c. Pekerjaan Pilecap1000x1000x500 mm
- Galian tanah m3 0.65 36,500 23,725
- Urugan tanah kembali m3 0.04 15,000 600
- Pasir Urug t=100 mm m3 0.07 160,000 11,981
- Lantai kerja t=50 mm m3 0.04 730,000 29,200
- Beton K225 m3 0.50 810,000 405,000
- Besi dia 19 mm kg 105.94 13,860 1,468,285
- Bekisting m2 2.00 120,780 241,560
PPN 10 % 6,167,461