NETRACON-SEPCC/CWTWC JV
CONTRACT NO. ADB-105-2017 (LOT-I)
5OOkV DOUBLE CIRCUIT D/C Q/B TRANSMISSION LINE IN & OUT OF EXISTING
500kV MULTAN-GATTI S/C TRANSMISSION LINE AT 500kV FAISALABAD WEST
SUBSTATION (APPROX.40kM-DRAKE CONDUCTOR)
DAILY ACTIVITY PROGRAM
Date of Submission: 01-03-2019 Date of Activity: 02-03-2019
Sr. Activity Location No. Time Remarks
No
Conventional Crew-01
1)T#81 8:00 AM
Conventional Crew-05
01 Layout & Excavation
2)T#101 8:00 AM
Conventional Crew-04
3)T#60 8:00 AM
Pile Cap Crew-03
02 Steel Fixing
1)T#3, 3rd & 4th Leg L#2, 4 8:00 AM
Pile Cap Crew-02
1)T#50, 3rd & 4th Leg L#2, 4 12:00 PM
Conventional Crew-03
2)T#121, 1st & 2nd Leg L#1, 3 9:00 AM
03 Concrete
Conventional Crew-04
3)T#60, 2nd Leg L#2 10:00 AM
Pile Cap Crew-03
4)T#3, 1st & 2nd Leg(L#1, 3) 9:00 AM
Conventional Crew-04
1)T#60, 1st Leg L#1 1:30 PM
Formwork Opening &
04 Pile Cap Crew-02
Curing
2)T#50, 1st & 2nd Leg(L#1, 3) 2:00 PM
Conventional Crew-05
1)99 (1st & 2nd Layers)
12:00 PM
Conventional Crew-03
2)110 (3rd Layer), 108 (5th)
2:00 PM
Conventional Crew-02
3)76, 77 (6th Layer),
05 Backfilling 78, 80 (3rd Layer),
3:00 PM
79 (4th Layer)
Conventional Crew-04
10:00 AM
4)58 (4th Layer),
44, 59 (3rd Layer)
Conventional Crew-01
1:00 PM
5)36 (4th Layer)
Piling Crew-03
1)T#48 LEG 2 PILE 1
-Drilling 6:00 AM
-Cage Lowering 7:30 AM
-Concrete @Lowering
LEG 3 PILE 2
-Drilling 11:00 AM
-Cage Lowering 12:00 PM
-Concrete @Lowering
06 Piling LEG 1, 4 PILE 3, 4
-CPC 3:00 PM
Piling Crew-02
2)T#62 LEG 3 PILE 1
-CPC 7:30 AM
-Drilling 8:00 AM
-Cage Lowering 9:00 AM
-Concrete @Lowering
LEG 1, 4 PILE 2, 3
-CPC 3:00 PM
ROWs
FOUNDATION: T# 41, 118, 120
PILING ROW: T# 20, 21
. .
CONTRACTOR’S CONSULTANT’S