Sr.

Previous
Activities To Till
No Week

1 Dismantling of Existing Building & Floor - 100%


2 Removal of Debris of Exiting Building - 80%
5 Tree Cutting. (Roots Removed 25%) 100%
6 Cleaning of plot Unit# 06. - 90%
Point staking out, Marking & Layout (Lime
7 3% 93%
Laying) (90%).
8 Excavation of Column Footings. (12.34%) 4.01% 91.5553

9 PCC (1:4:8) under Column Footings. (30.54%) 12.14% 95.9954

10
Steel Cutting, Bending & Binding for Footings 2.50% 10%
& Columns up to 3m Height.
11
Concrete Pouring of RCC Column Footings. 14.15% 95.6156
(28%)
Concrete Pouring of RCC Columns upto +2M
12 7.14% 81.75
from FFL
Complete
Under Progress
Complete
Under Progress

Under Progress
-4.01 Under Progress

12.14 Under Progress

Under Progress

14.15 Under Progress

7.14 Under Progress


Under Progress
Syntronics (Pvt.) Ltd
Unit# 05
Sr.No Description No L B H Qty Unit
1 Excavation
Upto 1500 mm
Footings
F2 15 3.45 3.45 1.20 214.25
F3 43 2.25 2.25 1.20 261.23
F4 5 1.65 1.65 1.20 16.34
F5 15 3.23 3.23 1.20 187.21
F6 2 2.55 2.55 2.00 26.01
F2' -
F3' -
F5' -
F7 16 2.70 3.30 1.50 213.84
F7' -
Masonry Walls Footings
Sec-1 & Sec- 2 2,000.00
Less Footings Area -
Sec-3 -
Less Footings Area -
Sec-4 -
Less Footings Area -
Sec-5 -
Less Footings Area -
Sec- 6 -
Less Footings Area -
Sec-11 -
Less Footings Area -
Sec-12 -
Less Footings Area -
Sec-13 -
Less Footings Area -
Sec-15 -
Less Footings Area -
Sec-16 -
Less Footings Area -
Trenches (Long Side) 1 150.00 2.29 0.60 206.10
Trenches (Short Side) -
UGWT -
3,124.97
3,124.97 M3

2 PCC
Upto 1500 mm
Footings
F2 15 3.45 3.45 0.08 13.39
F3 43 2.25 2.25 0.08 16.33
F4 2 1.65 1.65 0.08 0.41
F5 15 3.23 3.23 0.08 11.70
F6 2 2.55 2.55 0.08 0.98
F2' -
F3' -
F5' -
F7 10 3.30 2.10 0.08 5.20
F7' -
48.00
48.00 M3

b) Under Trenches & sub Floor


Trenches (Long Side) 1.8 150.00 2.06 0.10 55.49
Trenches (Long Side) 1.8 100.00 2.06 0.10 36.99
Trenches (Short Side) 5 32.92 2.06 0.10 33.91
Trenches (Short Side) 0 32.92 1.56 0.10 -
Sub Floor 0 150.00 9.00 0.10 -
Total Trenches 126.38

c) Masonry Walls Footings


Sec-1 & Sec- 2 2 32.92 0.80 0.15 7.90
Less Footings Area -2 10.00 0.80 0.15 - 2.40
Sec-3 0 62.42 0.80 0.15 -
Less Footings Area 0 13.99 0.80 0.15 -
Sec-4 1 12.42 0.80 0.15 1.49
Less Footings Area 1 4.09 0.80 0.15 0.49
Sec-5 1 20.50 0.80 0.15 2.46
Less Footings Area 1 9.68 0.80 0.15 1.16
Sec- 6 1 9.00 0.80 0.15 1.08
Less Footings Area 1 2.74 0.80 0.15 0.33
Sec-11 21 5.00 0.80 0.15 12.60
Less Footings Area -10 3.23 0.80 0.15 - 3.87
Less Footings Area -10 2.25 0.80 0.15 - 2.70
Sec-12 26 5.00 0.80 0.15 15.60
Less Footings Area -26 2.25 0.80 0.15 - 7.02
Sec-13 1 10.00 0.80 0.15 1.20
Less Footings Area -1 2.89 0.80 0.15 - 0.35
Sec-15 5 5.00 1.15 0.15 4.29
Less Footings Area -5 3.23 1.15 0.15 - 2.77
Less Footings Area -5 2.25 1.15 0.15 - 1.93
Sec-16 20 5.00 1.15 0.15 17.18
Less Footings Area -4 2.25 1.15 0.15 - 1.55
Internal walls of Service Bay 0 9.00 0.80 0.15 -
F8 0 142.64 0.65 0.15 -
F10 0 142.64 0.65 0.15 -
F7 0 8.00 1.14 0.15 -
43.19
Pcc under Brick Work 43.19 M3

