /M3
23 5,638.08 /bh
24 Batako Semen (semen, pasir, abu batu) 9x19x39 cm 3,000.00 /bh
25 Glassblock 20/20 DN (ex Kedawung) 22,500.00 /bh
26 Rooster beton 20x20x7 cm 7,012.00 /bh
27 Rooster bata merah 12x11,5x24 cm (Klingker) 5,000.00 /bh
28 Lempengan garis uk. 9x19x39 cm 2,765.00 /bh
29 Tanah urug / tanah merah 81,200.00 /M3
30 I j u k 13,000.00 /kg
31 Air 260.00 /liter
E MATERIAL BESI
1 Besi beton polos 8,000.00 /kg
2 Besi beton ulir 8,000.00 /kg
3 Besi plat strip 9,250.00 /kg
4 Baja profil siku 9,250.00 /kg
5 Baja WF 9,250.00 /kg
6 Baja H Beam 9,250.00 /kg
7 Baja Kanal C (Channal) 9,250.00 /kg
8 Besi plat hitam (segala ukuran) 9,250.00 /kg
9 Besi plat putih (segala ukuran) 9,250.00 /kg
10 Besi plat bordes 9,250.00 /kg
11 Kanal C galvaspan HI-TEN, type C 100.16 75,844.00 /M'
12 Kanal C galvaspan HI-TEN, type C 100.20 80,500.00 /M'
13 Kanal C galvaspan HI-TEN, type C 125.16 70,000.00 /M'
14 Kanal C galvaspan HI-TEN, type C 125.20 81,000.00 /M'
15 Kanal C galvaspan HI-TEN, type C 150.16 93,562.00 /M'
16 Kanal C galvaspan HI-TEN, type C 150.20 116,250.00 /M'
17 Kanal C galvaspan HI-TEN, type C 150.25 145,000.00 /M'
18 Kanal C galvaspan HI-TEN, type C 200.16 100,000.00 /M'
19 Kanal C galvaspan HI-TEN, type C 200.20 172,500.00 /M'
20 Kanal C galvaspan HI-TEN, type C 200.25 228,750.00 /M'
21 Besi Wire Mesh DM-10F1, 540 x 210 cm (11,34 M2) 968,000.00 85,361.55 /M2
22 Besi Wire Mesh DM-9F1, 540 x 210 cm (11,34 M2) 797,500.00 70,326.28 /M2
23 Besi Wire Mesh DM-8F1, 540 x 210 cm (11,34 M2) 605,000.00 53,350.97 /M2
24 Besi Wire Mesh DM-7F1, 540 x 210 cm (11,34 M2) 467,500.00 41,225.75 /M2
25 Besi Wire Mesh DM-6F1, 540 x 210 cm 346,500.00 30,555.56 /M2
26 Besi Wire Mesh DM-5F1, 540 x 210 cm 236,500.00 20,855.38 /M2
27 Besi Wire Mesh DM-4, 540 x 210 cm 181,500.00 16,005.29 /M2
28 Kawat beton 18,022.00 /kg
29 Kawat Las 30,000.00 /kg
30 Kawat duri 10 kg (60 m') 65,568.00 /kg
31 Paku halus (2 - 3 cm) 19,360.00 /kg
32 Paku ukuran sedang (4 - 5 cm) 16,420.00 /kg
33 Paku ukuran sedang (6 - 7 cm) 15,300.00 /kg
34 Paku ukuran (10-15 cm) 14,800.00 /kg
35 Seng Gelombang BJLS 20 45,000.00 /lmbr
36 Seng Gelombang BJLS 30 55,000.00 /lmbr
37 Seng plat BJLS 30, lebar 60 cm 30,000.00 /M'
38 Seng plat BJLS 30, lebar 90 cm 40,000.00 /M'
39 Paku Seng 25,000.00 /kg
40 Besi Hollow 30x60x2 (rangka utama) Rgk. Pintu besi/konstruksi 185,000.00 /btg/6m
41 Besi Hollow 40x40x2 (rangka utama) Rgk. Pintu besi/konstruksi 150,000.00 /btg/6m
42 Besi Hollow 20x40x2 (rangka pembagi) Rgk. Pintu besi/konstruksi 125,000.00 /btg/6m
43 Folding Gate :
44 - Folding Gate, bahan besi plate tbl. 0.3 mm lengkap dg finishing & kunci dll. 384,000.00 /m2
45 - Folding Gate, bahan besi plate tbl. 0.4 mm lengkap dg finishing & kunci dll. 408,000.00 /m2
46 - Folding Gate, bahan besi plate tbl. 0.5 mm lengkap dg finishing & kunci dll. 420,000.00 /m2
47 - Folding Gate, bahan galvalum, tbl. 0.3 mm lengkap dg finishing & kunci dll. 426,000.00 /m2
48 - Folding Gate, bahan galvalum, tbl. 0.4 mm lengkap dg finishing & kunci dll. 450,000.00 /m2
49 - Folding Gate, bahan galvalume, tbl. 0.5 mm lengkap dg finishing & kunci dll. 474,000.00 /m2
50 Rolling Door :
51 - Rolling Door, bahan besi plate tbl. 0.3 mm lengkap dg finishing & kunci dll. 276,000.00 /m2
52 - Rolling Door, bahan Galvalum tbl. 0.3 mm lengkap dg finishing & kunci dll. 336,000.00 /m2
53 - Rolling Door, bahan Allumunium tbl. 0.3 mm lengkap dg finishing & kunci dll. 384,000.00 /m2

F MATERIAL KAYU
Kayu Meranti basah
1 - Balok Meranti basah (8/15,8/12,6/15,6/12, 5/10x400 cm) katagori kelas - II 4,284,500.00 /M3
2 - Kasau Meranti basah (5/7x400, 4/6x400 cm) 4,275,200.00 /M3
3 - Reng (3/4x400, 2/3x400) 4,303,000.00 /M3

Harga Satuan Material - 2


4 - Papan Meranti basah ( 3 x 20 x 400 cm) 4,601,234.00 /M3
Kayu Rimba Campuran (KRC) basah katagori kelas - III
1 - Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) 3,635,500.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) 3,635,000.00 /M3
3 - Reng (3/4x400, 2/3x400) 3,658,000.00 /M3
4 - Papan (3/30, 3/20 & 2/30x400 cm) ( u/. Bekisting ) 3,928,000.00 /M3
5 - Kayu Dolken (kayu Galam 8-10cm, L=4m) ( u/. Bekisting ) 30,000.00 /btg
6 - Plastik cor ( u/. Bekisting ) 6,000.00 /M2
Kayu Terentang
1 - Papan uk. 3/30x400, 3/20x400 & 2/30x400 cm ( u/. Bekisting ) 2,500,000.00 /M3
Kayu Kamper Samarinda basah
1 - Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 8,819,167.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 8,743,834.00 /M3
3 - Reng (3/4x400) (u/. Rngk.Atap) 8,662,834.00 /M3
4 - Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 9,117,500.00 /M3
Kayu Borneo/Meranti Super
1 - Balok Borneo/Meranti Super, kelas-3 (u/. Rngk.Atap) 5,000,000.00 /M3
2 - Kasau Borneo/Meranti Super (u/. Rngk.Atap) 4,800,000.00 /M3
3 - Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 5,200,000.00 /M3
Kayu Kruing
1 - Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 6,791,875.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 6,591,875.00 /M3
3 - Reng (3/4x400) 6,391,875.00 /M3
4 - Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 6,991,875.00 /M3
Kayu Kamper Medan
1 - Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 6,791,875.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 6,591,875.00 /M3
3 - Reng (3/4x400) 6,391,875.00 /M3
4 - Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 6,991,875.00 /M3
Kayu Bengkirai
1 - Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 7,000,000.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 6,800,000.00 /M3
3 - Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 7,250,000.00 /M3
Kayu Kamper Singkil
1 - Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 7,000,000.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 6,800,000.00 /M3
Kayu Kamper Banjar
1 - Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 7,000,000.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 6,800,000.00 /M3
3 - Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 7,250,000.00 /M3
Kayu Jati Kelas I (Jawa Timur)
1 - Balok Jati Jawa Timur, Kelas-I (u/. Kosen/pintu) 55,000,000.00 /M3
2 - Papan Jati Jawa Timur, Kelas-I (u/. Kosen/pintu) 57,500,000.00 /M3
3 - Balok Jati Jawa Timur, Super (u/. Kosen/pintu) 65,000,000.00 /M3
4 - Papan Jati Jawa Timur, Super (u/. Kosen/pintu) 67,500,000.00 /M3
Kayu Jati Kelas II Basah (Jawa Tengah)
1 - Balok uk. 6x15x100 - 190 cm 45,000,000.00 /M3
2 - Balok uk. 6x15x200 - 240 cm 45,000,000.00 /M3
3 - Balok uk. 6x15x240 - 290 cm 45,000,000.00 /M3
4 - Balok uk. 6x15x240 - 340 cm 45,000,000.00 /M3
5 - Balok uk. 6x15x340 - 390 cm 45,000,000.00 /M3
Kayu Kruing
1 - Balok Kamper Kruing (oven) (u/. Kosen/pintu) 7,091,875.00 /M3
2 - Balok Kamper Medan (oven) (u/. Kosen/pintu) 7,091,875.00 /M3
Kayu Kamper Singkil oven
1 - Balok Kamper Singkil (oven) (u/. Kosen/pintu) 7,300,000.00 /M3
2 - Papan Kamper Singkil (oven) (u/. Kosen/pintu) 7,550,000.00 /M3
Kayu Kamper Samarinda (kering oven)
1 - Balok (8/12 x400 & 6/15x400 cm) (u/. Kosen) 9,757,500.00 /M3
2 - Kasau (5/7x400, 4/6x400 cm) 9,799,100.00 /M3
3 - Reng (3/4x400) 9,799,100.00 /M3
4 - Papan (3/20x400 cm) 10,612,500.00 /M3
5 - Papan (4/30, 4/25x400 cm) (u/. Pintu) 10,307,500.00 /M3
6 - Balok Kamper Samarinda, super (oven) (u/. Kosen/pintu) 10,057,500.00 /M3
7 - Papan Kamper Samarinda, super (oven) (u/. Kosen/pintu) 10,607,500.00 /M3
8 - Papan Meranti oven (u/. Kosen/pintu) 6,000,000.00 /M3
Kayu Bengkirai
1 - Balok Bengkirai (u/. Kosen/pintu) 7,500,000.00 /M3
2 - Papan Bengkirai (u/. Kosen/pintu) 7,750,000.00 /M3
Kayu Merbau
1 - Balok Merbau (oven) (u/. Kosen/pintu) 10,000,000.00 /M3
2 - Papan Merbau (oven) (u/. Kosen/pintu) 10,250,000.00 /M3

Harga Satuan Material - 3


G MATERIAL MULTIPLEKS
1 Multipleks, 1220x2440x25 mm 285,000.00 /lmbr
2 Multipleks, 1220x2440x22 mm 265,000.00 /lmbr
3 Multipleks, 1220x2440x20 mm 240,000.00 /lmbr
4 Multipleks, 1220x2440x18 mm 203,540.00 /lmbr
5 Multipleks, 1220x2440x15 mm 180,000.00 /lmbr
6 Multipleks, 1220x2440x12 mm 155,360.00 /lmbr
7 Multipleks, 1220x2440x9 mm 105,000.00 /lmbr
8 Multipleks, 1220x2440x6 mm 77,000.00 /lmbr
9 Multipleks, 1220x2440x4 mm 55,500.00 /lmbr
10 Teakwood 1220x2440x4 mm 111,450.00 /lmbr
11 Plywood Sungkai, uk. 1220x2440x3 mm 121,000.00 /lmbr
12 Plywood Sungkai, uk. 1220x2440x4 mm 135,000.00 /lmbr
13 Plywood Sungkai, uk. 1220x2440x18 mm (1 muka) 221,500.00 /lmbr
14 Plywood Sungkai, uk. 1220x2440x18 mm (2 muka) 257,000.00 /lmbr
15 Bloktik, uk. 1220x2440x18 mm (1 muka) 236,750.00 /lmbr
16 Melamin, uk. 1220x2440x3 mm (mengkilap) 78,500.00 /lmbr
17 Formika, 92 x 212 mm 85,000.00 /lmbr
18 HPL 4' x 8' 135,000.00 /lmbr

H MATERIAL : PLAFOND & PARTISI


1 Gypsum board 9 mm (water resistants) 105,000.00 /lmbr
2 Gypsum board 9 mm, ex Jayaboard 60,000.00 /lmbr
3 Gypsum board 12 mm, ex Jayaboard 76,000.00 /lmbr
4 Calcium Silikat 6 mm 101,300.00 /lmbr
5 Gypsum Tile 600x1200x9mm 17,500.00 /lmbr
6 AcousticTile 600x1200x15 mm Ex Armstrong 75,000.00 /lmbr
7 Gypsumboard Type Jaya Belt 120x240 cm, tebal 12 mm 275,500.00 /lmbr
8 Profil allumunium PN 400 Main Tee (p. 3,6m) 9,305.56 /m'
9 Profil allumunium PN 402 Cross Tee (p. 1,2 m) 8,333.33 /m'
10 Profil allumunium PN 401 Cross Tee (p. 0,60 m) 8,500.00 /m'
11 Profil allumunium PN 408 Wall Angle (p. 3,60 m) 5,305.56 /m'
12 Profil All PN 409 Rod 3 mm (p. 2,4 m) 1,583.33 /m'
13 PN 410 Clip 2,900.00 /bh
14 Gypsum bubuk (compound) 4,500.00 /kg
15 Paku skrup gypsum 40,000.00 /Kg
16 Paku skrup gypsum 300.00 /bh
17 Textile tape 17,500.00 /roll
18 Dina bolt / ramset 1,750.00 /bh
19 Hollow 40x40 mm galvanized (tebal standart) Rgk plafond/Partisi 6,500.00 /M'
20 Hollow 20x40 mm galvanized (tebal standart) Rgk plafond/Partisi 5,000.00 /M'
21 Hollow 40x40 mm dimenie (tebal standart) Rgk plafond/Partisi 6,000.00 /M'
22 Hollow 20x40 mm dimenie (tebal standart) Rgk plafond/Partisi 4,500.00 /M'
23 Metal Furing 75 mm Rgk plafond/Partisi 12,566.67 /M' (pnj 3m/btg
24 Kawat gantungan 3,000.00 /set
25 Paku beton 35,000.00 /kg
26 Sekrup 6x1-1,5 500.00 /bh
27 Sekrup fixer 600.00 /bh
28 Paku Ripet 250.00 /bh
29 List Profil Gypsum Uk. Sedang 12,000.00 /M'
30 List Profil Gypsum Uk. Kecil 10,500.00 /M'
31 List Kayu Profil, ukuran sedang 12,500.00 /M'
32 List plafond allumunium (Wall angle) 6,500.00 /m'
33 GRC BOARD, 1220x2440x5 mm 65,000.00 /lmbr
34 GRC BOARD, 1220x2440x6 mm 75,000.00 /lmbr
35 GRC BOARD, 1220x2440x8 mm 110,000.00 /lmbr
36 GRC BOARD, 1220x2440x10 mm 130,000.00 /lmbr
37 GRC SPR PANEL, 1220x2440x9 mm 175,000.00 /lmbr
38 GRC SPR PANEL, 1220x2440x12 mm 200,000.00 /lmbr
39 GRC SPR PANEL, 1220x2440x15 mm 250,000.00 /lmbr
40 Compound GRC (A +B) 60,000.00 /kg
41 Asbes plat 100x100x0,4 cm 30,000.00 /M2
42 Lem kayu Fox 30,000.00 /Kg
43 Wall Paper, lebar 50 cm 30,000.00 / M'

I MATERIAL KACA
- Kaca Tempered
1 Kaca polos tempered 12 mm, ex Asahi Mas 517,500.00 / M2
2 Kaca warna tempered 12 mm, ex Asahi Mas 966,000.00 / M2
3 Kaca polos tempered 10 mm, ex Asahi Mas 455,400.00 / M2
4 Kaca warna tempered 10 mm, ex Asahi Mas 821,100.00 / M2
5 Kaca polos tempered 8 mm, ex Asahi Mas 358,800.00 / M2
6 Kaca warna tempered 8 mm, ex Asahi Mas 531,300.00 / M2

Harga Satuan Material - 4


7 Kaca polos tempered 6 mm, ex Asahi Mas 248,400.00 / M2
8 Kaca warna tempered 6 mm, ex Asahi Mas 345,000.00 / M2
9 Kaca polos tempered 5 mm, ex Asahi Mas 186,300.00 / M2
10 Kaca warna tempered 5 mm, ex Asahi Mas 276,000.00 / M2
- Kaca polos (clear glass)
1 Kaca polos 12 mm, ex Asahi Mas 330,000.00 / M2
2 Kaca polos 10 mm, ex Asahi Mas 275,000.00 / M2
3 Kaca polos 8 mm, ex Asahi Mas 192,500.00 / M2
4 Kaca polos 6 mm, ex Asahi Mas 148,500.00 / M2
5 Kaca polos 5 mm, ex Asahi Mas 110,000.00 / M2
- Kaca Warna
1 Kaca warna Dark Grey (Rayban) 5 mm, ex Asahi Mas 126,500.00 / M2
2 Kaca warna Dark Grey (Rayban) 6 mm, ex Asahi Mas 176,000.00 / M2
3 Kaca warna Dark Grey (Rayban) 8 mm, ex Asahi Mas 325,000.00 / M2
4 Kaca warna Blue 5 mm, ex Asahi Mas 132,000.00 / M2
5 Kaca warna Brown 5 mm, ex Asahi Mas 148,500.00 / M2
6 Kaca warna Green 6 mm, ex Asahi Mas 181,500.00 / M2
7 Kaca warna Green 8 mm, ex Asahi Mas 325,000.00 / M2
- Kaca Stopsol
1 Kaca Stopsol, tebal 5 mm 350,000.00 / M2
2 Kaca Stopsol, tebal 6 mm 450,000.00 / M2
3 Kaca Stopsol, tebal 8 mm 575,000.00 / M2
4 Kaca Stopsol, tebal 10 mm warna green 925,000.00 / M2
5 Kaca Stopsol, tebal 12 mm 1,100,000.00 / M2
- Kaca Laminated (Kaca+PVB+Kaca)
1 Kaca polos (tebal 5mm+0,38+5 mm), ex ….. 414,000.00 / M2
2 Kaca polos (tebal 6mm+0,38+6 mm), ex ….. 471,500.00 / M2
3 Kaca polos (tebal 8mm+0,76+8 mm), ex ….. 782,000.00 / M2
4 Kaca polos (tebal 10mm+0,76+10 mm), ex ….. 908,500.00 / M2
5 Kaca polos (tebal 12mm+0,76+12 mm), ex ….. 989,000.00 / M2
6 Kaca polos (tebal 15mm+0,76+15 mm), ex ….. 2,029,750.00 / M2
- Jasa Proses Mesin
1 Gosok pinggir, kaca tebal 12 mm 21,450.00 / M'
2 Gosok adumanis, kaca tebal 12 mm 43,450.00 / M'
3 Bevel, kaca tebal 8 - 12 mm 36,300.00 / M'
4 Lubang, kaca tebal 8 - 12 mm 17,600.00 / Bh
5 Cowak pojok, kaca tebal 8 - 12 mm 47,850.00 / Bh
6 Cowak Tepi, kaca tebal 8 - 12 mm 66,550.00 / Bh
7 Sandblst (full block), kaca tebal 5 - 12 mm 106,250.00 / M2

J MATERIAL ALLUMUNIUM
ALLUMUNIUM PRODUK YKK
1 Profil kosen Allumunium 1 3/4 x 3", Silver Clear Anodized ex YKK 95,000.00 / M'
2 Profil kosen Allumunium 1 3/4 x 4", Silver Clear Anodized ex YKK 110,000.00 / M'
3 Profil Frame Allumunium Pintu kaca, Silver Clear Anodized ex YKK 100,000.00 / M'
4 Profil Frame Allumunium Jendela kaca, Silver Clear Anodized ex YKK 85,000.00 / M'
5 Profil kosen Allumunium 1 3/4 x 3", Black/Brown Anodized ex YKK 110,000.00 / M'
6 Profil kosen Allumunium 1 3/4 x 4", Black/Brown Anodized ex YKK 150,000.00 / M'
7 Profil Frame Allumunium Pintu kaca, Black/Brown Anodized ex YKK 140,000.00 / M'
8 Profil Frame Allumunium Jendela kaca, Black/Brown Anodized ex YKK 100,000.00 / M'
9 Profil kosen Allumunium 1 3/4 x 3", Powder Coating ex YKK 140,000.00 / M'
10 Profil kosen Allumunium 1 3/4 x 4", Powder Coating ex YKK 160,000.00 / M'
11 Profil Frame Allumunium Pintu kaca, Powder Coating ex YKK 154,000.00 / M'
12 Profil Frame Allumunium Jendela kaca, Powder Coating ex YKK 120,000.00 / M'
ALLUMUNIUM PRODUK ALEXINDO
1 Profil kosen Allumunium 1 3/4 x 3", Silver Clear Anodized ex Alexindo 55,000.00 / M'
2 Profil kosen Allumunium 1 3/4 x 4", Silver Clear Anodized ex Alexindo 70,000.00 / M'
3 Profil Frame Allumunium Pintu kaca, Silver Clear Anodized ex Alexindo 65,000.00 / M'
4 Profil Frame Allumunium Jendela kaca, Silver Clear Anodized ex Alexindo 55,000.00 / M'
5 Profil kosen Allumunium 1 3/4 x 3", Black/Brown Anodized ex Alexindo 70,000.00 / M'
6 Profil kosen Allumunium 1 3/4 x 4", Black/Brown Anodized ex Alexindo 75,000.00 / M'
7 Profil Frame Allumunium Pintu kaca, Black/Brown Anodized ex Alexindo 72,500.00 / M'
8 Profil Frame Allumunium Jendela kaca, Black/Brown Anodized ex alexindo 62,500.00 / M'
9 Profil kosen Allumunium 1 3/4 x 3", Powder Coating serat kayu, ex Alexindo 130,000.00 / M'
10 Profil kosen Allumunium 1 3/4 x 4", Powder Coating serat kayu, ex Alexindo 160,000.00 / M'
11 Profil Frame Allumunium Pintu kaca, Powder Coating serat kayu, ex Alexindo 150,000.00 / M'
12 Profil Frame Allumunium Jendela kaca, Powder Coating serat kayu, ex Alexindo 120,000.00 / M'
13 Sealant kaca 8,125.00 / M'
14 Karet kaca 2,750.00 / M'
15 Sticker kaca, type clear sandblast 85,000.00 / M2
16 Allumunium plat tebal 0,4 mm, uk. 1000x2000 mm 123,500.00 /lmbr
17 Allumunium plat tebal 0,4 mm, uk. 1220x2440 mm 183,500.00 /lmbr
18 Allumunium plat tebal 0,5 mm, uk. 1000x2000 mm 154,500.00 /lmbr

Harga Satuan Material - 5


19 Allumunium plat tebal 0,5 mm, uk. 1220x2440 mm 229,500.00 /lmbr
20 Allumunium Bordes tebal 2 mm, uk. 1000x2000 mm 716,500.00 /lmbr
21 Allumunium Bordes tebal 3 mm, uk. 1000x2000 mm 1,074,500.00 /lmbr
22 Profil Aluminium U Channel 30x20 mm, silver anodized 30,000.00 / M'
Allumunium Composite Panel (ACP)
1 - ALUBANG Green (tebal ACP 4mm, tebal All 0,5mm) 265,000.00 / M2
2 - ALUBANG Fire Resistance (tebal ACP 4mm, tebal All 0,5mm) 350,000.00 / M2
3 - SEVEN Bright silver 5005 (tebal ACP 4mm, tebal All 0,5mm) 325,000.00 / M2
4 - Rangka allumunium 25,000.00 / M'

K MATERIAL ATAP
1 Genteng Plentong Glazur, ex Jatiwangi 4,250.00 /bh
2 Nok Genteng Plentong Glazur, ex Jatiwangi 7,500.00 /bh
3 Genteng Plentong tidak Glazur, ex Jatiwangi 3,500.00 /bh
4 Nok Genteng Plentong tidak Glazur, ex Jatiwangi 6,000.00 /bh
5 Genteng Keramik Glazur ex Kanmuri Milenio, warna Natural 7,370.00 /bh
6 Genteng Keramik Glazur ex Kanmuri Milenio, warna Standart 8,250.00 /bh
7 Genteng Keramik Glazur ex Kanmuri Espancia, warna Natural 7,150.00 /bh
8 Genteng Keramik Glazur ex Kanmuri Espancia, warna Standart 9,570.00 /bh
9 Genteng Keramik Glazur ex M Class (Double Interlocking) warna Natural 7,150.00 /bh
10 Genteng Keramik Glazur ex M Class (Double Interlocking) warna Standart 7,700.00 /bh
11 Genteng Keramik Glazur ex KIA 8,500.00 /bh
12 Nok Genteng Keramik Glazur, ex KIA 25,300.00 /bh
13 Genteng Keramik ex Cisangkan type Victoria 10,000.00 /bh
14 Nok Genteng Keramik, ex Cisangkan 25,000.00 /bh
15 Genteng Morando Glazur, ex Jatiwangi 3,500.00 /bh
16 Genteng Morando tidak Glazur, ex Jatiwangi 4,000.00 /bh
17 Nok Genteng Morando tidak Glazur, ex Jatiwangi 10,000.00 /bh
18 Genteng Beton ex Karangpilang (berwarna) 9,000.00 /bh
19 Genteng Nok Beton Karangpilang (berwarna) 25,000.00 /bh
20 Djabes gelombang kecil (B100) uk. 300x105, tbl. 6mm 125,000.00 /Lbr
21 Djabes gelombang kecil (B100) uk. 300x105, tbl. 5mm 115,000.00 /Lbr
22 Djabes gelombang kecil (K200) uk. 240x105, tbl. 4mm 90,000.00 /Lbr
23 Asbes Gelombang kecil uk. 210 cm x 105 cm, tebal 4 mm 60,000.00 /Lbr
24 Asbes Gelombang kecil uk. 240 cm x 105 cm, tebal 4 mm 68,000.00 /Lbr
25 Asbes Gelombang kecil uk. 270 cm x 105 cm, tebal 4 mm 77,000.00 /Lbr
26 Asbes Gelombang kecil uk. 300 cm x 105 cm, tebal 4 mm 85,000.00 /Lbr
27 Asbes Gelombang besar uk. 200 cm x 102 cm, tebal 5 mm 75,000.00 /Lbr
28 Asbes Gelombang besar uk. 225 cm x 102 cm, tebal 5 mm 79,000.00 /Lbr
29 Asbes Gelombang besar uk. 250 cm x 102 cm, tebal 5 mm 82,000.00 /Lbr
30 Asbes Gelombang besar uk. 200 cm x 102 cm, tebal 6 mm 77,500.00 /Lbr
31 Asbes Gelombang besar uk. 225 cm x 102 cm, tebal 6 mm 85,000.00 /Lbr
32 Asbes Gelombang besar uk. 250 cm x 102 cm, tebal 6 mm 90,000.00 /Lbr
33 Jendela Naco (kerangka + kaca 5 mm) 150,000.00 /m2
34 Skrup + ring 450.00 /bh
35 Atap Sirap 225,000.00 /M2
36 Paku sirap 30,000.00 /Kg
37 Atap Metal Zincalume, type KLIP-LOK HI-TEN, tebal 0,5 mm ex BLUESCOPE LYSAGHT 168,850.00 /M2
38 Atap Metal Zincalume, type OPTIMA HI-TEN, tebal 0,5 mm ex BLUESCOPE LYSAGHT 158,070.00 /M2
39 Atap Metal Zincalume, type SPANDEK HI-TEN, tebal 0,5 mm ex BLUESCOPE LYSAGHT 133,980.00 /M2
40 Atap Metal Zincalume, type TRIMDEK HI-TEN, tebal 0,5 mm ex BLUESCOPE LYSAGHT 123,420.00 /M2
41 Atap Metal Zincalume, type CUSTOM-ORB HI-TEN, tebal 0,5 mm ex BLUESCOPE LYSAGHT 123,420.00 /M2
42 Atap Glmbg GALVALUME, type SPANDEK LYSAGHT, tbl 0,75 mm (ex. CV. Cipta Prima Sentosa) 186,450.00 /M2
43 Atap Glmbg GALVALUME, type SPANDEK LYSAGHT, tbl 0,50 mm (ex. CV. Cipta Prima Sentosa) 127,600.00 /M2
44 Atap Metal ZINCALUM, type ada sterofoam 5cm 220,000.00 /M2
45 Atap Metal Spandex Zincalum tebal 0,5 mm (ex. CV. Cipta Prima Sentosa) 127,600.00 /M2
46 Genteng Metal (Sakura Roof) 31,500.00 /lbr
47 Nok Genteng Metal (Sakura Roof) 28,500.00 /lbr
48 Atap Polli Carbonat, 2,1 x 11,8 m, tebal 4 mm 1,182,500.00 /lbr
49 Atap Polli Carbonat, 2,1 x 11,8 m, tebal 4,2 mm 1,265,000.00 /lbr
50 Atap Polli Carbonat, 2,1 x 11,8 m, tebal 5 mm 2,035,000.00 /lbr
51 Atap Polli Carbonat, 2,1 x 11,8 m, tebal 6 mm 2,420,000.00 /lbr
52 Atap Polli Carbonat, 2,1 x 11,8 m, tebal 10 mm 3,850,000.00 /lbr

L MATERIAL WATERPROOFING
1 Lapisan Coating PF Primer 15,000.00 /M2
2 Waterproofing Membrane, Sopralene 180 4 S/P (4 mm) (1 Roll = Rp. 545.000) 36,486.98 /M2
3 Waterproofing Membrane, Sopralene 180 3 S/P (3 mm) (1 Roll = Rp. 426.000) 28,520.10 /M2
4 Waterproofing Membrane, Sopralene 180 Granuler (3 mm) (1 Roll = Rp. 365.000) 24,436.24 /M2
5 Waterproofing Membrane, Eshagun 3 SP (3 mm) (1 Roll = Rp. 325.250) 21,775.03 /M2
6 Waterproofing Membrane, Eshagun 3 Ard (3 mm) (1 Roll = Rp. 345.000) 23,097.27 /M2
7 Waterproofing Membrane, Eshagun 3 SP (3 mm) (1 Roll = Rp. 378.650) 25,350.09 /M2
8 Waterproofing jenis Coating ex Sika/AM/setara 55,000.00 /Kg

Harga Satuan Material - 6


9 Kawat kassa / kawat loket 17,500.00 /M2

M MATERIAL KERAMIK, MARMER, GRANIT & HOMOGENOUS TILE


Granit
1 - Granit Import (Red China & Black China) jenis Slab 550,000.00 /M2
2 - Granit Import (Nero Absolute India) jenis slab 650,000.00 /M2
3 - Granit Import (Nero Absolute Xanxy) jenis slab 850,000.00 /M2
4 - Granit Import (New Imperial Red) jenis slab 1,250,000.00 /M2
Homogenous Tile Niro Granite
1 - Niro Granite 80x80 Cm, Seri Regal (Kode : GMR 81, 83 & 97) W : Light Grey, Vanilla, Black 325,000.00 /M2
2 - Niro Granite 60x60 Cm, Seri Solfen (Kode : S04, S06) W : Ocra, Pearl, Shade, Olive 250,000.00 /M2
3 - Niro Granite 60x60 Cm, Seri Yura (Kode : S05, S06) W : Tobbaco, Gold, Lead Grey 250,000.00 /M2
4 - Niro Granite 60x60 Cm, Seri Regal (Kode : Y01 s/d Y06) W : Light Grey, Grey, Black, No 275,000.00 /M2
5 - Niro Granite 30x60 Cm, Seri Solfen (Kode : S03, S04) W : Ocra, Pearl, Shade, Olive 250,000.00 /M2
6 - Niro Granite 40x40 Cm, Seri Solfen (Kode : S02,S03,S04,S06) W : Ocra, Pearl, Shade, Olive 180,000.00 /M2
Homogenous Tile Granito
1 - Granito-Salsa, Type Silver (Crystal/Polished) 60x60 Cm W : Pearl White, Ivory 243,100.00 /M2
2 - Granito-Salsa, Type Silver (Oasis/Un-Polished) 60x60 Cm W : Pearl White, Ivory 211,200.00 /M2
3 - Granito-Salsa, Type Silver (Crystal/Polished) 30x60 Cm W : Pearl White, Ivory 251,900.00 /M2
4 - Granito-Salsa, Type Diamond (Polished) 60x60 Cm W : Water stone, White Sand 298,100.00 /M2
5 - Granito Palazzo, Type …. (Miror Polished) 60x60 Cm W : Arezzo 298,100.00 /M2
6 - Granito Palazzo, Type …. (Miror Polished) 60x60 Cm W : Palermo 315,700.00 /M2
7 - Granito Palazzo, Type …. (Miror Polished) 60x60 Cm W : Monza 327,800.00 /M2
8 - Granito Aurora, Type Silver 60x60 Cm (Polished) W : Waffle, Latte, Salmon, Mil 322,300.00 /M2
9 - Granito Aurora, Type Gold 60x60 Cm (Polished) W : Astro 398,200.00 /M2
10 - Granito Lunar, Type Bronze 60x60 Cm (Rustic, Un-polished) W : Solar, Helium 259,600.00 /M2
11 - Granito Lunar, Type Silver 60x60 Cm (Rustic, Un-polished) W : Terra, Sephyr 271,700.00 /M2
12 - Granito Lunar, Type Gold 60x60 Cm (Rustic, Un-polished) W : Amber, Quarts 321,200.00 /M2
13 - Granito Lunar, Type Diamond 60x60 Cm (Rustic, Un-polished) W : Alumina, Oxide 341,000.00 /M2
14 - Granito-Salsa, Type Silver (Polished) 30x60 Cm W : Pearl White, Ivory 251,900.00 /M2
15 - Granitto Aurora, Type Silver (Miror, Polished) 30x60 Cm W : Waffel, Latte 332,200.00 /M2
16 - Granitto Lunar, Type Bronze 30x60 Cm (Un-polished) W : Solar, Helium type Rustic 269,500.00 /M2
17 - Granitto Lunar, Type Silver 30x60 Cm (Un-polished) W : Terra, Sephyr type Rustic 281,600.00 /M2
18 - Granitto Lunar, Type Gold 30x60 Cm (Un-polished) W : Amber, Quartz type Rustic 321,200.00 /M2
19 - Granitto Lunar, Type Diamond 30x60 Cm (Un-polished) W : Alumina, Oxide type Rustic 341,000.00 /M2
20 - Granitto-Salsa, 40x40 Cm (Polished) Type Silver W : Pearl White, Ivory, Greysto 206,800.00 /M2
21 - Granitto-Salsa, 40x40 Cm (Un-polished) Type Silver W : Pearl White, Ivory, Greysto 178,200.00 /M2
22 - Granitto-Castello, 40x40 Cm (Un-polished) Type Silver W : Cappucino, Rombo, crema 178,200.00 /M2
23 - Granitto 40/40 Cm (polish) Group Silver W : Greystone, Linen, Blush, Cl 178,200.00 /M2
24 - Granitto 40/40 Cm, Group Gold, type Crystal (polish) W : Black 247,500.00 /M2
25 - Granitto 40/40 Cm (Un-polish) Group Gold, type Oasis W : Forest Green, Brick, Cocoa, 201,300.00 /M2
26 - Granitto Gastello 30x30 Cm (Un-polish) Group Silver, type rustic W : Capucino, expreso, crème 178,200.00 /M2
27 - Homogenous Tile 60x60 Cm, ex China 145,000.00 /M2
28 - Stepnozing tangga, Granito Salsa Diamond / Palazzo Silver 10x60 cm 25,000.00 /bh
Homogenous Tile Inesa
1 - Inesa, 30/30,40/40, Onix (Un-Polished) 97,500.00 /M2
2 - Group A (Pearl, Opal, Agate, Cateye, Topaz, Zamrud)
3 Inesa, uk. 30/30 & 40/40 (Polished) 138,000.00 /M2
4 - Group A (Pearl, Opal, Agate, Cateye, Topaz, Zamrud)
5 Inesa, 30/30,40/40 UP (Onix, Phyrus, Ruby, Jade) 126,000.00 /M2
6 - Group B (un-polish) 30x30, warna agarte 92,500.00 /M2
7 - Group B (un-polish) 40x40, warna agarte 99,000.00 /M2
8 - Group B (polish) 30x30, warna topaz 137,600.00 /M2
9 - Group B (polish) 40x40, warna topaz 151,500.00 /M2
10 - Inesa, 30/30, 40/40 P (Onix, Phyrus, Ruby, Jade) Group C 139,300.00 /M2
11 - Inesa, 40/40 Group A (Corypha polish) 161,500.00 /M2
12 - Inesa, 60 x 60 Group A (Corypha polish) 204,750.00 /M2
13 - Inesa, 40x40 (Polish), warna Topaz 151,500.00 /M2
14 - Inesa, 60/60 (P), Raphia 204,750.00 /M2
15 - Marble group A warna corypha (mengkilat), uk. 60x60 204,750.00 /M2
Homogenous Tile Essenza
1 - Essenza 30/30, Papper Grey (Un-Polished) 150,000.00 /M2
2 - Essenza 30/30, Papper Grey (Polished) 175,000.00 /M2
3 - Essenza Group A 40x40, Papper Grey (Un-Polished) 165,440.00 /M2
4 - Essenza Group A 40x40 polish warna : prince rubber, silver sta 189,200.00 /M2
5 - Essenza 60x60, Blak Orchid (Polished) 275,000.00 /M2
6 - Essenza Group B 60x60 (Polished) warna : Corypha 286,330.00 /M2
7 - Essenza Group A 60x60 polish warna : prince rubber, silver sta 232,320.00 /M2
Homogenous Tile Uero Grace
1 - Uero Grace 60/60, FHQ 6207 (pgnt Raphia) 170,000.00 /M2
2 - Uero Grace 30/30, FHQ 6207 125,000.00 /M2
3 - Uero Grace 60/60, Golden Black (pgnt Onix) 225,000.00 /M2
Marmer

Harga Satuan Material - 7


1 - Marmer Import Grasia / Itali Jenis slab 750,000.00 /M2
2 - Marmer Import Dark Emperador Jenis slab 400,000.00 /M2
3 - Marmer Import Light Emparador Jenis slab 650,000.00 /M2
4 - Marmer Import Crema Evory Jenis slab 650,000.00 /M2
5 - Marmer Import Golden Perlanto Jenis slab 650,000.00 /M2
6 - Marmer Import Volacas Jenis slab 950,000.00 /M2
7 - Marmer Import Travertine Jenis slab 1,300,000.00 /M2
8 - Marmer Import Rossi Vietnam Jenis slab 600,000.00 /M2
9 - Marmer Tulung Agung, 60x60x2 cm 250,000.00 /M2
10 - Marmer Tulung Agung (jenis slab) 350,000.00 /M2
11 - Marmer Ujung Pandang (acid wash), 60x60x1,8 cm 400,000.00 /M2
12 - Marmer Ujung Pandang Golden Perlato/Blue 60x60x1.8 350,000.00 /M2
13 - Marmer Ujung Pandang Krem CL 150 x 150 x 1.8 Jenis slab 530,000.00 /M2
14 - Marmer Ujung Pandang Flower Grey 150 x 250 x 1.8 Jenis slab 750,000.00 /M2
15 - Marmer Bandung (ex Citatah), 30x30x2 175,000.00 /M2
16 - Marmer Bandung (ex Citatah), 60x60x2 300,000.00 /M2
17 - Teralux Marmer 60x60 cm 350,000.00 /M2
18 - Marmer Lampung Kristaline 60x60x2 350,000.00 /M2
19 - Marmer Lampung Kristaline 100x100x2 530,000.00 /M2
Floor Hardener
1 - Floor Hardener (Gan's Floor) 12,500.00 /kg
2 - Epoxy Resin 15,000.00 /kg
Keramik Tile ex Roman
1 - Porselen 11 x 11 cm 55,000.00 /M2
2 - Keramik Artistik 5x20 Cm 65,000.00 /M2
3 - Keramik lokal 10x20 Cm (ex Roman) 55,000.00 /M2
4 - Keramik lokal 20/20 Cm (ex Roman) Gol A U/lantai (un-polish) 82,000.00 /M2
5 - Keramik lokal 20/20 Cm (ex Roman) Gol A Wall Tile U/dinding (polish) 77,000.00 /M2
6 - Keramik lokal 20/25 Cm (ex Roman) Gol A U/lantai & dinding 76,000.00 /M2
7 - Keramik lokal 25/25 Cm (ex Roman) Gol A 77,000.00 /M2
8 - Keramik lokal 30x30 Cm (ex Roman) Gol B U/dinding polish 95,000.00 /M2
9 - Keramik lokal 33,3x33,3 Cm (ex Roman) Gol AS 98,000.00 /M2
10 - Keramik lokal 20x60 Cm (ex Roman) Gol AS (Wall Tile) U/dinding 123,500.00 /M2
11 - Keramik lokal 30x60 Cm (ex Roman) Gol AS (Wall Tile) U/dinding 128,500.00 /M2
12 - Keramik lokal 20/25 Cm (ex Roman) Gol A (Wall Tile) U/dinding 76,000.00 /M2
13 - Keramik lokal 20x40 Cm (ex Roman) Gol A 80,000.00 /M2
14 - Keramik lokal 25x45 Cm (ex Roman) Gol A 87,000.00 /M2
15 - Keramik lokal 40/40 Cm (ex Roman) Gol A 103,000.00 /M2
16 - Keramik lokal 45x45 Cm (ex Roman) Gol A 120,000.00 /M2
17 - Keramik lokal 50x50 Cm (ex Roman) Gol A 129,500.00 /M2
18 - Stepnozing tangga, Keramik Roman 8x30 cm 15,000.00 /bh
Keramik Tile ex Masterina
1 - Keramik lokal 20x20 Cm (ex Masterina) seri M2GS 46,300.00 /M2
2 - Keramik lokal 30x30 Cm (ex Masterina) seri M3D30 46,000.00 /M2
3 - Keramik lokal 30x30 Cm (ex Masterina) seri M3GS71 47,000.00 /M2
4 - Keramik lokal 40x40 Cm (ex Masterina) seri M0GS66 48,250.00 /M2
Keramik Tile ex Mulia
1 - Keramik lokal 20x20 Cm (ex Mulia), Wall Tile Warna : pastel biscuit 54,500.00 /M2
2 - Keramik lokal 20x25 Cm (ex Mulia), Wall Tile Warna : pastel biscuit 52,500.00 /M2
3 - Keramik lokal 20x40 Cm (ex Mulia), Wall Tile Warna : glossy white 61,000.00 /M2
4 - Keramik lokal 20x40 Cm (ex Mulia), Wall Tile, grafis 1 (digitec) Warna : grafis 1 digitec 78,500.00 /M2
5 - Keramik lokal 30x60 Cm (ex Mulia), Wall Tile Warna : glossy white 81,500.00 /M2
6 - Keramik lokal 30x60 Cm (ex Mulia), Wall Tile, marble spesial (ner Warna : marble special (nero) 87,500.00 /M2
7 - Keramik lokal 20x20 Cm (ex Mulia), Floor Tile Warna : rustic 45,000.00 /M2
8 - Keramik lokal 30x30 Cm (ex Mulia), Floor Tile Warna : bistol fuerte 51,500.00 /M2
9 - Keramik lokal 40x40 Cm (ex Mulia), Floor Tile Warna : glossy cream 62,000.00 /M2

