2075 Bhadra
Subject:- Estimating And Costing (CE 659)
Candidates are required to give their answer in their own words as far as practicable.
Attempt all the questions.
Assume necessary data.
2) Prepare an analysis of rate for brick work in (1:3) cement mortar in superstructure per m3 [6]
OR
Estimate the Quantity of earthwork of a portion of a road from the following data:
Road Width: 10m
Side slopes 2:1
Upward Grading 1in 200
Formation Level in Starting: 100
Distance(m) 0 30 60 90
3) Estimate the quantities of the following items of work from the accompanying building drawing
i. Brick work in foundation
ii. DPC in plinth Level
iii. E/W Excavation [12]
4) Write the purposes of estimation and make a format of detail of measurement and abstract of cost.[4+6]
OR
Write Short notes on any four
i. Salvage value
ii. Sinking fund
iii. Requirements of rate analysis
iv. Type of estimate
v. Development Method
vi. Method of Measurement