RATE ANALYSIS

PART-I : CIVIL WORKS (FOUNDATION, BASEMENT AND SUPERSTRUCTURE).

1.00 Earth work:


1.10 Up to (-) 20.50 meter from FGL
Unit- One Cum.

a. Labour 1.00 cum @ Tk. 320.00 Cum = Tk. 320.00


b. Machinery for cutting earth & 1.00 cum @ Tk. 280.00 Cum = Tk. 280.00
dewatering
c. Carrying from site to selected place 1.00 Cum @ Tk. 265.00 Cum = Tk. 265.00
Total = Tk. 865.00
Overhead expenses 3.50% = Tk. 30.28
Contractor's profit 10.00% = Tk. 86.50
= Tk. 981.78
Tax & VAT 11.73% = Tk. 115.16
Grand total = Tk. 1,096.94

Say, Tk. 1,100.00 Per Cum.

1.2.1 Back filling work with excavated earth


Unit- One Cum.
a. Labour 1.00 cum @ Tk. 320.00 Cum = Tk. 320.00
b. Machinery for compaction 1.00 cum @ Tk. 160.00 Cum = Tk. 160.00
c. Carrying from site to selected place 1.00 Cum @ Tk. 265.00 Cum = Tk. 265.00

Total = Tk. 425.00


Overhead expenses 3.50% = Tk. 14.88
Contractor's profit 10.00% = Tk. 42.50
= Tk. 482.38
Tax & VAT 11.73% = Tk. 56.58
Grand total = Tk. 538.96

Say, Tk. 538.00 Per Sqm.

1.2.2 Back filling work with imported earth


Unit- One Cum.
a. Cost of earth 1.00 cum @ Tk. 350.00 Cum = Tk. 350.00
b. Labour 1.00 cum @ Tk. 180.00 Cum = Tk. 180.00