N MATERIAL LANTAI KARPET


1 Karpet
2 - Underlayer / Rubber corrugated 40,000.00 /M2
3 - Karpet Sheet ex Lokal 90,000.00 /M2
4 - Carpet Tile 50x50, ex Leiko 300,000.00 /M2
5 - Lem karpet/vinyl 20,000.00 /Kg
6 - Vinyl tile 30x30 cm, ex ………….. 85,000.00 /M2

O MATERIAL LANTAI PARQUET


1 - Red Oak lam parquet uk. 1,5 x 6 x 30 cm 115,600.00 /M2
2 - Red Oak lam parquet uk. 1 x 5 x 30 cm 105,500.00 /M2
3 - Jati lem parquet uk. 1 x 5 x 30 cm 138,975.00 /M2
4 - Jati lem parquet uk. 1 x 7 x 35 cm 148,750.00 /M2
5 - Jati lem parquet uk. 1 x 5 x 25 cm 98,700.00 /M2
6 - Tg. Parquet Jati uk. 1,8 x 5 x 30 cm 102,600.00 /M2
7 - Graculad 166,200.00 /M2

Harga Satuan Material - 8


8 - Gracewood 144 179,700.00 /M2
9 - Parkit (Kronospan) uk. 19 x 120 cm 180,000.00 /M2
10 - Parkit (Dream Wood) uk. 19 x 120 cm 180,000.00 /M2
11 - Lantai Kayu Panil Gracewood 325,000.00 /M2

P MATERIAL BATU ALAM


1 - Batu Candi 20x40 cm 96,668.00 /M2
2 - Batu alur Candi 20x40 cm 122,500.00 /M2
3 - Batu Alam susun sirih stilestone 300x40x20 mm warna 102,300.00 /M2
4 - Batu sirih texture 100x40x20, 200x40x20, 300x40x20 mm (natural) 69,300.00 /M2
5 - Batu Stilestone 300x50x20 mm (warna) 102,300.00 /M2
6 - Batu Stilestone 600x50x20 mm (warna) 96,800.00 /M2
7 - Batu Stripstone 400x200x15 mm (natural) 138,600.00 /M2
8 - Batu Stripstone 400x300x25 mm (natural) 59,400.00 /M2
9 - Batu alam Paliaman 20X40 95,267.00 /M2
10 - Batu tempel acak hitam Sukabumi 75,000.00 /M2
11 - Batu acak Garut 71,334.00 /M2
12 - Batu acak Purwakarta 60,334.00 /M2
13 - Batu alam Purwakarta 91,000.00 /M2
14 - Batu alam Andesit 20/20 & 15/30 cm 126,168.00 /M2
15 - Batu alam Andesit 20/30 cm 135,000.00 /M2
16 - Batu alam Andesit 20/40 s/d 30/40 cm 145,000.00 /M2
17 - Paras Jogja 20/30s/d40/40 (cream/putih) 97,584.00 /M2
18 - Paras Jogja 20/40s/d40/60 (cream/putih) 105,000.00 /M2
19 - Batu Bali 400x200x15 mm (natural/warna) 138,600.00 /M2
20 - Batu Goa 200x200x15, 400x200x15 mm, natural 173,000.00 /M2
21 - Batu Goa 200x200x15 mm, warna 187,000.00 /M2

Q MATERIAL CONBLOCK / INTERBLOCK (Ex. INTERNUSA)


1 Interblock 16.6, warna abu-abu 95,000.00 /M2
2 Interblock 16.6, warna Mrh, Htm, Kng, Klasik 125,000.00 /M2
3 Interblock 16.6, warna Hijau 135,000.00 /M2
4 Interblock 16.8, warna abu-abu 130,000.00 /M2
5 Interblock 16.8, warna Mrh, Htm, Kng, Klasik 140,000.00 /M2
6 Interblock 16.8, warna Hijau 150,000.00 /M2
7 Zurich 12.6 / Tiga berlian 6, abu-abu 118,200.00 /M2
8 Zurich 12.6 / Tiga berlian 6, (Mrh, Htm, Kng, Klasik) 136,200.00 /M2
9 Zurich 12.6 / Tiga berlian 6, Hijau 150,000.00 /M2
10 Zurich 12.8 / Tiga berlian 8, abu-abu 138,000.00 /M2
11 Zurich 12.8 / Tiga berlian 8, (Mrh, Htm, Kng, Klasik) 156,000.00 /M2
12 Zurich 12.8 / Tiga berlian 8, Hijau 172,800.00 /M2
13 Grassblock 20.10.40 (abu-abu) 136,200.00 /M2
14 Grassblock 20.8.40 (abu-abu) 112,200.00 /M2
15 Kansteen 15 x 30 x 40 38,000.00 /Bh

R MATERIAL CAT
1 Cat Duco Danagloss 79,193.00 /Kg
2 Cat Duco Nipple 2000 55,575.00 /Kg
3 Dempul Duco Sanpolac 30,300.00 /Kg
4 Tinner Up 23,700.00 /Kg
5 Cat Tembok Catylac (Acrilyc Emulsion), putih 25,000.00 /Kg
6 Cat Tembok dalam, Dulux ICI (Acrilyc Emulsion), Pentalitte Warna putih BD = 1,4 kg/lt 41,918.57 /Kg
7 Cat Tembok dalam, Dulux ICI (Acrilyc Emulsion), Pentalitte Warna biasa 42,129.14 /Kg
8 Cat Tembok dalam, Dulux ICI (Acrilyc Emulsion), Pentalitte Warna tua 43,978.57 /Kg
9 Cat Tembok luar (ICI Dulux Weathershield) Warna putih 61,500.00 /Kg
10 Cat Tembok luar (ICI Dulux Weathershield) Warna biasa 65,000.00 /Kg
11 Cat Tembok luar (ICI Dulux Weathershield), warna tua Warna tua 63,500.00 /Kg
12 Alkali Resistants Dulux ICI 43,428.57 /Kg
13 Cat Tembok Mowilex (Acrilyc Emulsion) 37,500.00 /Kg
14 Cat Tembok Mowilex (Wather Coat) 45,750.00 /Kg
15 Cat Tembok (cat minyak) ex Mowilex 50,000.00 /Kg
16 Cat Tembok Vinilex Super 19,000.00 /Kg
17 Plamur Tembok Matex (5 kg) 9,360.00 /Kg
18 Cat Kayu/besi (ICI Dulux Super Gloss) 46,722.00 /Kg
19 Cat Kayu/besi (ex Danapaint, Gloss) 46,000.00 /Kg
20 Cat Kayu / besi (kwalitas sedang, Ftalit, Kuda Terbang) 45,000.00 /Kg
21 Cat antikarat Zinchromate 40,000.00 /Kg
22 Plamur kayu 22,585.00 /Kg
23 Pelitur 47,375.00 /Kg
24 Melamik (Ultran) 42,535.00 /Kg
25 Wood Stain (Cat warna Standart ex Ultran) 58,500.00 /Kg
26 Sanding Sealer (Ultran) 76,142.00 /Kg
27 Filler Ultran 50,000.00 /Kg

Harga Satuan Material - 9


28 Menie Kayu 22,500.00 /Kg
29 Residu 9,570.00 /Kg
30 Kuas Roll 35,000.00 /Bh
31 Kuas 15,000.00 /Bh
32 Ampelas 3,400.00 /Bh

S MATERIAL MEKANIKAL
1 Pompa air (dengan otomatis) 600,000.00 /Bh
2 Pompa air (jet pump) 2,500,000.00 /Bh
3 Pompa air (non otomatis) 350,000.00 /Bh
4 Pipa besi galvanis ø 0,5 (inch) 20,000.00 /M'
5 Pipa besi galvanis ø 0,75 (inch) 24,100.00 /M'
6 Pipa besi galvanis ø 1 (inch) 34,500.00 /M'
7 Pipa besi galvanis ø 1,25 (inch) 41,500.00 /M'
8 Pipa besi galvanis ø 1,5 (inch) 47,500.00 /M'
9 Pipa besi galvanis ø 2 (inch) 51,400.00 /M'
10 Pipa besi galvanis ø 3 (inch) 85,000.00 /M'
11 Pipa besi galvanis ø 4 (inch) 120,000.00 /M'
12 Pipa besi ø 0,5 (inch) 20,000.00 /M'
13 Pipa besi ø 0,75 (inch) 22,500.00 /M'
14 Pipa besi ø 1 (inch) 22,500.00 /M'
15 Pipa besi ø 1,25 (inch) 35,000.00 /M'
16 Pipa besi ø 1,5 (inch) 41,250.00 /M'
17 Pipa besi ø 2 (inch) 45,000.00 /M'
18 Pipa beton ø 20 cm, panjang 1 m' 73,600.00 /Bh
19 Pipa beton ø 60 cm, panjang 1 m' 121,325.00 /Bh
20 Pipa PVC ø 1/2 (inch) AW, panjang 4 m 5,000.00 /M'
21 Pipa PVC ø 3/4 (inch) AW, panjang 4 m 6,500.00 /M'
22 Pipa PVC ø 1(inch) AW, panjang 4 m 7,750.00 /M'
23 Pipa PVC ø 1,5 (inch) AW, panjang 4 m 15,000.00 /M'
24 Pipa PVC ø 2 (inch) AW, panjang 4 m 20,000.00 /M'
25 Pipa PVC ø 2,5 (inch) AW, panjang 4 m 30,000.00 /M'
26 Pipa PVC ø 3 (inch) AW, panjang 4 m 40,000.00 /M'
27 Pipa PVC ø 4 (inch) AW, panjang 4 m 55,000.00 /M'
28 Pipa PVC ø 6 (inch) AW, panjang 4 m 116,250.00 /M'
29 Pipa PVC ø 5/8 500.00 /M'
30 Tangki air / hydrant umum fiberglass 1.000 liter 1,550,000.00 /Bh
31 Tangki air / hydrant umum fiberglass 2.000 liter 3,050,000.00 /Bh
32 Tangki air / hydrant umum fiberglass 3.000 liter 6,328,450.00 /Bh
33 Tangki air / hydrant umum fiberglass 6.000 liter (horizontal) 19,263,075.00 /Bh
34 Tangki air / hydrant umum polyethylene 1.000 liter 1,774,450.00 /Bh
35 Tangki air / hydrant umum polyethylene 2.000 liter 4,083,075.00 /Bh
36 Tangki air / hydrant umum polyethylene 3.000 liter 5,506,200.00 /Bh
37 Tangki air / hydrant umum polyethylene 4.000 liter 7,036,850.00 /Bh
38 Tangki air / hydrant umum polyethylene 5.000 liter 8,225,950.00 /Bh
39 Tangki air / hydrant umum polyethylene 500 liter 900,000.00 /Bh
40 Tangki air fiberglass (oranye) 1.000 liter 1,350,000.00 /Bh
41 Tangki air fiberglass (oranye) 2.000 liter 2,700,000.00 /Bh
42 Tangki air fiberglass (oranye) 3.000 liter 3,500,000.00 /Bh
43 Tangki air fiberglass (oranye) 500 liter 800,000.00 /Bh

MATERIAL TAMAN
1 Rumput Gajah 15,000.00 /M2
2 Rabuk 20,000.00 /kg
3 Pohon Peneduh, tinggi 2 - 2,5 m 75,000.00 /pohon

MATERIAL ASPAL
1 Aspal Polimer lokal 11,900.00 /kg

MATERIAL SALURAN
1 Tutup Saluran
2 - Tutup U30 @ 60 cm LD 58,500.00 /Bh
3 - Tutup U40 @ 60 cm LD 89,500.00 /Bh
4 - Tutup U50 @ 60 cm LD 113,500.00 /Bh
5 - Tutup U60 @ 60 cm LD 136,500.00 /Bh
6 - Tutup U80 @ 60 cm LD 174,500.00 /Bh
7 - Tutup U100 @ 60 cm LD 262,500.00 /Bh
8 - Tutup U120 @ 60 cm LD 295,500.00 /Bh
9 - Tutup U140 @ 60 cm LD 449,500.00 /Bh
10 Saluran precast type 40 (uk 40 x 40) tebal 55 mm 197,472.00 /M'
11 Saluran precast type 40 (uk 40 x 60) tebal 55 mm 310,728.00 /M'
12 Saluran precast type 50 (uk 50 x 50) tebal 60 mm 270,072.00 /M'

Harga Satuan Material - 10


13 Saluran precast type 50 (uk 50 x 70) tebal 60 mm 372,680.00 /M'
14 Saluran precast type 60 (uk 60 x 60) tebal 60 mm 347,512.00 /M'
15 Saluran precast type 60 (uk 60 x 80) tebal 60 mm 434,632.00 /M'
16 Saluran precast type 80 (uk 80 x 80) tebal 65 mm 497,552.00 /M'
17 Saluran precast type 80 (uk 80 x 100) tebal 65 mm 678,568.00 /M'
18 Saluran precast type 100 (uk 100 x 100) tebal 65 mm 914,760.00 /M'
19 Saluran precast type 100 (uk 100 x 120) tebal 65 mm 1,161,160.00 /M'
20 Saluran precast type 120 (uk 120 x 120) tebal 65 mm 1,628,055.00 /M'
21 Saluran precast type 120 (uk 120 x 140) tebal 65 mm 1,806,805.00 /M'
22 Saluran precast type 140 (uk 140 x 140) tebal 65 mm 1,986,270.00 /M'
23 Saluran precast type 140 (uk 140 x 160) tebal 65 mm 2,216,500.00 /M'
24 Buis beton dia. 20 cm tanpa tulang, panjang 1 m 45,000.00 /Bh
25 Buis beton dia. 30 cm tanpa tulang, panjang 1 m 55,000.00 /Bh
26 Buis beton dia. 50 cm tanpa tulang, panjang 1 m 85,000.00 /Bh
27 Buis beton dia. 60 cm tanpa tulang, panjang 1 m 110,000.00 /Bh
28 Buis beton 1/2 dia. 20 cm tanpa tulang, panjang 1 m 47,190.00 /Bh
29 Buis beton 1/2 dia. 30 cm tanpa tulang, panjang 1 m 65,780.00 /Bh

T BAHAN BAKAR MINYAK


1 Minyak bekisting 2,478.00 /liter
2 Minyak pelarut cat (solvent) 27,250.00 /liter
3 Minyak pelumas (oli) 25,000.00 /liter
4 Minyak solar (subsidi) 4,500.00 /liter
5 Minyak solar (industri) Hrg berfluktuasi 9,000.00 /liter
6 Minyak solar (industri) Hrg berfluktuasi 10,800.00 /liter
7 Minyak tanah (subsidi) 3,450.00 /liter
8 Minyak tanah (industri) Hrg berfluktuasi 6,800.00 /liter
9 Minyak tanah (industri) Hrg berfluktuasi 9,800.00 /liter

Harga Satuan Material - 11


I. DAFTAR UPAH TENAGA KERJA

NO DAFTAR PEKERJA SATUAN UPAH KET.


1 Mandor OH 110,000.00 7 jam kerja
2 Kepala Tukang Kayu OH 100,000.00 7 jam kerja
3 Tukang Kayu OH 100,000.00 7 jam kerja
4 Kepala Tukang Batu OH 100,000.00 7 jam kerja
5 Tukang batu OH 90,000.00 7 jam kerja
6 Kepala Tukang Gypsum OH 100,000.00 7 jam kerja
7 Tukang Gypsum OH 90,000.00 7 jam kerja
8 Kepala Tukang Besi OH 100,000.00 7 jam kerja
9 Tukang besi OH 90,000.00 7 jam kerja
10 Kepala Tukang Gali OH 100,000.00 7 jam kerja
11 Tukang Gali OH 90,000.00 7 jam kerja
12 Kepala Tukang Cat OH 100,000.00 7 jam kerja
13 Tukang Cat OH 90,000.00 7 jam kerja
14 Kepala Tukang Allumunium OH 100,000.00 7 jam kerja
15 Tukang khusus allumunium OH 90,000.00 7 jam kerja
16 Kepala Tukang pipa OH 100,000.00 7 jam kerja
17 Tukang pipa OH 90,000.00 7 jam kerja
18 Surveyor OH 150,000.00 7 jam kerja
19 Pembantu Surveyor OH 95,000.00 7 jam kerja
20 Mekanik OH 150,000.00 7 jam kerja
21 Mekanik Pembantu OH 95,000.00 7 jam kerja
22 Operator terlatih OH 150,000.00 7 jam kerja
23 Operator kurang terlatih OH 120,000.00 7 jam kerja
24 Pembantu Operator OH 95,000.00 7 jam kerja
25 Supir Material / truck OH 150,000.00 7 jam kerja
26 Supir personil / mobil ringan OH 150,000.00 7 jam kerja
27 Pembantu Sopir / kenek OH 95,000.00 7 jam kerja
28 Pekerja OH 70,000.00 7 jam kerja
III. DAFTAR SEWA PERALATAN

III. PERALATAN (BIAYA PEMILIKAN DAN OPERASI)

1 Asphalt Mixing Plant (AMP) Kap 60 T/jam 7,015,788.77 /Jam


2 Asphalt Finisher Kap 10 T 373,027.34 /Jam
3 Asphalt Sprayer Kap 850 liter 69,660.86 /Jam
4 Bulldozer 100 - 150 HP 544,013.01 /Jam
5 Compressor 4000 - 6500 L/M Kap 5000 CPM (L/M) 179,864.85 /Jam
6 Concreate Mixer 0,3 - 0,6 m3 Kap 500 liter 96,437.67 /Jam
7 Crane 10 - 15 ton Kap 15 T 405,211.34 /Jam
8 Dump Truck 3 - 5 Ton Kap 6 Ton 272,765.92 /Jam
9 Dump Truck 10 Ton Kap 10 Ton 494,897.70 /Jam
10 Excavator 80 - 140 HP Kap 0,9 m3 531,286.87 /Jam
11 Flat Bed Truck 3 - 4 m3 Kap 10 Ton 355,121.16 /Jam
12 Generator Set Kap 135 kVA 384,209.76 /hari
13 Motor Grader > 100 HP Kap 10.800 661,489.75 /Jam
14 Track Loader 75 - 100 HP Kap 0,8 m3 385,368.58 /Jam
15 Wheel loader 1.0 - 1.6 m3 Kap 1.5 m3 456,429.16 /Jam
16 Three Wheel Roller 6 - 8 T Kap 8.0 T 197,748.91 /Jam
17 Tandem Roller 6 - 8 T Kap 8.0 T 277,852.88 /Jam
18 Tire Roller 8 - 10 T Kap 9.0 T 347,725.99 /Jam
19 Vibratory Roller 5 - 8 T Kap 7.0 T 340,223.69 /Jam
20 Concreate Vibrator Kap 25 38,681.06 /Jam
21 Stone Crusher Kap 50 T/jam 851,869.19 /Jam
22 Water pump 70 - 100 mm - 32,764.76 /Jam
23 Water Tanker 3000 - 4500 liter Kap 4.000 liter 246,403.90 /Jam
24 Pedestrian Roller Kap 835 T 57,599.86 /Jam
25 Tamper Kap 121 Ton 36,346.49 /Jam
26 Jack Hammer Kap 1.330 21,793.61 /Jam
27 Fulvi Mixer Kap 2.005 715,386.02 /Jam
28 Concreate Pump Kap 8 m3 243,306.27 /Jam
29 Trailer 20 Ton Kap 20 T 445,807.31 /Jam
30 Pile Driver + Hammer Kap 2.50 T 157,073.17 /Jam
31 Crane on Track 35 Ton Kap 35.0 T 586,513.93 /Jam
32 Welding set Kap 250 Amp 115,064.14 /Jam
33 Bore pile Machine Kap 2.000 meter 931,609.07 /Jam
34 Asphalt Liquid Mixer Kap 1000 liter 30,436.43 /Jam
35 Tronton Kap 15 Ton 384,714.29 /Jam
36 Cold Milling Kap 1000 m 502,718.29 /Jam
37 Rock Drill Breaker - 45,144.29 /Jam
38 Cold Recycler Kap 2.2 M 1,723,914.29 /Jam
39 Hot Recycler Kap 3 M 787,414.29 /Jam
40 Aggregat (Chip) Spreader Kap 3.5 M 303,864.29 /Jam
41 Asphalt Distributor Kap 4.000 liter 253,609.29 /Jam
42 Slip Form Paver Kap 2.5 M 234,879.29 /Jam
43 Concreate Pan Mixer Kap 600 liter 397,293.94 /Jam
44 Concreate Breaker Kap 20 m3/jam 581,384.29 /Jam
45 Asphalt Tanker Kap 4000 liter 418,541.43 /Jam
46 Cement tanker Kap 4000 liter 376,941.43 /Jam
47 Concreate Mixer (350) Kap 350 liter 89,635.28 /Jam
48 Vibrating Hammer Kap 80 Kg 30,773.43 /Jam
49 Truck Mixert (agitator) Kap 5 m3 551,671.07 /Jam
50 Bore pile Machine Kap 60 cm 309,821.42 /Jam
51 Crane on Track 75 - 100 Ton Kap 75 Ton 395,671.43 /Jam
52 Blending Equipment Kap 30 Ton 136,571.43 /Jam
53 Asphalt Liquid Mixer Kap 2000 liter 95,991.43 /Jam
54 Pompa Penakar - 33,994.35 /Jam
55 Chainshow - 25,712.35 /Jam
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

I. PEKERJAAN : PERSIAPAN

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Pengukuran Lapangan
Satuan Pembayaran : M2
Harga Satuan : Rp 8,593.20
AHSP-I-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pembantu Surveyor OH 0.0100 Rp 95,000.00 Rp 950.00
Surveyor OH 0.0100 Rp 150,000.00 Rp 1,500.00

Sub-Total ( 1 ) Rp 2,450.00

2 Bahan
Kayu/balok Gergajian kelas III m3 0.0012 Rp 3,635,500.00 Rp 4,362.60
Paku kg 0.0020 Rp 15,300.00 Rp 30.60

Sub-Total ( 2 ) Rp 4,393.20

3 Peralatan
Sewa Alat Ukur jam 0.0050 Rp 350,000.00 Rp 1,750.00

Sub-Total ( 3 ) Rp 1,750.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 8,593.20

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Pembersihan Lapangan
Satuan Pembayaran : M2
Harga Satuan : Rp 8,100.00
AHSP-I-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 8,100.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 8,100.00

Analisa Harga Satuan Pekerjaan - 14


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Papan Nama Proyek, uk. 80 x 120 cm
Satuan Pembayaran : Unit
Harga Satuan : Rp 781,347.39
AHSP-I-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Tukang Kayu OH 1.0000 Rp 100,000.00 Rp 100,000.00
Tukang Batu OH 0.0180 Rp 90,000.00 Rp 1,620.00
Tukang Cat OH 1.0000 Rp 90,000.00 Rp 90,000.00
Pekerja OH 2.1000 Rp 70,000.00 Rp 147,000.00
Mandor OH 1.0050 Rp 110,000.00 Rp 110,550.00

Sub-Total ( 1 ) Rp 449,170.00

2 Bahan
Kayu Meranti m³ 0.0350 Rp 4,601,234.00 Rp 161,043.19
Seng plate lebar 90 cm m' 1.4000 Rp 40,000.00 Rp 56,000.00
Paku kg 0.6000 Rp 16,420.00 Rp 9,852.00
Cat kayu kg 1.5000 Rp 45,000.00 Rp 67,500.00
Semen portland kg 16.8000 Rp 1,471.00 Rp 24,712.80
Pasir beton m³ 0.0270 Rp 192,800.00 Rp 5,205.60
Batu pecah/split 2/3 m³ 0.0410 Rp 191,800.00 Rp 7,863.80

Sub-Total ( 2 ) Rp 332,177.39

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 781,347.39

Analisa Harga Satuan Pekerjaan - 15


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Bangunan Direksi Keet
Satuan Pembayaran : M2
Harga Satuan : Rp 660,310.05
AHSP-I-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Kep. Tukang Kayu OH 0.3000 Rp 100,000.00 Rp 30,000.00
Tukang Kayu OH 1.0000 Rp 100,000.00 Rp 100,000.00
Tukang Batu OH 1.0000 Rp 90,000.00 Rp 90,000.00
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 295,500.00

2 Bahan
Kayu dolken Ø 8-10/400 cm btg 1.2500 Rp 30,000.00 Rp 37,500.00
Kayu Gergajian Kelas III m³ 0.0210 Rp 3,635,500.00 Rp 76,345.50
Paku biasa 2"-5" kg 0.8500 Rp 15,300.00 Rp 13,005.00
Besi pelat strip kg 1.1000 Rp 9,250.00 Rp 10,175.00
Semen portland kg 35.0000 Rp 1,471.00 Rp 51,485.00
Pasir pasang m³ 0.2500 Rp 183,700.00 Rp 45,925.00
Batu pecah/split 2/3 m³ 0.1500 Rp 191,800.00 Rp 28,770.00
Bata merah bh 30.0000 Rp 650.00 Rp 19,500.00
Asbes gelombang uk. 2,40x1,05 (m) t 4 mm Lbr 0.2500 Rp 90,000.00 Rp 22,500.00
Jendela nako (rangka) m2 0.0800 Rp 125,000.00 Rp 10,000.00
Kunci tanam sederhana bh 0.1500 Rp 80,000.00 Rp 12,000.00
Triplek tebal 4 mm uk. 1.22 x 2.44 (m) lbr 0.0800 Rp 55,500.00 Rp 4,440.00

Sub-Total ( 2 ) Rp 331,645.50

3 Peralatan
Alat Bantu Ls 1.0000 Rp 33,164.55 Rp 33,164.55

Sub-Total ( 3 ) Rp 33,164.55

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 660,310.05

Analisa Harga Satuan Pekerjaan - 16


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Gudang Semen & Peralatan
Satuan Pembayaran : M2
Harga Satuan : Rp 627,136.70
AHSP-I-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Kep. Tukang Kayu OH 0.3000 Rp 100,000.00 Rp 30,000.00
Tukang Kayu OH 2.0000 Rp 100,000.00 Rp 200,000.00
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 305,500.00

2 Bahan
Kayu dolken Ø 8-10/400 cm btg 1.2500 Rp 30,000.00 Rp 37,500.00
Kayu Gergajian Kelas III m³ 0.0210 Rp 3,635,500.00 Rp 76,345.50
Paku biasa 2"-5" kg 0.8500 Rp 15,300.00 Rp 13,005.00
Semen portland kg 10.5000 Rp 1,471.00 Rp 15,445.50
Pasir Pasang m³ 0.0300 Rp 183,700.00 Rp 5,511.00
Batu pecah/split 2/3 m³ 0.0500 Rp 191,800.00 Rp 9,590.00
Asbes gelombang uk. 2,40x1,05 (m) t 4 mm Lbr 1.5000 Rp 90,000.00 Rp 135,000.00

Sub-Total ( 2 ) Rp 292,397.00

3 Peralatan
Alat Bantu Ls 1.0000 Rp 29,239.70 Rp 29,239.70

Sub-Total ( 3 ) Rp 29,239.70

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 627,136.70

Analisa Harga Satuan Pekerjaan - 17


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Pagar Pengaman Proyek
Satuan Pembayaran : M'
Harga Satuan : Rp 223,549.70
AHSP-I-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Tukang kayu OH 0.2000 Rp 100,000.00 Rp 20,000.00
Pekerja OH 0.4000 Rp 70,000.00 Rp 28,000.00
Kepala tukang OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0200 Rp 110,000.00 Rp 2,200.00

Sub-Total ( 1 ) Rp 52,200.00

2 Bahan
Kayu dolken Ø 8-10/400 cm btg 1.2500 Rp 30,000.00 Rp 37,500.00
Semen portland kg 2.5000 Rp 1,471.00 Rp 3,677.50
Pasir Beton m³ 0.0050 Rp 192,800.00 Rp 964.00
Batu pecah/split 2/3 m³ 0.0090 Rp 191,800.00 Rp 1,726.20
Kayu Gergajian Kelas III m³ 0.0180 Rp 3,635,500.00 Rp 65,439.00
Paku biasa 2"-5" kg 0.0600 Rp 15,300.00 Rp 918.00
Seng gelombang 180 x 90 x 0.03 Lbr 1.2000 Rp 30,000.00 Rp 36,000.00
Cat meni besi kg 0.4500 Rp 22,500.00 Rp 10,125.00
Kuas bh 1.0000 Rp 15,000.00 Rp 15,000.00

Sub-Total ( 2 ) Rp 171,349.70

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 223,549.70

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Pengukuran dan Pemasangan Bowplank
Satuan Pembayaran : M2
Harga Satuan : Rp 102,367.04
AHSP-I-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Kep. Tukang Kayu OH 0.0100 Rp 100,000.00 Rp 1,000.00
Tukang Kayu OH 0.1000 Rp 100,000.00 Rp 10,000.00
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00
Sub-Total ( 1 ) Rp 18,550.00
2 Bahan
Kayu Meranti kasau m³ 0.0120 Rp 4,275,200.00 Rp 51,302.40
Kayu Meranti papan 3/20 m³ 0.0070 Rp 4,601,234.00 Rp 32,208.64
Paku kg 0.0200 Rp 15,300.00 Rp 306.00
Sub-Total ( 2 ) Rp 83,817.04
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 102,367.04

Analisa Harga Satuan Pekerjaan - 18


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Listrik Kerja (Sewa Genset)
Satuan Pembayaran : Bulan
Harga Satuan : Rp 22,366,292.80
AHSP-I-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Operator Genset OH 30.0000 Rp 150,000.00 Rp 4,500,000.00
Pembantu Operator OH 30.0000 Rp 95,000.00 Rp 2,850,000.00

Sub-Total ( 1 ) Rp 7,350,000.00

2 Bahan
Solar ltr/bln 300.0000 Rp 10,800.00 Rp 3,240,000.00
Pelumas ltr/bln 10.0000 Rp 25,000.00 Rp 250,000.00

Sub-Total ( 2 ) Rp 3,490,000.00

3 Peralatan
Sewa Generator set Jam 210.0000 Rp 54,887.11 Rp 11,526,292.80

Sub-Total ( 3 ) Rp 11,526,292.80

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 22,366,292.80

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Listrik Kerja (Penyambungan sementara PLN)
Satuan Pembayaran : Bulan
Harga Satuan : Rp 11,400,000.00
AHSP-I-08A
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Penyambungan daya sementara PLN 3.300 VA OH 3,300.00 Rp 1,500.00 Rp 4,950,000.00

Sub-Total ( 1 ) Rp 4,950,000.00

2 Bahan
Pemasangan instalasi titik lampu, berikut lampunya titik 8.00 Rp 375,000.00 Rp 3,000,000.00
Pemasangan instalasi titik stop kontak tenaga 500 watt titik 4.00 Rp 375,000.00 Rp 1,500,000.00
Pemasangan instalasi titik stop kontak tenaga 1000 watt titik 2.00 Rp 375,000.00 Rp 750,000.00
Pemasangan Bok MCB 3 group unit 1.00 Rp 250,000.00 Rp 250,000.00
- Pas. MCB 3 phase 16A bh 1.00 Rp 350,000.00 Rp 350,000.00
- Pas. MCB 1 phase 16A bh 3.00 Rp 200,000.00 Rp 600,000.00

Sub-Total ( 2 ) Rp 6,450,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 11,400,000.00

Analisa Harga Satuan Pekerjaan - 19


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Air Kerja
Satuan Pembayaran : Lot
Harga Satuan : Rp 11,892,000.00
AHSP-I-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.40 Rp 70,000.00 Rp 28,000.00
Tukang pasang pipa OH 0.70 Rp 90,000.00 Rp 63,000.00
Kepala tukang OH 0.75 Rp 100,000.00 Rp 75,000.00
Mandor OH 0.50 Rp 110,000.00 Rp 55,000.00

Sub-Total ( 1 ) Rp 221,000.00

2 Bahan
Pantek sumur unit 1.00 Rp 4,500,000.00 Rp 4,500,000.00
Pompa air (jet pump) unit 1.00 Rp 3,000,000.00 Rp 3,000,000.00
Pipa PVC dia.1 1/4" m' 20.00 Rp 15,000.00 Rp 300,000.00
Pipa GIP dia.1 1/4" m' 2.00 Rp 47,500.00 Rp 95,000.00
Sock draad dalam besi 1 1/4" bh 1.00 Rp 8,000.00 Rp 8,000.00
Sock draad luar PVC 1 1/4" bh 1.00 Rp 7,000.00 Rp 7,000.00
Tangki air 1000 liter bh 2.00 Rp 1,350,000.00 Rp 2,700,000.00

Sub-Total ( 2 ) Rp 10,610,000.00

3 Peralatan
Alat Bantu Ls 1.0000 Rp 1,061,000.00 Rp 1,061,000.00

Sub-Total ( 3 ) Rp 1,061,000.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 11,892,000.00

Analisa Harga Satuan Pekerjaan - 20


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PERSIAPAN
Jenis Pembayaran : Biaya Pengurusan IMB
Satuan Pembayaran : Bulan
Harga Satuan : Rp 80,181,320.96
AHSP-I-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Koefisien berdasarkan Nomor : 09 Tahun 2003


Koefisien Hiraki Kota 0.45
Koefisien Kelas Jalan 1.00
Koefisien Guna Bangunan 0.60
Koefisien Kelas Bangunan 1.00
Koefisien Status Bangunan 1.00
Koefisien Luas Bangunan 1.75
Koefisien Tingkat Bangunan 0.50
Jumlah Koefisien 6.30
Standart Harga Bangunan = Rp. 1.773.600,--
Harga Bangunan
Bangunan Gedung (berdasarkan luas bangunan) m2 3136.00 Rp 1,773,600.00 Rp 5,562,009,600.00

Sub-Total ( 1 ) Rp 5,562,009,600.00

2 Biaya Ijin Bangunan


Biaya Ijin Mendirikan Bangunan 0.20% 6.30 Rp 5,562,009,600.00 Rp 70,081,320.96
(0,20% x Koefisien Bangunan x Harga Bangunan)
Biaya Sempadan Bangunan ls 1.00 Rp 10,000,000.00 Rp 10,000,000.00
Biaya Administrasi ls 1.00 Rp 100,000.00 Rp 100,000.00

Sub-Total ( 2 ) Rp 80,181,320.96

T O T A L (2) Rp 80,181,320.96
HARGA SATUAN PEKERJAAN Rp 80,181,320.96

Analisa Harga Satuan Pekerjaan - 21


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

II. PEKERJAAN : TANAH

Pekerjaan : TANAH
Jenis Pembayaran : Pengupasan Lapisan Atas/ Scraping
Satuan Pembayaran : M2
Harga Satuan : Rp 18,820.00
AHSP-II-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2500 Rp 70,000.00 Rp 17,500.00
Mandor OH 0.0120 Rp 110,000.00 Rp 1,320.00

Sub-Total ( 1 ) Rp 18,820.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 18,820.00

Pekerjaan : TANAH
Jenis Pembayaran : Galian Tanah Biasa sedalam 1 m
Satuan Pembayaran : M3
Harga Satuan : Rp 55,250.00 SNI 2835, 6.1 - 2008
AHSP-II-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7500 Rp 70,000.00 Rp 52,500.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00

Sub-Total ( 1 ) Rp 55,250.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 55,250.00

Analisa Harga Satuan Pekerjaan - 22


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH
Jenis Pembayaran : Galian Tanah Biasa sedalam 2 m
Satuan Pembayaran : M3
Harga Satuan : Rp 67,950.00 SNI 2835, 6.2 - 2008
AHSP-II-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.9000 Rp 70,000.00 Rp 63,000.00
Mandor OH 0.0450 Rp 110,000.00 Rp 4,950.00

Sub-Total ( 1 ) Rp 67,950.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 67,950.00

Pekerjaan : TANAH
Jenis Pembayaran : Galian Tanah Keras, sedalam 1 m
Satuan Pembayaran : M3
Harga Satuan : Rp 73,520.00 SNI 2835, 6.4 - 2008
AHSP-II-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Mandor OH 0.0320 Rp 110,000.00 Rp 3,520.00

Sub-Total ( 1 ) Rp 73,520.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 73,520.00

Analisa Harga Satuan Pekerjaan - 23


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH
Jenis Pembayaran : Galian Tanah Cadas, sedalam 2 m
Satuan Pembayaran : M3
Harga Satuan : Rp 111,600.00
AHSP-II-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.5000 Rp 70,000.00 Rp 105,000.00
Mandor OH 0.0600 Rp 110,000.00 Rp 6,600.00

Sub-Total ( 1 ) Rp 111,600.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 111,600.00

Pekerjaan : TANAH
Jenis Pembayaran : Galian tanah dengan excavator (CUT)
Satuan Pembayaran : M3
Harga Satuan : Rp 90,427.50
AHSP-II-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3615 Rp 70,000.00 Rp 25,305.00
Mandor OH 0.0602 Rp 110,000.00 Rp 6,622.00

Sub-Total ( 1 ) Rp 31,927.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan
Excavator jam 0.0602 Rp 531,286.87 Rp 32,005.23
Dump Truck 3 - 5 ton jam 0.0971 Rp 272,765.92 Rp 26,495.26

Sub-Total ( 3 ) Rp 58,500.50

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 90,427.50

Analisa Harga Satuan Pekerjaan - 24


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH
Jenis Pembayaran : Urugan tanah dari sumber lokasi (FILL)
Satuan Pembayaran : M3
Harga Satuan : Rp 102,660.00
AHSP-II-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan
Wheel Loader jam 0.0178 Rp 456,429.16 Rp 8,124.44
Dump Truck 3 - 5 ton jam 0.2289 Rp 272,765.92 Rp 62,436.12
Motor Grader jam 0.0068 Rp 661,489.75 Rp 4,498.13
Vibro Roller jam 0.0111 Rp 340,223.69 Rp 3,776.48
Water Tanker jam 0.0070 Rp 246,403.90 Rp 1,724.83

Sub-Total ( 3 ) Rp 80,560.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 102,660.00

Pekerjaan : TANAH
Jenis Pembayaran : Urugan tanah dari sumber lain lokasi (didatangkan)
Satuan Pembayaran : M3
Harga Satuan : Rp 191,980.00
AHSP-II-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan
Urugan tanah biasa m3 1.1000 Rp 81,200.00 Rp 89,320.00

Sub-Total ( 2 ) Rp 89,320.00

3 Peralatan
Wheel Loader jam 0.0178 Rp 456,429.16 Rp 8,124.44
Dump Truck 3 - 5 ton jam 0.2289 Rp 272,765.92 Rp 62,436.12
Motor Grader jam 0.0068 Rp 661,489.75 Rp 4,498.13
Vibro Roller jam 0.0111 Rp 340,223.69 Rp 3,776.48
Water Tanker jam 0.0070 Rp 246,403.90 Rp 1,724.83

Sub-Total ( 3 ) Rp 80,560.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 191,980.00

Analisa Harga Satuan Pekerjaan - 25


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH
Jenis Pembayaran : Urugan tanah kembali
Satuan Pembayaran : M3
Harga Satuan : Rp 22,100.00
AHSP-II-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 22,100.00

Pekerjaan : TANAH
Jenis Pembayaran : Penyiapan Badan Jalan
Satuan Pembayaran : M2
Harga Satuan : Rp 5,647.35
AHSP-II-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0111 Rp 70,000.00 Rp 777.00
Mandor OH 0.0028 Rp 110,000.00 Rp 308.00

Sub-Total ( 1 ) Rp 1,085.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan
Motor Grader jam 0.0028 Rp 661,489.75 Rp 1,837.47
Vibro Roller jam 0.0044 Rp 340,223.69 Rp 1,496.98
Water Tanker jam 0.0033 Rp 246,403.90 Rp 813.13
Alat Bantu Ls 1.0000 Rp 414.76 Rp 414.76

Sub-Total ( 3 ) Rp 4,562.35

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 5,647.35

Analisa Harga Satuan Pekerjaan - 26


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH
Jenis Pembayaran : Pemadatan Tanah dengan alat Berat
Satuan Pembayaran : M2
Harga Satuan : Rp 31,716.39
AHSP-II-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0357 Rp 70,000.00 Rp 2,499.00
Mandor OH 0.0031 Rp 110,000.00 Rp 341.00

Sub-Total ( 1 ) Rp 2,840.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan
Wheel Loader jam 0.0356 Rp 456,429.16 Rp 16,248.88
Vibro Roller jam 0.0222 Rp 340,223.69 Rp 7,552.97
Water Tanker jam 0.0140 Rp 246,403.90 Rp 3,449.65
Alat Bantu Ls 1.0000 Rp 1,624.89 Rp 1,624.89

