Professional Documents
Culture Documents
Job Safety Analysis Power Transformer Testing
Job Safety Analysis Power Transformer Testing
Ratio Test
Purpose and Scope: The purpose of this SWP is to outline the requirement for
performing these tests on out of service power transformers: Over-potential Test
Power Frequency Withstand Test
Performing High Voltage Testing in the field Load Loss Test
Power Transformer DC Resistance Test No Load Loss Test
Oil Sampling
Staffing Resources: Persons holding a minimum qualification of electrical fitter with adequate training in this practice and apprentices, trainees or other staff while under
direct supervision of qualified personnel.
Past test results if available
Documentation/References:
Scope of works Instruction manual (Manufacturer’s or local) for relevant
Standard to which Transformer was designed. This SWP is based on: Insulation Resistance test equipment.
AS2374.1 – 1997, Power transformers - General DC Resistance test equipment
AS2374.3.0 – 1982, Power transformers – Insulation levels and dielectric tests – General No Load Loss test equipment
requirements Load Loss test equipment
Power Transformer Dielectric and Insulation Test Report form SP0504C01 Power Frequency Withstand test equipment
Power Transformer Cold Winding Resistance Test Report form SP0504C02 Over-potential Withstand test equipment
Power Transformer No Load Ratio Test Report form SP0504C03 Ratio test equipment Scope of works
Power Transformer No Load Loss Test Report form SP0504C04
Power Transformer Load Loss Test Report form SP0504C05 and load loss calculation forms
SP0504C06
Check this is the latest Process Zone version before use. Page 1 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
JOB SAFETY ANALYSIS POWER TRANSFORMER TESTING
Load Loss test equipment. Power Frequency Withstand test equipment
Key Tools and Equipment:
Supply source capable of supplying at least including suitable single-phase test transformers of
PPE – Long sleeve shirt and long trousers, safety 50% of winding Full Load Current (FLC), sufficient voltage and VA, voltage and current
footwear, safety helmet, gloves and protective DC Resistance equipment, measuring equipment.
eyewear where signed. RMS Voltmeter, Measuring VTs, Ammeter, Ammeter with parallel spark gap
Safety barriers and warning signs. Metering CTs, Wattmeter, (These meters may Measurement VT and voltage meter
Shorting leads. be replaced by power analysers or other Over-potential Withstand tests equipment including
Time piece to record one to ten minute readings. appropriate meters.) a three phase high frequency generator, three
Insulation Resistance test equipment. Shorting bars capable of full rated current of phase interposing test transformer, voltage and
DC Resistance test equipment the winding to be shorted current measuring equipment – suitable for use at
Ratio test equipment. No Load Loss test equipment: the test frequency.
Surface thermometer Voltage source capable of rated voltage of Voltage meters to measure test voltage (with
Oil sample test equipment. transformer under test, input impedance to match voltage divider).
Oil spill kit Average and RMS Voltmeters, Ammeters to measure the phase current.
Test equipment will vary form site to site. Measuring VTs, Ammeters, Metering CTs,
Wattmeter, (These meters may be replaced by
power analysers or other appropriate meters).
Development Team: Phil Ives and Helena Tholsgard Date Completed: 16 April 2003
Key Stakeholders:
Check this is the latest Process Zone version before use. Page 2 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
JOB SAFETY ANALYSIS POWER TRANSFORMER TESTING
Risk Score
Task Most Likely Breakdown Event (Loss Of Most Likely Outcome (Incident Additional/
Task Step Hazard Existing
No. Control) Outcome) Alternate
Controls
Controls
1 Preliminary steps Refer JSAs for Testing in the field
and workshop
2 Performing Insulation Test Voltage from Test Equipment Failure to keep persons clear of live Electric Shock Low
Resistance Testing Trapped Charges test equipment
Failure to discharge equipment under
test
3 Power Transformer Oil Transformer oil, PCB Spillage Skin irritation, Low
Sampling Oil under pressure from head of environmental harm
oil
4 Power Transformer DC High Electromagnetic Energy in Leads removed from winding before Electric Shock Low
Resistance Test charged windings discharge, high voltage spike from
collapsing magnetic field
5 Power Transformer Ratio Live LV from auxiliary supplies Inadvertent contact with LV in auxiliary Electric Shock Low
Test Live LV from ratio test set supplies or from test set Damage to equipment –
High Voltage from CT Open Circuited CT secondary CT secondary windings
secondaries windings, unearthed VT windings
6 Power Transformer Power High Voltage from CT Open Circuited CT secondary Electric Shock Low
Check this is the latest Process Zone version before use. Page 3 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
JOB SAFETY ANALYSIS POWER TRANSFORMER TESTING
Risk Score
Task Most Likely Breakdown Event (Loss Of Most Likely Outcome (Incident Additional/
Task Step Hazard Existing
No. Control) Outcome) Alternate
Controls
Controls
Frequency Withstand Test secondaries windings, unearthed VT windings Damage to equipment –
Floating VT voltages Failure to isolate & earth transformer CT secondary windings
High Voltage from Test Set under test after test
HV Test Set
LV from input supply to Test Set Inadvertent contact with LV supply
leads Transformer under test
Failure of leakage current ammeter
HV Test voltage exceeds set point or
control malfunction gives runaway
Insufficient clearance between test HV
leads and between test leads and
other apparatus
7 Power Transformer Over- High Voltage from CT Open Circuited CT secondary Electric Shock Low
potential Test secondaries windings, unearthed VT windings Damage to equipment –
Floating VT voltages Failure to isolate & earth transformer CT secondary windings
High Voltage from Test Set under test after test
