You are on page 1of 1

PEKERJAAN PONDASI SCULPTURE

NO. JENIS PEKERJAAN SAT. Volume Harga Satuan Jumlah

I PEKERJAAN STRUKTUR PONDASI


a. Pekerjaan Bore Pile dia 60 cm L= 3 m
- Bore Pile dia 60 cm m' 15.00 275,000 4,125,000
- Beton K225 m3 4.24 810,000 3,434,400
- Besi dia 19 mm kg 350.53 13,860 4,858,346
- Besi dia 10 mm kg 174.22 13,860 2,414,731

b. Pekerjaan Pilecap 800x800x500 mm


- Galian tanah m3 1.66 36,500 60,769
- Urugan tanah kembali m3 0.15 15,000 2,324
- Pasir Urug t=100 mm m3 0.08 160,000 12,800
- Lantai kerja t=50 mm m3 0.16 730,000 113,530
- Beton K225 m3 1.28 810,000 1,036,800
- Besi dia 19 mm kg 320.48 13,860 4,441,872
- Bekisting m2' 6.40 143,688 919,600

c. Pekerjaan Pilecap1000x1000x500 mm
- Galian tanah m3 0.65 36,500 23,725
- Urugan tanah kembali m3 0.04 15,000 600
- Pasir Urug t=100 mm m3 0.07 160,000 11,981
- Lantai kerja t=50 mm m3 0.04 730,000 29,200
- Beton K225 m3 0.50 810,000 405,000
- Besi dia 19 mm kg 105.94 13,860 1,468,285
- Bekisting m2 2.00 120,780 241,560

d. Pekerjaan Tie Beam 400x500 mm


- Galian tanah m3 4.20 36,500 153,300
- Urugan tanah kembali m3 1.60 15,000 24,000
- Pasir Urug t=100 mm m3 0.40 160,000 64,000
- Lantai kerja t=50 mm m3 0.20 730,000 146,000
- Beton K225 m3 2.00 810,000 1,620,000
- Besi dia 19 mm kg 172.96 13,860 2,397,228
- Besi dia 12 mm kg 129.07 13,860 1,788,897
- Bekisting m2 10.00 134,497 1,344,970

e. Pekerjaan Kolom Bulat


- Beton K225 m3 7.31 972,000 7,105,624
- Besi dia 19 mm kg 367.99 13,860 5,100,379
- Besi dia 10 mm kg 143.15 13,860 1,984,103
- Bekisting Bulat m2 33.36 395,859 13,206,846
- Plesteran + acian Kolom Bulat m2 33.36 94,080 3,138,744

Jumlah Total 61,674,612

PPN 10 % 6,167,461

TOTAL 67,842,073

MAKASSAR, 28 APRIL 2018


PT. REKATAMA PROSINDO

RONNY IRWAN TANZIL


DIREKTUR