Sub-Total ( 3 ) Rp 28,876.39

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 31,716.39

Pekerjaan : TANAH
Jenis Pembayaran : Pemadatan Tanah dengan Stamper
Satuan Pembayaran : M2
Harga Satuan : Rp 22,290.18
AHSP-II-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2499 Rp 70,000.00 Rp 17,493.00
Mandor OH 0.0217 Rp 110,000.00 Rp 2,387.00

Sub-Total ( 1 ) Rp 19,880.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan
Stamper jam 0.0712 Rp 30,773.43 Rp 2,191.07
Alat Bantu Ls 1.0000 Rp 219.11 Rp 219.11

Sub-Total ( 3 ) Rp 2,410.18

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 22,290.18

Analisa Harga Satuan Pekerjaan - 27


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH
Jenis Pembayaran : Limestone 30 cm
Satuan Pembayaran : M3
Harga Satuan : Rp 113,122.25
AHSP-II-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan
Lime stone m3 0.3630 Rp 250,750.00 Rp 91,022.25

Sub-Total ( 2 ) Rp 91,022.25

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 113,122.25

Pekerjaan : TANAH & PASIR


Jenis Pembayaran : Urugan Pasir Urug
Satuan Pembayaran : M3
Harga Satuan : Rp 183,980.00 SNI 2835, 6.11 - 2008
AHSP-II-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan
Pasir Urug m³ 1.2000 Rp 134,900.00 Rp 161,880.00

Sub-Total ( 2 ) Rp 161,880.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 183,980.00

Analisa Harga Satuan Pekerjaan - 28


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH & PASIR


Jenis Pembayaran : Urugan Sirtu 15 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 52,052.00
AHSP-II-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan
Sirtu m3 0.1800 Rp 166,400.00 Rp 29,952.00

Sub-Total ( 2 ) Rp 29,952.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 52,052.00

Pekerjaan : TANAH & PASIR


Jenis Pembayaran : Urugan Sirtu padat
Satuan Pembayaran : M3
Harga Satuan : Rp 226,781.89 SNI 2835 (6.15) - 2008
AHSP-II-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2500 Rp 70,000.00 Rp 17,500.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00

Sub-Total ( 1 ) Rp 20,250.00

2 Bahan
Sirtu m3 1.2000 Rp 166,400.00 Rp 199,680.00

Sub-Total ( 2 ) Rp 199,680.00

3 Peralatan
Sewa Vibratory Roller (pemadatan) jam 0.0100 Rp 340,223.69 Rp 3,402.24
Sewa Watertank hari 0.0020 Rp 1,724,827.30 Rp 3,449.65

Sub-Total ( 3 ) Rp 6,851.89

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 226,781.89

Analisa Harga Satuan Pekerjaan - 29


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TANAH & PASIR


Jenis Pembayaran : Urugan Pasir Extra Beton
Satuan Pembayaran : M3
Harga Satuan : Rp 253,460.00 SNI 2835 (6.11) - 2008
AHSP-II-017
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan
Pasir Extra Beton m³ 1.2000 Rp 192,800.00 Rp 231,360.00

Sub-Total ( 2 ) Rp 231,360.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 253,460.00

Pekerjaan : PENGERASAN JALAN


Jenis Pembayaran : Lapisan batu pecah split 2-3 cm tebal 10 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 47,628.58
AHSP-II-018
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 22,100.00

2 Bahan
Batu Pecah 2-3 cm m3 0.1331 Rp 191,800.00 Rp 25,528.58

Sub-Total ( 2 ) Rp 25,528.58

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 47,628.58

Analisa Harga Satuan Pekerjaan - 30


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PENGERASAN JALAN


Jenis Pembayaran : Lapisan Teak Coating
Satuan Pembayaran : M2
Harga Satuan : Rp 17,457.16
AHSP-II-019
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.0301 Rp 70,000.00 Rp 2,107.00
Mandor OH 0.0063 Rp 110,000.00 Rp 693.00

Sub-Total ( 1 ) Rp 2,800.00
2 Bahan
Aspal Polimer Lokal kg 0.8880 Rp 11,900.00 Rp 10,567.20
Minyak Tanah Ltr 0.2530 Rp 9,800.00 Rp 2,479.40

Sub-Total ( 2 ) Rp 13,046.60
3 Peralatan
Asphalt sprayer jam 0.0030 Rp 69,660.86 Rp 208.98
Air Compressor jam 0.0063 Rp 179,864.85 Rp 1,133.15
Alat Bantu Ls 1.0000 Rp 268.43 Rp 268.43

Sub-Total ( 3 ) Rp 1,610.56

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 17,457.16

Pekerjaan : PENGERASAN JALAN


Jenis Pembayaran : Finishing Asphal Hotmix
Satuan Pembayaran : M2
Harga Satuan : Rp 168,776.73
AHSP-II-020
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.2268 Rp 70,000.00 Rp 15,876.00
Mandor OH 0.0147 Rp 110,000.00 Rp 1,617.00

Sub-Total ( 1 ) Rp 17,493.00

2 Bahan
Batu pecah/split 2-3 m³ 0.0421 Rp 191,800.00 Rp 8,074.78
Abu batu m³ 0.0186 Rp 231,084.00 Rp 4,298.16
Filler untuk hotmix (semen) kg 6.0019 Rp 1,471.00 Rp 8,828.79
Aspal Polimer Lokal kg 8.2688 Rp 11,900.00 Rp 98,398.72

Sub-Total ( 2 ) Rp 119,600.46
3 Peralatan
Wheel Loader jam 0.0011 Rp 456,429.16 Rp 502.07
Asphalt Mixing Plant jam 0.0022 Rp 7,015,788.77 Rp 15,434.74
Genset jam 0.0022 Rp 384,209.76 Rp 845.26
Dump Truck 10 ton jam 0.0160 Rp 494,897.70 Rp 7,918.36
Asphalt Finisher jam 0.0027 Rp 373,027.34 Rp 1,007.17
Tandem Roller jam 0.0010 Rp 277,852.88 Rp 277.85
Pheneumatic Tire Roller jam 0.0012 Rp 347,725.99 Rp 417.27
Alat Bantu jam 1.0000 Rp 5,280.55 Rp 5,280.55

Sub-Total ( 3 ) Rp 31,683.28

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 168,776.73

Analisa Harga Satuan Pekerjaan - 31


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PENGERASAN JALAN


Jenis Pembayaran : Pas. Paving Block 6 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 127,360.00
AHSP-II-021
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2500 Rp 70,000.00 Rp 17,500.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0010 Rp 110,000.00 Rp 110.00

Sub-Total ( 1 ) Rp 27,610.00

2 Bahan
Paving Block tebal 6 cm (abu-abu) M2 1.0500 Rp 95,000.00 Rp 99,750.00

Sub-Total ( 2 ) Rp 99,750.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 127,360.00

Pekerjaan : PENGERASAN JALAN


Jenis Pembayaran : Pas. Kansteen beton
Satuan Pembayaran : M'
Harga Satuan : Rp 130,610.00
AHSP-II-022
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0010 Rp 110,000.00 Rp 110.00

Sub-Total ( 1 ) Rp 35,610.00

2 Bahan
Kansteen beton 15x30x40 cm Bh 2.5000 Rp 38,000.00 Rp 95,000.00

Sub-Total ( 2 ) Rp 95,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 130,610.00

Analisa Harga Satuan Pekerjaan - 32


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : TAMAN
Jenis Pembayaran : Tanaman Rumput
Satuan Pembayaran : M2
Harga Satuan : Rp 34,700.00
AHSP-II-023
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Mandor OH 0.0200 Rp 110,000.00 Rp 2,200.00

Sub-Total ( 1 ) Rp 16,200.00

2 Bahan
Rumput Gajahan M2 1.1000 Rp 15,000.00 Rp 16,500.00
Rabuk Kg 0.1000 Rp 20,000.00 Rp 2,000.00

Sub-Total ( 2 ) Rp 18,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 34,700.00

Pekerjaan : TAMAN
Jenis Pembayaran : Pohon Peneduh
Satuan Pembayaran : Pohon
Harga Satuan : Rp 131,200.00
AHSP-II-024
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Mandor OH 0.0200 Rp 110,000.00 Rp 2,200.00

Sub-Total ( 1 ) Rp 16,200.00

2 Bahan
Pohon Peneduh, tinggi 2 - 2,5 m phn 1.0000 Rp 75,000.00 Rp 75,000.00
Rabuk Kg 2.0000 Rp 20,000.00 Rp 40,000.00

Sub-Total ( 2 ) Rp 115,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 131,200.00

Analisa Harga Satuan Pekerjaan - 33


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

III. PEKEERJAAN : BETON

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Besi Ulir
Satuan Pembayaran : Kg
Harga Satuan : Rp 9,904.33 SNI 7394 (6.17) - 2008
AHSP-III-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0070 Rp 70,000.00 Rp 490.00
Tukang besi OH 0.0070 Rp 90,000.00 Rp 630.00
Kepala tukang OH 0.0007 Rp 100,000.00 Rp 70.00
Mandor OH 0.0004 Rp 110,000.00 Rp 44.00

Sub-Total ( 1 ) Rp 1,234.00

2 Bahan
Besi beton ulir kg 1.0500 Rp 8,000.00 Rp 8,400.00
Kawat beton kg 0.0150 Rp 18,022.00 Rp 270.33

Sub-Total ( 2 ) Rp 8,670.33

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 9,904.33

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Besi Polos
Satuan Pembayaran : Kg
Harga Satuan : Rp 9,814.22 SNI 7394 (6.18) - 2008
AHSP-III-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0070 Rp 70,000.00 Rp 490.00
Tukang besi OH 0.0070 Rp 90,000.00 Rp 630.00
Kepala tukang OH 0.0007 Rp 100,000.00 Rp 70.00
Mandor OH 0.0004 Rp 110,000.00 Rp 44.00

Sub-Total ( 1 ) Rp 1,234.00

2 Bahan
Besi beton polos kg 1.0500 Rp 8,000.00 Rp 8,400.00
Kawat beton kg 0.0100 Rp 18,022.00 Rp 180.22

Sub-Total ( 2 ) Rp 8,580.22

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 9,814.22

Analisa Harga Satuan Pekerjaan - 34


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Ready Mix K-250
Satuan Pembayaran : M3
Harga Satuan : Rp 1,393,380.00
AHSP-III-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.6500 Rp 70,000.00 Rp 115,500.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Kepala tukang OH 0.0280 Rp 100,000.00 Rp 2,800.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00

Sub-Total ( 1 ) Rp 152,180.00

2 Bahan
Beton Ready Mix K-250 M3 1.1000 Rp 856,750.00 Rp 942,425.00

Sub-Total ( 2 ) Rp 942,425.00

3 Peralatan
Sewa Mobil Mixer OH 0.1611 Rp 250,000.00 Rp 40,275.00
Sewa Concrete Pump OH 0.0780 Rp 3,000,000.00 Rp 234,000.00
Sewa Concrete Vibrator OH 0.0700 Rp 350,000.00 Rp 24,500.00

Sub-Total ( 3 ) Rp 298,775.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,393,380.00

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Ready Mix K-275
Satuan Pembayaran : M3
Harga Satuan : Rp 1,431,330.00
AHSP-III-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.6500 Rp 70,000.00 Rp 115,500.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Kepala tukang OH 0.0280 Rp 100,000.00 Rp 2,800.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00

Sub-Total ( 1 ) Rp 152,180.00

2 Bahan
Beton Ready Mix K-275 M3 1.1000 Rp 891,250.00 Rp 980,375.00

Sub-Total ( 2 ) Rp 980,375.00

3 Peralatan
Sewa Mobil Mixer OH 0.1611 Rp 250,000.00 Rp 40,275.00
Sewa Concrete Pump OH 0.0780 Rp 3,000,000.00 Rp 234,000.00
Sewa Concrete Vibrator OH 0.0700 Rp 350,000.00 Rp 24,500.00

Sub-Total ( 3 ) Rp 298,775.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,431,330.00

Analisa Harga Satuan Pekerjaan - 35


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Ready Mix K-300
Satuan Pembayaran : M3
Harga Satuan : Rp 1,481,930.00
AHSP-III-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.6500 Rp 70,000.00 Rp 115,500.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Kepala tukang OH 0.0280 Rp 100,000.00 Rp 2,800.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00

Sub-Total ( 1 ) Rp 152,180.00

2 Bahan
Beton Ready Mix K-300 M3 1.1000 Rp 937,250.00 Rp 1,030,975.00

Sub-Total ( 2 ) Rp 1,030,975.00

3 Peralatan
Sewa Mobil Mixer OH 0.1611 Rp 250,000.00 Rp 40,275.00
Sewa Concrete Pump OH 0.0780 Rp 3,000,000.00 Rp 234,000.00
Sewa Concrete Vibrator OH 0.0700 Rp 350,000.00 Rp 24,500.00

Sub-Total ( 3 ) Rp 298,775.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,481,930.00

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Membuat Beton mutu fc = 19.3 Mpa (K-225)
Satuan Pembayaran : M3
Harga Satuan : Rp 905,661.72 SNI 7394 (6.7) - 2008
AHSP-III-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.6500 Rp 70,000.00 Rp 115,500.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Kepala tukang OH 0.0280 Rp 100,000.00 Rp 2,800.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00

Sub-Total ( 1 ) Rp 152,180.00

2 Bahan
Semen PC kg 371.00 Rp 1,471.00 Rp 545,741.00
Pasir beton BD. = 1.6 2000 kg 698.00 Rp 96.40 Rp 67,287.20
Batu pecah/split 2-3 BD. = 1.9 2375 kg 1,047.00 Rp 80.76 Rp 84,553.52
Air ltr 215.00 Rp 260.00 Rp 55,900.00

Sub-Total ( 2 ) Rp 753,481.72

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 905,661.72

Analisa Harga Satuan Pekerjaan - 36


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Membuat Beton mutu fc = 21,7 Mpa (K-250)
Satuan Pembayaran : M3
Harga Satuan : Rp 923,560.25 SNI 7394 (6.8) - 2008
AHSP-III-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.6500 Rp 70,000.00 Rp 115,500.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Kepala tukang OH 0.0280 Rp 100,000.00 Rp 2,800.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00

Sub-Total ( 1 ) Rp 152,180.00

2 Bahan
Semen PC kg 384.00 Rp 1,471.00 Rp 564,864.00
Pasir beton BD. = 1.6 2000 kg 692.00 Rp 96.40 Rp 66,708.80
Batu pecah/split 2-3 BD. = 1.9 2375 kg 1,039.00 Rp 80.76 Rp 83,907.45
Air ltr 215.00 Rp 260.00 Rp 55,900.00

Sub-Total ( 2 ) Rp 771,380.25

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 923,560.25

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Membuat Beton mutu fc = 24 Mpa (K-275)
Satuan Pembayaran : M3
Harga Satuan : Rp 954,101.20 SNI 7394 (6.9) - 2008
AHSP-III-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.6500 Rp 70,000.00 Rp 115,500.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Kepala tukang OH 0.0280 Rp 100,000.00 Rp 2,800.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00

Sub-Total ( 1 ) Rp 152,180.00

2 Bahan
Semen PC kg 406.0000 Rp 1,471.00 Rp 597,226.00
Pasir beton BD. = 1.6 2000 kg 684.00 Rp 96.40 Rp 65,937.60
Batu pecah/split 2-3 BD. = 1.9 2375 kg 1,026.00 Rp 80.76 Rp 82,857.60
Air ltr 215.0000 Rp 260.00 Rp 55,900.00

Sub-Total ( 2 ) Rp 801,921.20

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 954,101.20

Analisa Harga Satuan Pekerjaan - 37


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Membuat Beton mutu fc = 26,4 Mpa (K-300)
Satuan Pembayaran : M3
Harga Satuan : Rp 963,705.21 SNI 7394 (6.10) - 2008
AHSP-III-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.6500 Rp 70,000.00 Rp 115,500.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Kepala tukang OH 0.0280 Rp 100,000.00 Rp 2,800.00
Mandor OH 0.0830 Rp 110,000.00 Rp 9,130.00

Sub-Total ( 1 ) Rp 152,180.00

2 Bahan
Semen PC kg 413.00 Rp 1,471.00 Rp 607,523.00
Pasir beton BD. = 1.6 2000 kg 681.00 Rp 96.40 Rp 65,648.40
Batu pecah/split 2-3 BD. = 1.9 2375 kg 1,021.00 Rp 80.76 Rp 82,453.81
Air ltr 215.00 Rp 260.00 Rp 55,900.00

Sub-Total ( 2 ) Rp 811,525.21

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 963,705.21

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Beton Cyklop, 60 % beton 1 Pc : 2 Psr : 3 Krl dan 40% batu belah
Satuan Pembayaran : M3
Harga Satuan : Rp 1,899,269.60 SNI 2836 (6.10) - 2008
AHSP-III-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Kep. Tukang Batu OH 0.0850 Rp 100,000.00 Rp 8,500.00
Tukang Batu OH 0.8500 Rp 90,000.00 Rp 76,500.00
Pekerja OH 3.4000 Rp 70,000.00 Rp 238,000.00
Mandor OH 0.1700 Rp 110,000.00 Rp 18,700.00

Sub-Total ( 1 ) Rp 341,700.00

2 Bahan
Semen PC kg 194.0000 Rp 1,471.00 Rp 285,374.00
Pasir beton M3 0.3120 Rp 192,800.00 Rp 60,153.60
Batu pecah/split 2-3 M3 0.4680 Rp 191,800.00 Rp 89,762.40
Batu belah M3 0.4800 Rp 170,500.00 Rp 81,840.00
Besi beton kg 126.0000 Rp 8,000.00 Rp 1,008,000.00
Kawat beton kg 1.8000 Rp 18,022.00 Rp 32,439.60

Sub-Total ( 2 ) Rp 1,557,569.60
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,899,269.60

Analisa Harga Satuan Pekerjaan - 38


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Lantai Kerja, mutu beton fc = 7,4 Mpa (K-100)
Satuan Pembayaran : M3
Harga Satuan : Rp 669,953.56 SNI 7394 (6.4) - 2008
AHSP-III-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.2000 Rp 70,000.00 Rp 84,000.00
Tukang batu OH 0.2000 Rp 90,000.00 Rp 18,000.00
Kepala tukang OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0600 Rp 110,000.00 Rp 6,600.00

Sub-Total ( 1 ) Rp 110,600.00

2 Bahan
Semen portland kg 230.0000 Rp 1,471.00 Rp 338,330.00
Pasir beton BD. = 1.6 2000 kg 893.00 Rp 96.40 Rp 86,085.20
Batu pecah/split 2/3 BD. = 1.9 2375 kg 1,027.00 Rp 80.76 Rp 82,938.36
Air ltr 200.0000 Rp 260.00 Rp 52,000.00

Sub-Total ( 2 ) Rp 559,353.56

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 669,953.56

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Kolom Praktis (11 x 11 cm)
Satuan Pembayaran : M'
Harga Satuan : Rp 58,520.99
AHSP-III-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1800 Rp 70,000.00 Rp 12,600.00
Tukang batu OH 0.0200 Rp 90,000.00 Rp 1,800.00
Tukang kayu OH 0.0200 Rp 100,000.00 Rp 2,000.00
Tukang besi OH 0.0200 Rp 90,000.00 Rp 1,800.00
Kepala Tukang batu OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0090 Rp 110,000.00 Rp 990.00
Sub-Total ( 1 ) Rp 19,790.00

2 Bahan
Semen PC kg 4.0000 Rp 1,471.00 Rp 5,884.00
Pasir beton m3 0.0060 Rp 192,800.00 Rp 1,156.80
Kerikil / split (2-3 cm) m3 0.0090 Rp 191,800.00 Rp 1,726.20
Kayu kelas III (kayu papan Terentang) M3 0.0020 Rp 2,500,000.00 Rp 5,000.00
Paku 5-12 cm Kg 0.0100 Rp 15,300.00 Rp 153.00
Besi beton polos Kg 3.0000 Rp 8,000.00 Rp 24,000.00
Kawat beton Kg 0.0450 Rp 18,022.00 Rp 810.99
Sub-Total ( 2 ) Rp 38,730.99

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 58,520.99

Analisa Harga Satuan Pekerjaan - 39


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Ring Balok Praktis (11 x 20 cm)
Satuan Pembayaran : M'
Harga Satuan : Rp 82,889.80
AHSP-III-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.2970 Rp 70,000.00 Rp 20,790.00
Tukang batu OH 0.0330 Rp 90,000.00 Rp 2,970.00
Tukang kayu OH 0.0330 Rp 100,000.00 Rp 3,300.00
Tukang besi OH 0.0330 Rp 90,000.00 Rp 2,970.00
Kepala Tukang batu OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 32,680.00
2 Bahan
Semen PC kg 5.5000 Rp 1,471.00 Rp 8,090.50
Pasir beton m3 0.0090 Rp 192,800.00 Rp 1,735.20
Kerikil / split (2-3 cm) m3 0.0150 Rp 191,800.00 Rp 2,877.00
Kayu kelas III (kayu papan Terentang) M3 0.0030 Rp 2,500,000.00 Rp 7,500.00
Paku 5-12 cm Kg 0.0200 Rp 15,300.00 Rp 306.00
Besi beton polos Kg 3.6000 Rp 8,000.00 Rp 28,800.00
Kawat beton Kg 0.0500 Rp 18,022.00 Rp 901.10

Sub-Total ( 2 ) Rp 50,209.80
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 82,889.80

Analisa Harga Satuan Pekerjaan - 40


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Plat lantai besi 125 kg/m3 + bekesting
Satuan Pembayaran : M3
Harga Satuan : Rp 5,063,360.30
AHSP-III-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 5.3000 Rp 70,000.00 Rp 371,000.00
Tukang batu OH 0.2750 Rp 90,000.00 Rp 24,750.00
Tukang kayu OH 1.3000 Rp 100,000.00 Rp 130,000.00
Tukang besi OH 1.0500 Rp 90,000.00 Rp 94,500.00
Kepala Tukang batu OH 0.2650 Rp 100,000.00 Rp 26,500.00
Mandor OH 0.2650 Rp 110,000.00 Rp 29,150.00

Sub-Total ( 1 ) Rp 675,900.00
2 Bahan
Kayu kelas III (kayu papan Terentang) M3 0.3200 Rp 2,500,000.00 Rp 800,000.00
Paku 5-12 cm Kg 3.2000 Rp 15,300.00 Rp 48,960.00
Minyak bekisting liter 1.6000 Rp 2,478.00 Rp 3,964.80
Besi beton polos Kg 131.2500 Rp 8,000.00 Rp 1,050,000.00
Kawat beton Kg 2.2500 Rp 18,022.00 Rp 40,549.50
Semen PC kg 336.0000 Rp 1,471.00 Rp 494,256.00
Pasir beton m3 0.5400 Rp 192,800.00 Rp 104,112.00
Kerikil / split (2-3 cm) m3 0.8100 Rp 191,800.00 Rp 155,358.00
Kayu kelas III (kayu basah Balok kelas III) M3 0.1200 Rp 3,635,500.00 Rp 436,260.00
Plywood/multiplex 9mm lmbr 2.8000 Rp 105,000.00 Rp 294,000.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m btg 32.0000 Rp 30,000.00 Rp 960,000.00
Sub-Total ( 2 ) Rp 4,387,460.30
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 5,063,360.30

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Bekisting Pondasi
Satuan Pembayaran : M2
Harga Satuan : Rp 120,278.90 SNI 7394 (6.20) - 2008
AHSP-III-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.5200 Rp 70,000.00 Rp 36,400.00
Tukang kayu OH 0.2600 Rp 100,000.00 Rp 26,000.00
Kepala tukang OH 0.0260 Rp 100,000.00 Rp 2,600.00
Mandor OH 0.0260 Rp 110,000.00 Rp 2,860.00

Sub-Total ( 1 ) Rp 67,860.00

2 Bahan
Kayu Terentang papan 3 cm m³ 0.0400 Rp 2,500,000.00 Rp 100,000.00
Paku biasa 2"-5" kg 0.3000 Rp 15,300.00 Rp 4,590.00
Minyak Bekisting lt 0.1000 Rp 2,478.00 Rp 247.80
Sub-Total bahan Rp 104,837.80

Sub-Total ( 2 ) penggunaan material untuk 2 x pakai Rp 52,418.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 120,278.90

Analisa Harga Satuan Pekerjaan - 41


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Bekisting Sloof / Tie Beam
Satuan Pembayaran : M2
Harga Satuan : Rp 126,528.90 SNI 7394 (6.21) - 2008
AHSP-III-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.5200 Rp 70,000.00 Rp 36,400.00
Tukang kayu OH 0.2600 Rp 100,000.00 Rp 26,000.00
Kepala tukang OH 0.0260 Rp 100,000.00 Rp 2,600.00
Mandor OH 0.0260 Rp 110,000.00 Rp 2,860.00

Sub-Total ( 1 ) Rp 67,860.00

2 Bahan
Kayu Terentang papan 3 cm m³ 0.0450 Rp 2,500,000.00 Rp 112,500.00
Paku biasa 2"-5" kg 0.3000 Rp 15,300.00 Rp 4,590.00
Minyak Bekisting lt 0.1000 Rp 2,478.00 Rp 247.80
Sub-Total bahan Rp 117,337.80

Sub-Total ( 2 ) penggunaan material untuk 2 x pakai Rp 58,668.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 126,528.90

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Bekisting Kolom
Satuan Pembayaran : M2
Harga Satuan : Rp 239,972.80 SNI 7394 (6.22) - 2008
AHSP-III-017
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6600 Rp 70,000.00 Rp 46,200.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00

Sub-Total ( 1 ) Rp 86,130.00

2 Bahan
Kayu gergajian kelas III (kasau) m³ 0.0400 Rp 3,635,000.00 Rp 145,400.00
Paku biasa 2"-5" kg 0.4000 Rp 15,300.00 Rp 6,120.00
Minyak bekisting lt 0.2000 Rp 2,478.00 Rp 495.60
Kayu gergajian kelas III (papan) m³ 0.0150 Rp 3,928,000.00 Rp 58,920.00
Plywood/multiplex 9mm lbr 0.3500 Rp 105,000.00 Rp 36,750.00
Kayu dolken Ø 8-10/400 cm btg 2.0000 Rp 30,000.00 Rp 60,000.00
Sub-Total bahan Rp 307,685.60

Sub-Total ( 2 ) penggunaan material untuk 2 x pakai Rp 153,842.80

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 239,972.80

Analisa Harga Satuan Pekerjaan - 42


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Bekisting Balok
Satuan Pembayaran : M2
Harga Satuan : Rp 245,864.80 SNI 7394 (6.23) - 2008
AHSP-III-018
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6600 Rp 70,000.00 Rp 46,200.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00

Sub-Total ( 1 ) Rp 86,130.00

2 Bahan
Kayu gergajian kelas III (kasau) m³ 0.0400 Rp 3,635,000.00 Rp 145,400.00
Paku biasa 2"-5" kg 0.4000 Rp 15,300.00 Rp 6,120.00
Minyak bekisting lt 0.2000 Rp 2,478.00 Rp 495.60
Kayu gergajian kelas III (papan) m³ 0.0180 Rp 3,928,000.00 Rp 70,704.00
Plywood/multiplex 9mm lbr 0.3500 Rp 105,000.00 Rp 36,750.00
Kayu dolken Ø 8-10/400 cm btg 2.0000 Rp 30,000.00 Rp 60,000.00
Sub-Total bahan Rp 319,469.60

Sub-Total ( 2 ) penggunaan material untuk 2 x pakai Rp 159,734.80

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 245,864.80

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Bekisting Plat Lantai
Satuan Pembayaran : M2
Harga Satuan : Rp 299,972.80 SNI 7394 (6.24) - 2008
AHSP-III-019
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6600 Rp 70,000.00 Rp 46,200.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00

Sub-Total ( 1 ) Rp 86,130.00

2 Bahan
Kayu gergajian kelas III (kasau) m³ 0.0400 Rp 3,635,000.00 Rp 145,400.00
Paku biasa 2"-5" kg 0.4000 Rp 15,300.00 Rp 6,120.00
Minyak bekisting lt 0.2000 Rp 2,478.00 Rp 495.60
Kayu gergajian kelas III (papan) m³ 0.0150 Rp 3,928,000.00 Rp 58,920.00
Plywood/multiplex 9mm lbr 0.3500 Rp 105,000.00 Rp 36,750.00
Kayu dolken Ø 8-10/400 cm btg 6.0000 Rp 30,000.00 Rp 180,000.00
Sub-Total bahan Rp 427,685.60

Sub-Total ( 2 ) penggunaan material untuk 2 x pakai Rp 213,842.80

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 299,972.80

Analisa Harga Satuan Pekerjaan - 43


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Bekisting Tangga
Satuan Pembayaran : M2
Harga Satuan : Rp 221,735.85 SNI 7394 (6.26) - 2008
AHSP-III-020
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6600 Rp 70,000.00 Rp 46,200.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00

Sub-Total ( 1 ) Rp 86,130.00

2 Bahan
Kayu gergajian kelas III (kasau) m³ 0.0300 Rp 3,635,000.00 Rp 109,050.00
Paku biasa 2"-5" kg 0.4000 Rp 15,300.00 Rp 6,120.00
Minyak bekisting lt 0.1500 Rp 2,478.00 Rp 371.70
Kayu gergajian kelas III (papan) m³ 0.0150 Rp 3,928,000.00 Rp 58,920.00
Plywood/multiplex 9mm lbr 0.3500 Rp 105,000.00 Rp 36,750.00
Kayu dolken Ø 8-10/400 cm btg 2.0000 Rp 30,000.00 Rp 60,000.00
Sub-Total bahan Rp 271,211.70

Sub-Total ( 2 ) penggunaan material untuk 2 x pakai Rp 135,605.85

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 221,735.85

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Bekisting Dinding beton
Satuan Pembayaran : M2
Harga Satuan : Rp 266,617.80 SNI 7394 (6.25) - 2008
AHSP-III-021
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6600 Rp 70,000.00 Rp 46,200.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0330 Rp 110,000.00 Rp 3,630.00

Sub-Total ( 1 ) Rp 86,130.00

2 Bahan
Kayu gergajian kelas III (kasau) m³ 0.0300 Rp 3,635,000.00 Rp 109,050.00
Paku biasa 2"-5" kg 0.4000 Rp 15,300.00 Rp 6,120.00
Minyak bekisting lt 0.2000 Rp 2,478.00 Rp 495.60
Kayu gergajian kelas III (papan) m³ 0.0200 Rp 3,928,000.00 Rp 78,560.00
Plywood/multiplex 9mm lbr 0.3500 Rp 105,000.00 Rp 36,750.00
Kayu dolken Ø 8-10/400 cm btg 3.0000 Rp 30,000.00 Rp 90,000.00
Formate/spacer/penjaga jarak bh 4.0000 Rp 10,000.00 Rp 40,000.00
Sub-Total bahan Rp 360,975.60

Sub-Total ( 2 ) penggunaan material untuk 2 x pakai Rp 180,487.80


3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 266,617.80

Analisa Harga Satuan Pekerjaan - 44


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BETON BERTULANG


Jenis Pembayaran : Membongkar Bekisting
Satuan Pembayaran : M3
Harga Satuan : Rp 280,000.00
AHSP-III-022
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 4.0000 Rp 70,000.00 Rp 280,000.00

Sub-Total ( 1 ) Rp 280,000.00

2 Bahan

Sub-Total ( 2 ) Rp -

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 280,000.00

Analisa Harga Satuan Pekerjaan - 45


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

IV. PEKERJAAN : PASANGAN

Pekerjaan : PASANGAN
Jenis Pembayaran : Aanstampeng Batu Kali
Satuan Pembayaran : M3
Harga Satuan : Rp 360,766.80 SNI 2836 (6.9) - 2008
AHSP-IV-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7800 Rp 70,000.00 Rp 54,600.00
Tukang batu OH 0.3900 Rp 90,000.00 Rp 35,100.00
Kep. Tukang Batu OH 0.0390 Rp 100,000.00 Rp 3,900.00
Mandor OH 0.0390 Rp 110,000.00 Rp 4,290.00

Sub-Total ( 1 ) Rp 97,890.00

2 Bahan
Batu kali M3 1.2000 Rp 170,500.00 Rp 204,600.00
Pasir urug M3 0.4320 Rp 134,900.00 Rp 58,276.80

Sub-Total ( 2 ) Rp 262,876.80

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 360,766.80

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Pondasi Batu Kali ad 1 Pc : 3 Psr
Satuan Pembayaran : M3
Harga Satuan : Rp 779,086.50 SNI 2836 (6.1) - 2008
AHSP-IV-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.5000 Rp 70,000.00 Rp 105,000.00
Tukang batu OH 0.7500 Rp 90,000.00 Rp 67,500.00
Kep. Tukang Batu OH 0.0750 Rp 100,000.00 Rp 7,500.00
Mandor OH 0.0750 Rp 110,000.00 Rp 8,250.00

Sub-Total ( 1 ) Rp 188,250.00

2 Bahan
Semen PC Kg 202.0000 Rp 1,471.00 Rp 297,142.00
Batu kali M3 1.2000 Rp 170,500.00 Rp 204,600.00
Pasir pasang M3 0.4850 Rp 183,700.00 Rp 89,094.50

Sub-Total ( 2 ) Rp 590,836.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 779,086.50

Analisa Harga Satuan Pekerjaan - 46


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Pondasi Batu Kali ad 1 Pc : 4 Psr
Satuan Pembayaran : M3
Harga Satuan : Rp 728,147.00 SNI 2836 (6.2) - 2008
AHSP-IV-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.5000 Rp 70,000.00 Rp 105,000.00
Tukang batu OH 0.7500 Rp 90,000.00 Rp 67,500.00
Kep. Tukang Batu OH 0.0750 Rp 100,000.00 Rp 7,500.00
Mandor OH 0.0750 Rp 110,000.00 Rp 8,250.00

Sub-Total ( 1 ) Rp 188,250.00

2 Bahan
Semen PC Kg 163.0000 Rp 1,471.00 Rp 239,773.00
Batu kali M3 1.2000 Rp 170,500.00 Rp 204,600.00
Pasir pasang M3 0.5200 Rp 183,700.00 Rp 95,524.00

Sub-Total ( 2 ) Rp 539,897.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 728,147.00

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Pondasi Batu Kali ad 1 Pc : 5 Psr
Satuan Pembayaran : M3
Harga Satuan : Rp 692,838.80 SNI 2836 (6.3) - 2008
AHSP-IV-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.5000 Rp 70,000.00 Rp 105,000.00
Tukang batu OH 0.7500 Rp 90,000.00 Rp 67,500.00
Kep. Tukang Batu OH 0.0750 Rp 100,000.00 Rp 7,500.00
Mandor OH 0.0750 Rp 110,000.00 Rp 8,250.00

Sub-Total ( 1 ) Rp 188,250.00

2 Bahan
Semen PC Kg 136.0000 Rp 1,471.00 Rp 200,056.00
Batu kali M3 1.2000 Rp 170,500.00 Rp 204,600.00
Pasir pasang M3 0.5440 Rp 183,700.00 Rp 99,932.80

Sub-Total ( 2 ) Rp 504,588.80

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 692,838.80

Analisa Harga Satuan Pekerjaan - 47


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Dinding Bata Merah (1 Batu), 1Pc : 3Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 221,486.15 SNI 6897 (6.2) - 2008
AHSP-IV-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6000 Rp 70,000.00 Rp 42,000.00
Tukang batu OH 0.2000 Rp 90,000.00 Rp 18,000.00
Kepala tukang OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0300 Rp 110,000.00 Rp 3,300.00

Sub-Total ( 1 ) Rp 65,300.00

2 Bahan
Semen PC kg 32.9500 Rp 1,471.00 Rp 48,469.45
Batu bata uk. 5 x 11 x 23 cm Bh 140.0000 Rp 650.00 Rp 91,000.00
Pasir pasang M3 0.0910 Rp 183,700.00 Rp 16,716.70

Sub-Total ( 2 ) Rp 156,186.15

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 221,486.15

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Dinding Bata Merah (1/2 Batu), 1Pc : 3Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 106,636.27 SNI 6897 (6.8) - 2008
AHSP-IV-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 32,650.00

2 Bahan
Semen PC kg 14.3700 Rp 1,471.00 Rp 21,138.27
Batu bata uk. 5 x 11 x 23 cm Bh 70.0000 Rp 650.00 Rp 45,500.00
Pasir pasang M3 0.0400 Rp 183,700.00 Rp 7,348.00

Sub-Total ( 2 ) Rp 73,986.27

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 106,636.27

Analisa Harga Satuan Pekerjaan - 48


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Dinding Bata Merah (1 Batu), 1Pc : 5Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 205,924.90 SNI 6897 (6.4) - 2008
AHSP-IV-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6000 Rp 70,000.00 Rp 42,000.00
Tukang batu OH 0.2000 Rp 90,000.00 Rp 18,000.00
Kepala tukang OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0300 Rp 110,000.00 Rp 3,300.00

Sub-Total ( 1 ) Rp 65,300.00

2 Bahan
Semen PC kg 18.5000 Rp 1,471.00 Rp 27,213.50
Batu bata uk. 5 x 11 x 23 cm Bh 140.0000 Rp 650.00 Rp 91,000.00
Pasir pasang M3 0.1220 Rp 183,700.00 Rp 22,411.40

Sub-Total ( 2 ) Rp 140,624.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 205,924.90

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Dinding Bata Merah (1/2 Batu), 1Pc : 5Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 100,655.78 SNI 6897 (6.10) - 2008
AHSP-IV-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 32,650.00

2 Bahan
Semen PC kg 9.6800 Rp 1,471.00 Rp 14,239.28
Batu bata uk. 5 x 11 x 23 cm Bh 70.0000 Rp 650.00 Rp 45,500.00
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50

Sub-Total ( 2 ) Rp 68,005.78

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 100,655.78

Analisa Harga Satuan Pekerjaan - 49


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Dinding bata ringan (Hebel) tebal 10 cm, perekat Mortar
Satuan Pembayaran : M2
Harga Satuan : Rp 132,210.00
AHSP-IV-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kepala tukang OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 37,650.00

2 Bahan
Batu bata ringan (ex Hebel), 10x16x60 cm bh 8.5000 Rp 10,400.00 Rp 88,400.00
Perekat PM-100 / MU-100 (perekat) kg 3.2000 Rp 1,925.00 Rp 6,160.00

Sub-Total ( 2 ) Rp 94,560.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 132,210.00

Pekerjaan : PASANGAN
Jenis Pembayaran : Pas. Dinding batako (1/2 batu), 1Pc : 3Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 101,377.04 SNI 6897 (6.20) - 2008
AHSP-IV-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 32,650.00

2 Bahan
Semen PC kg 15.1600 Rp 1,471.00 Rp 22,300.36
Batako semen, uk. 9 x 19 x 39 cm Bh 12.5000 Rp 3,000.00 Rp 37,500.00
Pasir pasang M3 0.0364 Rp 183,700.00 Rp 6,686.68
Besi angkur dia 8 mm kg 0.2800 Rp 8,000.00 Rp 2,240.00

Sub-Total ( 2 ) Rp 68,727.04

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 101,377.04

Analisa Harga Satuan Pekerjaan - 50


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PASANGAN
Jenis Pembayaran : Dinding Ornamen GRC
Satuan Pembayaran : M2
Harga Satuan : Rp 704,500.00
AHSP-IV-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
Biaya angkutan Jakarta - Kupang (Rp. 450.000,--/ 100m2) m2 1.0000 Rp 4,500.00 Rp 4,500.00
Harga Ornamen termasuk pemasangan m2 1.0000 Rp 700,000.00 Rp 700,000.00

Sub-Total ( 2 ) Rp 704,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 704,500.00

Analisa Harga Satuan Pekerjaan - 51


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

V. PEKERJAAN : FINISHING DINDING

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Dinding 15 mm, Camp. 1Pc : 2Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 56,363.50 SNI 2837 (6.2) - 2008
AHSP-V-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kepala tukang OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 37,650.00

2 Bahan
Semen PC kg 10.2240 Rp 1,471.00 Rp 15,039.50
Pasir pasang M3 0.0200 Rp 183,700.00 Rp 3,674.00

Sub-Total ( 2 ) Rp 18,713.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 56,363.50

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Dinding 15 mm, Camp. 1Pc : 3Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 53,313.60 SNI 2837 (6.3) - 2008
AHSP-V-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kepala tukang OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 37,650.00

2 Bahan
Semen PC kg 7.7760 Rp 1,471.00 Rp 11,438.50
Pasir pasang M3 0.0230 Rp 183,700.00 Rp 4,225.10

Sub-Total ( 2 ) Rp 15,663.60

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 53,313.60

Analisa Harga Satuan Pekerjaan - 52


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Dinding 15 mm, Camp. 1Pc : 5Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 50,051.86 SNI 2837 (6.5) - 2008
AHSP-V-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kepala tukang OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 37,650.00

2 Bahan
Semen PC kg 5.1840 Rp 1,471.00 Rp 7,625.66
Pasir pasang M3 0.0260 Rp 183,700.00 Rp 4,776.20

Sub-Total ( 2 ) Rp 12,401.86

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 50,051.86

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Dinding 20 mm, Camp. 1Pc : 3Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 71,366.03 SNI 2837 (6.14) - 2008
AHSP-V-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.4000 Rp 70,000.00 Rp 28,000.00
Tukang batu OH 0.2000 Rp 90,000.00 Rp 18,000.00
Kepala tukang OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0220 Rp 110,000.00 Rp 2,420.00

Sub-Total ( 1 ) Rp 50,420.00

2 Bahan
Semen PC kg 10.3680 Rp 1,471.00 Rp 15,251.33
Pasir pasang M3 0.0310 Rp 183,700.00 Rp 5,694.70

Sub-Total ( 2 ) Rp 20,946.03

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 71,366.03

Analisa Harga Satuan Pekerjaan - 53


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Dinding 20 mm, Camp. 1Pc : 5Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 67,017.05 SNI 2837 (6.16) - 2008
AHSP-V-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.4000 Rp 70,000.00 Rp 28,000.00
Tukang batu OH 0.2000 Rp 90,000.00 Rp 18,000.00
Kepala tukang OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0220 Rp 110,000.00 Rp 2,420.00

