Construction Progress Update Report

Uploaded by

Oviya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views3 pages

Construction Progress Update Report

Uploaded by

Oviya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Progress Update data from the Site

Status Date: 14/09/2024 (Sat)

Task Name Actual Actual Phys. % Actual Remaining Actual Rem.


Start Finish complete Duration Duration Work Work
04-09 11-09 Grading
crew-350
Grading and hr
Site Prep
Supervisor
– 25 hr
12-09 14-09 JCB – 11hr*
Dig Diesel- 110
Foundation litres*

Lay 14-09 1d Concrete Concrete


Foundation crew – 80 h Crew -
drains 40h

*Actual Work Details for Dig Foundation

Date JCB Diesel


12/09 (Tue) 2.5h 25 liters
13/09 (Wed) 4.5h 45 liters
14/09 (Thu) 4h 40 liters

10 | P a g e
Status Date: 28/09/2024 (Sat)

Task Name Actual Actual Phys. % Actual Remaining Actual Rem


Start Finish complete Duration Duration Work Work
Grading 04-09 11-09 Grading
and Site crew-350
Prep hr
Supervisor
– 25 hr
Dig 12-09 14-09 JCB – 11hr
Foundation Diesel –
110 ltr

Lay 14-09 16-09 Concrete


Foundation crew – 120
drains h
16-09 16-09 Concrete
Rough in
Crew –
drainage
70h
17-09 17-09 Concrete
Crew – 78
h
RMC – 11
Pour cum
Footings Plywood –
2.5 sqm
Timber – 6
cft

16-09 17-09 100% Concrete


crew -450
h
Pour RMC-23
basement cum
floor Plywood –
38 sqm
Timber -24
cft

11 | P a g e
Task Name Actual Actual Phys. % Actual Remaining Actual Rem
Start Finish complete Duration Duration Work Work
19-09 20-09 Concrete
crew -145
h
RMC-11.5
Pour
cum
basement
Plywood –
walls
34 sqm
Timber -19
cft

Cure 21-09 23-09 Concrete


basement Crew – 30
walls h
24-09 27-09 Framing
Crew –
Frame 195 h
Walls Framer
(Contract)
– 200 h
28-09 2d 1d Framing Framing
crew – 90 crew
h 75h
Roof Joists
Framer Framer
(Contract)- – 75 h
90h
28-09 60/500 = 1d 3d Framing Framing
12% crew -40 h crew -
Roof
Framer – 10h
Sheathing
40h Framer
– 10h
Installation 28-09 4/28 = 1d 6d Framing 310h
of 14% crew – 40
windows/ h
doors

12 | P a g e