HV Test Set
LV from input supply to Test Set Inadvertent contact with LV supply
leads Transformer under test
HV Test voltage exceeds set point or
control malfunction gives runaway
Insufficient clearance between test HV
leads and between test leads and
other apparatus
8 Power Transformer Load High Voltage from CT Open Circuited CT secondary Electric Shock Low
Loss Test secondaries windings, unearthed VT windings Damage to equipment –
Check this is the latest Process Zone version before use. Page 4 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
JOB SAFETY ANALYSIS POWER TRANSFORMER TESTING
Risk Score
Task Most Likely Breakdown Event (Loss Of Most Likely Outcome (Incident Additional/
Task Step Hazard Existing
No. Control) Outcome) Alternate
Controls
Controls
Floating VT voltages Exceeding the current rating of the CT secondary windings
Applied Test Voltages Test Equipment – use of incorrect CT Test Set
tapings on measuring circuit
Hot test leads and connections Transformer under test
Use of under rated shorting bars
Failure to isolate & earth transformer
under test after test
Inadvertent contact with test supply
leads
Insufficient clearance between test HV
leads and between test leads and
other apparatus
9 Power Transformer No Load High Voltage from CT Open Circuited CT secondary Electric Shock Low
Loss Test secondaries windings, unearthed VT windings Damage to equipment –
Floating VT voltages Exceeding the rating of the Test CT secondary windings
Applied Test Voltages Equipment – use of incorrect VT ratios
on measuring circuit Test Set
Failure to isolate & earth transformer Transformer under test
under test after test
Inadvertent contact with test supply
leads
Insufficient clearance between test HV
leads and between test leads and
other apparatus
10 Complete and Clean up Undischarged or energised test Failure to isolate, discharge and earth Electric Shock Low
equipment all test equipment Damage to equipment –
Energised HV apparatus without Failure to restore transformer under VT secondary windings
fault protection test to condition as delivered (such as
shorted CTs) Transformer that was
under test
Check this is the latest Process Zone version before use. Page 5 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
JOB SAFETY ANALYSIS POWER TRANSFORMER TESTING
Existing Control Measures
1 Control measures are in place as described in the JSA “Carry Out Field Testing” SP0506R01 and it’s related
SWP SP0506 as well as the SWP “Power Transformer Testing” SP0504
2 Standard PPE, 2 4 4 Low
fall restraint
harness
4 2 4 4 Low
Check this is the latest Process Zone version before use. Page 6 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
JOB SAFETY ANALYSIS POWER TRANSFORMER TESTING
Additional/Alternative Control Measures
Check this is the latest Process Zone version before use. Page 7 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802
JOB SAFETY ANALYSIS POWER TRANSFORMER TESTING
1: DETERMINE CONSEQUENCE: - The most likely outcome of a potential incident resulting from exposure to the 4: RISK ASSESSMENT MATRIX
identified hazard.
Probability x Exposure
Level Descriptor Definition
5 Disaster Fatality; toxic release off-site with detrimental effect; financial loss (>$1,000,000). 1 to 2 3 to 5 6 to 10 11 to 23 24 to 36
Extensive injuries (e.g. permanent disability, amputation) requiring medical treatment, hospitalisation and
4 Very Serious long term rehabilitation; off-site release with no detrimental effects loss of production capability; financial Likelihood (How often?)
loss ($500,000 to $1,000,000).
Almost Quite
Disabling injuries requiring medical treatment and rehabilitation (e.g. broken limbs, hospitalisation); on-site Unlikely but Extremely
3 Serious Consequences certain will possible Possible
release contained with outside assistance; financial loss ($50,000 to $500,000). possible unlikely
(How Bad?) occur could occur
Medical treatment required (e.g. stitches, removal of foreign body); on-site release immediately contained;
2 Substantial
financial loss ($5,000 to $50,000). 5. Disaster Extreme Extreme Extreme High Moderate
1 Minor First aid treatment; negligible environmental damage; financial loss (<$5,000).
3 Occasional Weekly.
1. Minor High Moderate Low Low Low
4 Infrequent Between weekly and monthly.
Level Descriptor Definition Moderate Action required within agreed timeframe to minimise risk to “As Low As Reasonably
Practicable” (ALARP). Further action may be required and management responsibility
1 Almost Certain Breakdown event will almost certainly occur from exposure to hazard. specified to take this action. The ALARP principle implies that controls have been
determined such that the level of risk-reducing action is in proportion to the benefit
2 Quite Possible Not unusual for breakdown event occurring, even 50/50 chance. obtained.
3 Unusual but Possible Unusual for breakdown event to occur but possible. Action as soon as possible to minimise risk to acceptable level. Requires attention by
High
senior management and measures should be put in place to reduce the probability,
4 Remotely Possible Remote possibility of breakdown event occurring but history of occurrence exists within industry.
exposure and/or consequence of the outcome occurring to ALARP.
Conceivable but
5 No known history of breakdown event occurring after years of exposure but is conceivably possible. Same treatment as for high risks however immediate action required to minimise risk to
Unlikely Extreme
acceptable level.
6 Practically Impossible Practically impossible for breakdown event to occur. Has never occurred before and is not likely to occur.
(Adapted from AS/NZS 4360:1999 Risk Management and NSCA Risk Score Calculator, 2001)
Check this is the latest Process Zone version before use. Page 8 of 8 Reference SP0504R01 Ver 1
Reference Owner: Neil Dwyer, Manager Technical Services
Ergon Energy Corporation Limited ABN 50 087 646 062
Ergon Energy Queensland Pty Ltd ABN 11 121 177 802