Sub-Total ( 1 ) Rp 50,420.00

2 Bahan
Semen PC kg 6.9120 Rp 1,471.00 Rp 10,167.55
Pasir pasang M3 0.0350 Rp 183,700.00 Rp 6,429.50

Sub-Total ( 2 ) Rp 16,597.05

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 67,017.05

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Brafen batu kali, 1Pc : 3Ps
Satuan Pembayaran : M2
Harga Satuan : Rp 60,260.50
AHSP-V-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kepala tukang OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 37,650.00

2 Bahan
Semen PC kg 11.0000 Rp 1,471.00 Rp 16,181.00
Pasir pasang M3 0.0350 Rp 183,700.00 Rp 6,429.50

Sub-Total ( 2 ) Rp 22,610.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 60,260.50

Analisa Harga Satuan Pekerjaan - 54


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Dinding Campuran Mortar, tebal 10 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 85,992.50
AHSP-V-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 25,100.00

2 Bahan
Perekat mortar & beton (MU L-500) Kg 0.1100 Rp 131,750.00 Rp 14,492.50
Plester premium (MU 100) kg 20.0000 Rp 1,925.00 Rp 38,500.00
Acian plesteran (MU 250) kg 2.0000 Rp 3,950.00 Rp 7,900.00

Sub-Total ( 2 ) Rp 60,892.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 85,992.50

Analisa Harga Satuan Pekerjaan - 55


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Ciprat / Kamprotan 1Pc : 2PP
Satuan Pembayaran : M2
Harga Satuan : Rp 40,106.92 SNI 2837 (6.23) - 2008
AHSP-V-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 32,650.00

2 Bahan
Semen PC kg 4.3200 Rp 1,471.00 Rp 6,354.72
Pasir pasang M3 0.0060 Rp 183,700.00 Rp 1,102.20

Sub-Total ( 2 ) Rp 7,456.92

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 40,106.92

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Acian dengan Semen
Satuan Pembayaran : M2
Harga Satuan : Rp 29,880.75 SNI 2837 (6.27) - 2008
AHSP-V-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 25,100.00

2 Bahan
Semen PC kg 3.2500 Rp 1,471.00 Rp 4,780.75

Sub-Total ( 2 ) Rp 4,780.75

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 29,880.75

Analisa Harga Satuan Pekerjaan - 56


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Acian Beton Expose, dengan Mortar
Satuan Pembayaran : M2
Harga Satuan : Rp 34,205.00
AHSP-V-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1500 Rp 70,000.00 Rp 10,500.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 21,380.00

2 Bahan
Acian plesteran / beton expose (MU 200) kg 3.0000 Rp 4,275.00 Rp 12,825.00

Sub-Total ( 2 ) Rp 12,825.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 34,205.00

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Keramik 20x25 Cm,
Satuan Pembayaran : M2
Harga Satuan : Rp 175,454.90
AHSP-V-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.3000 Rp 90,000.00 Rp 27,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 51,330.00

2 Bahan (SNI 7395 (6.54) - 2008)


Semen PC kg 9.3000 Rp 1,471.00 Rp 13,680.30
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Keramik dinding 20x25 cm, ex Roman M2 1.0600 Rp 76,000.00 Rp 80,560.00
Semen Warna Kg 1.9400 Rp 13,700.00 Rp 26,578.00

Sub-Total ( 2 ) Rp 124,124.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 175,454.90

Analisa Harga Satuan Pekerjaan - 57


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Keramik 20x20 Cm,
Satuan Pembayaran : M2
Harga Satuan : Rp 176,514.90
AHSP-V-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.3000 Rp 90,000.00 Rp 27,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 51,330.00

2 Bahan (SNI 7395 (6.54) - 2008)


Semen PC kg 9.3000 Rp 1,471.00 Rp 13,680.30
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Keramik dinding 20x20 cm, ex Roman Wall Tile M2 1.0600 Rp 77,000.00 Rp 81,620.00
Semen Warna Kg 1.9400 Rp 13,700.00 Rp 26,578.00

Sub-Total ( 2 ) Rp 125,184.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 176,514.90

Analisa Harga Satuan Pekerjaan - 58


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Keramik 30x30 Cm,
Satuan Pembayaran : M2
Harga Satuan : Rp 195,594.90
AHSP-V-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.3000 Rp 90,000.00 Rp 27,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 51,330.00

2 Bahan (SNI 7395 (6.54) - 2008)


Semen PC kg 9.3000 Rp 1,471.00 Rp 13,680.30
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Keramik dinding 30x30 cm, ex Roman M2 1.0600 Rp 95,000.00 Rp 100,700.00
Semen Warna Kg 1.9400 Rp 13,700.00 Rp 26,578.00

Sub-Total ( 2 ) Rp 144,264.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 195,594.90

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Keramik 20x40 Cm,
Satuan Pembayaran : M2
Harga Satuan : Rp 179,694.90
AHSP-V-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.3000 Rp 90,000.00 Rp 27,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 51,330.00

2 Bahan (SNI 7395 (6.54) - 2008)


Semen PC kg 9.3000 Rp 1,471.00 Rp 13,680.30
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Keramik dinding 20x40 cm, ex Roman M2 1.0600 Rp 80,000.00 Rp 84,800.00
Semen Warna Kg 1.9400 Rp 13,700.00 Rp 26,578.00

Sub-Total ( 2 ) Rp 128,364.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 179,694.90

Analisa Harga Satuan Pekerjaan - 59


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Keramik 20x60 Cm,
Satuan Pembayaran : M2
Harga Satuan : Rp 225,804.90
AHSP-V-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.3000 Rp 90,000.00 Rp 27,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 51,330.00

2 Bahan (SNI 7395 (6.54) - 2008)


Semen PC kg 9.3000 Rp 1,471.00 Rp 13,680.30
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Keramik dinding 20x60 cm, ex Roman M2 1.0600 Rp 123,500.00 Rp 130,910.00
Semen Warna Kg 1.9400 Rp 13,700.00 Rp 26,578.00

Sub-Total ( 2 ) Rp 174,474.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 225,804.90

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Keramik 30x60 Cm,
Satuan Pembayaran : M2
Harga Satuan : Rp 231,104.90
AHSP-V-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang batu OH 0.3000 Rp 90,000.00 Rp 27,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 51,330.00

2 Bahan (SNI 7395 (6.54) - 2008)


Semen PC kg 9.3000 Rp 1,471.00 Rp 13,680.30
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Keramik dinding 30x60 cm, ex Roman M2 1.0600 Rp 128,500.00 Rp 136,210.00
Semen Warna Kg 1.9400 Rp 13,700.00 Rp 26,578.00

Sub-Total ( 2 ) Rp 179,774.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 231,104.90

Analisa Harga Satuan Pekerjaan - 60


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Marmer 100 x 100 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 674,043.24 SNI 7395 (6.55) - 2008
AHSP-V-017
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7000 Rp 70,000.00 Rp 49,000.00
Tukang batu OH 0.3500 Rp 90,000.00 Rp 31,500.00
Kepala tukang OH 0.0350 Rp 100,000.00 Rp 3,500.00
Mandor OH 0.0350 Rp 110,000.00 Rp 3,850.00

Sub-Total ( 1 ) Rp 87,850.00

2 Bahan
Semen PC kg 12.4400 Rp 1,471.00 Rp 18,299.24
Marmer Lampung Kristaline 100x100x2 m2 1.0600 Rp 530,000.00 Rp 561,800.00
Pasir Pasang m3 0.0250 Rp 183,700.00 Rp 4,592.50
Paku 12 mm bh 3.0030 Rp 500.00 Rp 1,501.50

Sub-Total ( 2 ) Rp 586,193.24

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 674,043.24

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Granit Import
Satuan Pembayaran : M2
Harga Satuan : Rp 801,243.24 SNI 7395 (6.55) - 2008
AHSP-V-018
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7000 Rp 70,000.00 Rp 49,000.00
Tukang batu OH 0.3500 Rp 90,000.00 Rp 31,500.00
Kepala tukang OH 0.0350 Rp 100,000.00 Rp 3,500.00
Mandor OH 0.0350 Rp 110,000.00 Rp 3,850.00

Sub-Total ( 1 ) Rp 87,850.00

2 Bahan
Semen PC kg 12.4400 Rp 1,471.00 Rp 18,299.24
Granit Import (Nero Absolute India) jenis slab m2 1.0600 Rp 650,000.00 Rp 689,000.00
Pasir Pasang m3 0.0250 Rp 183,700.00 Rp 4,592.50
Paku 12 mm bh 3.0030 Rp 500.00 Rp 1,501.50

Sub-Total ( 2 ) Rp 713,393.24

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 801,243.24

Analisa Harga Satuan Pekerjaan - 61


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Plesteran Skoning (benangan/ tali air) dengan mortar
Satuan Pembayaran : M2
Harga Satuan : Rp 13,677.50
AHSP-V-019
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0570 Rp 70,000.00 Rp 3,990.00
Tukang batu OH 0.0380 Rp 90,000.00 Rp 3,420.00
Kepala tukang OH 0.0380 Rp 100,000.00 Rp 3,800.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 11,540.00

2 Bahan
Acian plesteran / beton expose (MU 200) kg 0.5000 Rp 4,275.00 Rp 2,137.50

Sub-Total ( 2 ) Rp 2,137.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 13,677.50

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding Allumunium Composit Panel
Satuan Pembayaran : M2
Harga Satuan : Rp 784,350.00
AHSP-V-020
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.5000 Rp 70,000.00 Rp 105,000.00
Tukang allumunium OH 1.5000 Rp 90,000.00 Rp 135,000.00
Kepala tukang OH 0.1500 Rp 100,000.00 Rp 15,000.00
Mandor OH 0.0600 Rp 110,000.00 Rp 6,600.00

Sub-Total ( 1 ) Rp 261,600.00

2 Bahan
ACP SEVEN Bright silver 5005 (tebal ACP 4mm, tebal All 0,5mm) m2 1.1000 Rp 325,000.00 Rp 357,500.00
Rangka allumunium hollow m' 5.0000 Rp 25,000.00 Rp 125,000.00
Paku skrup kg 0.6000 Rp 40,000.00 Rp 24,000.00
Sealant m' 2.0000 Rp 8,125.00 Rp 16,250.00

Sub-Total ( 2 ) Rp 522,750.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 784,350.00

Analisa Harga Satuan Pekerjaan - 62


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding batu alam Andesit
Satuan Pembayaran : M2
Harga Satuan : Rp 250,348.55 SNI 7395 (6.57) - 2008
AHSP-V-021
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7000 Rp 70,000.00 Rp 49,000.00
Tukang batu OH 0.3500 Rp 90,000.00 Rp 31,500.00
Kepala tukang OH 0.0350 Rp 100,000.00 Rp 3,500.00
Mandor OH 0.0350 Rp 110,000.00 Rp 3,850.00

Sub-Total ( 1 ) Rp 87,850.00

2 Bahan
Semen PC kg 11.7500 Rp 1,471.00 Rp 17,284.25
Batu alam Andesit 15/30 cm m2 1.1000 Rp 126,168.00 Rp 138,784.80
Pasir Pasang m3 0.0350 Rp 183,700.00 Rp 6,429.50

Sub-Total ( 2 ) Rp 162,498.55

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 250,348.55

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding batu paras
Satuan Pembayaran : M2
Harga Satuan : Rp 218,906.15 SNI 7395 (6.57) - 2008
AHSP-V-022
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7000 Rp 70,000.00 Rp 49,000.00
Tukang batu OH 0.3500 Rp 90,000.00 Rp 31,500.00
Kepala tukang OH 0.0350 Rp 100,000.00 Rp 3,500.00
Mandor OH 0.0350 Rp 110,000.00 Rp 3,850.00

Sub-Total ( 1 ) Rp 87,850.00

2 Bahan
Semen PC kg 11.7500 Rp 1,471.00 Rp 17,284.25
Batu alam Paras Jogya 20/30 cm (cream/putih) m2 1.1000 Rp 97,584.00 Rp 107,342.40
Pasir Pasang m3 0.0350 Rp 183,700.00 Rp 6,429.50

Sub-Total ( 2 ) Rp 131,056.15

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 218,906.15

Analisa Harga Satuan Pekerjaan - 63


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Dinding batu tempel acak hitam
Satuan Pembayaran : M2
Harga Satuan : Rp 194,063.75 SNI 7395 (6.58) - 2008
AHSP-V-023
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7000 Rp 70,000.00 Rp 49,000.00
Tukang batu OH 0.3500 Rp 90,000.00 Rp 31,500.00
Kepala tukang OH 0.0350 Rp 100,000.00 Rp 3,500.00
Mandor OH 0.0350 Rp 110,000.00 Rp 3,850.00

Sub-Total ( 1 ) Rp 87,850.00

2 Bahan
Semen PC kg 11.7500 Rp 1,471.00 Rp 17,284.25
Batu tempel acak hitam Sukabumi m2 1.1000 Rp 75,000.00 Rp 82,500.00
Pasir Pasang m3 0.0350 Rp 183,700.00 Rp 6,429.50

Sub-Total ( 2 ) Rp 106,213.75

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 194,063.75

Pekerjaan : FINISHING DINDING


Jenis Pembayaran : Lapisan Wall paper
Satuan Pembayaran : M2
Harga Satuan : Rp 105,127.50 SNI 7395 (6.60) - 2008
AHSP-V-024
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2625 Rp 70,000.00 Rp 18,375.00
Tukang batu OH 0.1313 Rp 90,000.00 Rp 11,812.50
Kepala tukang OH 0.0128 Rp 100,000.00 Rp 1,275.00
Mandor OH 0.0015 Rp 110,000.00 Rp 165.00

Sub-Total ( 1 ) Rp 31,627.50

2 Bahan
Wall Paper, lebar 50 cm m' 2.2000 Rp 30,000.00 Rp 66,000.00
Lem kg 0.2500 Rp 30,000.00 Rp 7,500.00

Sub-Total ( 2 ) Rp 73,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 105,127.50

Analisa Harga Satuan Pekerjaan - 64


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

VI. PEKERJAAN : FINISHING LANTAI

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Homogenius tile 60 x 60 (polish)
Satuan Pembayaran : M2
Harga Satuan : Rp 374,787.70
AHSP-VI-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.5000 Rp 70,000.00 Rp 35,000.00
Tukang Batu OH 0.2500 Rp 90,000.00 Rp 22,500.00
Kep. Tukang Batu OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 60,550.00
2 Bahan
Semen PC kg 9.6000 Rp 1,471.00 Rp 14,121.60
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Homogenous Tile 60x60 cm, ex Granito (polish) M2 1.1160 Rp 243,100.00 Rp 271,299.60
Semen warna Kg 1.5000 Rp 13,700.00 Rp 20,550.00

Sub-Total ( 2 ) Rp 314,237.70
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 374,787.70

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Homogenius tile 60 x 60 (un-polish)
Satuan Pembayaran : M2
Harga Satuan : Rp 339,187.30
AHSP-VI-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.5000 Rp 70,000.00 Rp 35,000.00
Tukang Batu OH 0.2500 Rp 90,000.00 Rp 22,500.00
Kep. Tukang Batu OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 60,550.00
2 Bahan
Semen PC kg 9.6000 Rp 1,471.00 Rp 14,121.60
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Homogenous Tile 60x60 cm, ex Granito (un-polish) M2 1.1160 Rp 211,200.00 Rp 235,699.20
Semen warna Kg 1.5000 Rp 13,700.00 Rp 20,550.00

Sub-Total ( 2 ) Rp 278,637.30
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 339,187.30

Analisa Harga Satuan Pekerjaan - 65


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Plint Homogenius tile 10 x 60 cm + tali air
Satuan Pembayaran : M'
Harga Satuan : Rp 55,213.50
AHSP-VI-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0950 Rp 70,000.00 Rp 6,650.00
Tukang Batu OH 0.1280 Rp 90,000.00 Rp 11,520.00
Kep. Tukang Batu OH 0.0470 Rp 100,000.00 Rp 4,700.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 23,750.00

2 Bahan
Semen PC kg 1.6400 Rp 1,471.00 Rp 2,412.44
Pasir pasang M3 0.0030 Rp 183,700.00 Rp 551.10
Homogenous Tile 10x60 cm, ex Granito M2 0.1116 Rp 243,100.00 Rp 27,129.96
Semen warna Kg 0.1000 Rp 13,700.00 Rp 1,370.00

Sub-Total ( 2 ) Rp 31,463.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 55,213.50

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Homogenius tile 40 x 40 (polish)
Satuan Pembayaran : M2
Harga Satuan : Rp 308,313.90
AHSP-VI-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3500 Rp 70,000.00 Rp 24,500.00
Tukang Batu OH 0.1750 Rp 90,000.00 Rp 15,750.00
Kep. Tukang Batu OH 0.0175 Rp 100,000.00 Rp 1,750.00
Mandor OH 0.0175 Rp 110,000.00 Rp 1,925.00

Sub-Total ( 1 ) Rp 43,925.00

2 Bahan (SNI 7395 (6.35) - 2008)


Semen PC kg 10.0000 Rp 1,471.00 Rp 14,710.00
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Homogenous Tile 40x40 cm, ex Granito (polish) M2 1.0680 Rp 206,800.00 Rp 220,862.40
Semen warna Kg 1.5000 Rp 13,700.00 Rp 20,550.00

Sub-Total ( 2 ) Rp 264,388.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 308,313.90

Analisa Harga Satuan Pekerjaan - 66


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Homogenius tile 40 x 40 (un-polish)
Satuan Pembayaran : M2
Harga Satuan : Rp 277,769.10
AHSP-VI-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3500 Rp 70,000.00 Rp 24,500.00
Tukang Batu OH 0.1750 Rp 90,000.00 Rp 15,750.00
Kep. Tukang Batu OH 0.0175 Rp 100,000.00 Rp 1,750.00
Mandor OH 0.0175 Rp 110,000.00 Rp 1,925.00

Sub-Total ( 1 ) Rp 43,925.00

2 Bahan (SNI 7395 (6.35) - 2008)


Semen PC kg 10.0000 Rp 1,471.00 Rp 14,710.00
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Homogenous Tile 40x40 cm, ex Granito (un-polish) M2 1.0680 Rp 178,200.00 Rp 190,317.60
Semen warna Kg 1.5000 Rp 13,700.00 Rp 20,550.00

Sub-Total ( 2 ) Rp 233,844.10

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 277,769.10

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Plint Homogenius tile 10x40 cm + tali air
Satuan Pembayaran : M'
Harga Satuan : Rp 51,162.42
AHSP-VI-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0950 Rp 70,000.00 Rp 6,650.00
Tukang Batu OH 0.1280 Rp 90,000.00 Rp 11,520.00
Kep. Tukang Batu OH 0.0470 Rp 100,000.00 Rp 4,700.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 23,750.00

2 Bahan
Semen PC kg 1.6400 Rp 1,471.00 Rp 2,412.44
Pasir pasang M3 0.0030 Rp 183,700.00 Rp 551.10
Homogenous Tile 40x40 cm, ex Granito (polish) M2 0.1116 Rp 206,800.00 Rp 23,078.88
Semen warna Kg 0.1000 Rp 13,700.00 Rp 1,370.00

Sub-Total ( 2 ) Rp 27,412.42

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 51,162.42

Analisa Harga Satuan Pekerjaan - 67


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Homogenius tile 30 x 30 (un-polish)
Satuan Pembayaran : M2
Harga Satuan : Rp 277,769.10
AHSP-VI-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3500 Rp 70,000.00 Rp 24,500.00
Tukang Batu OH 0.1750 Rp 90,000.00 Rp 15,750.00
Kep. Tukang Batu OH 0.0175 Rp 100,000.00 Rp 1,750.00
Mandor OH 0.0175 Rp 110,000.00 Rp 1,925.00

Sub-Total ( 1 ) Rp 43,925.00

2 Bahan (SNI 7395 (6.35) - 2008)


Semen PC kg 10.0000 Rp 1,471.00 Rp 14,710.00
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Granitto Gastello 30x30 Cm (Un-polish) Group Silver, type rustic M2 1.0680 Rp 178,200.00 Rp 190,317.60
Semen warna Kg 1.5000 Rp 13,700.00 Rp 20,550.00

Sub-Total ( 2 ) Rp 233,844.10

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 277,769.10

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Plint Homogenius tile 10x30 cm + tali air
Satuan Pembayaran : M'
Harga Satuan : Rp 47,970.66
AHSP-VI-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0950 Rp 70,000.00 Rp 6,650.00
Tukang Batu OH 0.1280 Rp 90,000.00 Rp 11,520.00
Kep. Tukang Batu OH 0.0470 Rp 100,000.00 Rp 4,700.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 23,750.00

2 Bahan
Semen PC kg 1.6400 Rp 1,471.00 Rp 2,412.44
Pasir pasang M3 0.0030 Rp 183,700.00 Rp 551.10
Granitto Gastello 30x30 Cm (Un-polish) Group Silver, type rustic M2 0.1116 Rp 178,200.00 Rp 19,887.12
Semen warna Kg 0.1000 Rp 13,700.00 Rp 1,370.00

Sub-Total ( 2 ) Rp 24,220.66

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 47,970.66

Analisa Harga Satuan Pekerjaan - 68


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Marmer 100x100 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 634,943.99 SNI 7395 (6.43) - 2008
AHSP-VI-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3500 Rp 70,000.00 Rp 24,500.00
Tukang Batu OH 0.1750 Rp 90,000.00 Rp 15,750.00
Kep. Tukang Batu OH 0.0175 Rp 100,000.00 Rp 1,750.00
Mandor OH 0.0175 Rp 110,000.00 Rp 1,925.00

Sub-Total ( 1 ) Rp 43,925.00

2 Bahan (SNI 7395 (6.35) - 2008)


Semen PC kg 8.1900 Rp 1,471.00 Rp 12,047.49
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Marmer Lampung Kristaline 100x100x2 M2 1.0600 Rp 530,000.00 Rp 561,800.00
Semen warna Kg 0.6500 Rp 13,700.00 Rp 8,905.00

Sub-Total ( 2 ) Rp 591,018.99

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 634,943.99

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Keramik 20 x 20 cm (un-polish)
Satuan Pembayaran : M2
Harga Satuan : Rp 176,603.90 SNI 7395 (6.36) - 2008
AHSP-VI-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3500 Rp 70,000.00 Rp 24,500.00
Tukang Batu OH 0.1750 Rp 90,000.00 Rp 15,750.00
Kep. Tukang Batu OH 0.0175 Rp 100,000.00 Rp 1,750.00
Mandor OH 0.0175 Rp 110,000.00 Rp 1,925.00

Sub-Total ( 1 ) Rp 43,925.00

2 Bahan (SNI 7395 (6.36) - 2008)


Semen PC kg 10.4000 Rp 1,471.00 Rp 15,298.40
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Keramik lokal 20/20 Cm (ex Roman) Gol A, un-polish M2 1.0600 Rp 82,000.00 Rp 86,920.00
Semen warna Kg 1.6200 Rp 13,700.00 Rp 22,194.00

Sub-Total ( 2 ) Rp 132,678.90

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 176,603.90

Analisa Harga Satuan Pekerjaan - 69


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Keramik 30x30 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 188,911.50 SNI 7395 (6.35) - 2008
AHSP-VI-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3500 Rp 70,000.00 Rp 24,500.00
Tukang Batu OH 0.1750 Rp 90,000.00 Rp 15,750.00
Kep. Tukang Batu OH 0.0175 Rp 100,000.00 Rp 1,750.00
Mandor OH 0.0175 Rp 110,000.00 Rp 1,925.00

Sub-Total ( 1 ) Rp 43,925.00

2 Bahan (SNI 7395 (6.35) - 2008)


Semen PC kg 10.0000 Rp 1,471.00 Rp 14,710.00
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Keramik lokal 30x30 Cm (ex Roman) Gol B M2 1.0680 Rp 95,000.00 Rp 101,460.00
Semen warna Kg 1.5000 Rp 13,700.00 Rp 20,550.00

Sub-Total ( 2 ) Rp 144,986.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 188,911.50

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Keramik 40x40 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 197,455.50
AHSP-VI-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3500 Rp 70,000.00 Rp 24,500.00
Tukang Batu OH 0.1750 Rp 90,000.00 Rp 15,750.00
Kep. Tukang Batu OH 0.0175 Rp 100,000.00 Rp 1,750.00
Mandor OH 0.0175 Rp 110,000.00 Rp 1,925.00

Sub-Total ( 1 ) Rp 43,925.00

2 Bahan (SNI 7395 (6.35) - 2008)


Semen PC kg 10.0000 Rp 1,471.00 Rp 14,710.00
Pasir pasang M3 0.0450 Rp 183,700.00 Rp 8,266.50
Keramik lokal 40/40 Cm (ex Roman) Gol A M2 1.0680 Rp 103,000.00 Rp 110,004.00
Semen warna Kg 1.5000 Rp 13,700.00 Rp 20,550.00

Sub-Total ( 2 ) Rp 153,530.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 197,455.50

Analisa Harga Satuan Pekerjaan - 70


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Plint Keramik 10x40 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 39,098.46
AHSP-VI-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0950 Rp 70,000.00 Rp 6,650.00
Tukang Batu OH 0.1280 Rp 90,000.00 Rp 11,520.00
Kep. Tukang Batu OH 0.0470 Rp 100,000.00 Rp 4,700.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 23,750.00

2 Bahan
Semen PC kg 1.6400 Rp 1,471.00 Rp 2,412.44
Pasir pasang M3 0.0030 Rp 183,700.00 Rp 551.10
Keramik lokal 40/40 Cm (ex Roman) Gol A M2 0.1116 Rp 98,700.00 Rp 11,014.92
Semen warna Kg 0.1000 Rp 13,700.00 Rp 1,370.00

Sub-Total ( 2 ) Rp 15,348.46

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 39,098.46

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Plint Keramik 10x30 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 38,685.54
AHSP-VI-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0950 Rp 70,000.00 Rp 6,650.00
Tukang Batu OH 0.1280 Rp 90,000.00 Rp 11,520.00
Kep. Tukang Batu OH 0.0470 Rp 100,000.00 Rp 4,700.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 23,750.00

2 Bahan
Semen PC kg 1.6400 Rp 1,471.00 Rp 2,412.44
Pasir pasang M3 0.0030 Rp 183,700.00 Rp 551.10
Keramik lokal 30x30 Cm (ex Roman) Gol B M2 0.1116 Rp 95,000.00 Rp 10,602.00
Semen warna Kg 0.1000 Rp 13,700.00 Rp 1,370.00

Sub-Total ( 2 ) Rp 14,935.54

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 38,685.54

Analisa Harga Satuan Pekerjaan - 71


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Scred Lantai 1 PC : 3 PS (dasaran karpet)
Satuan Pembayaran : M2
Harga Satuan : Rp 68,977.19
AHSP-VI-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang Batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kep. Tukang Batu OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 37,650.00

2 Bahan
Semen PC kg 15.5520 Rp 1,471.00 Rp 22,876.99
Pasir pasang M3 0.0460 Rp 183,700.00 Rp 8,450.20

Sub-Total ( 2 ) Rp 31,327.19

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 68,977.19

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Underlayer / pelapis bawah Karpet
Satuan Pembayaran : M2
Harga Satuan : Rp 70,060.00 SNI 7395 (6.45) - 2008
AHSP-VI-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1200 Rp 70,000.00 Rp 8,400.00
Tukang kayu OH 0.1200 Rp 90,000.00 Rp 10,800.00
Kepala tukang OH 0.0120 Rp 100,000.00 Rp 1,200.00
Mandor OH 0.0060 Rp 110,000.00 Rp 660.00

Sub-Total ( 1 ) Rp 21,060.00

2 Bahan
Underlayer / Rubber corrugated m2 1.0500 Rp 40,000.00 Rp 42,000.00
Lem karpet/vinyl kg 0.3500 Rp 20,000.00 Rp 7,000.00

Sub-Total ( 2 ) Rp 49,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 70,060.00

Analisa Harga Satuan Pekerjaan - 72


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Karpet sheet ex lokal
Satuan Pembayaran : M2
Harga Satuan : Rp 133,090.00 SNI 7395 (6.44) - 2008
AHSP-VI-017
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1700 Rp 70,000.00 Rp 11,900.00
Tukang kayu OH 0.1700 Rp 100,000.00 Rp 17,000.00
Kepala tukang OH 0.0170 Rp 100,000.00 Rp 1,700.00
Mandor OH 0.0090 Rp 110,000.00 Rp 990.00

Sub-Total ( 1 ) Rp 31,590.00

2 Bahan
Karpet Sheet ex Lokal m2 1.0500 Rp 90,000.00 Rp 94,500.00
Lem karpet/vinyl kg 0.3500 Rp 20,000.00 Rp 7,000.00

Sub-Total ( 2 ) Rp 101,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 133,090.00

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Carpet Tile, ex Leiko
Satuan Pembayaran : M2
Harga Satuan : Rp 353,590.00 SNI 7395 (6.44) - 2008
AHSP-VI-018
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1700 Rp 70,000.00 Rp 11,900.00
Tukang kayu OH 0.1700 Rp 100,000.00 Rp 17,000.00
Kepala tukang OH 0.0170 Rp 100,000.00 Rp 1,700.00
Mandor OH 0.0090 Rp 110,000.00 Rp 990.00

Sub-Total ( 1 ) Rp 31,590.00

2 Bahan
Carpet Tile 50x50, ex Leiko m2 1.0500 Rp 300,000.00 Rp 315,000.00
Lem karpet/vinyl kg 0.3500 Rp 20,000.00 Rp 7,000.00

Sub-Total ( 2 ) Rp 322,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 353,590.00

Analisa Harga Satuan Pekerjaan - 73


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Scred Lantai 1 PC : 3 PS + Floor Hardener
Satuan Pembayaran : M2
Harga Satuan : Rp 132,977.19
AHSP-VI-019
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang Batu OH 0.1500 Rp 100,000.00 Rp 15,000.00
Kep. Tukang Batu OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 39,150.00

2 Bahan
Semen PC kg 15.5520 Rp 1,471.00 Rp 22,876.99
Pasir pasang M3 0.0460 Rp 183,700.00 Rp 8,450.20
Floor Hardener (Tesa/Gan's Floor), 5 kg/m2 Kg 5.0000 Rp 12,500.00 Rp 62,500.00

Sub-Total ( 2 ) Rp 93,827.19

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 132,977.19

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Scred Lantai 1 PC : 3 PS + Floor Epoxy
Satuan Pembayaran : M2
Harga Satuan : Rp 159,227.19
AHSP-VI-020
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang Batu OH 0.1500 Rp 100,000.00 Rp 15,000.00
Kep. Tukang Batu OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 39,150.00

2 Bahan
Semen PC kg 15.5520 Rp 1,471.00 Rp 22,876.99
Pasir pasang M3 0.0460 Rp 183,700.00 Rp 8,450.20
Hardener (Tesa/Gan's Floor) Kg 3.5000 Rp 12,500.00 Rp 43,750.00
Epoxy resin Kg 3.0000 Rp 15,000.00 Rp 45,000.00

Sub-Total ( 2 ) Rp 120,077.19

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 159,227.19

Analisa Harga Satuan Pekerjaan - 74


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Floor Hardener
Satuan Pembayaran : M2
Harga Satuan : Rp 84,760.00 SNI 7395 (6.61) - 2008
AHSP-VI-021
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1200 Rp 70,000.00 Rp 8,400.00
Tukang Batu OH 0.1200 Rp 100,000.00 Rp 12,000.00
Kep. Tukang Batu OH 0.0120 Rp 100,000.00 Rp 1,200.00
Mandor OH 0.0060 Rp 110,000.00 Rp 660.00

Sub-Total ( 1 ) Rp 22,260.00

2 Bahan
Floor Hardener (Tesa/Gan's Floor), 5 kg/m2 Kg 5.0000 Rp 12,500.00 Rp 62,500.00

Sub-Total ( 2 ) Rp 62,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 84,760.00

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Epoxy Flooring
Satuan Pembayaran : M2
Harga Satuan : Rp 111,010.00
AHSP-VI-022
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1200 Rp 70,000.00 Rp 8,400.00
Tukang Batu OH 0.1200 Rp 100,000.00 Rp 12,000.00
Kep. Tukang Batu OH 0.0120 Rp 100,000.00 Rp 1,200.00
Mandor OH 0.0060 Rp 110,000.00 Rp 660.00

Sub-Total ( 1 ) Rp 22,260.00

2 Bahan
Hardener (Tesa/Gan's Floor) Kg 3.5000 Rp 12,500.00 Rp 43,750.00
Epoxy resin Kg 3.0000 Rp 15,000.00 Rp 45,000.00

Sub-Total ( 2 ) Rp 88,750.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 111,010.00

Analisa Harga Satuan Pekerjaan - 75


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Lantai Parquet kayu
Satuan Pembayaran : M2
Harga Satuan : Rp 230,730.00 SNI 7395 (6.46) - 2008
AHSP-VI-023
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7000 Rp 70,000.00 Rp 49,000.00
Tukang kayu OH 0.3500 Rp 100,000.00 Rp 35,000.00
Kep. Tukang kayu OH 0.0350 Rp 100,000.00 Rp 3,500.00
Mandor OH 0.0350 Rp 110,000.00 Rp 3,850.00

Sub-Total ( 1 ) Rp 91,350.00

2 Bahan
Red Oak lam parquet uk. 1,5 x 6 x 30 cm m2 1.0500 Rp 115,600.00 Rp 121,380.00
Lem Kg 0.6000 Rp 30,000.00 Rp 18,000.00

Sub-Total ( 2 ) Rp 139,380.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 230,730.00

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Plint kayu Kamper Samarinda, uk 2x10 cm (finish melamik)
Satuan Pembayaran : M'
Harga Satuan : Rp 65,773.33 SNI 7395 (6.63) - 2008
AHSP-VI-024
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1200 Rp 70,000.00 Rp 8,400.00
Tukang Batu OH 0.1200 Rp 100,000.00 Rp 12,000.00
Kep. Tukang Batu OH 0.0120 Rp 100,000.00 Rp 1,200.00
Mandor OH 0.0060 Rp 110,000.00 Rp 660.00

Sub-Total ( 1 ) Rp 22,260.00

2 Bahan
Kayu Kamper Samarinda m3 0.0030 Rp 9,117,500.00 Rp 27,352.50
Melamik m2 0.1200 Rp 134,673.55 Rp 16,160.83

Sub-Total ( 2 ) Rp 43,513.33

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 65,773.33

Analisa Harga Satuan Pekerjaan - 76


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Scred Lantai 1 PC : 3 PS + Waterprofing jenis coating
Satuan Pembayaran : M2
Harga Satuan : Rp 122,596.03
AHSP-VI-025
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang Batu OH 0.1500 Rp 100,000.00 Rp 15,000.00
Kep. Tukang Batu OH 0.0150 Rp 100,000.00 Rp 1,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 39,150.00

2 Bahan
Semen PC kg 10.3680 Rp 1,471.00 Rp 15,251.33
Pasir pasang M3 0.0310 Rp 183,700.00 Rp 5,694.70
Waterproofing ex Sika / setara kg 1.0000 Rp 55,000.00 Rp 55,000.00
Kuas Bh 0.5000 Rp 15,000.00 Rp 7,500.00

Sub-Total ( 2 ) Rp 83,446.03

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 122,596.03

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Stepnozing Tangga, Homogenous tile 10x60 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 73,785.71
AHSP-VI-026
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0950 Rp 70,000.00 Rp 6,650.00
Tukang Batu OH 0.1280 Rp 100,000.00 Rp 12,800.00
Kep. Tukang Batu OH 0.0470 Rp 100,000.00 Rp 4,700.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 25,030.00

2 Bahan
Semen PC kg 1.6400 Rp 1,471.00 Rp 2,412.44
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Stepnozing tangga, Granito Salsa Diamond / Palazzo Silver 10x60 c bh 1.6667 Rp 25,000.00 Rp 41,666.67
Semen warna Kg 0.1000 Rp 13,700.00 Rp 1,370.00

Sub-Total ( 2 ) Rp 48,755.71

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 73,785.71

Analisa Harga Satuan Pekerjaan - 77


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : FINISHING LANTAI


Jenis Pembayaran : Stepnozing Tangga, Keramik tile 8x30 cm
Satuan Pembayaran : M2
Harga Satuan : Rp 82,119.04
AHSP-VI-027
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0950 Rp 70,000.00 Rp 6,650.00
Tukang Batu OH 0.1280 Rp 100,000.00 Rp 12,800.00
Kep. Tukang Batu OH 0.0470 Rp 100,000.00 Rp 4,700.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 25,030.00

2 Bahan
Semen PC kg 1.6400 Rp 1,471.00 Rp 2,412.44
Pasir pasang M3 0.0180 Rp 183,700.00 Rp 3,306.60
Stepnozing tangga, Keramik Roman 8x30 cm bh 3.3333 Rp 15,000.00 Rp 50,000.00
Semen warna Kg 0.1000 Rp 13,700.00 Rp 1,370.00

Sub-Total ( 2 ) Rp 57,089.04

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 82,119.04

Analisa Harga Satuan Pekerjaan - 78


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

VII. PEKERJAAN : PLAFOND

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Gypsum Board 9 mm + Rangka Hollow
Satuan Pembayaran : M2
Harga Satuan : Rp 118,916.50
AHSP-VII-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2600 Rp 70,000.00 Rp 18,200.00
Tukang gypsum OH 0.0500 Rp 90,000.00 Rp 4,500.00
Tukang Allumunium OH 0.2600 Rp 90,000.00 Rp 23,400.00
Kepala tukang OH 0.0310 Rp 100,000.00 Rp 3,100.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00

Sub-Total ( 1 ) Rp 50,630.00

2 Bahan
Paku peluru ramset bh 0.3900 Rp 1,750.00 Rp 682.50
Hollow 40x40 mm galvanized (tebal standart) btg 0.4590 Rp 26,000.00 Rp 11,934.00
Hollow 20x40 mm galvanized (tebal standart) btg 0.4310 Rp 20,000.00 Rp 8,620.00
Paku beton kg 0.0100 Rp 35,000.00 Rp 350.00
Sekrup 6x1-1,5 bh 14.0000 Rp 500.00 Rp 7,000.00
Gypsumboard 120x240 cm 9 mm lbr 0.3640 Rp 60,000.00 Rp 21,840.00
Sekrup gypsum bh 21.0000 Rp 600.00 Rp 12,600.00
Textile tape rol 0.0240 Rp 17,500.00 Rp 420.00
Compound gypsum kg 1.0000 Rp 4,500.00 Rp 4,500.00
Amplas lbr 0.1000 Rp 3,400.00 Rp 340.00

Sub-Total ( 2 ) Rp 68,286.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 118,916.50

Analisa Harga Satuan Pekerjaan - 79


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Gypsum Board 9 mm + Rangka Metal Furing
Satuan Pembayaran : M2
Harga Satuan : Rp 151,629.17
AHSP-VII-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2600 Rp 70,000.00 Rp 18,200.00
Tukang gypsum OH 0.0500 Rp 90,000.00 Rp 4,500.00
Tukang Allumunium OH 0.2600 Rp 90,000.00 Rp 23,400.00
Kepala tukang OH 0.0310 Rp 100,000.00 Rp 3,100.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00

Sub-Total ( 1 ) Rp 50,630.00

2 Bahan
Paku peluru ramset bh 0.3900 Rp 1,750.00 Rp 682.50
Rangka Metal furing m' 4.0000 Rp 12,566.67 Rp 50,266.67
Kawat gantungan set 1.0000 Rp 3,000.00 Rp 3,000.00
Paku beton kg 0.0100 Rp 35,000.00 Rp 350.00
Sekrup 6x1-1,5 bh 14.0000 Rp 500.00 Rp 7,000.00
Gypsumboard 120x240 cm 9 mm lbr 0.3640 Rp 60,000.00 Rp 21,840.00
Sekrup gypsum bh 21.0000 Rp 600.00 Rp 12,600.00
Textile tape rol 0.0240 Rp 17,500.00 Rp 420.00
Compound gypsum kg 1.0000 Rp 4,500.00 Rp 4,500.00
Amplas lbr 0.1000 Rp 3,400.00 Rp 340.00

Sub-Total ( 2 ) Rp 100,999.17

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 151,629.17

Analisa Harga Satuan Pekerjaan - 80


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Gypsum Waterresisten + Rangka Hollow
Satuan Pembayaran : M2
Harga Satuan : Rp 135,296.50
AHSP-VII-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2600 Rp 70,000.00 Rp 18,200.00
Tukang gypsum OH 0.0500 Rp 90,000.00 Rp 4,500.00
Tukang Allumunium OH 0.2600 Rp 90,000.00 Rp 23,400.00
Kepala tukang OH 0.0310 Rp 100,000.00 Rp 3,100.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00

Sub-Total ( 1 ) Rp 50,630.00

2 Bahan
Paku peluru ramset bh 0.3900 Rp 1,750.00 Rp 682.50
Hollow 40x40 mm galvanized (tebal standart) btg 0.4590 Rp 26,000.00 Rp 11,934.00
Hollow 20x40 mm galvanized (tebal standart) btg 0.4310 Rp 20,000.00 Rp 8,620.00
Paku beton kg 0.0100 Rp 35,000.00 Rp 350.00
Sekrup 6x1-1,5 bh 14.0000 Rp 500.00 Rp 7,000.00
Gypsumboard Waterresisten 120x240 cm 9 mm lbr 0.3640 Rp 105,000.00 Rp 38,220.00
Sekrup gypsum bh 21.0000 Rp 600.00 Rp 12,600.00
Textile tape rol 0.0240 Rp 17,500.00 Rp 420.00
Compound gypsum kg 1.0000 Rp 4,500.00 Rp 4,500.00
Amplas lbr 0.1000 Rp 3,400.00 Rp 340.00

Sub-Total ( 2 ) Rp 84,666.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 135,296.50