6 Masonary in Foundation
-
Sec-11 Steps 21 5.000 0.518 0.300 16.317
Less Footings & Columns -21 2.737 0.518 0.300 - 8.932
Sec-11 upto FFL 21 4.540 0.230 1.135 24.889
Over Footings slopes (F5) 21 1.308 0.230 0.200 1.264
Over Footings slopes (F3) 21 0.970 0.230 0.263 1.230
Sec-15 steps 5 5.000 0.748 0.450 8.415
Less Footings & Columns -5 2.737 0.748 0.450 - 4.606
sec- 15 upto FFL 5 4.540 0.345 1.060 8.301
Over Footings slopes (F5) 5 1.308 0.345 0.200 0.451
Over Footings slopes (F3) 5 0.970 0.345 0.263 0.439
Sec-12 Steps 24 5.000 0.575 0.300 20.700
Less Footings & Columns -24 2.100 0.575 0.300 - 8.694
Sec-12 upto FFL 24 4.540 0.345 1.360 51.124
Over Footings Slopes (F3) 24 1.640 0.345 0.175 2.376
Sec-16 Steps 4 5.000 0.748 0.460 6.882
Less Footings & Columns -4 2.100 0.748 0.460 - 2.890
Sec-16 upto FFL 4 4.540 0.345 1.060 6.641
Over Footings Slopes (F3) 4 1.640 0.345 0.175 0.396
Sec-6 Steps 1 9.000 0.575 0.225 1.164
Less Footings & Columns -1 2.737 0.575 0.225 - 0.354
Sec-6 upto FFL 1 8.540 0.345 1.135 3.344
Over Footings slopes (F5) 2 1.308 0.345 0.200 0.181
Over Footings Slopes (F3) 2 0.970 0.345 0.263 0.176
Sec-1 & 2 steps 2 32.920 0.575 0.225 8.518
Less Footings & Columns (F4) -2 1.500 0.575 0.225 - 0.388
Less Footings & Columns (F6) -2.0 2.400 0.575 0.225 - 0.621
Less Footings & Columns (F7) -2 2.000 0.575 0.225 - 0.518
Sec-1 upto FFL 2 32.920 0.345 1.135 25.781
Over Footings Slpoes (F6) 2 1.940 0.345 0.138 0.185
Over Footings Slpoes (F4) 2 1.120 0.345 0.138 0.107
B/w footings slopes 2 4.750 0.345 0.450 1.475
Sec-3 Steps 0 62.420 0.575 0.225 -
Less Footings & Columns (F4) 0 1.500 0.575 0.225 -
Less Footing & Columns (F5) 0 3.075 0.575 0.225 -
Sec-3 upto FFL 0 59.725 0.345 1.510 -
Less Footings Tapper (F4) 0 0.560 0.345 0.075 -
Less Footings Tapper (F5) 0 1.508 0.345 0.200 -
Sec-4 Steps 1 12.420 0.575 0.225 1.607
Less Columns & Footings (F4) -1 1.500 0.575 0.225 - 0.194
Less Columns & Footings (F5) -1 3.075 0.575 0.225 - 0.398
Sec-4 upto FFL 1 11.620 0.345 1.510 6.053
Sec-5 Steps 1 20.500 0.575 0.225 2.652
Less Columns & Footings (F4) -1 1.500 0.575 0.225 - 0.194
Less Columns & Footings (F5) -1 3.300 0.575 0.225 - 0.427
Sec-5 upto FFL 1 19.240 0.345 1.585 10.521
Sec-13 Steps 1 10.000 0.518 0.300 1.554
Less Column Footings -1 1.195 0.518 0.300 - 0.186
Sec-13 upto FFL 1 9.540 0.345 1.405 4.624
Trenches
Long sides along Walls Along grid F 1 130.000 0.230 0.900 26.910
Long sides along Walls Along grid F 1 130.000 0.345 0.475 21.304
LongSides external 2 150.000 0.345 0.475 49.163
2 150.000 0.230 0.900 62.100
Short Sides along walls 0 42.000 0.230 1.815 -
9.5 29.870 0.460 0.475 62.003
9.5 29.870 0.230 0.900 58.739

