0% found this document useful (0 votes)
55 views1 page

JC Enterprises Daily Activities Report 2017

A daily activities report from JC Enterprises dated November 12, 2017 details 4 construction tasks completed on Sunday including copping panel fixing at two locations, column panel fixing, and ceiling panel fixing using a total of 3 workers. The report provides location, quantity, manpower, and remarks for each task.

Uploaded by

pragith kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views1 page

JC Enterprises Daily Activities Report 2017

A daily activities report from JC Enterprises dated November 12, 2017 details 4 construction tasks completed on Sunday including copping panel fixing at two locations, column panel fixing, and ceiling panel fixing using a total of 3 workers. The report provides location, quantity, manpower, and remarks for each task.

Uploaded by

pragith kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Date : 12 - 11 - 2017

JC ENTERPRISES : Daily Activities Report 2017 Day :Sunday

Foreman & Charge Hand ………………….

Daily Activities Location Qty Manpower Remarks


1 Copping Panel Fixing (The Concreted North Level – 14 10 03
Chipping With All )
2 Copping Panel Fixing (The Router & South Level - 15 04 03
Cutting Refabricated )
3 Column Panel Fixing ( L Angle Cutting ) South Level - 15 02 03
4 Ceiling Panel Fixing South Level - 15 20 03