Analisa Harga Satuan Pekerjaan - 81


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Gypsum Waterresisten + Rangka Metal Furing
Satuan Pembayaran : M2
Harga Satuan : Rp 168,009.17
AHSP-VII-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2600 Rp 70,000.00 Rp 18,200.00
Tukang gypsum OH 0.0500 Rp 90,000.00 Rp 4,500.00
Tukang Allumunium OH 0.2600 Rp 90,000.00 Rp 23,400.00
Kepala tukang OH 0.0310 Rp 100,000.00 Rp 3,100.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00

Sub-Total ( 1 ) Rp 50,630.00

2 Bahan
Paku peluru ramset bh 0.3900 Rp 1,750.00 Rp 682.50
Rangka Metal furing m' 4.0000 Rp 12,566.67 Rp 50,266.67
Kawat gantungan set 1.0000 Rp 3,000.00 Rp 3,000.00
Paku beton kg 0.0100 Rp 35,000.00 Rp 350.00
Sekrup 6x1-1,5 bh 14.0000 Rp 500.00 Rp 7,000.00
Gypsumboard Waterresisten 120x240 cm 9 mm lbr 0.3640 Rp 105,000.00 Rp 38,220.00
Sekrup gypsum bh 21.0000 Rp 600.00 Rp 12,600.00
Textile tape rol 0.0240 Rp 17,500.00 Rp 420.00
Compound gypsum kg 1.0000 Rp 4,500.00 Rp 4,500.00
Amplas lbr 0.1000 Rp 3,400.00 Rp 340.00

Sub-Total ( 2 ) Rp 117,379.17

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 168,009.17

Analisa Harga Satuan Pekerjaan - 82


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Kalsiboard 6 mm + Rangka Hollow
Satuan Pembayaran : M2
Harga Satuan : Rp 129,539.70
AHSP-VII-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2600 Rp 70,000.00 Rp 18,200.00
Tukang gypsum OH 0.0500 Rp 90,000.00 Rp 4,500.00
Tukang Allumunium OH 0.2600 Rp 90,000.00 Rp 23,400.00
Kepala tukang OH 0.0310 Rp 100,000.00 Rp 3,100.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00

Sub-Total ( 1 ) Rp 50,630.00

2 Bahan
Paku peluru ramset bh 0.3900 Rp 1,750.00 Rp 682.50
Hollow 40x40 mm galvanized (tebal standart) btg 0.4590 Rp 26,000.00 Rp 11,934.00
Hollow 20x40 mm galvanized (tebal standart) btg 0.4310 Rp 20,000.00 Rp 8,620.00
Paku beton kg 0.0100 Rp 35,000.00 Rp 350.00
Sekrup 6x1-1,5 bh 14.0000 Rp 500.00 Rp 7,000.00
Calsium Board 1200x2400x6 mm lbr 0.3640 Rp 101,300.00 Rp 36,873.20
Sekrup gypsum bh 21.0000 Rp 600.00 Rp 12,600.00
Textile tape rol 0.0240 Rp 17,500.00 Rp 420.00
Compound gypsum kg 0.0200 Rp 4,500.00 Rp 90.00
Amplas lbr 0.1000 Rp 3,400.00 Rp 340.00

Sub-Total ( 2 ) Rp 78,909.70

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 129,539.70

Analisa Harga Satuan Pekerjaan - 83


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Kalsiboard 6 mm + Rangka Metal Furing
Satuan Pembayaran : M2
Harga Satuan : Rp 162,252.37
AHSP-VII-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2600 Rp 70,000.00 Rp 18,200.00
Tukang gypsum OH 0.0500 Rp 90,000.00 Rp 4,500.00
Tukang Allumunium OH 0.2600 Rp 90,000.00 Rp 23,400.00
Kepala tukang OH 0.0310 Rp 100,000.00 Rp 3,100.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00

Sub-Total ( 1 ) Rp 50,630.00

2 Bahan
Paku peluru ramset bh 0.3900 Rp 1,750.00 Rp 682.50
Rangka Metal furing m' 4.0000 Rp 12,566.67 Rp 50,266.67
Kawat gantungan set 1.0000 Rp 3,000.00 Rp 3,000.00
Paku beton kg 0.0100 Rp 35,000.00 Rp 350.00
Sekrup 6x1-1,5 bh 14.0000 Rp 500.00 Rp 7,000.00
Calsium Board 1200x2400x6 mm lbr 0.3640 Rp 101,300.00 Rp 36,873.20
Sekrup gypsum bh 21.0000 Rp 600.00 Rp 12,600.00
Textile tape rol 0.0240 Rp 17,500.00 Rp 420.00
Compound gypsum kg 0.0200 Rp 4,500.00 Rp 90.00
Amplas lbr 0.1000 Rp 3,400.00 Rp 340.00

Sub-Total ( 2 ) Rp 111,622.37

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 162,252.37

Analisa Harga Satuan Pekerjaan - 84


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Gypsum Tile 60x120x9 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 132,987.50
AHSP-VII-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0750 Rp 70,000.00 Rp 5,250.00
Tukang gypsum OH 0.2500 Rp 90,000.00 Rp 22,500.00
Tukang Allumunium OH 0.2500 Rp 90,000.00 Rp 22,500.00
Kepala tukang OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 53,300.00

2 Bahan
Profil allumunium Main Tee (p. 3,6m) m' 3.60 Rp 9,305.56 Rp 33,500.00
Profil allumunium Cross Tee (p. 1,2 m) m' 1.20 Rp 8,333.33 Rp 10,000.00
Profil allumunium Cross Tee (p. 0,60 m) m' 0.60 Rp 8,500.00 Rp 5,100.00
Kawat diameter 4mm kg 0.15 Rp 20,000.00 Rp 3,000.00
Paku peluru ramset bh 1.05 Rp 1,750.00 Rp 1,837.50
Gypsum Tile 600x1200x9 mm lmbr 1.50 Rp 17,500.00 Rp 26,250.00

Sub-Total ( 2 ) Rp 79,687.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 132,987.50

Analisa Harga Satuan Pekerjaan - 85


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Gypsum Board Type Jayabelt 12 mm, rangka hollow
Satuan Pembayaran : M2
Harga Satuan : Rp 192,948.50
AHSP-VII-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2600 Rp 70,000.00 Rp 18,200.00
Tukang gypsum OH 0.0500 Rp 90,000.00 Rp 4,500.00
Tukang Allumunium OH 0.2600 Rp 90,000.00 Rp 23,400.00
Kepala tukang OH 0.0310 Rp 100,000.00 Rp 3,100.00
Mandor OH 0.0130 Rp 110,000.00 Rp 1,430.00
Sub-Total ( 1 ) Rp 50,630.00

2 Bahan
Paku peluru ramset bh 0.3900 Rp 1,750.00 Rp 682.50
Hollow 40x40 mm galvanized (tebal standart) btg 0.4590 Rp 26,000.00 Rp 11,934.00
Hollow 20x40 mm galvanized (tebal standart) btg 0.4310 Rp 20,000.00 Rp 8,620.00
Paku beton kg 0.0100 Rp 35,000.00 Rp 350.00
Sekrup 6x1-1,5 bh 14.0000 Rp 500.00 Rp 7,000.00
Gypsumboard Type Jaya Belt 120x240 cm, tebal 12 mm lbr 0.3640 Rp 275,500.00 Rp 100,282.00
Sekrup gypsum bh 21.0000 Rp 600.00 Rp 12,600.00
Textile tape rol 0.0240 Rp 17,500.00 Rp 420.00
Compound gypsum kg 0.0200 Rp 4,500.00 Rp 90.00
Amplas lbr 0.1000 Rp 3,400.00 Rp 340.00
Sub-Total ( 2 ) Rp 142,318.50

3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 192,948.50

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Acautic Tile 60x120x15 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 238,587.50 SNI 2839 (6.9) - 2008
AHSP-VII-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.5000 Rp 70,000.00 Rp 35,000.00
Tukang gypsum OH 0.5000 Rp 90,000.00 Rp 45,000.00
Kepala tukang OH 0.0500 Rp 100,000.00 Rp 5,000.00
Mandor OH 0.0250 Rp 110,000.00 Rp 2,750.00
Sub-Total ( 1 ) Rp 87,750.00

2 Bahan
Profil allumunium "Tee" m' 3.60 Rp 9,305.56 Rp 33,500.00
Kawat diameter 4mm kg 0.15 Rp 20,000.00 Rp 3,000.00
Paku peluru ramset bh 1.05 Rp 1,750.00 Rp 1,837.50
Acaustic Tile 600x1200x15 mm (Armstrong) lmbr 1.50 Rp 75,000.00 Rp 112,500.00
Sub-Total ( 2 ) Rp 150,837.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 238,587.50

Analisa Harga Satuan Pekerjaan - 86


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Acian Plafond Beton Expose, dengan Mortar
Satuan Pembayaran : M2
Harga Satuan : Rp 34,205.00
AHSP-VII-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1500 Rp 70,000.00 Rp 10,500.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0080 Rp 110,000.00 Rp 880.00

Sub-Total ( 1 ) Rp 21,380.00
2 Bahan
Acian plesteran / beton expose (MU 200) kg 3.0000 Rp 4,275.00 Rp 12,825.00

Sub-Total ( 2 ) Rp 12,825.00
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 34,205.00

Pekerjaan : PLAFOND
Jenis Pembayaran : List Allumunium, plafond
Satuan Pembayaran : M'
Harga Satuan : Rp 19,830.00
AHSP-VII-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1130 Rp 70,000.00 Rp 7,910.00
Tukang gypsum OH 0.0400 Rp 90,000.00 Rp 3,600.00
Kepala tukang OH 0.0040 Rp 100,000.00 Rp 400.00
Mandor OH 0.0070 Rp 110,000.00 Rp 770.00

Sub-Total ( 1 ) Rp 12,680.00

2 Bahan
Wall angle allumunium m' 1.1000 Rp 6,500.00 Rp 7,150.00

Sub-Total ( 2 ) Rp 7,150.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 19,830.00

Analisa Harga Satuan Pekerjaan - 87


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : List plafond, gypsum profil
Satuan Pembayaran : M'
Harga Satuan : Rp 23,805.00 SNI 2839 (6.8) - 2008
AHSP-VII-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0600 Rp 70,000.00 Rp 4,200.00
Tukang gypsum OH 0.0600 Rp 90,000.00 Rp 5,400.00
Kepala tukang OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 10,530.00

2 Bahan
List Frofil Gypsum Uk. Sedang m' 1.0500 Rp 12,000.00 Rp 12,600.00
Compound gypsum kg 0.1500 Rp 4,500.00 Rp 675.00

Sub-Total ( 2 ) Rp 13,275.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 23,805.00

Pekerjaan : PLAFOND
Jenis Pembayaran : List plafond, kayu profil
Satuan Pembayaran : M'
Harga Satuan : Rp 22,619.20 SNI 2839 (6.10) - 2008
AHSP-VII-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0500 Rp 70,000.00 Rp 3,500.00
Tukang kayu OH 0.0500 Rp 100,000.00 Rp 5,000.00
Kepala tukang OH 0.0050 Rp 100,000.00 Rp 500.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 9,330.00

2 Bahan
List kayu profil, ukuran Sedang m' 1.0500 Rp 12,500.00 Rp 13,125.00
Paku 4 - 5 cm kg 0.0100 Rp 16,420.00 Rp 164.20

Sub-Total ( 2 ) Rp 13,289.20

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 22,619.20

Analisa Harga Satuan Pekerjaan - 88


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Rangka Plafond (60x60 cm), kayu Kruing
Satuan Pembayaran : M2
Harga Satuan : Rp 159,372.56 SNI 3434 (6.20) - 2008
AHSP-VII-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang kayu OH 0.3000 Rp 100,000.00 Rp 30,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 48,100.00

2 Bahan
Kasau-kasau 5x7 cm, kayu Kruing m' 0.0163 Rp 6,591,875.00 Rp 107,447.56
Paku 7 - 10 cm kg 0.2500 Rp 15,300.00 Rp 3,825.00

Sub-Total ( 2 ) Rp 111,272.56

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 159,372.56

Pekerjaan : PLAFOND
Jenis Pembayaran : Rangka Plafond (60x60 cm), kayu Borneo/Meranti super
Satuan Pembayaran : M2
Harga Satuan : Rp 130,165.00 SNI 3434 (6.20) - 2008
AHSP-VII-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang kayu OH 0.3000 Rp 100,000.00 Rp 30,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 48,100.00

2 Bahan
Kasau-kasau 5x7 cm, kayu Kruing m' 0.0163 Rp 4,800,000.00 Rp 78,240.00
Paku 7 - 10 cm kg 0.2500 Rp 15,300.00 Rp 3,825.00

Sub-Total ( 2 ) Rp 82,065.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 130,165.00

Analisa Harga Satuan Pekerjaan - 89


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond (Langit2) Asbes 4 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 43,433.60 SNI 2839 (6.1) - 2008
AHSP-VII-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0300 Rp 70,000.00 Rp 2,100.00
Tukang kayu OH 0.0700 Rp 100,000.00 Rp 7,000.00
Kepala tukang OH 0.0070 Rp 100,000.00 Rp 700.00
Mandor OH 0.0040 Rp 110,000.00 Rp 440.00

Sub-Total ( 1 ) Rp 10,240.00

2 Bahan
Asbes plat 100x100x0,4 cm m' 1.1000 Rp 30,000.00 Rp 33,000.00
Paku triplek (paku halus) kg 0.0100 Rp 19,360.00 Rp 193.60

Sub-Total ( 2 ) Rp 33,193.60

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 43,433.60

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond (Langit2) Tripleks 4 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 39,556.10 SNI 2839 (6.5) - 2008
AHSP-VII-017
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Tukang kayu OH 0.1000 Rp 100,000.00 Rp 10,000.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 18,550.00

2 Bahan
Tripleks 4 mm (122x244 cm) m' 0.3750 Rp 55,500.00 Rp 20,812.50
Paku triplek (paku halus) kg 0.0100 Rp 19,360.00 Rp 193.60

Sub-Total ( 2 ) Rp 21,006.10

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 39,556.10

Analisa Harga Satuan Pekerjaan - 90


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Lambresering kayu Kamper, tebal 9 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 257,343.60 SNI 2839 (6.6) - 2008
AHSP-VII-018
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.8000 Rp 70,000.00 Rp 56,000.00
Tukang kayu OH 0.8000 Rp 100,000.00 Rp 80,000.00
Kepala tukang OH 0.0800 Rp 100,000.00 Rp 8,000.00
Mandor OH 0.0400 Rp 110,000.00 Rp 4,400.00

Sub-Total ( 1 ) Rp 148,400.00

2 Bahan
Papan kayu Kamper m' 0.0150 Rp 7,250,000.00 Rp 108,750.00
Paku triplek (paku halus) kg 0.0100 Rp 19,360.00 Rp 193.60

Sub-Total ( 2 ) Rp 108,943.60

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 257,343.60

Pekerjaan : PLAFOND
Jenis Pembayaran : Plafond Gypsum Board, tebal 9 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 39,290.00 SNI 2839 (6.7) - 2008
AHSP-VII-019
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Tukang kayu OH 0.0500 Rp 100,000.00 Rp 5,000.00
Kepala tukang OH 0.0050 Rp 100,000.00 Rp 500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 13,050.00

2 Bahan
Gypsum board 9 mm (120x240 cm) m' 0.3640 Rp 60,000.00 Rp 21,840.00
Paku skrup kg 0.1100 Rp 40,000.00 Rp 4,400.00

Sub-Total ( 2 ) Rp 26,240.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 39,290.00

Analisa Harga Satuan Pekerjaan - 91


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

VIII. PEKERJAAN : KOSEN, PINTU & JENDELA

Pekerjaan : KOSEN
Jenis Pembayaran : Profil Kosen Aluminium 4", Brown Anodized ex YKK
Satuan Pembayaran : M2
Harga Satuan : Rp 182,678.50 SNI 7393 (6.11) - 2008
AHSP-VIII-01A
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Profil kosen Allumunium 4", Brown Anodized ex YKK m' 1.1000 Rp 150,000.00 Rp 165,000.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 175,137.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 182,678.50

Pekerjaan : KOSEN
Jenis Pembayaran : Profil Kosen Aluminium 4", Brown Anodized ex Alexindo
Satuan Pembayaran : M2
Harga Satuan : Rp 100,178.50 SNI 7393 (6.11) - 2008
AHSP-VIII-01B
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Profil kosen Allumunium 4", Brown Anodized ex Alexindo m' 1.1000 Rp 75,000.00 Rp 82,500.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 92,637.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 100,178.50

Analisa Harga Satuan Pekerjaan - 92


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Profil Kosen Aluminium 3", Brown Anodized ex YKK
Satuan Pembayaran : M2
Harga Satuan : Rp 138,678.50 SNI 7393 (6.11) - 2008
AHSP-VIII-01C
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Profil kosen Allumunium 3", Brown Anodized ex YKK m' 1.1000 Rp 110,000.00 Rp 121,000.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 131,137.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 138,678.50

Pekerjaan : KOSEN
Jenis Pembayaran : Profil Kosen Aluminium 3", Brown Anodized ex Alexindo
Satuan Pembayaran : M2
Harga Satuan : Rp 94,678.50 SNI 7393 (6.11) - 2008
AHSP-VIII-01D
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Profil kosen Allumunium 3", Brown Anodized ex Alexindo m' 1.1000 Rp 70,000.00 Rp 77,000.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 87,137.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 94,678.50

Analisa Harga Satuan Pekerjaan - 93


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Frame Allumunium Pintu Kaca, Brown anodized ex YKK
Satuan Pembayaran : M2
Harga Satuan : Rp 171,678.50 SNI 7393 (6.11) - 2008
AHSP-VIII-02A
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Frame Allumunium Pintu kaca, Brown Anodized ex YKK m' 1.1000 Rp 140,000.00 Rp 154,000.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 164,137.50

3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 171,678.50

Pekerjaan : KOSEN
Jenis Pembayaran : Frame Allumunium Pintu Kaca, Brown anodized ex Alexindo
Satuan Pembayaran : M2
Harga Satuan : Rp 97,428.50 SNI 7393 (6.11) - 2008
AHSP-VIII-02B
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Frame Allumunium Pintu kaca, Brown Anodized ex Alexindo m' 1.1000 Rp 72,500.00 Rp 79,750.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 89,887.50

3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 97,428.50

Analisa Harga Satuan Pekerjaan - 94


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Frame Allumunium Jendela Kaca, Brown anodized ex YKK
Satuan Pembayaran : M2
Harga Satuan : Rp 127,678.50 SNI 7393 (6.11) - 2008
AHSP-VIII-03A
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Frame Allumunium Jendela kaca, Brown Anodized ex YKK m' 1.1000 Rp 100,000.00 Rp 110,000.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 120,137.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 127,678.50

Pekerjaan : KOSEN
Jenis Pembayaran : Frame Allumunium Jendela Kaca, Brown anodized ex Alexindo
Satuan Pembayaran : M2
Harga Satuan : Rp 86,428.50 SNI 7393 (6.11) - 2008
AHSP-VIII-03B
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Frame Allumunium Jendela kaca, Brown Anodized ex Alexindo m' 1.1000 Rp 62,500.00 Rp 68,750.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 78,887.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 86,428.50

Analisa Harga Satuan Pekerjaan - 95


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Profil Aluminium U Channel 30x20 mm, silver anodized
Satuan Pembayaran : M2
Harga Satuan : Rp 50,678.50
AHSP-VIII-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0430 Rp 70,000.00 Rp 3,010.00
Tukang Allumunium OH 0.0430 Rp 90,000.00 Rp 3,870.00
Kepala tukang OH 0.0043 Rp 100,000.00 Rp 430.00
Mandor OH 0.0021 Rp 110,000.00 Rp 231.00

Sub-Total ( 1 ) Rp 7,541.00

2 Bahan
Profil Aluminium U Channel 30x20 mm, silver anodized m' 1.1000 Rp 30,000.00 Rp 33,000.00
Skrup fixer bh 2.0000 Rp 600.00 Rp 1,200.00
Sealant m' 1.1000 Rp 8,125.00 Rp 8,937.50

Sub-Total ( 2 ) Rp 43,137.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 50,678.50

Pekerjaan : KOSEN
Jenis Pembayaran : Kosen kayu Jati Jawa Timur (kelas I)
Satuan Pembayaran : M3
Harga Satuan : Rp 63,387,000.00 SNI 3434 (6.1) - 2008
AHSP-VIII-05A
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 7.0000 Rp 70,000.00 Rp 490,000.00
Tukang Kayu OH 21.0000 Rp 100,000.00 Rp 2,100,000.00
Kepala tukang OH 2.1000 Rp 100,000.00 Rp 210,000.00
Mandor OH 0.3500 Rp 110,000.00 Rp 38,500.00

Sub-Total ( 1 ) Rp 2,838,500.00

2 Bahan
Balok Jati Jawa Timur, Kelas-I m' 1.1000 Rp 55,000,000.00 Rp 60,500,000.00
Paku 10 cm kg 1.2500 Rp 14,800.00 Rp 18,500.00
Lem Kayu kg 1.0000 Rp 30,000.00 Rp 30,000.00

Sub-Total ( 2 ) Rp 60,548,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 63,387,000.00

Analisa Harga Satuan Pekerjaan - 96


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kosen kayu Kamper Samarinda oven (kelas II)
Satuan Pembayaran : M3
Harga Satuan : Rp 14,190,500.00 SNI 3434 (6.2) - 2008
AHSP-VIII-05B
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 6.0000 Rp 70,000.00 Rp 420,000.00
Tukang Kayu OH 18.0000 Rp 100,000.00 Rp 1,800,000.00
Kepala tukang OH 1.8000 Rp 100,000.00 Rp 180,000.00
Mandor OH 0.3000 Rp 110,000.00 Rp 33,000.00

Sub-Total ( 1 ) Rp 2,433,000.00

2 Bahan
Kayu Balok Kamper Samarinda oven m' 1.2000 Rp 9,757,500.00 Rp 11,709,000.00
Paku 10 cm kg 1.2500 Rp 14,800.00 Rp 18,500.00
Lem Kayu kg 1.0000 Rp 30,000.00 Rp 30,000.00

Sub-Total ( 2 ) Rp 11,757,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 14,190,500.00

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos tebal 6 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 182,743.00
AHSP-VIII-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0165 Rp 70,000.00 Rp 1,155.00
Tukang kayu OH 0.1650 Rp 100,000.00 Rp 16,500.00
Kepala tukang OH 0.0165 Rp 100,000.00 Rp 1,650.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00

Sub-Total ( 1 ) Rp 19,393.00

2 Bahan
Kaca polos 6 mm, ex Asahimas m2 1.1000 Rp 148,500.00 Rp 163,350.00

Sub-Total ( 2 ) Rp 163,350.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 182,743.00

Analisa Harga Satuan Pekerjaan - 97


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos tebal 8 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 231,143.00
AHSP-VIII-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0165 Rp 70,000.00 Rp 1,155.00
Tukang kayu OH 0.1650 Rp 100,000.00 Rp 16,500.00
Kepala tukang OH 0.0165 Rp 100,000.00 Rp 1,650.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00

Sub-Total ( 1 ) Rp 19,393.00

2 Bahan
Kaca polos 8 mm, ex Asahimas m2 1.1000 Rp 192,500.00 Rp 211,750.00

Sub-Total ( 2 ) Rp 211,750.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 231,143.00

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos tebal 10 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 341,286.00
AHSP-VIII-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca polos 10 mm, ex Asahimas m2 1.1000 Rp 275,000.00 Rp 302,500.00

Sub-Total ( 2 ) Rp 302,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 341,286.00

Analisa Harga Satuan Pekerjaan - 98


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos tebal 12 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 401,786.00
AHSP-VIII-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca polos 12 mm, ex Asahimas m2 1.1000 Rp 330,000.00 Rp 363,000.00

Sub-Total ( 2 ) Rp 363,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 401,786.00

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos Tempered tebal 6 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 292,633.00
AHSP-VIII-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0165 Rp 70,000.00 Rp 1,155.00
Tukang kayu OH 0.1650 Rp 100,000.00 Rp 16,500.00
Kepala tukang OH 0.0165 Rp 100,000.00 Rp 1,650.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00

Sub-Total ( 1 ) Rp 19,393.00

2 Bahan
Kaca polos Tempered 6 mm, ex Asahimas m2 1.1000 Rp 248,400.00 Rp 273,240.00

Sub-Total ( 2 ) Rp 273,240.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 292,633.00

Analisa Harga Satuan Pekerjaan - 99


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos Tempered tebal 8 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 414,073.00
AHSP-VIII-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0165 Rp 70,000.00 Rp 1,155.00
Tukang kayu OH 0.1650 Rp 100,000.00 Rp 16,500.00
Kepala tukang OH 0.0165 Rp 100,000.00 Rp 1,650.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00

Sub-Total ( 1 ) Rp 19,393.00

2 Bahan
Kaca polos Tempered 8 mm, ex Asahimas m2 1.1000 Rp 358,800.00 Rp 394,680.00

Sub-Total ( 2 ) Rp 394,680.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 414,073.00

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos Tempered tebal 10 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 539,726.00
AHSP-VIII-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca polos Tempered 10 mm, ex Asahimas m2 1.1000 Rp 455,400.00 Rp 500,940.00

Sub-Total ( 2 ) Rp 500,940.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 539,726.00

Analisa Harga Satuan Pekerjaan - 100


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos Tempered tebal 12 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 608,036.00
AHSP-VIII-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca polos Tempered 12 mm, ex Asahimas m2 1.1000 Rp 517,500.00 Rp 569,250.00

Sub-Total ( 2 ) Rp 569,250.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 608,036.00

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Polos Tempered tebal 12 mm, ex Asahimas (khusus pintu)
Satuan Pembayaran : M2
Harga Satuan : Rp 867,476.50
AHSP-VIII-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca polos Tempered 12 mm, ex Asahimas m2 1.1000 Rp 517,500.00 Rp 569,250.00
Pembuatan Lubang bh 2.0000 Rp 17,600.00 Rp 35,200.00
Gosok pinggir ml 2.8900 Rp 21,450.00 Rp 61,990.50
Coak Tepi bh 1.0000 Rp 66,550.00 Rp 66,550.00
Coak Pojok bh 2.0000 Rp 47,850.00 Rp 95,700.00

Sub-Total ( 2 ) Rp 828,690.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 867,476.50

Analisa Harga Satuan Pekerjaan - 101


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Stopsol tebal 6 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 514,393.00
AHSP-VIII-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0165 Rp 70,000.00 Rp 1,155.00
Tukang kayu OH 0.1650 Rp 100,000.00 Rp 16,500.00
Kepala tukang OH 0.0165 Rp 100,000.00 Rp 1,650.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00

Sub-Total ( 1 ) Rp 19,393.00

2 Bahan
Kaca Stopsol tebal 6 mm, ex Asahimas m2 1.1000 Rp 450,000.00 Rp 495,000.00

Sub-Total ( 2 ) Rp 495,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 514,393.00

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Stopsol tebal 8 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 651,893.00
AHSP-VIII-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0165 Rp 70,000.00 Rp 1,155.00
Tukang kayu OH 0.1650 Rp 100,000.00 Rp 16,500.00
Kepala tukang OH 0.0165 Rp 100,000.00 Rp 1,650.00
Mandor OH 0.0008 Rp 110,000.00 Rp 88.00

Sub-Total ( 1 ) Rp 19,393.00

2 Bahan
Kaca Stopsol tebal 8 mm, ex Asahimas m2 1.1000 Rp 575,000.00 Rp 632,500.00

Sub-Total ( 2 ) Rp 632,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 651,893.00

Analisa Harga Satuan Pekerjaan - 102


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Stopsol tebal 10 mm, ex Asahimas
Satuan Pembayaran : M2
Harga Satuan : Rp 1,056,286.00
AHSP-VIII-017
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca Stopsol tebal 10 mm, ex Asahimas m2 1.1000 Rp 925,000.00 Rp 1,017,500.00

Sub-Total ( 2 ) Rp 1,017,500.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,056,286.00

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Laminated 6 mm, (Kaca+PVB+Kaca)
Satuan Pembayaran : M2
Harga Satuan : Rp 557,436.00
AHSP-VIII-018
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca polos laminated (tebal 6mm+0,38+6 mm) m2 1.1000 Rp 471,500.00 Rp 518,650.00

Sub-Total ( 2 ) Rp 518,650.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 557,436.00

Analisa Harga Satuan Pekerjaan - 103


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Kaca Laminated 8 mm, (Kaca+PVB+Kaca)
Satuan Pembayaran : M2
Harga Satuan : Rp 898,986.00
AHSP-VIII-019
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0330 Rp 70,000.00 Rp 2,310.00
Tukang kayu OH 0.3300 Rp 100,000.00 Rp 33,000.00
Kepala tukang OH 0.0330 Rp 100,000.00 Rp 3,300.00
Mandor OH 0.0016 Rp 110,000.00 Rp 176.00

Sub-Total ( 1 ) Rp 38,786.00

2 Bahan
Kaca polos laminated (tebal 8mm+0,76+8 mm) m2 1.1000 Rp 782,000.00 Rp 860,200.00

Sub-Total ( 2 ) Rp 860,200.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 898,986.00

Pekerjaan : KOSEN
Jenis Pembayaran : Pintu Double Triplek 6 mm lapis HPL, rgk. Kamper
Satuan Pembayaran : M2
Harga Satuan : Rp 746,108.00 SNI 3434 (6.9) - 2008
AHSP-VIII-020
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.8000 Rp 70,000.00 Rp 56,000.00
Tukang kayu OH 2.4000 Rp 100,000.00 Rp 240,000.00
Kepala tukang OH 0.2400 Rp 100,000.00 Rp 24,000.00
Mandor OH 0.0400 Rp 110,000.00 Rp 4,400.00

Sub-Total ( 1 ) Rp 324,400.00

2 Bahan
Papan Kamper samarinda oven M3 0.0256 Rp 10,307,500.00 Rp 263,872.00
Multiplex 122x244x6 mm Lmbr 0.7000 Rp 77,000.00 Rp 53,900.00
HPL Lmbr 0.7000 Rp 135,000.00 Rp 94,500.00
Paku halus Kg 0.1000 Rp 19,360.00 Rp 1,936.00
Lem Kayu Kg 0.2500 Rp 30,000.00 Rp 7,500.00

Sub-Total ( 2 ) Rp 421,708.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 746,108.00

Analisa Harga Satuan Pekerjaan - 104


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Pintu Double Triplek 6 mm lapis HPL & Formika, rgk. Kamper
Satuan Pembayaran : M2
Harga Satuan : Rp 728,608.00 SNI 3434 (6.9) - 2008
AHSP-VIII-021
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.8000 Rp 70,000.00 Rp 56,000.00
Tukang kayu OH 2.4000 Rp 100,000.00 Rp 240,000.00
Kepala tukang OH 0.2400 Rp 100,000.00 Rp 24,000.00
Mandor OH 0.0400 Rp 110,000.00 Rp 4,400.00

Sub-Total ( 1 ) Rp 324,400.00

2 Bahan
Papan Kamper samarinda oven M3 0.0256 Rp 10,307,500.00 Rp 263,872.00
Multiplex 122x244x6 mm Lmbr 0.7000 Rp 77,000.00 Rp 53,900.00
HPL Lmbr 0.3500 Rp 135,000.00 Rp 47,250.00
Formika Lmbr 0.3500 Rp 85,000.00 Rp 29,750.00
Paku halus Kg 0.1000 Rp 19,360.00 Rp 1,936.00
Lem Kayu Kg 0.2500 Rp 30,000.00 Rp 7,500.00

Sub-Total ( 2 ) Rp 404,208.00
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 728,608.00

Pekerjaan : KOSEN
Jenis Pembayaran : Pintu Double Teakwood, rangka Kamper
Satuan Pembayaran : M2
Harga Satuan : Rp 635,133.30 SNI 3434 (6.8) - 2008
AHSP-VIII-022
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.7000 Rp 70,000.00 Rp 49,000.00
Tukang kayu OH 2.1000 Rp 100,000.00 Rp 210,000.00
Kepala tukang OH 0.2100 Rp 100,000.00 Rp 21,000.00
Mandor OH 0.0350 Rp 110,000.00 Rp 3,850.00

Sub-Total ( 1 ) Rp 283,850.00

2 Bahan
Papan Kamper samarinda oven M3 0.0250 Rp 10,307,500.00 Rp 257,687.50
Teakwood 122x244x4 mm Lmbr 0.7000 Rp 111,450.00 Rp 78,015.00
Paku halus Kg 0.0300 Rp 19,360.00 Rp 580.80
Lem Kayu Kg 0.5000 Rp 30,000.00 Rp 15,000.00

Sub-Total ( 2 ) Rp 351,283.30

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 635,133.30

Analisa Harga Satuan Pekerjaan - 105


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Pintu Panel solid, kayu Kamper Samarinda oven
Satuan Pembayaran : M2
Harga Satuan : Rp 819,300.00 SNI 3434 (6.5) - 2008
AHSP-VIII-023
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Tukang kayu OH 3.0000 Rp 100,000.00 Rp 300,000.00
Kepala tukang OH 0.3000 Rp 100,000.00 Rp 30,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 405,500.00

2 Bahan
Papan Kamper samarinda oven M3 0.0400 Rp 10,307,500.00 Rp 412,300.00
Lem Kayu Kg 0.0500 Rp 30,000.00 Rp 1,500.00

Sub-Total ( 2 ) Rp 413,800.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 819,300.00

Pekerjaan : KOSEN
Jenis Pembayaran : Pintu / Jendela kaca, kayu Kamper Samarinda oven
Satuan Pembayaran : M2
Harga Satuan : Rp 559,180.00 SNI 3434 (6.6) - 2008
AHSP-VIII-024
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.8000 Rp 70,000.00 Rp 56,000.00
Tukang kayu OH 2.4000 Rp 100,000.00 Rp 240,000.00
Kepala tukang OH 0.0240 Rp 100,000.00 Rp 2,400.00
Mandor OH 0.0400 Rp 110,000.00 Rp 4,400.00

Sub-Total ( 1 ) Rp 302,800.00

2 Bahan
Papan Kamper samarinda oven M3 0.0240 Rp 10,307,500.00 Rp 247,380.00
Lem Kayu Kg 0.3000 Rp 30,000.00 Rp 9,000.00

Sub-Total ( 2 ) Rp 256,380.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 559,180.00

Analisa Harga Satuan Pekerjaan - 106


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : KOSEN
Jenis Pembayaran : Pintu / Jendela Krepyak, kayu Kamper Samarinda oven
Satuan Pembayaran : M2
Harga Satuan : Rp 1,080,180.00 SNI 3434 (6.7) - 2008
AHSP-VIII-025
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Tukang kayu OH 3.0000 Rp 100,000.00 Rp 300,000.00
Kepala tukang OH 0.3000 Rp 100,000.00 Rp 30,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 405,500.00

2 Bahan
Papan Kamper samarinda oven M3 0.0640 Rp 10,307,500.00 Rp 659,680.00
Lem Kayu Kg 0.5000 Rp 30,000.00 Rp 15,000.00

Sub-Total ( 2 ) Rp 674,680.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,080,180.00

Pekerjaan : KOSEN
Jenis Pembayaran : Papan Jalusi Kosen, kayu Kamper Samarinda oven
Satuan Pembayaran : M2
Harga Satuan : Rp 925,104.00 SNI 3434 (6.10) - 2008
AHSP-VIII-026
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.6700 Rp 70,000.00 Rp 46,900.00
Tukang kayu OH 2.0000 Rp 100,000.00 Rp 200,000.00
Kepala tukang OH 0.2000 Rp 100,000.00 Rp 20,000.00
Mandor OH 0.3350 Rp 110,000.00 Rp 36,850.00

Sub-Total ( 1 ) Rp 303,750.00

2 Bahan
Papan 2/12, Kamper Samarinda oven M3 0.0600 Rp 10,307,500.00 Rp 618,450.00
Paku halus Kg 0.1500 Rp 19,360.00 Rp 2,904.00

Sub-Total ( 2 ) Rp 621,354.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 925,104.00

Analisa Harga Satuan Pekerjaan - 107


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

IX. PEKERJAAN : PARTISI

Pekerjaan : PARTISI
Jenis Pembayaran : Partisi Double Gypsum 12 mm, Rangka Metal Furing
Satuan Pembayaran : M2
Harga Satuan : Rp 207,075.00
AHSP-IX-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Tukang Allumunium OH 0.2000 Rp 90,000.00 Rp 18,000.00
Tukang gypsum OH 0.3000 Rp 90,000.00 Rp 27,000.00
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00
Sub-Total ( 1 ) Rp 60,650.00
2 Bahan
Metal Furing 75 mm btg 1.2500 Rp 37,700.00 Rp 47,125.00
Paku rivet bh 8.0000 Rp 250.00 Rp 2,000.00
Sekrup 6x1-1,5 bh 8.0000 Rp 500.00 Rp 4,000.00
Gypsumboard 120x240 cm 12 mm lbr 0.7000 Rp 76,000.00 Rp 53,200.00
Textile tape roll 0.2400 Rp 17,500.00 Rp 4,200.00
Compound gypsum kg 6.0000 Rp 4,500.00 Rp 27,000.00
Sekrup gypsum bh 24.0000 Rp 300.00 Rp 7,200.00
Amplas lbr 0.5000 Rp 3,400.00 Rp 1,700.00
Sub-Total ( 2 ) Rp 146,425.00
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 207,075.00

Pekerjaan : PARTISI
Jenis Pembayaran : Partisi Double Gypsum 12 mm, Rangka Hollow
Satuan Pembayaran : M2
Harga Satuan : Rp 192,450.00
AHSP-IX-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Tukang Allumunium OH 0.2000 Rp 90,000.00 Rp 18,000.00
Tukang gypsum OH 0.3000 Rp 90,000.00 Rp 27,000.00
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00
Sub-Total ( 1 ) Rp 60,650.00
2 Bahan
Hollow 40x40 mm galvanized (tebal standart) btg 1.2500 Rp 26,000.00 Rp 32,500.00
Paku rivet bh 8.0000 Rp 250.00 Rp 2,000.00
Sekrup 6x1-1,5 bh 8.0000 Rp 500.00 Rp 4,000.00
Gypsumboard 120x240 cm 12 mm lbr 0.7000 Rp 76,000.00 Rp 53,200.00
Textile tape roll 0.2400 Rp 17,500.00 Rp 4,200.00
Compound gypsum kg 6.0000 Rp 4,500.00 Rp 27,000.00
Sekrup gypsum bh 24.0000 Rp 300.00 Rp 7,200.00
Amplas lbr 0.5000 Rp 3,400.00 Rp 1,700.00
Sub-Total ( 2 ) Rp 131,800.00
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 192,450.00

Analisa Harga Satuan Pekerjaan - 108


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PARTISI
Jenis Pembayaran : Partisi Single Gypsum 12 mm, Rangka Metal Furing
Satuan Pembayaran : M2
Harga Satuan : Rp 147,375.00
AHSP-IX-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Tukang Allumunium OH 0.2000 Rp 90,000.00 Rp 18,000.00
Tukang gypsum OH 0.2000 Rp 90,000.00 Rp 18,000.00
Pekerja OH 0.1500 Rp 70,000.00 Rp 10,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00
Sub-Total ( 1 ) Rp 47,600.00
2 Bahan
Metal Furing 75 mm btg 1.2500 Rp 37,700.00 Rp 47,125.00
Paku rivet bh 8.0000 Rp 250.00 Rp 2,000.00
Sekrup 6x1-1,5 bh 8.0000 Rp 500.00 Rp 4,000.00
Gypsumboard 120x240 cm 12 mm lbr 0.3500 Rp 76,000.00 Rp 26,600.00
Textile tape roll 0.1200 Rp 17,500.00 Rp 2,100.00
Compound gypsum kg 3.0000 Rp 4,500.00 Rp 13,500.00
Sekrup gypsum bh 12.0000 Rp 300.00 Rp 3,600.00
Amplas lbr 0.2500 Rp 3,400.00 Rp 850.00
Sub-Total ( 2 ) Rp 99,775.00
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 147,375.00

Pekerjaan : PARTISI
Jenis Pembayaran : Partisi Single Gypsum 12 mm, Rangka Hollow
Satuan Pembayaran : M2
Harga Satuan : Rp 132,750.00
AHSP-IX-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Tukang Allumunium OH 0.2000 Rp 90,000.00 Rp 18,000.00
Tukang gypsum OH 0.2000 Rp 90,000.00 Rp 18,000.00
Pekerja OH 0.1500 Rp 70,000.00 Rp 10,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 47,600.00
2 Bahan
Hollow 40x40 mm galvanized (tebal standart) btg 1.2500 Rp 26,000.00 Rp 32,500.00
Paku rivet bh 8.0000 Rp 250.00 Rp 2,000.00
Sekrup 6x1-1,5 bh 8.0000 Rp 500.00 Rp 4,000.00
Gypsumboard 120x240 cm 12 mm lbr 0.3500 Rp 76,000.00 Rp 26,600.00
Textile tape roll 0.1200 Rp 17,500.00 Rp 2,100.00
Compound gypsum kg 3.0000 Rp 4,500.00 Rp 13,500.00
Sekrup gypsum bh 12.0000 Rp 300.00 Rp 3,600.00
Amplas lbr 0.2500 Rp 3,400.00 Rp 850.00

Sub-Total ( 2 ) Rp 85,150.00
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 132,750.00

Analisa Harga Satuan Pekerjaan - 109


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PARTISI
Jenis Pembayaran : Partisi Single Multiplex 12 mm, Rangka Metal Furing
finish lapis HPL
Satuan Pembayaran : M2
Harga Satuan : Rp 218,201.00
AHSP-IX-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Tukang Allumunium OH 0.2000 Rp 90,000.00 Rp 18,000.00
Tukang gypsum OH 0.2000 Rp 90,000.00 Rp 18,000.00
Pekerja OH 0.1500 Rp 70,000.00 Rp 10,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 47,600.00
2 Bahan
Metal Furing 75 mm btg 1.2500 Rp 37,700.00 Rp 47,125.00
Paku rivet bh 8.0000 Rp 250.00 Rp 2,000.00
Sekrup 6x1-1,5 bh 8.0000 Rp 500.00 Rp 4,000.00
Multiplex 120x240 cm 12 mm lbr 0.3500 Rp 155,360.00 Rp 54,376.00
HPL lbr 0.3500 Rp 135,000.00 Rp 47,250.00
Lem kayu kg 0.5000 Rp 30,000.00 Rp 15,000.00
Amplas lbr 0.2500 Rp 3,400.00 Rp 850.00

