A. MATERIALS
Total 335,268.00
Add 5% BRA Tax % 5.0% 16,763.40
335,268.00
Add 7.5% Tax % 7.5% 25,145.10
335,268.00
Sub Total ( A ) 377,176.50
B LABOUR
1 Fixing of Marble Strip & Laying of Flooring Sft 10,000.00 11.00 110,000.00
Total (A + B) 513,126.50
Less alrady paid=