1.

Form work :
All arrangement done to support the green concrete till it attains the
strength is known as form work or temporary work.
Form work determines the geometry,shape.size and finish of the form
work.
2.Centering :
Part of the form work which supports the horizontal surface is called
centering for example slab bottom , beam bottom etc.

3.Shuttering :Part of the form work which supports the Vertical surface
is called Shuttering for example column sides, beam sides,slab side ,wall
side etc.

4.Staging : That portion which support centering & shuttering is called


Staging. This can be :

1. Wooden Ballies
2. Pipes/Props/Jacks
3. H frames
4. Space frames using Coupler / Cup-Lock system
5.Scaffolding : That arrangement which is meant to be a supporting
platform for people ( labor , supervisor, mason ,fitter,painter,carpenter
etc. ) is known as scaffolding.