Sub-Total ( 2 ) Rp 170,601.00
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 218,201.00

Pekerjaan : PARTISI
Jenis Pembayaran : Dinding Partisi Cubical, Toilet (CB-1)
Satuan Pembayaran : Unit
Harga Satuan : Rp 8,607,850.00
AHSP-IX-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga

Sub-Total ( 1 ) Rp -
2 Bahan
- Frontal & Devider panel, Plywood Lumberkoll 18 mm water m2 4.87 Rp 725,000.00 Rp 3,527,850.00
resistance finish HPL laminated, dengan frame allumunium.
- Door Panel Plywood Lumberkoll 18 mm ukuran 600mm x2000 mm, m2 2.40 Rp 1,700,000.00 Rp 4,080,000.00
water resistance finish HPL laminated, dengan frame allumunium,
lengkap termasuk Door Accessories stainless Steel.
- Pedestal Stainless steel 10 cm bh 4.00 Rp 250,000.00 Rp 1,000,000.00

Sub-Total ( 2 ) Rp 8,607,850.00
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 8,607,850.00

Analisa Harga Satuan Pekerjaan - 110


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

X. PEKERJAAN : BESI

Pekerjaan : BESI
Jenis Pembayaran : Grill / Tralis Allumunium hollow 20x40 mm
(Modul 1,2 x 0,72 = 0,86 M2)
Satuan Pembayaran : M2
Harga Satuan : Rp 327,600.00
AHSP-X-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Upah kerja lot 1.0000 Rp 65,016.00 Rp 65,016.00

Sub-Total ( 1 ) Rp 65,016.00

2 Bahan
Allumunium hollow 40x20 mm m' 8.6688 Rp 25,000.00 Rp 216,720.00

Sub-Total ( 2 ) Rp 216,720.00

3 Peralatan

Sub-Total ( 3 ) Rp -

A. T O T A L ( 1 + 2 + 3) Rp 281,736.00
B. HARGA SATUAN PEKERJAAN / M2 Rp 327,600.00

Pekerjaan : BESI
Jenis Pembayaran : Grill / Tralis Lovre Allumunium
(Modul 1 x 4,60 = 4,6 M2)
Satuan Pembayaran : M2
Harga Satuan : Rp 357,500.00
AHSP-X-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Upah kerja lot 1.0000 Rp 379,500.00 Rp 379,500.00

Sub-Total ( 1 ) Rp 379,500.00

2 Bahan
Allumunium louvre m' 46.00 Rp 27,500.00 Rp 1,265,000.00

Sub-Total ( 2 ) Rp 1,265,000.00

3 Peralatan

Sub-Total ( 3 ) Rp -

A. T O T A L ( 1 + 2 + 3) Rp 1,644,500.00
B. HARGA SATUAN PEKERJAAN / M2 Rp 357,500.00

Analisa Harga Satuan Pekerjaan - 111


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BESI
Jenis Pembayaran : Tralis besi hollow 20x40 frame holoow 40x60 mm
(modul 7.5x0.90 = 6,75 m2)
Satuan Pembayaran : M2
Harga Satuan : Rp 659,094.10
AHSP-X-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Upah kerja lot 1.0000 Rp 1,153,414.67 Rp 1,153,414.67

Sub-Total ( 1 ) Rp 1,153,414.67

2 Bahan
- Frame besi hollow 60x40x2 mm m' 15.00 42,456.92 Rp 636,853.75
- Tralis besi hollow 20x40x1,8 mm m' 68.00 29,250.00 Rp 1,989,000.00
- Finishing pengecatan m2 13.55 49,418.21 Rp 669,616.75

Sub-Total ( 2 ) Rp 3,295,470.50

3 Peralatan

Sub-Total ( 3 ) Rp -

A. T O T A L ( 1 + 2 + 3) Rp 4,448,885.17
B. HARGA SATUAN PEKERJAAN / M2 Rp 659,094.10

Pekerjaan : BESI
Jenis Pembayaran : Tralis louvre besi, rangka hollow 50x100 mm
Modul : 4,20 x 0,60 m = 2,52 m2
Satuan Pembayaran : M2
Harga Satuan : Rp 716,249.86
AHSP-X-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Upah kerja lot 1.0000 Rp 467,949.91 Rp 467,949.91

Sub-Total ( 1 ) Rp 467,949.91

2 Bahan
- Frame besi hollow 50x100 m' 12.00 45,500.00 Rp 546,000.00
- Grill besi plat tebal 2 mm m2 2.52 167,987.40 Rp 423,328.25
- Finishing pengecatan m2 7.44 49,418.21 Rp 367,671.48

Sub-Total ( 2 ) Rp 1,336,999.73

3 Peralatan

Sub-Total ( 3 ) Rp -

A. T O T A L ( 1 + 2 + 3) Rp 1,804,949.64
B. HARGA SATUAN PEKERJAAN / M2 Rp 716,249.86

Analisa Harga Satuan Pekerjaan - 112


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : BESI
Jenis Pembayaran : Baja Profil WF
Satuan Pembayaran : Kg
Harga Satuan : Rp 21,167.50 SNI 7393 (6.2) - 2008
AHSP-X-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0600 Rp 70,000.00 Rp 4,200.00
Tukang besi OH 0.0600 Rp 90,000.00 Rp 5,400.00
Kepala tukang OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 10,530.00

2 Bahan
Baja Profil WF Kg 1.1500 9,250.00 Rp 10,637.50

Sub-Total ( 2 ) Rp 10,637.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 21,167.50

Pekerjaan : BESI
Jenis Pembayaran : Railling Tangga Besi (Black Steel)
Satuan Pembayaran : M'
Harga Satuan : Rp 726,050.00
AHSP-X-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.8000 Rp 70,000.00 Rp 56,000.00
Tukang besi OH 0.8000 Rp 90,000.00 Rp 72,000.00
Kepala tukang OH 0.0800 Rp 100,000.00 Rp 8,000.00
Mandor OH 0.0800 Rp 110,000.00 Rp 8,800.00

Sub-Total ( 1 ) Rp 144,800.00

2 Bahan
- Railling besi bahan pipa besi hitam dia. 2" (hand rail) m' 1.0000 141,667 Rp 141,666.67
- Railling besi bahan pipa besi hitam dia. 1,5" (tiang) m' 1.0000 108,333 Rp 108,333.33
- Railling besi bahan pipa besi hitam dia. 1" (pembagi) m' 3.0000 62,500 Rp 187,500.00
- Base plate + baut angkur bh 4.0000 25,000.00 Rp 100,000.00
- Finishing pengecatan lot 1.0000 43,750.00 Rp 43,750.00

Sub-Total ( 2 ) Rp 581,250.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 726,050.00

Analisa Harga Satuan Pekerjaan - 113


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

XI. PEKERJAAN : ATAP

Pekerjaan : ATAP
Jenis Pembayaran : Atap Gelombang Galvalume, Spandek Lysaght, 0,75 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 212,472.50
AHSP-XI-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0800 Rp 70,000.00 Rp 5,600.00
Tukang besi OH 0.0800 Rp 90,000.00 Rp 7,200.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 14,900.00

2 Bahan
Atap Gelombang GALVALUME, SPANDEK LYSAGHT, tbl 0,75 mm m2 1.0500 Rp 186,450.00 Rp 195,772.50
Skrup + ring Bh 4.0000 Rp 450.00 Rp 1,800.00

Sub-Total ( 2 ) Rp 197,572.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 212,472.50

Pekerjaan : ATAP
Jenis Pembayaran : Atap Gelombang Galvalume, Spandek Lysaght 0,50 mm
Satuan Pembayaran : M2
Harga Satuan : Rp 150,680.00
AHSP-XI-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0800 Rp 70,000.00 Rp 5,600.00
Tukang besi OH 0.0800 Rp 90,000.00 Rp 7,200.00
Kepala tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 14,900.00

2 Bahan
Atap Gelombang GALVALUME, SPANDEK LYSAGHT, tbl 0,50 mm m2 1.0500 Rp 127,600.00 Rp 133,980.00
Skrup + ring Bh 4.0000 Rp 450.00 Rp 1,800.00

Sub-Total ( 2 ) Rp 135,780.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 150,680.00

Analisa Harga Satuan Pekerjaan - 114


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Listplank Galvalume Plate 0,75 mm, lebar 1,60 cm
Satuan Pembayaran : M'
Harga Satuan : Rp 151,170.00
AHSP-XI-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1500 Rp 70,000.00 Rp 10,500.00
Tukang besi OH 0.2500 Rp 90,000.00 Rp 22,500.00
Kepala tukang OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 36,600.00

2 Bahan
Galvalume Plate 0,75 mm, lebar 1,60 cm m2 0.8000 139,837.50 Rp 111,870.00
Skrup + ring Bh 6.0000 450.00 Rp 2,700.00

Sub-Total ( 2 ) Rp 114,570.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 151,170.00

Pekerjaan : ATAP
Jenis Pembayaran : Flashing (Talang datar) Galvalume plate 0,75 mm
Satuan Pembayaran : M'
Harga Satuan : Rp 100,318.75
AHSP-XI-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Tukang besi OH 0.2000 Rp 90,000.00 Rp 18,000.00
Kepala tukang OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 28,600.00

2 Bahan
Galvalume Plate 0,75 mm, lebar 0,60 cm m2 0.5000 139,837.50 Rp 69,918.75
Skrup + ring Bh 4.0000 450.00 Rp 1,800.00

Sub-Total ( 2 ) Rp 71,718.75

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 100,318.75

Analisa Harga Satuan Pekerjaan - 115


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Talang tegak PVC 3" class AW
Satuan Pembayaran : M'
Harga Satuan : Rp 82,700.00
AHSP-XI-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1250 Rp 70,000.00 Rp 8,750.00
Tukang kayu OH 0.2500 Rp 90,000.00 Rp 22,500.00
Kepala tukang OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 34,300.00

2 Bahan
Pipa PVC 3" AW m' 1.1000 Rp 40,000.00 Rp 44,000.00

Sub-Total ( 2 ) Rp 44,000.00

3 Peralatan
Alat bantu lot 1.0000 4,400.00 Rp 4,400.00

Sub-Total ( 3 ) Rp 4,400.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 82,700.00

Pekerjaan : ATAP
Jenis Pembayaran : Lisplank GRC Board lebar 30 cm, rangka hollow
Satuan Pembayaran : M'
Harga Satuan : Rp 68,955.00
AHSP-XI-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja Oh 0.0600 Rp 70,000.00 Rp 4,200.00
Tukang kayu Oh 0.0900 Rp 90,000.00 Rp 8,100.00
Tukang alumunium Oh 0.0600 Rp 100,000.00 Rp 6,000.00
Mandor Oh 0.0045 Rp 110,000.00 Rp 495.00

Sub-Total ( 1 ) Rp 18,795.00
2 Bahan
Hollow 4x4 cm tbl 0.4 mm meni btg 0.3750 Rp 24,000.00 Rp 9,000.00
Hollow 2x4 cm tbl 0.35 mm btg 0.2400 Rp 18,000.00 Rp 4,320.00
Paku rivet bh 1.2000 Rp 250.00 Rp 300.00
Sekrup 6x1-1,5 bh 2.4000 Rp 500.00 Rp 1,200.00
GRC Board tebal 10 mm lbr 0.2250 Rp 130,000.00 Rp 29,250.00
Textile tape roll 0.0720 Rp 17,500.00 Rp 1,260.00
Compound GRC Kg 0.0360 Rp 60,000.00 Rp 2,160.00
Sekrup gypsum bh 7.2000 Rp 300.00 Rp 2,160.00
Amplas lbr 0.1500 Rp 3,400.00 Rp 510.00

Sub-Total ( 2 ) Rp 50,160.00
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 68,955.00

Analisa Harga Satuan Pekerjaan - 116


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Scred Lantai 1 PC : 3 PS + Waterprofing membrane
Satuan Pembayaran : M2
Harga Satuan : Rp 154,958.38
AHSP-XI-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang Batu OH 0.1500 Rp 90,000.00 Rp 13,500.00
Kep. Tukang Batu OH 0.0150 Rp 100,000.00 Rp 1,500.00
Tukang Waterprrofing OH 0.1500 Rp 90,000.00 Rp 13,500.00
Mandor OH 0.0150 Rp 110,000.00 Rp 1,650.00

Sub-Total ( 1 ) Rp 51,150.00

2 Bahan
Semen PC kg 20.4000 Rp 1,471.00 Rp 30,008.40
Pasir pasang M3 0.0390 Rp 183,700.00 Rp 7,164.30
Lapisan Coating PF Primer m2 1.1000 Rp 15,000.00 Rp 16,500.00
Waterproofing Membrane, Sopralene 180 4 S/P (4 mm) m2 1.1000 Rp 36,486.98 Rp 40,135.68

Sub-Total ( 2 ) Rp 93,808.38

3 Peralatan
Alat pembakar lot 1.0000 Rp 10,000.00 Rp 10,000.00

Sub-Total ( 3 ) Rp 10,000.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 154,958.38

Pekerjaan : ATAP
Jenis Pembayaran : Scred 1 PC : 3 PS (4 cm) + kawat ayam, pelindung waterproofing
Satuan Pembayaran : M2
Harga Satuan : Rp 79,772.70
AHSP-XI-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang Batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kep. Tukang Batu OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 25,100.00

2 Bahan
Semen PC kg 20.4000 Rp 1,471.00 Rp 30,008.40
Pasir pasang M3 0.0390 Rp 183,700.00 Rp 7,164.30
Kawat ayam / kawat loket m2 1.0000 Rp 17,500.00 Rp 17,500.00

Sub-Total ( 2 ) Rp 54,672.70

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 79,772.70

Analisa Harga Satuan Pekerjaan - 117


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Kuda-kuda kayu kelas II (Kruing/Kamper Medan)
Satuan Pembayaran : M3
Harga Satuan : Rp 9,314,692.50 SNI 3434 (6.13) - 2008
AHSP-XI-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 4.0000 Rp 70,000.00 Rp 280,000.00
Tukang Kayu OH 12.0000 Rp 100,000.00 Rp 1,200,000.00
Kep. Tukang Kayu OH 1.2000 Rp 100,000.00 Rp 120,000.00
Mandor OH 0.2000 Rp 110,000.00 Rp 22,000.00

Sub-Total ( 1 ) Rp 1,622,000.00

2 Bahan
Balok kayu Kruing/Kamper Medan m3 1.1000 Rp 6,791,875.00 Rp 7,471,062.50
Besi strip tebal 5 mm kg 15.0000 Rp 9,250.00 Rp 138,750.00
Paku 12 cm kg 5.6000 Rp 14,800.00 Rp 82,880.00

Sub-Total ( 2 ) Rp 7,692,692.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 9,314,692.50

Pekerjaan : ATAP
Jenis Pembayaran : Gordeng kayu kelas II (Kruing/Kamper Medan)
Satuan Pembayaran : M3
Harga Satuan : Rp 8,627,412.50 SNI 3434 (6.15) - 2008
AHSP-XI-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 2.4000 Rp 70,000.00 Rp 168,000.00
Tukang Kayu OH 7.2000 Rp 100,000.00 Rp 720,000.00
Kep. Tukang Kayu OH 0.7200 Rp 100,000.00 Rp 72,000.00
Mandor OH 0.1200 Rp 110,000.00 Rp 13,200.00

Sub-Total ( 1 ) Rp 973,200.00

2 Bahan
Balok kayu Kruing/Kamper Medan m3 1.1000 Rp 6,791,875.00 Rp 7,471,062.50
Besi strip tebal 5 mm kg 15.0000 Rp 9,250.00 Rp 138,750.00
Paku 12 cm kg 3.0000 Rp 14,800.00 Rp 44,400.00

Sub-Total ( 2 ) Rp 7,654,212.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 8,627,412.50

Analisa Harga Satuan Pekerjaan - 118


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Rangka Atap Genteng Keramik (Kruing/Kamper Medan)
Satuan Pembayaran : M2
Harga Satuan : Rp 137,547.00 SNI 3434 (6.16) - 2008
AHSP-XI-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Tukang Kayu OH 0.1000 Rp 100,000.00 Rp 10,000.00
Kep. Tukang Kayu OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 18,550.00

2 Bahan
Kasau 5x7 cm, kayu Kruing/Kamper Medan m3 0.0140 Rp 6,591,875.00 Rp 92,286.25
Reng 3x4 cm, kayu Kruing/Kamper Medan m3 0.0036 Rp 6,391,875.00 Rp 23,010.75
Paku 5 cm dan 10 cm kg 0.2500 Rp 14,800.00 Rp 3,700.00

Sub-Total ( 2 ) Rp 118,997.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 137,547.00

Pekerjaan : ATAP
Jenis Pembayaran : Listplank 3x20 cm, papan kayu Kamper Samarinda oven
Satuan Pembayaran : M'
Harga Satuan : Rp 115,930.00 SNI 3434 (6.21) - 2008
AHSP-XI-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Tukang Kayu OH 0.2000 Rp 100,000.00 Rp 20,000.00
Kep. Tukang Kayu OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 29,550.00

2 Bahan
Papan Kamper Samarinda oven m3 0.0080 Rp 10,612,500.00 Rp 84,900.00
Paku 5 cm dan 7 cm kg 0.1000 Rp 14,800.00 Rp 1,480.00

Sub-Total ( 2 ) Rp 86,380.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 115,930.00

Analisa Harga Satuan Pekerjaan - 119


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Listplank 3x30 cm, papan kayu Kamper Samarinda oven
Satuan Pembayaran : M'
Harga Satuan : Rp 147,027.50 SNI 3434 (6.22) - 2008
AHSP-XI-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Tukang Kayu OH 0.2000 Rp 100,000.00 Rp 20,000.00
Kep. Tukang Kayu OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 29,550.00

2 Bahan
Papan Kamper Samarinda oven m3 0.0110 Rp 10,612,500.00 Rp 116,737.50
Paku 5 cm dan 7 cm kg 0.0500 Rp 14,800.00 Rp 740.00

Sub-Total ( 2 ) Rp 117,477.50

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 147,027.50

Analisa Harga Satuan Pekerjaan - 120


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Atap Genteng Keramik KIA
Satuan Pembayaran : M2
Harga Satuan : Rp 148,350.00
AHSP-XI-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang Batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kep. Tukang Batu OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 25,100.00

2 Bahan
Genteng Keramik KIA Standart bh 14.5000 Rp 8,500.00 Rp 123,250.00

Sub-Total ( 2 ) Rp 123,250.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 148,350.00

Pekerjaan : ATAP
Jenis Pembayaran : Nok Genteng Keramik KIA
Satuan Pembayaran : M2
Harga Satuan : Rp 181,479.70
AHSP-XI-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.4000 Rp 70,000.00 Rp 28,000.00
Tukang Batu OH 0.2000 Rp 90,000.00 Rp 18,000.00
Kep. Tukang Batu OH 0.0200 Rp 100,000.00 Rp 2,000.00
Mandor OH 0.0200 Rp 110,000.00 Rp 2,200.00

Sub-Total ( 1 ) Rp 50,200.00

2 Bahan
Genteng Nok KIA Standart bh 5.0000 Rp 25,300.00 Rp 126,500.00
Semen PC kg 2.5000 Rp 1,471.00 Rp 3,677.50
Pasir pasang M3 0.0060 Rp 183,700.00 Rp 1,102.20

Sub-Total ( 2 ) Rp 131,279.70

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 181,479.70

Analisa Harga Satuan Pekerjaan - 121


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : ATAP
Jenis Pembayaran : Talang datar/jurai, seng BJLS 28 lbr 90
Satuan Pembayaran : M'
Harga Satuan : Rp 232,691.93 SNI 7393 (6.18) - 2008
AHSP-XI-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang Kayu OH 0.4000 Rp 100,000.00 Rp 40,000.00
Kep. Tukang Kayu OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 57,600.00

2 Bahan
Papan kayu Kruing/Kamper medan m3 0.0190 Rp 6,991,875.00 Rp 132,845.63
Paku 3 cm dan 5 cm kg 0.0150 Rp 16,420.00 Rp 246.30
Seng plat BJLS 28 lebar 90 cm m' 1.0500 Rp 40,000.00 Rp 42,000.00

Sub-Total ( 2 ) Rp 175,091.93

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 232,691.93

Pekerjaan : ATAP
Jenis Pembayaran : Talang 1/2 lingkaran D-15 cm, seng BJLS 30 lbr 45 cm
Satuan Pembayaran : M'
Harga Satuan : Rp 83,418.60 SNI 7393 (6.19) - 2008
AHSP-XI-017
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.2000 Rp 70,000.00 Rp 14,000.00
Tukang Kayu OH 0.4000 Rp 100,000.00 Rp 40,000.00
Kep. Tukang Kayu OH 0.0250 Rp 100,000.00 Rp 2,500.00
Mandor OH 0.0100 Rp 110,000.00 Rp 1,100.00

Sub-Total ( 1 ) Rp 57,600.00

2 Bahan
Seng plat BJLS 30 lebar 90 cm m' 0.5250 Rp 40,000.00 Rp 21,000.00
Paku 1 cm - 3 cm kg 0.0100 Rp 19,360.00 Rp 193.60
Besi Strip kg 0.5000 Rp 9,250.00 Rp 4,625.00

Sub-Total ( 2 ) Rp 25,818.60

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 83,418.60

Analisa Harga Satuan Pekerjaan - 122


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

XII. PEKERJAAN : PENGECATAN

Pekerjaan : PENGECATAN
Jenis Pembayaran : Cat Tembok Dalam, ICI Dulux Pentalite
Satuan Pembayaran : M2
Harga Satuan : Rp 27,758.85
AHSP-XII-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja Oh 0.0300 Rp 70,000.00 Rp 2,100.00
Tukang Cat OH 0.0600 Rp 90,000.00 Rp 5,400.00
Kep. Tukang Cat OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
Sub-Total ( 1 ) Rp 8,430.00
2 Bahan
Cat Tembok dalam, ICI Dulux Pentalite kg 0.3600 Rp 41,918.57 Rp 15,090.69
Plamur tembok m3 0.1000 Rp 9,360.00 Rp 936.00
Amplas besi m3 0.3000 Rp 3,400.00 Rp 1,020.00
Kuas Roll M3 0.0150 Rp 35,000.00 Rp 525.00
Sub-Total ( 2 ) Rp 17,571.69
3 Peralatan
Alat Bantu ls 1.0000 Rp 1,757.17 Rp 1,757.17
Sub-Total ( 3 ) Rp 1,757.17

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 27,758.85

Pekerjaan : PENGECATAN
Jenis Pembayaran : Cat Tembok Dalam, Catylac
Satuan Pembayaran : M2
Harga Satuan : Rp 21,059.10
AHSP-XII-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja Oh 0.0300 Rp 70,000.00 Rp 2,100.00
Tukang Cat OH 0.0600 Rp 90,000.00 Rp 5,400.00
Kep. Tukang Cat OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
Sub-Total ( 1 ) Rp 8,430.00
2 Bahan
Cat Tembok dalam, Catylac kg 0.3600 Rp 25,000.00 Rp 9,000.00
Plamur tembok m3 0.1000 Rp 9,360.00 Rp 936.00
Amplas besi m3 0.3000 Rp 3,400.00 Rp 1,020.00
Kuas Roll M3 0.0150 Rp 35,000.00 Rp 525.00
Sub-Total ( 2 ) Rp 11,481.00
3 Peralatan
Alat Bantu ls 1.0000 Rp 1,148.10 Rp 1,148.10
Sub-Total ( 3 ) Rp 1,148.10

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 21,059.10

Analisa Harga Satuan Pekerjaan - 123


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PENGECATAN
Jenis Pembayaran : Cat Tembok Dalam, Mowilex
Satuan Pembayaran : M2
Harga Satuan : Rp 26,009.10
AHSP-XII-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja Oh 0.0300 Rp 70,000.00 Rp 2,100.00
Tukang Cat OH 0.0600 Rp 90,000.00 Rp 5,400.00
Kep. Tukang Cat OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00
Sub-Total ( 1 ) Rp 8,430.00
2 Bahan
Cat Tembok Mowilex (Acrilyc Emulsion) kg 0.3600 Rp 37,500.00 Rp 13,500.00
Plamur tembok m3 0.1000 Rp 9,360.00 Rp 936.00
Amplas besi m3 0.3000 Rp 3,400.00 Rp 1,020.00
Kuas Roll M3 0.0150 Rp 35,000.00 Rp 525.00
Sub-Total ( 2 ) Rp 15,981.00
3 Peralatan
Alat Bantu ls 1.0000 Rp 1,598.10 Rp 1,598.10
Sub-Total ( 3 ) Rp 1,598.10

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 26,009.10

Pekerjaan : PENGECATAN
Jenis Pembayaran : Cat Tembok Luar, ICI Weathershield
Satuan Pembayaran : M2
Harga Satuan : Rp 35,134.86
AHSP-XII-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja Oh 0.0300 Rp 70,000.00 Rp 2,100.00
Tukang Cat OH 0.0600 Rp 90,000.00 Rp 5,400.00
Kep. Tukang Cat OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 8,430.00

2 Bahan
Cat Tembok luar, ICI Weathershield Kg 0.2200 Rp 65,000.00 Rp 14,300.00
Alkali Resistants Bh 0.1100 Rp 43,428.57 Rp 4,777.14
Amplas besi Bh 0.5000 Rp 3,400.00 Rp 1,700.00
Kuas Roll Bh 0.1000 Rp 35,000.00 Rp 3,500.00

Sub-Total ( 2 ) Rp 24,277.14

3 Peralatan
Alat Bantu ls 1.0000 Rp 2,427.71 Rp 2,427.71

Sub-Total ( 3 ) Rp 2,427.71

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 35,134.86

Analisa Harga Satuan Pekerjaan - 124


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PENGECATAN
Jenis Pembayaran : Cat Tembok Luar, Mowilex (Water Coat)
Satuan Pembayaran : M2
Harga Satuan : Rp 30,476.36
AHSP-XII-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja Oh 0.0300 Rp 70,000.00 Rp 2,100.00
Tukang Cat OH 0.0600 Rp 90,000.00 Rp 5,400.00
Kep. Tukang Cat OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 8,430.00

2 Bahan
Cat Tembok Mowilex (Wather Coat) Kg 0.2200 Rp 45,750.00 Rp 10,065.00
Alkali Resistants Bh 0.1100 Rp 43,428.57 Rp 4,777.14
Amplas besi Bh 0.5000 Rp 3,400.00 Rp 1,700.00
Kuas Roll Bh 0.1000 Rp 35,000.00 Rp 3,500.00

Sub-Total ( 2 ) Rp 20,042.14

3 Peralatan
Alat Bantu ls 1.0000 Rp 2,004.21 Rp 2,004.21

Sub-Total ( 3 ) Rp 2,004.21

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 30,476.36

Pekerjaan : PENGECATAN
Jenis Pembayaran : Cat Antikarat permukaan baja, dengan zinchromate
Satuan Pembayaran : Kg
Harga Satuan : Rp 1,502.75
AHSP-XII-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.0035 Rp 70,000.00 Rp 245.00
Tukang cat OH 0.0045 Rp 90,000.00 Rp 405.00
Kepala tukang OH 0.0003 Rp 100,000.00 Rp 30.00
Mandor OH 0.0001 Rp 110,000.00 Rp 13.75

Sub-Total ( 1 ) Rp 693.75
2 Bahan
Cat zinchromate kg 0.0150 Rp 40,000.00 Rp 600.00
Minyak cat/ thinner ltr 0.0050 Rp 23,700.00 Rp 118.50
Amplas lbr 0.0200 Rp 3,400.00 Rp 68.00
kuas bh 0.0015 Rp 15,000.00 Rp 22.50

Sub-Total ( 2 ) Rp 809.00
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,502.75

Analisa Harga Satuan Pekerjaan - 125


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PENGECATAN
Jenis Pembayaran : Cat Antikarat permukaan baja, dengan zinchromate
Satuan Pembayaran : M2
Harga Satuan : Rp 30,055.00
AHSP-XII-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0700 Rp 70,000.00 Rp 4,900.00
Tukang cat OH 0.0900 Rp 90,000.00 Rp 8,100.00
Kepala tukang OH 0.0060 Rp 100,000.00 Rp 600.00
Mandor OH 0.0025 Rp 110,000.00 Rp 275.00

Sub-Total ( 1 ) Rp 13,875.00

2 Bahan
Cat zinchromate kg 0.3000 Rp 40,000.00 Rp 12,000.00
Minyak cat/ thinner ltr 0.1000 Rp 23,700.00 Rp 2,370.00
Amplas lbr 0.4000 Rp 3,400.00 Rp 1,360.00
kuas bh 0.0300 Rp 15,000.00 Rp 450.00

Sub-Total ( 2 ) Rp 16,180.00

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 30,055.00

Pekerjaan : PENGECATAN
Jenis Pembayaran : Pek Cat finish, permukaan baja
Satuan Pembayaran : Kg
Harga Satuan : Rp 1,603.58
AHSP-XII-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.0035 Rp 70,000.00 Rp 245.00
Tukang cat OH 0.0045 Rp 90,000.00 Rp 405.00
Kepala tukang OH 0.0003 Rp 100,000.00 Rp 30.00
Mandor OH 0.0001 Rp 110,000.00 Rp 13.75

Sub-Total ( 1 ) Rp 693.75

2 Bahan
Cat Kayu/besi (ICI Dulux Super Gloss) kg 0.0150 Rp 46,722.00 Rp 700.83
Minyak cat/ thinner ltr 0.0050 Rp 23,700.00 Rp 118.50
Amplas lbr 0.0200 Rp 3,400.00 Rp 68.00
kuas bh 0.0015 Rp 15,000.00 Rp 22.50

Sub-Total ( 2 ) Rp 909.83

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,603.58

Analisa Harga Satuan Pekerjaan - 126


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PENGECATAN
Jenis Pembayaran : Pengecatan Cat Kayu / besi
Satuan Pembayaran : M2
Harga Satuan : Rp 49,418.21
AHSP-XII-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.1000 Rp 70,000.00 Rp 7,000.00
Tukang cat OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala tukang OH 0.0050 Rp 100,000.00 Rp 500.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 17,050.00

2 Bahan
Cat Kayu/besi (ICI Dulux Super Gloss) kg 0.4300 Rp 46,722.00 Rp 20,090.46
Dempul kayu / besi kg 0.1500 Rp 22,585.00 Rp 3,387.75
Minyak cat/ thinner ltr 0.2000 Rp 23,700.00 Rp 4,740.00
Amplas lbr 1.0000 Rp 3,400.00 Rp 3,400.00
Kuas bh 0.0500 Rp 15,000.00 Rp 750.00

Sub-Total ( 2 ) Rp 32,368.21

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 49,418.21

Pekerjaan : PENGECATAN
Jenis Pembayaran : Finishing Cat Duco
Satuan Pembayaran : M2
Harga Satuan : Rp 149,155.00
AHSP-XII-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.4000 Rp 70,000.00 Rp 28,000.00
Tukang cat OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala tukang OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0040 Rp 110,000.00 Rp 440.00

Sub-Total ( 1 ) Rp 68,440.00
2 Bahan
Cat Duco Nipple 2000 Kg 0.4000 Rp 55,575.00 Rp 22,230.00
Dempul Duco Kg 0.7500 Rp 30,300.00 Rp 22,725.00
Tinner Up ltr 0.8000 Rp 23,700.00 Rp 18,960.00
Amplas besi Bh 2.0000 Rp 3,400.00 Rp 6,800.00

Sub-Total ( 2 ) Rp 70,715.00
3 Peralatan
Alat semprot Ls 1.0000 Rp 10,000.00 Rp 10,000.00

Sub-Total ( 3 ) Rp 10,000.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 149,155.00

Analisa Harga Satuan Pekerjaan - 127


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : PENGECATAN
Jenis Pembayaran : Finishing Cat Melamik
Satuan Pembayaran : M2
Harga Satuan : Rp 134,673.55
AHSP-XII-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.3000 Rp 70,000.00 Rp 21,000.00
Tukang cat OH 0.3000 Rp 90,000.00 Rp 27,000.00
Kepala tukang OH 0.0300 Rp 100,000.00 Rp 3,000.00
Mandor OH 0.0030 Rp 110,000.00 Rp 330.00

Sub-Total ( 1 ) Rp 51,330.00

2 Bahan
Wood Filler Ultran Kg 0.250 Rp 50,000.00 Rp 12,500.00
Sending sealer Impra Kg 0.150 Rp 76,142.00 Rp 11,421.30
Cat warna Ultran Kg 0.150 Rp 58,500.00 Rp 8,775.00
Melamik Impra Kg 0.350 Rp 42,535.00 Rp 14,887.25
Tinner (High class) Kg 0.800 Rp 23,700.00 Rp 18,960.00
Amplas besi Bh 2.000 Rp 3,400.00 Rp 6,800.00

Sub-Total ( 2 ) Rp 73,343.55

3 Peralatan
Alat semprot Ls 1.0000 Rp 10,000.00 Rp 10,000.00

Sub-Total ( 3 ) Rp 10,000.00

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 134,673.55

Analisa Harga Satuan Pekerjaan - 128


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

XIII. PEKERJAAN : SALURAN

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran terbuka, pas bata + buis beton 1/2 ф 30 cm,
Satuan Pembayaran : M'
Harga Satuan : Rp 274,116.34
AHSP-XIII-001
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.5000 Rp 70,000.00 Rp 35,000.00
Tukang batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kep. Tukang OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 45,550.00

2 Bahan
Dinding dari pas batu bata 1Pc : 5Ps M2 1.0000 Rp 100,655.78 Rp 100,655.78
Pas. Bata sambungan buis beton M2 0.1200 Rp 100,655.78 Rp 12,078.69
Plesteran dinding bata M2 1.0000 Rp 50,051.86 Rp 50,051.86
Buis beton 1/2 dia 30 cm, @ panjang 1 m bh 1.0000 Rp 65,780.00 Rp 65,780.00

Sub-Total ( 2 ) Rp 228,566.34
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 274,116.34

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran tertutup, pas bata + buis beton 1/2 ф 30 cm, +
tutup plat beton 10 cm
Satuan Pembayaran : M'
Harga Satuan : Rp 328,456.04
AHSP-XIII-002
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.5000 Rp 70,000.00 Rp 35,000.00
Tukang Batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala Tukang Batu OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 45,550.00

2 Bahan
Dinding dari pas batu bata 1Pc : 5Ps M2 1.0000 Rp 100,655.78 Rp 100,655.78
Pas. Bata sambungan buis beton M2 0.1200 Rp 100,655.78 Rp 12,078.69
Plesteran dinding bata M2 1.0000 Rp 50,051.86 Rp 50,051.86
Buis beton 1/2 dia 30 cm, @ panjang 1 m bh 1.0000 Rp 65,780.00 Rp 65,780.00
Tutup beton tulang tebal 10 cm M3 0.0600 Rp 905,661.72 Rp 54,339.70
Sub-Total ( 2 ) Rp 282,906.04
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 328,456.04

Analisa Harga Satuan Pekerjaan - 129


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran tertutup, pas bata + buis beton 1/2 ф 30 cm, +
tutup plat beton 15 cm
Satuan Pembayaran : M'
Harga Satuan : Rp 355,625.89
AHSP-XIII-003
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.5000 Rp 70,000.00 Rp 35,000.00
Tukang Batu OH 0.1000 Rp 90,000.00 Rp 9,000.00
Kepala Tukang Batu OH 0.0100 Rp 100,000.00 Rp 1,000.00
Mandor OH 0.0050 Rp 110,000.00 Rp 550.00

Sub-Total ( 1 ) Rp 45,550.00

2 Bahan
Dinding dari pas batu bata 1Pc : 5Ps M2 1.0000 Rp 100,655.78 Rp 100,655.78
Pas. Bata sambungan buis beton M2 0.1200 Rp 100,655.78 Rp 12,078.69
Plesteran dinding bata M2 1.0000 Rp 50,051.86 Rp 50,051.86
Buis beton 1/2 dia 30 cm, @ panjang 1 m bh 1.0000 Rp 65,780.00 Rp 65,780.00
Tutup beton tulang tebal 15 cm M3 0.0900 Rp 905,661.72 Rp 81,509.55

Sub-Total ( 2 ) Rp 310,075.89

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 355,625.89

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran Tertutup (U Ditch uk. 40x40x120 cm + tutup)
Satuan Pembayaran : M'
Harga Satuan : Rp 688,025.10
AHSP-XIII-004
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Tukang Batu OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala Tukang Batu OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 115,500.00

2 Bahan
Saluran U Ditch uk. 40x40x120 cm bh 1.0000 Rp 197,472.00 Rp 197,472.00
Tutup saluran U.40 @ 60 cm HD bh 2.0000 Rp 89,500.00 Rp 179,000.00
Semen portland kg 91.6000 Rp 1,471.00 Rp 134,743.60
Pasir pasang m³ 0.2750 Rp 183,700.00 Rp 50,517.50
Pasir urug m³ 0.0800 Rp 134,900.00 Rp 10,792.00

Sub-Total ( 2 ) Rp 572,525.10
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 688,025.10

Analisa Harga Satuan Pekerjaan - 130


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran Tertutup (U Ditch, uk. 40x60x120 cm + tutup)
Satuan Pembayaran : M'
Harga Satuan : Rp 801,281.10
AHSP-XIII-005
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Tukang Batu OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala Tukang Batu OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 115,500.00

2 Bahan
Saluran U Ditch uk. 40x60x120 cm bh 1.0000 Rp 310,728.00 Rp 310,728.00
Tutup saluran U.40 @ 60 cm HD bh 2.0000 Rp 89,500.00 Rp 179,000.00
Semen portland kg 91.6000 Rp 1,471.00 Rp 134,743.60
Pasir pasang m³ 0.2750 Rp 183,700.00 Rp 50,517.50
Pasir urug m³ 0.0800 Rp 134,900.00 Rp 10,792.00

Sub-Total ( 2 ) Rp 685,781.10

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 801,281.10

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran Terbuka (U Ditch, uk. 40x60x120 cm)
Satuan Pembayaran : M'
Harga Satuan : Rp 608,281.10
AHSP-XIII-05A
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 0.8000 Rp 70,000.00 Rp 56,000.00
Tukang Batu OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala Tukang Batu OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 101,500.00

2 Bahan
Saluran U Ditch uk. 40x60x120 cm bh 1.0000 Rp 310,728.00 Rp 310,728.00
Semen portland kg 91.6000 Rp 1,471.00 Rp 134,743.60
Pasir pasang m³ 0.2750 Rp 183,700.00 Rp 50,517.50
Pasir urug m³ 0.0800 Rp 134,900.00 Rp 10,792.00

Sub-Total ( 2 ) Rp 506,781.10

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 608,281.10

Analisa Harga Satuan Pekerjaan - 131


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran Tertutup (U Ditch, uk. 60x80x120 cm + tutup)
Satuan Pembayaran : M'
Harga Satuan : Rp 1,019,185.10
AHSP-XIII-006
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Tukang Batu OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala Tukang Batu OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 115,500.00
2 Bahan
Saluran U Ditch uk. 60x80x120 cm bh 1.0000 Rp 434,632.00 Rp 434,632.00
Tutup saluran U.60 @ 60 cm HD bh 2.0000 Rp 136,500.00 Rp 273,000.00
Semen portland kg 91.6000 Rp 1,471.00 Rp 134,743.60
Pasir pasang m³ 0.2750 Rp 183,700.00 Rp 50,517.50
Pasir urug m³ 0.0800 Rp 134,900.00 Rp 10,792.00

Sub-Total ( 2 ) Rp 903,685.10
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,019,185.10

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran Terbuka (U Ditch, uk. 60x80x120 cm)
Satuan Pembayaran : M'
Harga Satuan : Rp 732,185.10
AHSP-XIII-06A
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 0.8000 Rp 70,000.00 Rp 56,000.00
Tukang Batu OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala Tukang Batu OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 101,500.00
2 Bahan
Saluran U Ditch uk. 60x80x120 cm bh 1.0000 Rp 434,632.00 Rp 434,632.00
Semen portland kg 91.6000 Rp 1,471.00 Rp 134,743.60
Pasir pasang m³ 0.2750 Rp 183,700.00 Rp 50,517.50
Pasir urug m³ 0.0800 Rp 134,900.00 Rp 10,792.00

Sub-Total ( 2 ) Rp 630,685.10
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 732,185.10

Analisa Harga Satuan Pekerjaan - 132


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran Tertutup (U Ditch, uk. 80x100x120 cm + tutup)
Satuan Pembayaran : M'
Harga Satuan : Rp 1,339,121.10
AHSP-XIII-007
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Tukang Batu OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala Tukang Batu OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 115,500.00

2 Bahan
Saluran U Ditch uk. 80x100x120 cm bh 1.0000 Rp 678,568.00 Rp 678,568.00
Tutup saluran U.80 @ 60 cm HD bh 2.0000 Rp 174,500.00 Rp 349,000.00
Semen portland kg 91.6000 Rp 1,471.00 Rp 134,743.60
Pasir pasang m³ 0.2750 Rp 183,700.00 Rp 50,517.50
Pasir urug m³ 0.0800 Rp 134,900.00 Rp 10,792.00

Sub-Total ( 2 ) Rp 1,223,621.10

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,339,121.10

Pekerjaan : SALURAN
Jenis Pembayaran : Saluran Tertutup (U Ditch, uk. 100x120x120 cm + tutup)
Satuan Pembayaran : M'
Harga Satuan : Rp 1,997,713.10
AHSP-XIII-008
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Pekerja OH 1.0000 Rp 70,000.00 Rp 70,000.00
Tukang Batu OH 0.4000 Rp 90,000.00 Rp 36,000.00
Kepala Tukang Batu OH 0.0400 Rp 100,000.00 Rp 4,000.00
Mandor OH 0.0500 Rp 110,000.00 Rp 5,500.00

