The document provides a rate analysis for various civil works including:
1) Earth work up to 20.5 meters depth costing 1,100 Tk per cubic meter including labor, machinery, transportation, overhead expenses, profit, tax and VAT.
2) Backfilling with excavated earth costing 538 Tk per cubic meter including similar cost components.
3) Backfilling with imported earth including cost of earth, labor, and similar additional expenses totaling 928 Tk per cubic meter.
The document provides a rate analysis for various civil works including:
1) Earth work up to 20.5 meters depth costing 1,100 Tk per cubic meter including labor, machinery, transportation, overhead expenses, profit, tax and VAT.
2) Backfilling with excavated earth costing 538 Tk per cubic meter including similar cost components.
3) Backfilling with imported earth including cost of earth, labor, and similar additional expenses totaling 928 Tk per cubic meter.
The document provides a rate analysis for various civil works including:
1) Earth work up to 20.5 meters depth costing 1,100 Tk per cubic meter including labor, machinery, transportation, overhead expenses, profit, tax and VAT.
2) Backfilling with excavated earth costing 538 Tk per cubic meter including similar cost components.
3) Backfilling with imported earth including cost of earth, labor, and similar additional expenses totaling 928 Tk per cubic meter.
PART-I : CIVIL WORKS (FOUNDATION, BASEMENT AND SUPERSTRUCTURE).
1.00 Earth work:
1.10 Up to (-) 20.50 meter from FGL Unit- One Cum.
a. Labour 1.00 cum @ Tk. 320.00 Cum = Tk. 320.00
b. Machinery for cutting earth & 1.00 cum @ Tk. 280.00 Cum = Tk. 280.00 dewatering c. Carrying from site to selected place 1.00 Cum @ Tk. 265.00 Cum = Tk. 265.00 Total = Tk. 865.00 Overhead expenses 3.50% = Tk. 30.28 Contractor's profit 10.00% = Tk. 86.50 = Tk. 981.78 Tax & VAT 11.73% = Tk. 115.16 Grand total = Tk. 1,096.94
Say, Tk. 1,100.00 Per Cum.
1.2.1 Back filling work with excavated earth
Unit- One Cum. a. Labour 1.00 cum @ Tk. 320.00 Cum = Tk. 320.00 b. Machinery for compaction 1.00 cum @ Tk. 160.00 Cum = Tk. 160.00 c. Carrying from site to selected place 1.00 Cum @ Tk. 265.00 Cum = Tk. 265.00