Elements Cost/GFA (RM/m2) Index Adjustment

195
125.00 𝑥 125.00 = 162.50
Substructure 150

195
Superstructure 250.00 𝑥 250.00 = 325.00
150

195
𝑥 155.00 = 201.50
150
Finishes 155.00
201.50 x 1.15 = 231.73

195
5.00 𝑥 5.00 = 6.50
Furniture & Fittings 150

195
𝑥 60.00 = 78.00
150
Services 60.00
78.00 x 1.05 = 81.90

Total Building Cost 807.63


195
𝑥 45.00 = 58.50
150
External Works 45.00
58.50 x 1.03 = 60.26

Total Construction Cost 867.89


195
Preliminaries 30.00 𝑥 30 = 39.00
150

Total Project Cost 906.89

Total cost of proposed building

= RM906.89/m2 x 200m2 = RM181,378.00