Sub-Total ( 1 ) Rp 115,500.00
2 Bahan
Saluran U Ditch uk. 100x120x120 cm bh 1.0000 Rp 1,161,160.00 Rp 1,161,160.00
Tutup saluran U.100 @ 60 cm HD bh 2.0000 Rp 262,500.00 Rp 525,000.00
Semen portland kg 91.6000 Rp 1,471.00 Rp 134,743.60
Pasir pasang m³ 0.2750 Rp 183,700.00 Rp 50,517.50
Pasir urug m³ 0.0800 Rp 134,900.00 Rp 10,792.00

Sub-Total ( 2 ) Rp 1,882,213.10
3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,997,713.10

Analisa Harga Satuan Pekerjaan - 133


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Bak Kontrol uk 40 x 40 cm
Satuan Pembayaran : Unit
Harga Satuan : Rp 307,623.57
AHSP-XIII-009
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
Beton K-250 m3 0.0960 Rp 905,661.72 Rp 86,943.52
Besi U39 kg 14.4000 Rp 9,904.33 Rp 142,622.35
Bekesting m2 0.6400 Rp 120,278.90 Rp 76,978.50
Pasir urug m3 0.0080 Rp 134,900.00 Rp 1,079.20

Sub-Total ( 2 ) Rp 307,623.57

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 307,623.57

Pekerjaan : SALURAN
Jenis Pembayaran : Bak Kontrol uk 60 x 60 cm
Satuan Pembayaran : Unit
Harga Satuan : Rp 692,153.04
AHSP-XIII-010
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
Beton K-250 m3 0.2160 Rp 905,661.72 Rp 195,622.93
Besi U39 kg 32.4000 Rp 9,904.33 Rp 320,900.29
Bekesting m2 1.4400 Rp 120,278.90 Rp 173,201.62
Pasir urug m3 0.0180 Rp 134,900.00 Rp 2,428.20

Sub-Total ( 2 ) Rp 692,153.04

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 692,153.04

Analisa Harga Satuan Pekerjaan - 134


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Bak Kontrol uk 80 x 80 cm
Satuan Pembayaran : Unit
Harga Satuan : Rp 1,230,494.29
AHSP-XIII-011
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
Beton K-250 m3 0.3840 Rp 905,661.72 Rp 347,774.10
Besi U39 kg 57.6000 Rp 9,904.33 Rp 570,489.41
Bekesting m2 2.5600 Rp 120,278.90 Rp 307,913.98
Pasir urug m3 0.0320 Rp 134,900.00 Rp 4,316.80

Sub-Total ( 2 ) Rp 1,230,494.29

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,230,494.29

Pekerjaan : SALURAN
Jenis Pembayaran : Bak Kontrol uk 100 x 100 cm
Satuan Pembayaran : Unit
Harga Satuan : Rp 1,922,647.33
AHSP-XIII-012
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
Beton K-250 m3 0.6000 Rp 905,661.72 Rp 543,397.03
Besi U39 kg 90.0000 Rp 9,904.33 Rp 891,389.70
Bekesting m2 4.0000 Rp 120,278.90 Rp 481,115.60
Pasir urug m3 0.0500 Rp 134,900.00 Rp 6,745.00

Sub-Total ( 2 ) Rp 1,922,647.33

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 1,922,647.33

Analisa Harga Satuan Pekerjaan - 135


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Ducting beton 2100x1800 tebal 12 cm
Satuan Pembayaran : M'
Harga Satuan : Rp 6,414,896.89
AHSP-XIII-013
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)
1 Tenaga
Sub-Total ( 1 ) Rp -
Bahan
1 Ducting Beton
Beton K-250 m³ 0.9810 Rp 905,661.72 Rp 888,454.14
Besi beton kg 99.5790 Rp 9,904.33 Rp 986,263.28
Bekisting dinding m2 10.2000 Rp 266,617.80 Rp 2,719,501.56
Pasir urug alas saluran m³ 0.1800 Rp 134,900.00 Rp 24,282.00
2 Bracket
Bracket besi siku 50.5.5 (6 unit/m') kg 18.0960 Rp 21,167.50 Rp 383,047.08
Finishing cat besi siku (zinkromate) m2 10.0800 Rp 30,055.00 Rp 302,954.40
Dinabolt 10 mm bh 24.0000 Rp 20,000.00 Rp 480,000.00
3 Beton tumbuk dudukan pipa m3 0.1200 Rp 669,953.56 Rp 80,394.43
4 Karet Rubbering pcs 1.0000 Rp 550,000.00 Rp 550,000.00
Sub-Total ( 2 ) Rp 6,414,896.89
3 Peralatan
Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 6,414,896.89

Pekerjaan : SALURAN
Jenis Pembayaran : Ducting beton 2300x1800 tebal 20 cm
Satuan Pembayaran : M'
Harga Satuan : Rp 7,365,697.92
AHSP-XIII-014
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
1 Ducting Beton
Beton K-250 m³ 1.7650 Rp 905,661.72 Rp 1,598,492.93
Besi beton kg 102.3523 Rp 9,904.33 Rp 1,013,731.29
Bekisting dinding m2 11.0000 Rp 266,617.80 Rp 2,932,795.80
Pasir urug alas saluran m³ 0.1800 Rp 134,900.00 Rp 24,282.00
2 Bracket
Bracket besi siku 50.5.5 (6 unit/m') kg 18.0960 Rp 21,167.50 Rp 383,047.08
Finishing cat besi siku (zinkromate) m2 10.0800 Rp 30,055.00 Rp 302,954.40
Dinabolt 10 mm bh 24.0000 Rp 20,000.00 Rp 480,000.00
3 Beton tumbuk dudukan pipa ad 1 : 3 : 5 m3 0.1200 Rp 669,953.56 Rp 80,394.43
4 Karet Rubbering pcs 1.0000 Rp 550,000.00 Rp 550,000.00

Sub-Total ( 2 ) Rp 7,365,697.92

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 7,365,697.92

Analisa Harga Satuan Pekerjaan - 136


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Bak Kontrol Ducting beton Type persimpangan 2
Satuan Pembayaran : Unit
Harga Satuan : Rp 15,692,366.99
AHSP-XIII-015
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
1 Ducting Beton
Beton K-250 m³ 2.3080 Rp 905,661.72 Rp 2,090,267.24
Besi beton kg 275.7636 Rp 9,904.33 Rp 2,731,253.70
Bekisting dinding (2x pakai) m2 5.9550 Rp 266,617.80 Rp 1,587,709.00
Pasir urug alas saluran m³ 0.4410 Rp 134,900.00 Rp 59,490.90
2 Toping Ducting
Beton K-250 m³ 1.7280 Rp 905,661.72 Rp 1,564,983.44
Besi beton kg 162.3872 Rp 9,904.33 Rp 1,608,336.42
Bekisting dinding (2x pakai) m2 2.8800 Rp 266,617.80 Rp 767,859.26
3 Bracket
Bracket besi siku 50.5.5 (6 unit/m') kg 40.7160 Rp 21,167.50 Rp 861,855.93
Finishing cat besi siku (zinkromate) m2 22.6800 Rp 30,055.00 Rp 681,647.40
Dinabolt 10 mm bh 24.0000 Rp 20,000.00 Rp 480,000.00
4 Beton tumbuk dudukan pipa m3 0.2040 Rp 669,953.56 Rp 136,670.53
5 Tangga pipa GIP dia 2" bh 1.0000 Rp 1,000,000.00 Rp 1,000,000.00
6 Tutup Kontrol
Tutup bak kontrol, besi plat tebal 19 mm kg 98.4444 Rp 21,167.50 Rp 2,083,822.78
Finishing cat besi siku (zinkromate) m2 1.2800 Rp 30,055.00 Rp 38,470.40

Sub-Total ( 2 ) Rp 15,692,366.99

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 15,692,366.99

Analisa Harga Satuan Pekerjaan - 137


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Bak Kontrol Ducting beton Type persimpangan 3
Satuan Pembayaran : Unit
Harga Satuan : Rp 15,456,189.87
AHSP-XIII-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
1 Ducting Beton
Beton K-250 m³ 2.0213 Rp 905,661.72 Rp 1,830,568.74
Besi beton kg 279.7320 Rp 9,904.33 Rp 2,770,558.37
Bekisting dinding (2x pakai) m2 5.9550 Rp 266,617.80 Rp 1,587,709.00
Pasir urug alas saluran m³ 0.3240 Rp 134,900.00 Rp 43,707.60
2 Toping Ducting
Beton K-250 m³ 1.7280 Rp 905,661.72 Rp 1,564,983.44
Besi beton kg 162.3872 Rp 9,904.33 Rp 1,608,336.42
Bekisting dinding (2x pakai) m2 2.8800 Rp 266,617.80 Rp 767,859.26
3 Bracket
Bracket besi siku 50.5.5 (6 unit/m') kg 40.7160 Rp 21,167.50 Rp 861,855.93
Finishing cat besi siku (zinkromate) m2 22.6800 Rp 30,055.00 Rp 681,647.40
Dinabolt 10 mm bh 24.0000 Rp 20,000.00 Rp 480,000.00
4 Beton tumbuk dudukan pipa m3 0.2040 Rp 669,953.56 Rp 136,670.53
5 Tangga pipa GIP dia 2" bh 1.0000 Rp 1,000,000.00 Rp 1,000,000.00
6 Tutup Kontrol
Tutup bak kontrol, besi plat tebal 19 mm kg 98.4444 Rp 21,167.50 Rp 2,083,822.78
Finishing cat besi siku (zinkromate) m2 1.2800 Rp 30,055.00 Rp 38,470.40

Sub-Total ( 2 ) Rp 15,456,189.87

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 15,456,189.87

Analisa Harga Satuan Pekerjaan - 138


DAFTAR ANALISA HARGA SATUAN PEKERJAAN
( ACUAN SNI - TH 2008 )

Pekerjaan : SALURAN
Jenis Pembayaran : Bak Kontrol Ducting beton Type persimpangan 4 (PIT)
Satuan Pembayaran : Unit
Harga Satuan : Rp 18,300,561.99
AHSP-XIII-016
Harga Satuan
No Komponen Satuan Volume Jumlah Harga (Rp)
(Rp)

1 Tenaga

Sub-Total ( 1 ) Rp -

2 Bahan
1 Ducting Beton
Beton K-250 m³ 3.7960 Rp 905,661.72 Rp 3,437,891.87
Besi beton kg 402.4526 Rp 9,904.33 Rp 3,986,023.36
Bekisting dinding (2x pakai) m2 5.9550 Rp 266,617.80 Rp 1,587,709.00
Pasir urug alas saluran m³ 0.4840 Rp 134,900.00 Rp 65,291.60
2 Toping Ducting
Beton K-250 m³ 1.7280 Rp 905,661.72 Rp 1,564,983.44
Besi beton kg 162.3872 Rp 9,904.33 Rp 1,608,336.42
Bekisting dinding (2x pakai) m2 2.8800 Rp 266,617.80 Rp 767,859.26
3 Bracket
Bracket besi siku 50.5.5 (6 unit/m') kg 40.7160 Rp 21,167.50 Rp 861,855.93
Finishing cat besi siku (zinkromate) m2 22.6800 Rp 30,055.00 Rp 681,647.40
Dinabolt 10 mm bh 24.0000 Rp 20,000.00 Rp 480,000.00
4 Beton tumbuk dudukan pipa m3 0.2040 Rp 669,953.56 Rp 136,670.53
5 Tangga pipa GIP dia 2" bh 1.0000 Rp 1,000,000.00 Rp 1,000,000.00
6 Tutup Kontrol
Tutup bak kontrol, besi plat tebal 19 mm kg 98.4444 Rp 21,167.50 Rp 2,083,822.78
Finishing cat besi siku (zinkromate) m2 1.2800 Rp 30,055.00 Rp 38,470.40

Sub-Total ( 2 ) Rp 18,300,561.99

3 Peralatan

Sub-Total ( 3 ) Rp -

TOTAL BIAYA PEKERJAAN ( 1 + 2 + 3) Rp 18,300,561.99

Analisa Harga Satuan Pekerjaan - 139


DAFTAR ANALISA BESI TULANGAN
###
###

II. PEKERJAAN PONDASI

2.1. PONDASI TIANG PANCANG, 25x25 Cm


Panjang 18,00 m

VOLUME TIANG PANCANG


NO TYPE PILE CAP JML JML PNCG Ttk Pancang PJG PNCG TTL PANCANG
- Pondasi Type P-1 5.00 1.00 5.00 ttk 18.00 90.000 m'
- Pondasi Type P-1 7.00 1.00 7.00 ttk 18.00 126.000 m'
- Pondasi Type P-2 10.00 2.00 20.00 ttk 18.00 360.000 m'
- Pondasi Type P-3 4.00 3.00 12.00 ttk 18.00 216.000 m'
- Pondasi Type P-4 4.00 4.00 16.00 ttk 18.00 288.000 m'
- Pondasi Type P-5 5.00 5.00 25.00 ttk 18.00 450.000 m'
- Pondasi Type P-6 3.00 6.00 18.00 ttk 18.00 324.000 m'
- Pondasi Type P-8 3.00 8.00 24.00 ttk 18.00 432.000 m'
- Pondasi Type P-9 3.00 8.00 24.00 ttk 18.00 432.000 m'
- Pondasi Type P-10 1.00 8.00 8.00 ttk 18.00 144.000 m'
- Pondasi Type P-11 3.00 8.00 24.00 ttk 18.00 432.000 m'
- Pondasi Type P-12 2.00 8.00 16.00 ttk 18.00 288.000 m'
- Pondasi Type P-13 3.00 8.00 24.00 ttk 18.00 432.000 m'
- Pondasi Type P-15 3.00 8.00 24.00 ttk 18.00 432.000 m'

TOTAL 127.00 ttk 2,286.000 m'


56.00 -

III. PEK. STRUKTUR BAWAH

VOLUME GALIAN TANAH


NO TYPE PONDASI Jumlah/bh Lebar Panjang Tinggi Volume

1 Galian tanah Pile Cap


- Pile Cap type P-1 (500x500x800) 5.00 0.80 x 0.80 x 1.20 = 3.84 m3
- Pile Cap type P-2 (500x1250x800) 7.00 0.80 x 1.55 x 1.20 = 10.42 m3
- Pile Cap type P-3 (1300x1100x800) 10.00 1.60 x 1.40 x 1.20 = 26.88 m3
- Pile Cap type P-4 (1250x1250x800) 4.00 1.45 x 1.45 x 1.20 = 10.09 m3
- Pile Cap type P-5 (1560x1560x900) 4.00 1.86 x 1.86 x 1.30 = 17.99 m3
- Pile Cap type P-6 (2000x1250x900) 5.00 2.30 x 1.55 x 1.30 = 23.17 m3
- Pile Cap type P-7 (2000x1560x900) 3.00 2.30 x 1.86 x 1.30 = 16.68 m3
- Pile Cap type P-8 (2000x1800x900) 3.00 2.30 x 2.10 x 1.30 = 18.84 m3
- Pile Cap type P-9 (2000x1800x900) 3.00 2.30 x 2.10 x 1.30 = 18.84 m3
- Pile Cap type P-10 (2270x1800x1000) 1.00 2.57 x 2.10 x 1.40 = 7.56 m3
- Pile Cap type P-11 (2750x1800x1000) 3.00 3.05 x 2.10 x 1.40 = 26.90 m3
- Pile Cap type P-12 (2750x1800x1000) 2.00 3.05 x 2.10 x 1.40 = 17.93 m3
- Pile Cap type P-13 (3500x1800x1000) 3.00 3.80 x 2.10 x 1.40 = 33.52 m3
- Pile Cap type P-15 (3500x1800x1000) 3.00 3.80 x 2.10 x 1.40 = 33.52 m3

T O T A L 266.17 m3
2 Galian tanah Tie Beam
- Tie-Beam TB-1 (400x800) 0.70 x 181.10 x 1.10 = 139.45 m3
- Tie-Beam TB-2 (400x800) 0.70 x 248.50 x 1.10 = 191.35 m3
- Tie-Beam TB-3 (400x900) 0.70 x 116.80 x 1.20 = 98.11 m3
T O T A L 330.79 m3

3 Galian tanah Pit Lift


- Pit Lift - 1 2.70 x 2.70 x 1.85 = 13.49 m3
- Pit Lift - 2 2.70 x 2.70 x 1.85 = 13.49 m3
- Pit Lift - 3 5.40 x 2.20 x 1.85 = 21.98 m3
- Tie-Beam Pilt Lift(250x500) 0.25 x 0.25 x 36.80 = 2.30 m3
T O T A L 51.25 m3

VOLUME URUGAN PASIR

analisa tulangan - 140


1 Urugan pasir alas Pile Cap
- Pile Cap type P-1 (500x500x800) 5.00 0.50 x 0.50 x 0.10 = 0.13 m3
- Pile Cap type P-2 (500x1250x800) 7.00 0.50 x 0.50 x 0.10 = 0.18 m3
- Pile Cap type P-3 (1300x1100x800) 10.00 0.80 x 1.25 x 0.10 = 1.00 m3
- Pile Cap type P-4 (1250x1250x800) 4.00 1.30 x 1.10 x 0.10 = 0.57 m3
- Pile Cap type P-5 (1560x1560x900) 4.00 1.25 x 1.25 x 0.10 = 0.63 m3
- Pile Cap type P-6 (2000x1250x900) 5.00 1.56 x 1.56 x 0.10 = 1.22 m3
- Pile Cap type P-7 (2000x1560x900) 3.00 2.00 x 1.25 x 0.10 = 0.75 m3
- Pile Cap type P-8 (2000x1800x900) 3.00 2.30 x 1.86 x 0.10 = 1.28 m3
- Pile Cap type P-9 (2000x1800x900) 3.00 2.30 x 2.10 x 0.10 = 1.45 m3
- Pile Cap type P-10 (2270x1800x1000) 1.00 2.30 x 2.10 x 0.10 = 0.48 m3
- Pile Cap type P-11 (2750x1800x1000) 3.00 2.57 x 2.10 x 0.10 = 1.62 m3
- Pile Cap type P-12 (2750x1800x1000) 2.00 3.05 x 2.10 x 0.10 = 1.28 m3
- Pile Cap type P-13 (3500x1800x1000) 3.00 3.05 x 2.10 x 0.10 = 1.92 m3
- Pile Cap type P-15 (3500x1800x1000) 3.00 3.80 x 2.10 x 0.10 = 2.39 m3
T O T A L 5.75 m3
2 Urugan pasir alas Tie-Beam
- Tie-Beam TB-1 (400x800) 0.40 x 181.10 x 0.10 = 7.24 m3
- Tie-Beam TB-2 (400x800) 0.40 x 248.50 x 0.10 = 9.94 m3
- Tie-Beam TB-3 (400x900) 0.40 x 116.80 x 0.10 = 4.67 m3
T O T A L 17.18 m3
3 Urugan Pasir Pit Lift
- Pit Lift - 1 2.70 x 2.70 x 0.10 = 0.73 m3
- Pit Lift - 2 2.70 x 2.70 x 0.10 = 0.73 m3
- Pit Lift - 3 5.40 x 2.20 x 0.10 = 1.19 m3
T O T A L 0.73 m3

VOLUME LANTAI KERJA


1 Lantai Kerjaalas Pile Cap
- Pile Cap type P-1 (500x500x800) 5.00 0.50 x 0.50 = 1.25 m2
- Pile Cap type P-2 (500x1250x800) 7.00 0.50 x 0.50 = 1.75 m2
- Pile Cap type P-3 (1300x1100x800) 10.00 0.80 x 1.25 = 10.00 m2
- Pile Cap type P-4 (1250x1250x800) 4.00 1.30 x 1.10 = 5.72 m2
- Pile Cap type P-5 (1560x1560x900) 4.00 1.25 x 1.25 = 6.25 m2
- Pile Cap type P-6 (2000x1250x900) 5.00 1.56 x 1.56 = 12.17 m2
- Pile Cap type P-7 (2000x1560x900) 3.00 2.00 x 1.25 = 7.50 m2
- Pile Cap type P-8 (2000x1800x900) 3.00 2.30 x 1.86 = 12.83 m2
- Pile Cap type P-9 (2000x1800x900) 3.00 2.30 x 2.10 = 14.49 m2
- Pile Cap type P-10 (2270x1800x1000) 1.00 2.30 x 2.10 = 4.83 m2
- Pile Cap type P-11 (2750x1800x1000) 3.00 2.57 x 2.10 = 16.19 m2
- Pile Cap type P-12 (2750x1800x1000) 2.00 3.05 x 2.10 = 12.81 m2
- Pile Cap type P-13 (3500x1800x1000) 3.00 3.05 x 2.10 = 19.22 m2
- Pile Cap type P-15 (3500x1800x1000) 3.00 3.80 x 2.10 = 23.94 m2
T O T A L 57.47 m2
2 Lantai Kerja alas Tie-Beam
- Tie-Beam TB-1 (400x800) 0.40 x 181.10 = 72.44 m2
- Tie-Beam TB-2 (400x800) 0.40 x 248.50 = 99.40 m2
- Tie-Beam TB-3 (400x900) 0.40 x 116.80 = 46.72 m2
T O T A L 171.84 m2
3 Lantai kerja Pit Lift
- Pit Lift - 1 1.00 2.70 x 2.70 x = 7.29 m2
- Pit Lift - 2 1.00 2.70 x 2.70 x = 7.29 m2
- Pit Lift - 3 1.00 5.40 x 2.20 x = 11.88 m2
T O T A L 7.29 m2
TULANGAN PILE CAP
NO TYPE PILE CAP TULANGAN RINCIAN BERAT / M' TTL BRT BESI

1 Pile Cap type P-1 (500x500x800) (X) (Y)


- Volume beton / unit 0.50 x 0.50 x 0.80 = 0.200
- Besi tulangan
- Tulangan atas (X) D13 - 150 3.33 x 0.70 x 1.042 = 2.43
- Tulangan atas (Y) D13 - 150 3.33 x 0.70 x 1.042 = 2.43
- Tulangan bawah (X) D19 - 150 3.33 x 2.10 x 2.250 = 15.75
- Tulangan bawah (Y) D19 - 150 3.33 x 2.10 x 2.250 = 15.75
- Tulang pinggang 1 D.13 1.00 x 2.00 x 1.042 = 2.08
Sub-Total 38.44
Faktor penyusutan dll. 10% 3.84
Total 42.29
Besi tulangan / M3 beton 211.44

2 Pile Cap type P-2 (500x1250x800) (X) (Y)

analisa tulangan - 141


- Volume beton / unit 0.50 x 1.25 x 0.80 = 0.500
- Besi tulangan
- Tulangan atas (X) D13 - 150 3.33 x 1.45 x 1.042 = 5.03
- Tulangan atas (Y) D13 - 150 8.33 x 0.70 x 1.042 = 6.08
- Tulangan bawah (X) D19 - 150 3.33 x 2.85 x 2.250 = 21.38
- Tulangan bawah (Y) D19 - 150 8.33 x 2.10 x 2.250 = 39.38
- Tulang pinggang 1 D.13 1.00 x 3.50 x 1.042 = 3.65
Sub-Total 75.51
Faktor penyusutan dll. 10% 7.55
Total 83.06
Besi tulangan / M3 beton 166.12

3 Pile Cap type P-3 (1300x1100x800) (X) (Y)


- Volume beton / unit 1.30 x 1.10 x 0.80 = 1.144
- Besi tulangan
- Tulangan atas (X) D13 - 150 8.67 x 1.30 x 1.042 = 11.74
- Tulangan atas (Y) D13 - 150 7.33 x 1.50 x 1.042 = 11.46
- Tulangan bawah (X) D19 - 150 8.67 x 2.70 x 2.250 = 52.65
- Tulangan bawah (Y) D19 - 150 7.33 x 2.90 x 2.250 = 47.85
- Tulang pinggang 1 D.13 1.00 x 4.80 x 1.042 = 5.00
Sub-Total 128.69
Faktor penyusutan dll. 10% 12.87
Total 141.56
Besi tulangan / M3 beton 123.74

4 Pile Cap type P-4 (1250x1250x800) (X) (Y)


- Volume beton / unit 1.25 x 1.25 x 0.80 = 1.250
- Besi tulangan
- Tulangan atas (X) D13 - 150 8.33 x 1.45 x 1.042 = 12.59
- Tulangan atas (Y) D13 - 150 8.33 x 1.45 x 1.042 = 12.59
- Tulangan bawah (X) D19 - 150 8.33 x 2.25 x 2.250 = 42.19
- Tulangan bawah (Y) D19 - 150 8.33 x 2.25 x 2.250 = 42.19
- Tulang pinggang 1 D.13 1.00 x 5.20 x 1.042 = 5.42
Sub-Total 114.97
Faktor penyusutan dll. 10% 11.50
Total 126.46
Besi tulangan / M3 beton 101.17

5 Pile Cap type P-5 (1560x1560x900) (X) (Y)


- Volume beton / unit 1.56 x 1.56 x 0.90 = 2.190
- Besi tulangan
- Tulangan atas (X) D16 - 150 10.40 x 1.76 x 1.583 = 28.98
- Tulangan atas (Y) D16 - 150 10.40 x 1.76 x 1.583 = 28.98
- Tulangan bawah (X) D22 - 150 10.40 x 3.36 x 2.983 = 104.25
- Tulangan bawah (Y) D22 - 150 10.40 x 3.36 x 2.983 = 104.25
- Tulang pinggang 1 D.16 1.00 x 6.44 x 1.583 = 10.20
Sub-Total 276.66
Faktor penyusutan dll. 10% 27.67
Total 304.32
Besi tulangan / M3 beton 138.95

6 Pile Cap type P-6 (2000x1250x900) (X) (Y)


- Volume beton / unit 2.00 x 1.25 x 0.90 = 2.250
- Besi tulangan
- Tulangan atas (X) D16 - 150 13.33 x 1.45 x 1.583 = 30.61
- Tulangan atas (Y) D16 - 150 8.33 x 2.20 x 1.583 = 29.03
- Tulangan bawah (X) D22 - 150 13.33 x 3.05 x 2.983 = 121.32
- Tulangan bawah (Y) D22 - 150 8.33 x 3.80 x 2.983 = 94.47
- Tulang pinggang 1 D.16 1.00 x 6.70 x 1.583 = 10.61
Sub-Total 286.04
Faktor penyusutan dll. 10% 28.60
Total 314.65
Besi tulangan / M3 beton 139.84

7 Pile Cap type P-7 (2000x1560x900) (X) (Y)


- Volume beton / unit 2.00 x 1.56 x 0.90 = 2.808
- Besi tulangan
- Tulangan atas (X) D16 - 150 13.33 x 1.76 x 1.583 = 37.16
- Tulangan atas (Y) D16 - 150 10.40 x 2.20 x 1.583 = 36.23
- Tulangan bawah (X) D22 - 150 13.33 x 3.36 x 2.983 = 133.65
- Tulangan bawah (Y) D22 - 150 10.40 x 3.80 x 2.983 = 117.90
- Tulang pinggang 1 D.16 1.00 x 7.32 x 1.583 = 11.59

analisa tulangan - 142


Sub-Total 336.53
Faktor penyusutan dll. 10% 33.65
Total 370.18
Besi tulangan / M3 beton 131.83

8 Pile Cap type P-8 (2000x1800x900) (X) (Y)


- Volume beton / unit 2.00 x 1.80 x 0.90 = 3.240
- Besi tulangan
- Tulangan atas (X) D16 - 150 13.33 x 2.00 x 1.583 = 42.22
- Tulangan atas (Y) D16 - 150 12.00 x 2.20 x 1.583 = 41.80
- Tulangan bawah (X) D22 - 150 13.33 x 3.60 x 2.983 = 143.20
- Tulangan bawah (Y) D22 - 150 12.00 x 3.80 x 2.983 = 136.04
- Tulang pinggang 1 D.16 1.00 x 7.80 x 1.583 = 12.35
Sub-Total 375.61
Faktor penyusutan dll. 10% 37.56
Total 413.17
Besi tulangan / M3 beton 127.52

9 Pile Cap type P-9 (2000x1800x900) (X) (Y)


- Volume beton / unit 2.00 x 1.80 x 0.90 = 3.240
- Besi tulangan
- Tulangan atas (X) D16 - 150 13.33 x 2.00 x 1.583 = 42.22
- Tulangan atas (Y) D16 - 150 12.00 x 2.20 x 1.583 = 41.80
- Tulangan bawah (X) D22 - 150 13.33 x 3.60 x 2.983 = 143.20
- Tulangan bawah (Y) D22 - 150 12.00 x 3.80 x 2.983 = 136.04
- Tulang pinggang 1 D.16 1.00 x 7.80 x 1.583 = 12.35
Sub-Total 375.61
Faktor penyusutan dll. 10% 37.56
Total 413.17
Besi tulangan / M3 beton 127.52

10 Pile Cap type P-10 (2270x1800x1000) (X) (Y)


- Volume beton / unit 2.27 x 1.80 x 1.00 = 4.086
- Besi tulangan
- Tulangan atas (X) D16 - 150 15.13 x 2.00 x 1.583 = 47.92
- Tulangan atas (Y) D16 - 150 12.00 x 2.47 x 1.583 = 46.93
- Tulangan bawah (X) D22 - 150 15.13 x 3.80 x 2.983 = 171.56
- Tulangan bawah (Y) D22 - 150 12.00 x 4.27 x 2.983 = 152.87
- Tulang pinggang 1 D.16 1.00 x 8.34 x 1.583 = 13.21
Sub-Total 432.48
Faktor penyusutan dll. 10% 43.25
Total 475.73
Besi tulangan / M3 beton 116.43

11 Pile Cap type P-11 (2750x1800x1000) (X) (Y)


- Volume beton / unit 2.75 x 1.80 x 1.00 = 4.950
- Besi tulangan
- Tulangan atas (X) D16 - 150 18.33 x 2.00 x 1.583 = 58.06
- Tulangan atas (Y) D16 - 150 12.00 x 2.95 x 1.583 = 56.05
- Tulangan bawah (X) D22 - 150 18.33 x 3.80 x 2.983 = 207.84
- Tulangan bawah (Y) D22 - 150 12.00 x 4.75 x 2.983 = 170.05
- Tulang pinggang 1 D.16 1.00 x 9.30 x 1.583 = 14.73
Sub-Total 506.72
Faktor penyusutan dll. 10% 50.67
Total 557.39
Besi tulangan / M3 beton 112.60

12 Pile Cap type P-12 (2750x1800x1000) (X) (Y)


- Volume beton / unit 2.75 x 1.80 x 1.00 = 4.950
- Besi tulangan
- Tulangan atas (X) D16 - 150 18.33 x 2.00 x 1.583 = 58.06
- Tulangan atas (Y) D16 - 150 12.00 x 2.95 x 1.583 = 56.05
- Tulangan bawah (X) D22 - 150 18.33 x 3.80 x 2.983 = 207.84
- Tulangan bawah (Y) D22 - 150 12.00 x 4.75 x 2.983 = 170.05
- Tulang pinggang 1 D.16 1.00 x 9.30 x 1.583 = 14.73
Sub-Total 506.72
Faktor penyusutan dll. 10% 50.67
Total 557.39
Besi tulangan / M3 beton 112.60

analisa tulangan - 143


13 Pile Cap type P-13 (3500x1800x1000) (X) (Y)
- Volume beton / unit 3.50 x 1.80 x 1.00 = 6.300
- Besi tulangan
- Tulangan atas (X) D16 - 150 23.33 x 2.00 x 1.583 = 73.89
- Tulangan atas (Y) D16 - 150 12.00 x 3.70 x 1.583 = 70.30
- Tulangan bawah (X) D22 - 150 23.33 x 3.80 x 2.983 = 264.52
- Tulangan bawah (Y) D22 - 150 12.00 x 5.50 x 2.983 = 196.90
- Tulang pinggang 1 D.16 1.00 x 10.80 x 1.583 = 17.10
Sub-Total 622.71
Faktor penyusutan dll. 10% 62.27
Total 684.98
Besi tulangan / M3 beton 108.73

14 Pile Cap type P-15 (3500x1800x1000) (X) (Y)


- Volume beton / unit 3.50 x 1.80 x 1.00 = 6.300
- Besi tulangan
- Tulangan atas (X) D16 - 150 23.33 x 2.00 x 1.583 = 73.89
- Tulangan atas (Y) D16 - 150 12.00 x 3.70 x 1.583 = 70.30
- Tulangan bawah (X) D22 - 150 23.33 x 3.80 x 2.983 = 264.52
- Tulangan bawah (Y) D22 - 150 12.00 x 5.50 x 2.983 = 196.90
- Tulang pinggang 1 D.16 1.00 x 10.80 x 1.583 = 17.10
Sub-Total 622.71
Faktor penyusutan dll. 10% 62.27
Total 684.98
Besi tulangan / M3 beton 108.73

TULANGAN TIE BEAM


NO TYPE PILE CAP TULANGAN RINCIAN BERAT / M' TTL BRT BESI

1. Tie-Beam TB-1 (400x800)


- Volume balok / m' 1.00 x 0.40 x 0.80 = 0.320
- Besi tulangan
- Tulangan Utama atas 5 D22 5.00 x 1.00 x 2.983 = 14.92
- Tulangan Utama bawah 5 D22 5.00 x 1.00 x 2.983 = 14.92
- Tulang pinggang 2 D.10 2.00 x 1.00 x 0.617 = 1.23
- Sengkang D 10 - 150 6.67 x 1.64 x 0.617 = 6.74
Sub-Total 37.81
Faktor penyusutan dll. 10% 3.78
Total 41.59
Besi tulangan / M3 beton 129.97

2 Tie-Beam TB-2 (400x800)


- Volume balok / m' 1.00 x 0.40 x 0.80 = 0.320
- Besi tulangan
- Tulangan Utama atas 6 D22 6.00 x 1.00 x 2.983 = 17.90
- Tulangan Utama bawah 6 D22 6.00 x 1.00 x 2.983 = 17.90
- Tulang pinggang 2 D.13 2.00 x 1.00 x 1.042 = 2.08
- Sengkang D 10 - 150 6.67 x 1.44 x 0.617 = 5.92
Sub-Total 43.80
Faktor penyusutan dll. 10% 4.38
Total 48.18
Besi tulangan / M3 beton 150.57

3 Tie-Beam TB-3 (400x900)


- Volume balok / m' 1.00 x 0.40 x 0.90 = 0.360
- Besi tulangan
- Tulangan Utama atas 6 D22 6.00 x 1.00 x 2.983 = 17.90
- Tulangan Utama bawah 6 D22 6.00 x 1.00 x 2.983 = 17.90
- Tulang pinggang 2 D.13 2.00 x 1.00 x 1.042 = 2.08
- Sengkang D 10 - 150 6.67 x 1.44 x 1.042 = 10.00
Sub-Total 47.88
Faktor penyusutan dll. 10% 4.79
Total 52.67
Besi tulangan / M3 beton 146.31

4 Tie-Beam Pilt Lift(250x500)


- Volume balok / m' 1.00 x 0.25 x 0.50 = 0.125
- Besi tulangan
- Tulangan Utama atas 4 D16 4.00 x 1.00 x 1.583 = 6.33

analisa tulangan - 144


- Tulangan Utama bawah 4 D16 4.00 x 1.00 x 1.583 = 6.33
- Tulang pinggang - x 1.00 x 1.042 = -
- Sengkang D 10 - 150 6.67 x 1.44 x 0.617 = 5.92
Sub-Total 18.59
Faktor penyusutan dll. 10% 1.86
Total 20.45
Besi tulangan / M3 beton 163.56

5 BALOK SEPARATOR BEAM PIT LIFT, SB1 (150x300)


- Volume balok / m' 1.00 x 0.15 x 0.30 = 0.045
- Besi tulangan
- Tulangan Utama atas 2 D13 2.00 x 1.00 x 1.583 = 3.17
- Tulangan Utama bawah 2 D13 2.00 x 1.00 x 1.583 = 3.17
- Tulang pinggang - x 1.00 x 0.617 = -
- Sengkang d 8 - 150 6.67 x 1.44 x 0.617 = 5.92
Sub-Total 12.25
Faktor penyusutan dll. 10% 1.23
Total 13.48
Besi tulangan / M3 beton 299.53
1. Pelat lantai Dasar Pit Lift
- Volume Plat lantai, modul 2,7 x 2,7 m, tbl. 25 cm 2.70 x 2.70 x 0.25 = 1.823
- Besi tulangan
- Tulangan atas & bawah ( X ) D13 - 150 36.00 x 2.70 x 1.583 = 153.90
- Tulangan atas & bawah ( Y ) D13 - 150 21.60 x 2.70 x 1.583 = 92.34
Sub-Total = 246.24
Faktor penyusutan dll. 10% 24.62
Total 270.86
Besi tulangan / M3 beton 148.62

2. Pelat Dinding Pit Lift


- Volume Dinding , modul 2,7 x 2,2 m, tbl. 20 cm 2.70 x 1.60 x 0.20 = 0.864
- Besi tulangan
- Tulangan horisontal ( X ) D13 - 150 21.33 x 2.70 x 1.823 = 104.98
- Tulangan vertikal ( Y ) D13 - 150 21.60 x 1.60 x 1.823 = 62.99
Sub-Total = 167.96
Faktor penyusutan dll. 10% 16.80
Total 184.76
Besi tulangan / M3 beton 213.84

1. Pelat lantai Dasar


- Volume Plat lantai, modul 2,67 x 6 m, tbl. 12 cm 1.00 x 1.00 x 0.12 = 0.120
- Besi tulangan
- Tulangan atas & bawah ( X ) D10 - 200 10.00 x 1.00 x 1.042 = 10.42
- Tulangan atas & bawah ( Y ) D10 - 200 10.00 x 1.00 x 1.042 = 10.42
Sub-Total = 20.83
Faktor penyusutan dll. 10% 2.08
Total 22.92
Besi tulangan / M3 beton 190.97

TULANGAN KOLOM
NO TYPE KOLOM TULANGAN RINCIAN BERAT / M' TTL BRT BESI

1 Kolom Beton Type K-0 (500x500), khusus Lantai-Dasar


- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.50 x 0.50 = 1.050 m3
- Besi tulangan
- Tulangan kaki kolom 20 D 19 20.00 x 1.50 x 2.250 = 67.50
- Tulangan Utama 20 D 19 20.00 x 4.20 x 2.250 = 189.00
- Tulangan stek atas (40D) 20 D 19 20.00 x 0.76 x 2.250 = 34.20
- Sengkang D 10 - 150 28.00 x 1.90 x 1.042 = 55.42
- Tulangan pengekang 2x2D10-500 33.60 x 0.65 x 1.042 = 22.75
Sub-Total 368.87
Faktor penyusutan dll. 10%
Total 368.87
Besi tulangan / M3 beton 351.30

1.a Kolom Beton Type K-0 (500x500), khusus Lantai-2


- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.50 x 0.50 = 1.050 m3
- Besi tulangan
- Tulangan kaki kolom - - x 1.50 x 2.250 = -

analisa tulangan - 145


- Tulangan Utama 20 D 19 20.00 x 4.20 x 2.250 = 189.00
- Tulangan stek atas (40D) 20 D 19 20.00 x 0.76 x 2.250 = 34.20
- Sengkang D 10 - 150 28.00 x 1.90 x 0.617 = 32.81
- Tulangan pengekang 2x2D10-500 33.60 x 0.65 x 0.617 = 13.47
Sub-Total 269.47
Faktor penyusutan dll. 10%
Total 269.47
Besi tulangan / M3 beton 256.64

2 Kolom Beton Type K-1 (450x550), khusus Lantai-Dasar


- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.45 x 0.55 = 1.040 m3
- Besi tulangan
- Tulangan kaki kolom 20 D 19 20.00 x 1.50 x 2.250 = 67.50
- Tulangan Utama 20 D 19 20.00 x 3.90 x 2.250 = 175.50
- Tulangan stek atas (40D) 20 D 19 20.00 x 0.76 x 2.250 = 34.20
- Sengkang D 10 - 150 28.00 x 1.90 x 0.617 = 32.81
- Tulangan pengekang 2x2D10-500 33.60 x 0.65 x 0.617 = 13.47
Sub-Total 323.47
Faktor penyusutan dll. 10%
Total 323.47
Besi tulangan / M3 beton 311.18
2.a. Kolom Beton Type K-1 (450x550), khusus Lantai 2
- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.45 x 0.55 = 1.040 m3
- Besi tulangan
- Tulangan kaki kolom - - x 1.50 x 2.250 = -
- Tulangan Utama 20 D 19 20.00 x 3.90 x 2.250 = 175.50
- Tulangan stek atas (40D) 20 D 19 20.00 x 0.76 x 2.250 = 34.20
- Sengkang D 10 - 150 28.00 x 1.90 x 0.617 = 32.81
- Tulangan pengekang 2x2D10-500 33.60 x 0.65 x 0.617 = 13.47
Sub-Total 255.97
Faktor penyusutan dll. 10%
Total 255.97
Besi tulangan / M3 beton 246.25
3 Kolom Beton Type K-2 (450x500), khusus Lantai-Dasar
- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.45 x 0.50 = 0.945 m3
- Besi tulangan
- Tulangan kaki kolom 18 D 19 18.00 x 1.50 x 2.250 = 60.75
- Tulangan Utama 18 D 19 18.00 x 3.90 x 2.250 = 157.95
- Tulangan stek atas (40D) 18 D 19 18.00 x 0.76 x 2.250 = 30.78
- Sengkang D 10 - 150 28.00 x 1.80 x 1.042 = 52.50
- Tulangan pengekang 2x2D10-500 33.60 x 0.60 x 1.042 = 21.00
Sub-Total 322.98
Faktor penyusutan dll. 10%
Total 322.98
Besi tulangan / M3 beton 341.78

3.a Kolom Beton Type K-2 (450x500), khusus Lantai-2


- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.45 x 0.50 = 0.945 m3
- Besi tulangan
- Tulangan kaki kolom - - x 1.50 x 2.250 = -
- Tulangan Utama 18 D 19 18.00 x 3.90 x 2.250 = 157.95
- Tulangan stek atas (40D) 18 D 19 18.00 x 0.76 x 2.250 = 30.78
- Sengkang D 10 - 150 28.00 x 1.80 x 0.617 = 31.08
- Tulangan pengekang 2x2D10-500 33.60 x 0.60 x 0.617 = 12.43
Sub-Total 232.24
Faktor penyusutan dll. 10%
Total 232.24
Besi tulangan / M3 beton 245.76