Service Bay Internal Walls Steps 21 8.500 0.518 0.300 27.739


Service Bay Internal Walls upto FFL 21 8.500 0.230 1.910 78.415

For Drain 0 150.000 0.345 0.750 -


For Boundary Wall in Foundation 0 160.000 0.230 0.900 -
-
575.337 M3

6 Brick Masonry in Superstructure


A~F/1 1 32.000 0.345 6.000 66.240
A~F/2 1 32.000 0.345 6.000 66.240
A~F/33 1 32.000 0.345 6.000 66.240
F/ 1~2 1 9.540 0.345 6.000 19.748
F/2~32 32 4.540 0.230 6.000 200.486
F/2~32 32 4.540 0.230 6.000 200.486
GHIJ/2~31 32 4.540 0.230 6.000 200.486
Service Bay Internal Walls 18 9.000 0.230 4.000 149.040
in Diaphragms 30 Area 0.230 6.025 41.573
Starex Hall 0 50.000 0.345 6.000 -
0 12.000 0.345 6.000 -
1,010.540 M3
152.29

6 Plasterwork
A~F/1 1 32.000 6.000 192.000
A~F/2 2 32.000 6.000 384.000
A~F/33 1 32.000 6.000 192.000
F/ 1~2 1 9.540 6.000 57.240
F/2~32 64 4.540 6.000 1,743.360
A/2~32 32 4.540 6.000 871.680
GHIJ/2~31 32 4.540 6.000 871.680
Service Bay Internal Walls 18 9.000 4.000 648.000
in Diaphragms 30 Area 6.025 180.750
Starex Hall 0 50.000 6.000 -
0 12.000 6.000 -
Trenches 1 500.000 1.375 687.500
5,828.210 M2

6 Plinth Beam
A/1~31 (sec-8) 15 9.540 0.345 0.550 27.153
C/1~31 (sec-10) 15 9.540 0.345 0.550 27.153
A~F/ 1 (sec-1) 1 32.000 0.345 0.550 6.072
A~F/2 (Sec-2) 1 32.000 0.345 0.550 6.072
F/1~2 (sec-13) 1 9.540 0.345 0.550 1.810
F~J/2 (Sec-6) 0 9.040 0.345 0.550 -
F/2~12 & 15~29 (sec-11) 18 4.540 0.230 0.550 10.338
F/12~15 & 29~31 (sec-15) 0 4.540 0.345 0.550 -
G-J/2~12 & 15~30 (sec-12) 0 4.540 0.230 0.550 -
G/12~15/30~31 (Sec-16) 0 4.540 0.345 0.550 -
F~J/16,17,31,32 (Sec-7 & 7') 0 8.040 0.345 0.550 -
A~F/ 31 (Sec-4 & 5) 0 32.000 0.345 0.550 -
78.598 M3
102.92
24.32

