Daily Activity Report for 500kV Transmission Line

1) The document outlines the daily activity program for March 2nd, 2019 for a 500kV transmission line project between Multan and Gatti stations. 2) It details the tasks of various crews including layout, excavation, steel fixing, concrete pouring, formwork opening and curing, backfilling, and piling work at different tower locations. 3) Piling work is scheduled for tower 48 and 62, including drilling, cage lowering, and concrete pouring at different legs, while foundation work is ongoing at towers 41, 118, and 120.

Uploaded by

Ahsan Islam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views2 pages

Daily Activity Report for 500kV Transmission Line

1) The document outlines the daily activity program for March 2nd, 2019 for a 500kV transmission line project between Multan and Gatti stations. 2) It details the tasks of various crews including layout, excavation, steel fixing, concrete pouring, formwork opening and curing, backfilling, and piling work at different tower locations. 3) Piling work is scheduled for tower 48 and 62, including drilling, cage lowering, and concrete pouring at different legs, while foundation work is ongoing at towers 41, 118, and 120.

Uploaded by

Ahsan Islam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

NETRACON-SEPCC/CWTWC JV

CONTRACT NO. ADB-105-2017 (LOT-I)


5OOkV DOUBLE CIRCUIT D/C Q/B TRANSMISSION LINE IN & OUT OF EXISTING
500kV MULTAN-GATTI S/C TRANSMISSION LINE AT 500kV FAISALABAD WEST
SUBSTATION (APPROX.40kM-DRAKE CONDUCTOR)

DAILY ACTIVITY PROGRAM


Date of Submission: 01-03-2019 Date of Activity: 02-03-2019

Sr. Activity Location No. Time Remarks


No
Conventional Crew-01
1)T#81 8:00 AM
Conventional Crew-05
01 Layout & Excavation
2)T#101 8:00 AM
Conventional Crew-04
3)T#60 8:00 AM

Pile Cap Crew-03


02 Steel Fixing
1)T#3, 3rd & 4th Leg L#2, 4 8:00 AM

Pile Cap Crew-02


1)T#50, 3rd & 4th Leg L#2, 4 12:00 PM

Conventional Crew-03
2)T#121, 1st & 2nd Leg L#1, 3 9:00 AM
03 Concrete
Conventional Crew-04
3)T#60, 2nd Leg L#2 10:00 AM

Pile Cap Crew-03


4)T#3, 1st & 2nd Leg(L#1, 3) 9:00 AM

Conventional Crew-04
1)T#60, 1st Leg L#1 1:30 PM
Formwork Opening &
04 Pile Cap Crew-02
Curing
2)T#50, 1st & 2nd Leg(L#1, 3) 2:00 PM
Conventional Crew-05
1)99 (1st & 2nd Layers)
12:00 PM
Conventional Crew-03
2)110 (3rd Layer), 108 (5th)
2:00 PM
Conventional Crew-02
3)76, 77 (6th Layer),
05 Backfilling 78, 80 (3rd Layer),
3:00 PM
79 (4th Layer)

Conventional Crew-04
10:00 AM
4)58 (4th Layer),
44, 59 (3rd Layer)

Conventional Crew-01
1:00 PM
5)36 (4th Layer)
Piling Crew-03
1)T#48 LEG 2 PILE 1
-Drilling 6:00 AM
-Cage Lowering 7:30 AM
-Concrete @Lowering

LEG 3 PILE 2
-Drilling 11:00 AM
-Cage Lowering 12:00 PM
-Concrete @Lowering

06 Piling LEG 1, 4 PILE 3, 4


-CPC 3:00 PM

Piling Crew-02
2)T#62 LEG 3 PILE 1
-CPC 7:30 AM
-Drilling 8:00 AM
-Cage Lowering 9:00 AM
-Concrete @Lowering

LEG 1, 4 PILE 2, 3
-CPC 3:00 PM

ROWs
FOUNDATION: T# 41, 118, 120
PILING ROW: T# 20, 21

. .