4 Kolom Beton Type K-3 (450x450), khusus Lantai-Dasar


- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.45 x 0.45 = 0.851 m3
- Besi tulangan
- Tulangan kaki kolom 16 D 19 12.00 x 1.50 x 2.250 = 40.50
- Tulangan Utama 16 D 19 12.00 x 3.90 x 2.250 = 105.30
- Tulangan stek atas (40D) 16 D 19 12.00 x 0.76 x 2.250 = 20.52
- Sengkang D 10 - 150 28.00 x 1.30 x 1.042 = 37.92
- Tulangan pengekang 1D10 - 500 8.40 x 0.35 x 1.042 = 3.06
Sub-Total 207.30
Faktor penyusutan dll. 10%
Total 207.30
Besi tulangan / M3 beton 243.74

analisa tulangan - 146


4.a Kolom Beton Type K-3 (450x450), khusus Lantai-2
- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.45 x 0.45 = 0.851 m3
- Besi tulangan
- Tulangan kaki kolom - - x 1.50 x 2.250 = -
- Tulangan Utama 16 D 19 16.00 x 3.90 x 2.250 = 140.40
- Tulangan stek atas (40D) 16 D 19 16.00 x 0.76 x 2.250 = 27.36
- Sengkang D 10 - 150 28.00 x 1.30 x 0.617 = 22.45
- Tulangan pengekang 1D10 - 500 8.40 x 0.35 x 0.617 = 1.81
Sub-Total 192.02
Faktor penyusutan dll. 10%
Total 192.02
Besi tulangan / M3 beton 225.77

4.b Kolom Beton Type K-0/1/2/3 (300x300), khusus Lantai-Atap


- Volume kolom, tinggi 4,2 M (-30 s/d +390) 4.20 x 0.30 x 0.30 = 0.378 m3
- Besi tulangan
- Tulangan kaki kolom - - x 1.50 x 2.250 = -
- Tulangan Utama 12 D 16 16.00 x 3.90 x 1.583 = 98.80
- Tulangan stek atas (40D) 12 D 16 16.00 x 0.76 x 1.583 = 19.25
- Sengkang D 10 - 150 28.00 x 1.30 x 1.042 = 37.92
- Tulangan pengekang 1D10 - 500 8.40 x 0.35 x 1.042 = 3.06
Sub-Total 159.03
Faktor penyusutan dll. 10%
Total 159.03
Besi tulangan / M3 beton 420.72

5 Kolom Beton Type K-4 (200x400), khusus Lantai-Dasar


- Volume kolom, tinggi 4,2 M (-15 s/d +390) 4.20 x 0.20 x 0.40 = 0.336 m3
- Besi tulangan
- Tulangan kaki kolom 8 D 16 8.00 x 1.80 x 1.583 = 22.80
- Tulangan Utama 8 D 16 8.00 x 4.20 x 1.583 = 53.20
- Tulangan stek atas (40D) 8 D 16 8.00 x 0.52 x 1.583 = 6.59
- Sengkang D 10 - 150 28.00 x 1.15 x 1.042 = 33.54
Sub-Total 116.13
Faktor penyusutan dll. 10%
Total 116.13
Besi tulangan / M3 beton 345.62

5.a Kolom Beton Type K-4 (200x400), khusus Lantai-2


- Volume kolom, tinggi 4,2 M (-15 s/d +390) 4.20 x 0.20 x 0.40 = 0.336 m3
- Besi tulangan
- Tulangan kaki kolom - - x 1.80 x 1.583 = -
- Tulangan Utama 8 D 16 8.00 x 4.20 x 1.583 = 53.20
- Tulangan stek atas (40D) 8 D 16 8.00 x 0.52 x 1.583 = 6.59
- Sengkang D 10 - 150 28.00 x 1.15 x 0.617 = 19.86
Sub-Total 79.64
Faktor penyusutan dll. 10%
Total 79.64
Besi tulangan / M3 beton 237.03

6 Kolom Beton Pedestal Baja K5(500x500)


- Volume kolom, tinggi 1,0 M (-11,5 s/d +12,5) 1.00 x 0.50 x 0.50 = 0.250 m3
- Besi tulangan
- Tulangan kaki kolom 14 D16 - x 0.55 x 1.583 = -
- Tulangan Utama 14 D16 14.00 x 1.60 x 1.583 = 35.47
- Tulangan stek atas (40D) - - x 0.76 x 1.583 = -
- Sengkang D 10 - 150 6.67 x 1.00 x 1.042 = 6.94
- Tulangan pengekang - - x 0.35 x 1.042 = -
Sub-Total 42.41
Faktor penyusutan dll. 10%
Total 42.41
Besi tulangan / M3 beton 169.64

7 Kolom Beton + Baja K5A(500x500)


- Volume kolom, tinggi 1,0 M (-11,5 s/d +12,5) 1.00 x 0.50 x 0.50 = 0.250 m3
- Besi tulangan
- Tulangan kaki kolom 12 D13 - x 0.55 x 1.208 = -
- Tulangan Utama 12 D13 14.00 x 1.60 x 1.208 = 27.07
- Tulangan stek atas (40D) - - x 0.76 x 1.208 = -
- Sengkang D 10 - 150 6.67 x 1.00 x 0.617 = 4.11

analisa tulangan - 147


- Tulangan pengekang - - x 0.35 x 0.617 = -
Sub-Total 31.18
Faktor penyusutan dll. 10%
Total 31.18
Besi tulangan / M3 beton 124.71

TULANGAN TANGGA
NO TYPE KOLOM TULANGAN RINCIAN BERAT / M' TTL BRT BESI

1 TANGGA BETON (TYPICAL)


- Volume plat Tangga, modul 3,5x1m, tebal 15 cm. 3.50 x 1.00 x 0.15 = 0.525 m3
- Besi tulangan
- Tulangan utama D13-150 13.33 x 3.50 x 1.042 = 48.61
- Tulangan pembagi / sengkang D10-150 23.33 x 2.50 x 1.042 = 60.76
- Tulangan pengekang T-D10-300 38.89 x 0.60 x 1.042 = 24.31
Sub-Total 133.68
Faktor penyusutan dll. 10% 13.37
Total 147.05
Besi tulangan / M3 beton 280.09

V. PEK. STRUKTUR LANTAI - 2

5.1. TULANGAN BALOK PLAT LANTAI (TYPICAL) TOTAL BERAT


NO TYPE BALOK TULANGAN RINCIAN BERAT / M' BESI

1. Balok Plat Lantai, Type B1 (250x650)


- Volume balok, bentang 8m' 8.00 x 0.25 x 0.65 = 1.300
- Besi tulangan
- Tulangan Utama atas 4 D.19 4.00 x 8.00 x 2.250 = 72.00
- Tulangan Utama bawah 4 D.19 4.00 x 8.00 x 2.250 = 72.00
- Tulangan extra atas (1/4 L) 2 x 4 D.19 8.00 x 2.65 x 2.250 = 47.70
- Tulangan extra bawah (1/2 L) 1 x 4 D.19 4.00 x 5.30 x 2.250 = 47.70
- Sengkang tumpuan (2x1/4L) D 10 - 125 32.00 x 1.95 x 0.617 = 38.48
- Sengkang lapangan (1/2L) D 10 - 175 22.86 x 1.95 x 0.617 = 27.49
- Tulang pinggang 2 D.10 2.00 x 8.00 x 0.617 = 9.87
Sub-Total 315.23
Faktor penyusutan dll. 10% 31.52
Total 346.76
Besi tulangan / M3 beton 266.74

1.a. Balok Plat Lantai, Type B1 (250x650)


- Volume balok, bentang 8m' 8.00 x 0.25 x 0.65 = 1.300
- Besi tulangan
- Tulangan Utama atas 4D.19 4.00 x 8.00 x 2.250 = 72.00
- Tulangan Utama bawah 4 D.19 4.00 x 8.00 x 2.250 = 72.00
- Tulangan extra atas (1/4 L) 2 x 2 D.19 4.00 x 2.65 x 2.250 = 23.85
- Tulangan extra bawah (1/2 L) 1 x 2 D.19 2.00 x 5.30 x 2.250 = 23.85
- Sengkang tumpuan (2x1/4L) D 10 - 125 32.00 x 1.95 x 0.617 = 38.48
- Sengkang lapangan (1/2L) D 10 - 175 22.86 x 1.95 x 0.617 = 27.49
- Tulang pinggang 2 D.10 2.00 x 8.00 x 0.617 = 9.87
Sub-Total 267.53
Faktor penyusutan dll. 10% 26.75
Total 294.29
Besi tulangan / M3 beton 226.37

1.b. Balok Plat Lantai, Type BA1 (250x650)


- Volume balok, bentang 6m' 6.00 x 0.25 x 0.65 = 0.975
- Besi tulangan
- Tulangan Utama atas 2 D.19 2.00 x 6.00 x 2.250 = 27.00
- Tulangan Utama bawah 2 D.19 2.00 x 6.00 x 2.250 = 27.00
- Tulangan extra atas (1/4 L) 2 x 3 D.19 6.00 x 2.15 x 2.250 = 29.03
- Tulangan extra bawah (1/2 L) 1 x 3 D.19 3.00 x 4.30 x 2.250 = 29.03
- Sengkang tumpuan (2x1/4L) D 10 - 125 24.00 x 1.95 x 0.617 = 28.86
- Sengkang lapangan (1/2L) D 10 - 175 17.14 x 1.95 x 0.617 = 20.61
- Tulang pinggang 2 D.10 2.00 x 6.00 x 0.617 = 7.40
Sub-Total 168.92
Faktor penyusutan dll. 10% 16.89
Total 185.82
Besi tulangan / M3 beton 190.58

1.c. Balok Plat Lantai, Type BA2(250x500)


- Volume balok, bentang 6m' 6.00 x 0.25 x 0.65 = 0.975
- Besi tulangan
- Tulangan Utama atas 2 D.16 2.00 x 6.00 x 1.583 = 19.00

analisa tulangan - 148


- Tulangan Utama bawah 2 D.16 2.00 x 6.00 x 1.583 = 19.00
- Tulangan extra atas (1/4 L) 2 x 3 D.16 6.00 x 2.15 x 1.583 = 20.43
- Tulangan extra bawah (1/2 L) 1 x 3 D.16 3.00 x 4.30 x 1.583 = 20.43
- Sengkang tumpuan (2x1/4L) D 10 - 125 24.00 x 1.95 x 0.617 = 28.86
- Sengkang lapangan (1/2L) D 10 - 175 17.14 x 1.95 x 0.617 = 20.61
- Tulang pinggang 2 D.10 2.00 x 6.00 x 0.617 = 7.40
Sub-Total 135.72
Faktor penyusutan dll. 10% 13.57
Total 149.30
Besi tulangan / M3 beton 153.12

1.d. Balok Plat Lantai, Type BA3(200x400)


- Volume balok, bentang 8m' 2.10 x 0.20 x 0.40 = 0.168
- Besi tulangan
- Tulangan Utama atas 2 D.16 2.00 x 2.10 x 1.583 = 6.65
- Tulangan Utama bawah 2 D.16 2.00 x 2.10 x 1.583 = 6.65
- Tulangan extra atas (1/4 L) 2 x 2 D.16 4.00 x 0.93 x 1.583 = 5.86
- Tulangan extra bawah (1/2 L) 1 x 2 D.16 2.00 x 1.85 x 1.583 = 5.86
- Sengkang tumpuan (2x1/4L) D 10 - 150 7.00 x 1.35 x 0.617 = 5.83
- Sengkang lapangan (1/2L) D 10 - 200 5.25 x 1.35 x 0.617 = 4.37
- Tulang pinggang 2 D.10 2.00 x 2.10 x 0.617 = 2.59
Sub-Total 37.80
Faktor penyusutan dll. 10% 3.78
Total 41.59
Besi tulangan / M3 beton 247.53

1.e. Balok Plat Lantai, Type BA4(150x400)


- Volume balok, bentang 8m' 2.10 x 0.15 x 0.40 = 0.126
- Besi tulangan
- Tulangan Utama atas 2 D.13 2.00 x 2.10 x 1.042 = 4.38
- Tulangan Utama bawah 2 D.13 2.00 x 2.10 x 1.042 = 4.38
- Tulangan extra atas (1/4 L) 2 x 2 D.13 4.00 x 0.93 x 1.042 = 3.85
- Tulangan extra bawah (1/2 L) 1 x 2 D.13 2.00 x 1.85 x 1.042 = 3.85
- Sengkang tumpuan (2x1/4L) D 10 - 150 7.00 x 1.25 x 0.617 = 5.40
- Sengkang lapangan (1/2L) D 10 - 200 5.25 x 1.25 x 0.617 = 4.05
- Tulang pinggang 2 D.10 2.00 x 2.10 x 0.617 = 2.59
Sub-Total 28.49
Faktor penyusutan dll. 10% 2.85
Total 31.34
Besi tulangan / M3 beton 248.73
2. Balok Plat Lantai, Type B2 (300x600)
- Volume balok, bentang 8.0 m' 8.00 x 0.30 x 0.60 = 1.440
- Besi tulangan
- Tulangan Utama atas 4 D.19 4.00 x 8.00 x 2.250 = 72.00
- Tulangan Utama bawah 4 D.19 4.00 x 8.00 x 2.250 = 72.00
- Tulangan extra atas (1/4 L) 2 x 2 D.16 4.00 x 2.60 x 2.250 = 23.40
- Tulangan extra bawah (1/2 L) 1 x 2 D.16 2.00 x 5.20 x 2.250 = 23.40
- Sengkang tumpuan (2x1/4L) D 10 - 125 32.00 x 1.95 x 0.617 = 38.48
- Sengkang lapangan (1/2L) D 10 - 175 22.86 x 1.95 x 0.617 = 27.49
- Tulang pinggang 2 D.10 2.00 x 8.00 x 0.617 = 9.87
Sub-Total 266.63
Faktor penyusutan dll. 10% 26.66
Total 293.30
Besi tulangan / M3 beton 203.68

3. Balok Plat Lantai, Type B3 (250x500)


- Volume balok, bentang 4,00 m' 4.00 x 0.25 x 0.50 = 0.500
- Besi tulangan
- Tulangan Utama atas 3 D.16 3.00 x 4.00 x 2.250 = 27.00
- Tulangan Utama bawah 3 D.16 3.00 x 4.00 x 2.250 = 27.00
- Tulangan extra atas (1/4 L) 2 x 2 D.16 4.00 x 1.50 x 2.250 = 13.50
- Tulangan extra bawah (1/2 L) 1 x 2 D.16 2.00 x 3.00 x 2.250 = 13.50
- Sengkang tumpuan (2x1/4L) D 10 - 150 13.33 x 1.65 x 0.617 = 13.57
- Sengkang lapangan (1/2L) D 10 - 200 10.00 x 1.65 x 0.617 = 10.18
- Tulang pinggang 2 D.10 2.00 x 4.00 x 0.617 = 4.93
Sub-Total 109.68
Faktor penyusutan dll. 10% 10.97
Total 120.64
Besi tulangan / M3 beton 241.29

4. Balok Plat Lantai, Type B4 (250x400)


- Volume balok, bentang 4,00 m' 4.00 x 0.25 x 0.40 = 0.400
- Besi tulangan
- Tulangan Utama atas 3 D.13 3.00 x 4.00 x 1.042 = 12.50
- Tulangan Utama bawah 3 D.13 3.00 x 4.00 x 1.042 = 12.50
- Tulangan extra atas (1/4 L) 2 x 2 D.13 4.00 x 1.40 x 1.042 = 5.83
- Tulangan extra bawah (1/2 L) 1 x 2 D.13 2.00 x 2.80 x 1.042 = 5.83
- Sengkang tumpuan (2x1/4L) D 10 - 150 13.33 x 1.45 x 0.617 = 11.92
- Sengkang lapangan (1/2L) D 10 - 200 10.00 x 1.45 x 0.617 = 8.94
- Tulang pinggang 2 D.10 - x 4.00 x 0.617 = -
Sub-Total 57.53
Faktor penyusutan dll. 10% 5.75

analisa tulangan - 149


Total 63.28
Besi tulangan / M3 beton 158.21

5. Balok Plat Lantai, Type B5 (200x400)


- Volume balok, bentang 7,20 m' 7.20 x 0.20 x 0.40 = 0.576
- Besi tulangan
- Tulangan Utama atas 4 D.13 4.00 x 7.20 x 1.042 = 30.00
- Tulangan Utama bawah 4 D.13 4.00 x 7.20 x 1.042 = 30.00
- Tulangan extra atas (1/4 L) 2 x 2 D.13 - x 2.20 x 1.042 = -
- Tulangan extra bawah (1/2 L) 1 x 2 D.13 - x 4.40 x 1.042 = -
- Sengkang tumpuan (2x1/4L) D 10 - 150 - x 1.35 x 0.617 = -
- Sengkang lapangan (1/2L) D 10 - 200 - x 1.35 x 0.617 = -
- Tulang pinggang 2 D.10 - x 7.20 x 0.617 = -
Sub-Total 60.00
Faktor penyusutan dll. 10% 6.00
Total 66.00
Besi tulangan / M3 beton 114.58

6. Balok Plat Lantai, Type B6 (150x600)


- Volume balok, bentang 7.20 m' 7.20 x 0.15 x 0.60 = 0.648
- Besi tulangan
- Tulangan Utama atas 2 D.16 2.00 x 7.20 x 2.250 = 32.40
- Tulangan Utama bawah 3 D.16 3.00 x 7.20 x 2.250 = 48.60
- Tulangan extra atas (1/4 L) 2 x 1 D.16 2.00 x 2.40 x 2.250 = 10.80
- Tulangan extra bawah (1/2 L) 1 x 2 D.16 2.00 x 4.80 x 2.250 = 21.60
- Sengkang tumpuan (2x1/4L) D 10 - 150 24.00 x 1.65 x 0.617 = 24.42
- Sengkang lapangan (1/2L) D 10 - 200 18.00 x 1.65 x 0.617 = 18.32
- Tulang pinggang 2 D.10 2.00 x 7.20 x 0.617 = 8.88
Sub-Total 165.02
Faktor penyusutan dll. 10% 16.50
Total 181.52
Besi tulangan / M3 beton 280.12

7. Balok Plat Lantai, Type B7 (150x500)


- Volume balok, bentang 7,20 m' 7.20 x 0.15 x 0.50 = 0.540
- Besi tulangan
- Tulangan Utama atas 2 D.13 2.00 x 7.20 x 1.042 = 15.00
- Tulangan Utama bawah 2 D.13 2.00 x 7.20 x 1.042 = 15.00
- Tulangan extra atas (1/4 L) 2 x 1 D.13 2.00 x 2.30 x 1.042 = 4.79
- Tulangan extra bawah (1/2 L) 1 x 2 D.13 2.00 x 4.60 x 1.042 = 9.58
- Sengkang tumpuan (2x1/4L) D 10 - 150 24.00 x 1.45 x 0.617 = 21.46
- Sengkang lapangan (1/2L) D 10 - 200 18.00 x 1.45 x 0.617 = 16.10
- Tulang pinggang 2 D.10 2.00 x 7.20 x 0.617 = 8.88
Sub-Total 90.81
Faktor penyusutan dll. 10% 9.08
Total 99.89
Besi tulangan / M3 beton 184.98

7. Balok Opening Plat Lantai Lift, Type B8 (200x300)


- Volume balok, bentang 3,40 m' 3.40 x 0.20 x 0.30 = 0.204
- Besi tulangan
- Tulangan Utama atas 3 D.13 3.00 x 3.40 x 1.042 = 10.63
- Tulangan Utama bawah 3 D.13 3.00 x 3.40 x 1.042 = 10.63
- Tulangan extra atas (1/4 L) 2 x 1 D.13 - x 1.15 x 1.042 = -
- Tulangan extra bawah (1/2 L) 1 x 2 D.13 - x 2.30 x 1.042 = -
- Sengkang tumpuan (2x1/4L) D 10 - 150 22.67 x 1.10 x 0.617 = 15.38
- Sengkang lapangan (1/2L) D 10 - 200 - x 1.10 x 0.617 = -
- Tulang pinggang 2 D.10 - x 3.40 x 0.617 = -
Sub-Total 36.63
Faktor penyusutan dll. 10% 3.66
Total 40.29
Besi tulangan / M3 beton 197.49
8. Balok Plat Lantai, Type BA1 (250x500)
- Volume balok, bentang 7.20 m' 7.20 x 0.25 x 0.50 = 0.900
- Besi tulangan
- Tulangan Utama atas 3 D.16 3.00 x 7.20 x 2.250 = 48.60
- Tulangan Utama bawah 3 D.16 3.00 x 7.20 x 2.250 = 48.60
- Tulangan extra atas (1/4 L) 2 x 2 D.16 4.00 x 2.30 x 2.250 = 20.70
- Tulangan extra bawah (1/2 L) 1 x 2 D.16 2.00 x 4.60 x 2.250 = 20.70
- Sengkang tumpuan (2x1/4L) D 10 - 150 24.00 x 1.65 x 0.617 = 24.42
- Sengkang lapangan (1/2L) D 10 - 200 18.00 x 1.65 x 0.617 = 18.32
- Tulang pinggang 2 D.10 2.00 x 7.20 x 0.617 = 8.88
Sub-Total 190.22
Faktor penyusutan dll. 10% 19.02
Total 209.24
Besi tulangan / M3 beton 232.49

9 Balok Plat Lantai, Type BA2 (150x300)


- Volume balok, bentang 3,60 m' 3.60 x 0.15 x 0.30 = 0.162
- Besi tulangan
- Tulangan Utama atas 2 D.13 2.00 x 3.60 x 1.042 = 7.50
- Tulangan Utama bawah 2 D.13 2.00 x 3.60 x 1.042 = 7.50
- Tulangan extra atas (1/4 L) 2 x 1 D.13 2.00 x 1.20 x 1.042 = 2.50

analisa tulangan - 150


- Tulangan extra bawah (1/2 L) 1 x 2 D.13 2.00 x 2.40 x 1.042 = 5.00
- Sengkang tumpuan (2x1/4L) D 10 - 150 12.00 x 1.05 x 0.617 = 7.77
- Sengkang lapangan (1/2L) D 10 - 200 9.00 x 1.05 x 0.617 = 5.83
- Tulang pinggang 2 D.10 - x 3.60 x 0.617 = -
Sub-Total 36.10
Faktor penyusutan dll. 10% 3.61
Total 39.71
Besi tulangan / M3 beton 245.11

10 Balok Plat Lantai, Type B1C (300x600)


- Volume balok, bentang 1.77 m' 1.77 x 0.30 x 0.60 = 0.319
- Besi tulangan
- Tulangan Utama atas 6 D.19 6.00 x 1.77 x 2.250 = 23.90
- Tulangan Utama bawah 4 D.19 4.00 x 1.77 x 2.250 = 15.93
- Tulangan extra atas (1/4 L) 2 x 2 D.19 - x 1.04 x 2.250 = -
- Tulangan extra bawah (1/2 L) 1 x 2 D.19 - x 2.09 x 2.250 = -
- Sengkang tumpuan (2x1/4L) D 10 - 100 8.85 x 1.95 x 0.617 = 10.64
- Sengkang lapangan (1/2L) D 10 - 150 5.90 x 1.95 x 0.617 = 7.09
- Tulang pinggang 2 D.10 2.00 x 1.77 x 0.617 = 2.18
Sub-Total 59.74
Faktor penyusutan dll. 10% 5.97
Total 65.72
Besi tulangan / M3 beton 206.28

11 Balok Plat Lantai, Type B3C (250x500)


- Volume balok, bentang 1.77 m' 1.77 x 0.25 x 0.60 = 0.266
- Besi tulangan
- Tulangan Utama atas 5 D.16 5.00 x 1.77 x 2.250 = 19.91
- Tulangan Utama bawah 3 D.16 3.00 x 1.77 x 2.250 = 11.95
- Tulangan extra atas (1/4 L) 2 x 2 D.16 - x 1.04 x 2.250 = -
- Tulangan extra bawah (1/2 L) 1 x 2 D.16 - x 2.09 x 2.250 = -
- Sengkang tumpuan (2x1/4L) D 10 - 100 8.85 x 1.85 x 0.617 = 10.10
- Sengkang lapangan (1/2L) D 10 - 150 5.90 x 1.85 x 0.617 = 6.73
- Tulang pinggang 2 D.10 2.00 x 1.77 x 0.617 = 2.18
Sub-Total 50.87
Faktor penyusutan dll. 10% 5.09
Total 55.96
Besi tulangan / M3 beton 210.76

5.2. TULANGAN BALOK PLAT LANTAI (TYPICAL) TOTAL BERAT


NO TYPE BALOK TULANGAN RINCIAN BERAT / M' BESI

1. PELAT LANTAI 1 dan 2 , tebal 12 cm


- Volume Plat modul uk. 360 x 720 2.67 x 6.00 x 0.12 = 1.922
- Besi tulangan
- Tulangan atas ( X ) D10 - 150 40.00 x 2.67 x 0.617 = 65.86
- Tulangan atas ( Y ) D10 - 150 17.80 x 6.00 x 0.617 = 65.86
- Tulangan bawah ( X ) D10 - 150 40.00 x 2.67 x 0.617 = 65.86
- Tulangan bawah ( Y ) D10 - 150 17.80 x 6.00 x 0.617 = 65.86
- Tulangan pengekang D10 - 150 16.02 x 0.70 x 0.617 = 6.92
Sub-Total = 270.36
Faktor penyusutan dll. 10% 27.04
Total 297.39
Besi tulangan / M3 beton 154.70

2 PELAT LANTAI ATAP, tebal 11 cm


- Volume Plat modul uk. 300 x 600 3.00 x 6.00 x 0.11 = 1.980
- Besi tulangan
- Tulangan atas ( X ) D10 - 200 30.00 x 3.00 x 0.617 = 55.50
- Tulangan atas ( Y ) D10 - 200 15.00 x 6.00 x 0.617 = 55.50
- Tulangan bawah ( X ) D10 - 200 30.00 x 3.00 x 0.617 = 55.50
- Tulangan bawah ( Y ) D10 - 200 15.00 x 6.00 x 0.617 = 55.50
- Tulangan pengekang D10 - 200 18.00 x 0.70 x 0.617 = 7.77
Sub-Total = 229.77
Faktor penyusutan dll. 10% 22.98
Total 252.75
Besi tulangan / M3 beton 127.65

analisa tulangan - 151


ETABS v 9.7.0 File:LOT #NAME? A-25-11-16 -6LT-STK- EKUIVALENT Un its:KN-m N

STOR Y DATA

STORY SIMILAR TO HEIGHT ELEVATION

LRF None 5.5 41


L6 None 8 35.5
L5 None 8 27.5
L4 None 8 19.5
L3 None 8 11.5
L2 None 3.5 3.5
BASE None 0

ETABS v 9.7.0 File:LOT #NAME? A-25-11-16 -6LT-STK- EKUIVALENT Un its:KN-m N

MATE RIAL LI ST B Y ELE MENT TYPE

ELEMENT TOTAL NUMBER NUMBER


TYPE MATERIAL MASS PIECES STUDS
tons

Column A36 457.1 326


Beam A36 611.5 2681 0
Floor K250 3113.5
Metal D eck N.A. 131.4

ETABS v 9.7.0 File:LOT #NAME? A-25-11-16 -6LT-STK- EKUIVALENT Un its:KN-m N

MATE RIAL LI ST B Y SEC TION

ELEMENT NUMBER TOTAL TOTAL NUMBER


SECTION TYPE PIECES LENGTH MASS STUDS
meters tons

WF15 Beam 105 377.4 5 0


H25 Column 36 246 17.1
H20 Column 30 205 10
WF30 Beam 21 71.9 2.5 0
W2 Beam 929 3092.3 63.2 0
WF5 Beam 878 3564.1 303.7 0
WF35 Beam 6 18.9 0.8 0
WF25 Beam 72 186 4.8 0
H40 Column 30 205 34.5
WF6 Beam 46 154.3 15.7 0
VW5 Beam 118 783.2 64.7 0
V95L Beam 209 732.6 61.3 0
V95R Beam 227 810.1 68 0
V106L Beam 35 109.7 10.8 0
V106R Beam 35 112.9 11.1 0
KC50 Column 6 41 7.1
KC60 Column 119 804.5 163.4
KC6B Column 61 466.5 134.7
KC7 Column 44 253 90.3
D12 Floor 3113.5
D12 Metal Deck 131.4

ETABS v 9.7.0 File:LOT #NAME? A-25-11-16 -6LT-STK- EKUIVALENT Un its:KN-m N


MATE RIAL LI ST B Y STO RY

ELEMENT TOTAL FLOOR UNIT


STORY TYPE MATER IAL WEIGHT AREA WEIGHT
tons m2 kg/m2

LRF Column A36 52.9 2005.131 26.3799


LRF Beam A36 103.7 2005.131 51.7068
LRF Floor K250 533.3 2005.131 265.9446
LRF Metal Deck N.A. 22.5 2005.131 11.2271

L6 Column A36 76.9 2005.131 38.3708


L6 Beam A36 103.7 2005.131 51.7068
L6 Floor K250 533.3 2005.131 265.9446
L6 Metal Deck N.A. 22.5 2005.131 11.2271

L5 Column A36 88.6 2005.131 44.1796


L5 Beam A36 103.7 2005.131 51.7249
L5 Floor K250 533.3 2005.131 265.9446
L5 Metal Deck N.A. 22.5 2005.131 11.2271

L4 Column A36 89.3 2005.131 44.5213


L4 Beam A36 103.7 2005.131 51.726
L4 Floor K250 533.3 2005.131 265.9446
L4 Metal Deck N.A. 22.5 2005.131 11.2271

L3 Column A36 103.3 1766.349 58.5089


L3 Beam A36 93.6 1766.349 53.013
L3 Floor K250 469.8 1766.349 265.9446
L3 Metal Deck N.A. 19.8 1766.349 11.2271

L2 Column A36 46 1920.44 23.972


L2 Beam A36 103.1 1920.44 53.6717
L2 Floor K250 510.7 1920.44 265.9446
L2 Metal Deck N.A. 21.6 1920.44 11.2271

SUM Column A36 457.1 11707.314 39.0418


SUM Beam A36 611.5 11707.314 52.2326
SUM Floor K250 3113.5 11707.314 265.9446
SUM Metal Deck N.A. 131.4 11707.314 11.2271

TOTAL All All 4313.5 11707.314 368.446

ETABS v 9.7.0 File:LOT #NAME? A-25-11-16 -6LT-STK- EKUIVALENT Un its:KN-m N

MATE RIAL PR OPER TY DA TA

MATERIA L MATERIAL DESIG N MAT ERIAL MODULUS OF POISSON'S


NAME TYPE TYPE DIR /PLANE ELASTICITY RATIO

A36 Iso Steel All 199900000 0.3


K250 Iso Concr ete All 24821128.4 0.2
OTHER Iso None All 199947978.8 0.3
KACA Iso Concr ete All 24821128.4 0.2

MATE RIAL PR OPER TY MA SS A ND WEIG HT

MATERIA L MASS P ER WEI GHT PER


NAME UNIT V OL U NIT VOL

A36 7,8271E+ 00 7,6 8.20E+03


K250 2,4007E+ 00 2,3 5.62E+03
OTHER 7,8271E+ 00 7,6 8.20E+03
KACA 2,6000E+ 00 2,6 0.00E+00

MATE RIAL DE SIGN DATA FOR STEEL MATERI

MATERIA L STE EL STEEL STEEL


NAME FY FU COST ($)

A36 240000 ,0 3 60000 271447.16

MATE RIAL DE SIGN DATA FOR CONCRE TE MAT

MATERIA L LIGHTWEIGH T C ONCRETE REBAR REBAR LIGHTWT


NAME CONCRETE FC FY FYS REDUC FACT

K250 No 20000 390000 240000 N/A


KACA No 20000 390000 240000 N/A
ovember 26, 2 016 14:38 PAGE 1

ovember 26, 2 016 14:38 PAGE 2

ovember 26, 2 016 14:38 PAGE 3

ovember 26, 2 016 14:38 PAGE 4


NUMBER NUMBER
PIECES STUDS

54
457 0

54
457 0

54
457 0

54
457 0

54
408 0

56
445 0

326
2681 0

3007 0

ovember 26, 2 016 14:38 PAGE 5

THERMAL SHEAR
COEFF MODULUS

1.17E-05 76884615.4
9.90E-06 10342136.8
1.17E-05 76903068.8
9.90E-06 10342136.8
ALS

ERIALS
RENCANA ANGGARAN BIAYA

VOLUME SATUANHARGA SATUAN TOTAL HARGA


NO. URAIAN PEKERJAAN ANALISA
( Rp ) ( Rp )

I. PEKERJAAN PERSIAPAN UMUM

1 Pekerjaan Pengukuran Site AHSP-I-001 825.0 m2 -

2 Gambar Kerja (Shop Drawing) 1.0 ls -

3 Gambar Terlaksana (As Built Drawing) 1.0 ls -

4 Kantor Direksi di Lapangan AHSP-I-004 24.0 m2 -


5 Gudang semen & peralatan AHSP-I-005 36.0 m2 -
6 Pemeriksaan dan Pengujian Bahan 1.0 ls -
7 Penjagaan proyek 4.0 bln -
8 Photo-Photo Kemajuan Pekerjaan 1.0 ls -
9 Kebersihan dan Kerapian 1.0 ls -
10 Penyediaan Sumber Air untuk Kerja AHSP-I-009 1.0 Ls -
11 Penyedian Tenaga Listrik untuk Kerja AHSP-I-08A 4.0 bln -
12 Asuransi Tenaga Kerja (Astek) 1.0 ls -
13 Pek. Bowplank / papan ukur AHSP-I-007 118.0 M' -
14 Pek. Pagar seng sementara AHSP-I-006 85.0 M' -
15 Mobilisasi dan Demobilisasi 1.0 lot -

SUB-TOTAL PEKERJAAN PERSIAPAN (I) -

II. PEKERJAAN STRUKTUR

II.1 PEK. STRUKTUR PONDASI


II.1.1 Pekerjaan Tiang pancang

1 Pek. Pengadaan tiang pancang ukuran 25x25 cm


panjang 18,0 m 2,286.0 M' -

2 Pek. Pemancangan tiang pancang


- Pemancangan tiang pancang 2,286.0 M' -
- Handling 2,286.0 M' -
- Pemotongan kepala tiang pancang 127.0 nos -
- Mobilisasi & demobilisasi alat tiang pancang 1.0 Ls -

3 Pekerjaan Loading TestPDA


- Mob/Demob Alat blok beton 1.0 ls -
- Load Test Aksial 200 % x100 ton 1.0 ttk -
- Lateral Test 2.0 ton x 200% 2.0 ttk -

SUB-TOTAL STR. PONDASI (II.1) -

II.2 PEK. STRUKTUR BAWAH

II.2.1 Pek. Galian Tanah


###
1 Pek. Galian Tanah Pile Cap 266.2 m3 -
###
2 Pek. Galian Tanah Tiebeam 330.8 m3 -
###
3 Pek. Urugan tanah kembali Tiebeam 292.1 m3 -
4 Pek. Galian Tanah Pit Lift 51.3 m3 -

II.2.2 Pek. Urugan pasir


###
1 Pek. Urugan pasir urug, alas Pilecap, t. 10 cm 5.7 m3 -
###
2 Pek. Urugan pasir urug, alas Tiebeam, t. 10 cm 17.2 m3 -
3 Pek. Urugan pasir urug, alas lantai-Dasar, t. 10 cm 70.2 m3 -
4 Pek. Urugan pasir urug, alas lantai-pit lift, t. 10 cm 0.7 m3 -

II.2.3 Pek. Lantai Kerja


###
1 Pek. Lantai kerja, alas Pilecap, t. 5 cm 57.5 m2 -
###
2 Pek. Lantai kerja, alas Tiebeam, t. 5 cm 171.8 m2 -
###
3 Pek. Lantai kerja, alas Pit Lift, t. 5 cm 7.3 m2 -

II.2.4 Pek. Beton Tulang Pile Cap

Rab Struktur - 158


RENCANA ANGGARAN BIAYA

VOLUME SATUANHARGA SATUAN TOTAL HARGA


NO. URAIAN PEKERJAAN ANALISA
( Rp ) ( Rp )

1 Pile Cap type P-1 (500x500x800)


- Beton mutu K-300 (f'c = 25 Mpa) 1.1 m3 -
- Besi beton 228.4 kg -
- Bekisting dinding bata 7.2 m2 -

2 Pile Cap type P-2 (500x1250x800)


- Beton mutu K-300 (f'c = 25 Mpa) 3.4 m3 -
- Besi beton 565.1 kg -
- Bekisting dinding bata 16.4 m2 -

3 Pile Cap type P-3 (1300x1100x800)


- Beton mutu K-300 (f'c = 25 Mpa) 6.1 m3 -
- Besi beton 760.8 kg -
- Bekisting dinding bata 24.0 m2 -

4 Pile Cap type P-4 (1250x1250x800)


- Beton mutu K-300 (f'c = 25 Mpa) 2.5 m3 -
- Besi beton 248.8 kg -
- Bekisting dinding bata 9.6 m2 -

5 Pile Cap type P-5 (1560x1560x900)


- Beton mutu K-300 (f'c = 25 Mpa) 2.5 m3 -
- Besi beton 341.7 kg -
- Bekisting dinding bata 9.6 m2 -

6 Pile Cap type P-6 (2000x1250x900)


- Beton mutu K-300 (f'c = 25 Mpa) 3.1 m3 -
- Besi beton 429.9 kg -
- Bekisting dinding bata 12.0 m2 -

7 Pile Cap type P-7 (2000x1560x900)


- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 243.2 kg -
- Bekisting dinding bata 7.2 m2 -

8 Pile Cap type P-8 (2000x1800x900)


- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 235.2 kg -
- Bekisting dinding bata 7.2 m2 -

9 Pile Cap type P-9 (2000x1800x900)


- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 235.2 kg -
- Bekisting dinding bata 7.2 m2 -

10 Pile Cap type P-10 (2270x1800x1000)


- Beton mutu K-300 (f'c = 25 Mpa) 0.6 m3 -
- Besi beton 71.6 kg -
- Bekisting dinding bata 2.4 m2 -

11 Pile Cap type P-11 (2750x1800x1000)


- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 207.7 kg -
- Bekisting dinding bata 7.2 m2 -

12 Pile Cap type P-12 (2750x1800x1000)


- Beton mutu K-300 (f'c = 25 Mpa) 1.2 m3 -
- Besi beton 138.5 kg -
- Bekisting dinding bata 4.8 m2 -

13 Pile Cap type P-13 (3500x1800x1000)


- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 200.6 kg -
- Bekisting dinding bata 7.2 m2 -

14 Pile Cap type P-15 (3500x1800x1000)


- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 200.6 kg -
- Bekisting dinding bata 7.2 m2 -

Rab Struktur - 159


RENCANA ANGGARAN BIAYA

VOLUME SATUANHARGA SATUAN TOTAL HARGA


NO. URAIAN PEKERJAAN ANALISA
( Rp ) ( Rp )

II.2.5 Pek. Beton Tulang Tie Beam

1 Tie-Beam TB-1 (400x800)


- Beton mutu K-300 (f'c = 25 Mpa) 0 27.2 m3 -
- Besi beton 0 3,530.6 kg -
- Bekisting dinding bata AHSP-III-016 181.1 m2 -

2 Tie-Beam TB-2 (400x800)


- Beton mutu K-300 (f'c = 25 Mpa) 24.9 m3 -
- Besi beton 3,741.8 kg -
- Bekisting dinding bata 248.5 m2 -

3 Tie-Beam TB-3 (400x900)


- Beton mutu K-300 (f'c = 25 Mpa) 9.3 m3 -
- Besi beton 1,367.1 kg -
- Bekisting dinding bata 93.4 m2 -

4 Tie-Beam Pilt Lift(250x500)


- Beton mutu K-300 (f'c = 25 Mpa) 2.9 m3 -
- Besi beton 481.5 kg -
- Bekisting dinding bata 29.4 m2 -

II.2.6 Pek. Beton Tulang Pit Lift

1. Pek. Beton Tulang Pit Lift - 1


a. Pek.Beton Tulang Plat Lantai, tebal 25 cm
- Lantai Kerja 7.3 m2 -
- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 270.9 kg -

b. Pekerjaan Dinding Pit Lift , tebal 20 cm


- Beton mutu K-300 (f'c = 25 Mpa) 3.9 m3 -
- Besi beton 831.4 kg -
- Bekisting dinding bata 34.6 m2 -

2. Pek. Beton Tulang Pit Lift - 2


a. Pek.Beton Tulang Plat Lantai, tebal 25 cm
- Lantai Kerja 7.3 m2 -
- Beton mutu K-300 (f'c = 25 Mpa) 1.8 m3 -
- Besi beton 270.9 kg -

b. Pekerjaan Dinding Pit Lift , tebal 20 cm


- Beton mutu K-300 (f'c = 25 Mpa) 3.9 m3 -
- Besi beton 831.4 kg -
- Bekisting dinding bata 34.6 m2 -

3 Pek. Beton Tulang Pit Lift - 2


a. Pek.Beton Tulang Plat Lantai, tebal 25 cm
- Lantai Kerja 11.9 m2 -
- Beton mutu K-300 (f'c = 25 Mpa) 3.0 m3 -
- Besi beton 441.4 kg -

b. Pekerjaan Dinding Pit Lift , tebal 20 cm


- Beton mutu K-300 (f'c = 25 Mpa) 5.5 m3 -
- Besi beton 1,170.1 kg -
- Bekisting dinding bata 48.6 m2 -

SUB-TOTAL STRUKTUR BAWAH (II.2) -


NILAI TOTAL
DIBULATKAN
TERBILANG

Rab Struktur - 160