6 Bracing Beams
A/1~31 (sec-8) 1 9.540 0.345 0.550 1.810
A~F/ 1 (sec-1) 1 32.000 0.345 0.550 6.072
A~F/2 (Sec-2) 1 32.000 0.345 0.550 6.072
F/1~2 (sec-13) 1 9.540 0.345 0.550 1.810
A~F/ 31 (Sec-4 & 5) 0 32.000 0.345 0.550 -
15.764 M3

3 Re Inforcement As Per BBS prepared by Unit#04 Dwgs 197.00 Ton

4 RCC (1:2:4) in Footings a)


F2 Straight Portion 15 3.30 3.30 0.20 32.67
Tapper 15 3.30 3.30 34.06
F5 Straight Portion 15 3.08 3.08 0.20 28.37
Tapper 15 3.08 3.08 24.74
F6 Straight Portion 2 2.40 2.40 0.20 2.30
Tapper 2 2.40 2.40 2.18
F3 Straight Portion 43 2.10 2.10 0.20 37.93
Tapper 43 2.10 2.10 16.51
F4 Straight Portion 5 1.50 1.50 0.20 2.25
Tapper 5 1.50 1.50 1.16
F3 Straight Portion -
-
Footing F5 -
Tapper Portion -
Footing F6 -
-
Footing F4 -
-
Footing F7 & F7' (Bridge Footing) 16 2.10 2.70 0.60 54.43
-

Plinth Beam -
-
Beams over Trench in LT Room -
-
Boundary Wall Footings -

236.60 M3

b) Diaphragm
D3 External Back
D3 External Front (Sec 6-6) 15 10.600 0.230 0.300 10.971
Vertical Supports Sec 5'-5' 30 0.300 0.230 1.560 3.229
Bottom Beam Straight Portion 15 9.540 0.230 0.300 9.874
Both Sides Corner 30 0.230 0.700 0.700 3.381
D1 External Back
D3 External Front (Sec 6-6) 14 10.611 0.230 0.300 10.250
Vertical Supports Sec 5'-5' 28 0.300 0.230 1.560 3.014
Bottom Beam Straight Portion 14 9.540 0.230 0.300 9.216
Both Sides Corner 28 0.230 0.700 0.700 3.156
D2 Internal
Arc Beam Sec 8-8 15 10.620 0.180 0.300 8.602
Vertical Supports Sec 5-5 30 0.180 0.300 1.560 2.527
Bottom Beam Straight Portion Sec 3-3 15 9.540 0.180 0.300 7.727
Both Sides Corner 30 0.230 0.700 0.700 3.381
-
77.152 M3

c) Valley Beams
VB1 4 37.916 0.280 0.750 31.850
Valley Wings (Including Gutters) 4 37.916 0.580 0.090 7.917
VB2 16 37.916 0.180 0.750 81.899
Valley Wings (Including Gutters) 32 37.916 0.580 0.090 63.335
-
185.000 M3

d) Shells
Shell Slab 30 10.000 16.460 0.077 380.226
-
443.890 M3

f) Flat Roof
Extention of Unit# 04 1 Area 255.000 0.180 45.900

-
45.900 M3

g) Retaining Walls
UGWT Walls 2 10.000 0.300 4.500 27.000
2 5.000 0.300 4.500 13.500
-
-
-
40.500 M3

5 RCC (1:1.5:3) in Columns


C1 Upto 1st Pour 0 0.46 0.46 3.60 -
C1 Upto Beam Soffit 39 0.46 0.46 8.055 66.47
C3 at grid J I 5 0.46 0.46 6.88 7.28
C3 at grid GHI 25 0.46 0.46 5.99 31.69
C3 at grid F & J 13 0.46 0.46 1.50 4.13

