You are on page 1of 2

Item No.- 02.16.

1
Site development / improvement by other method/ means than dredging
Considering 1000 cft of work in/c dressing and local carriage 1000.00 cft
wastage, no shrinkage as it is coming & placing in Tk. 0.15 = 1150.00 cft
saturated condition
1. Royalty for Earth Tk. 1,150 cft @ 2200.00 per % 0 = 2530.00
cft
2. Carriage of earth including cost of labour for 1150.00 cft @ 8.50 per cft = 9775.00
loading and unloading
3. Labour for local carriage, levelling & compacting etc. complete:

(a) Ordinary labour 8.00 nos @ 550.00 per day = 4400.00


(b) Skilled labour 1.00 nos @ 600.00 per day = 600.00
4. Sundries, T & P etc. LS = 225.90
Sub - = 17530.90
Total
Profit 0.10 = 1753.09
Overhead 0.04 = 613.58
Total = 19897.57
Add VAT with adjustment factor 1.08 0.08 = 1613.31
Grand = 21510.89
Total
Rate per cft = 21.51
Rate per cum = 759.66

Say, 759.66 .00 per cum

Site development/Improvement by carted earth or dredged sand, sandy silt (free


from any organic, foreign, environmental hazardous substances) carried by head or
truck or any other means including cost of cutting or by dredging of sand, sandy silt,
02.16
all; including local carrying, placing the earth/sand, sandy silt in the designated area,
maintaining slopes, breaking lumps, levelling and dressing in layers up to finished
level etc. all complete as per direction and accepted by the engineer in charge.

02.16.1 By other method/means than dredgeing.


Sand filling in foundation trenches and plinth with sand having minimum F.M. 0.5 in
150 mm layers including leveling, watering and compaction to achieve minimum dry
02.10.1 density of 95% with optimum moisture content (Modified proctor test) by ramming
each layer up to finished level as per design supplied by the design office only, all
complete and accepted by the Engineer-in-charge.

Item No.- 02.10.1


Sand filling in foundation and plinth with local sand (Minimum F.M. 0.50)
Considering 100 cft of work
1. Sand (F.M. 0.5) considering additional
30% for compaction 130.00 cft @ 1530.00 per % cft = 1989.00
2. Head mason 0.1 no @ 800.00 per day = 100.00
3. Labour for levelling,
compacting, watering etc. 0.7 no @ 550.00 per day = 366.67
4. Sundries, T & P etc. LS = 55.00
Sub - = 2510.67
Total
Profit 0.10 = 251.07
Overhead 0.04 = 87.87
Total = 2849.61
Add VAT with adjustment factor 1.08 0.08 = 231.05
Grand = 3080.66
Total
Rate per cft = 30.81
Rate per cum = 1087.93

Say, 1087.93 .00 per cum

You might also like