C2 (Area=.225) 12 0.23 7.87 21.24


-
130.80 M3

7 Horizontal DPC
External Walls -
Long Walls Steps 2 130.000 0.345 89.700
Internal walls
Extention of Unit# 04 2 32.000 0.345 22.080
-
111.780 M2
8 Vertical DPC
External Walls -
Long Walls Steps 1 130.000 0.450 58.500
1 32.000 0.450 14.400
-
72.900 M2
Syntronics (Pvt.) Ltd
Unit# 06
Sr.No Description No L B H Qty Unit
1 Excavation
Upto 1500 mm
Footings
F2 15 3.45 3.45 1.50 267.81
F3 13 2.25 2.25 1.50 98.72
F4 -
F5 14 3.23 3.23 1.50 218.41
F6 1 2.55 2.55 2.00 13.01
F2' -
F3' -
F5' -
F7 16 2.25 2.85 1.50 153.90
F7' -
Masonry Walls Footings
Sec-1 & Sec- 2 1,500.00
Less Footings Area -
Sec-3 -
Less Footings Area -
Sec-4 -
Less Footings Area -
Sec-5 -
Less Footings Area -
Sec- 6 -
Less Footings Area -
Sec-11 -
Less Footings Area -
Sec-12 -
Less Footings Area -
Sec-13 -
Less Footings Area -
Sec-15 -
Less Footings Area -
Sec-16 -
Less Footings Area -
Trenches (Long Side) -
Trenches (Short Side) -
UGWT -
2,251.84
2,251.84 M3

2 PCC
Upto 1500 mm
Footings
F2 15 3.45 3.45 0.08 13.39
F3 13 2.25 2.25 0.08 4.94
F4 -
F5 15 3.23 3.23 0.08 11.70
F6 1 2.55 2.55 0.08 0.49
F2' -
F3' -
F5' -
F7 16 2.25 2.85 0.08 7.70
F7' -
38.21
Total PCC in Column Footings 38.21 M3

b) Under Trenches & sub Floor


Trenches (Long Side) 1 75.00 1.56 0.10 11.70
Trenches (Short Side) 1 32.92 2.06 0.10 6.78
Trenches (Short Side) 0 32.92 1.56 0.10 -
Sub Floor 0 150.00 9.00 0.10 -
PCc Total Trenches 18.48

c) Masonry Walls Footings


Sec-1 & Sec- 2 1 32.92 0.80 0.15 3.95
Less Footings Area 1 10.00 0.80 0.15 1.20
Sec-3 0 62.42 0.80 0.15 -
Less Footings Area 0 13.99 0.80 0.15 -
Sec-4 0 12.42 0.80 0.15 -
Less Footings Area 0 4.09 0.80 0.15 -
Sec-5 0 20.50 0.80 0.15 -
Less Footings Area 0 9.68 0.80 0.15 -
Sec- 6 0 9.00 0.80 0.15 -
Less Footings Area 0 2.74 0.80 0.15 -
Sec-11 23 5.00 0.80 0.15 13.80
Less Footings Area -5 3.23 0.80 0.15 - 1.94
Less Footings Area -5 2.25 0.80 0.15 - 1.35
Sec-12 0 5.00 0.80 0.15 -
Less Footings Area 0 2.25 0.80 0.15 -
Sec-13 0 10.00 0.80 0.15 -
Less Footings Area 0 2.89 0.80 0.15 -
Sec-15 0 5.00 1.15 0.15 -
Less Footings Area 0 3.23 1.15 0.15 -
Less Footings Area 0 2.25 1.15 0.15 -
Sec-16 2 5.00 1.15 0.15 1.72
Less Footings Area 1 2.25 1.15 0.15 0.39
Internal walls of Service Bay 0 9.00 0.80 0.15 -
F8 0 142.64 0.65 0.15 -
F10 0 142.64 0.65 0.15 -
F7 0 8.00 1.14 0.15 -
17.77
Pcc under Wall Footings 17.77 M3

6 Masonary in Foundation
-
Sec-11 Steps 23 5.000 0.518 0.300 17.871
Less Footings & Columns -23 2.737 0.518 0.300 - 9.783
Sec-11 upto FFL 23 4.540 0.230 1.135 27.259
Over Footings slopes (F5) 23 1.308 0.230 0.200 1.384
Over Footings slopes (F3) 23 0.970 0.230 0.263 1.347
Sec-15 steps 5 5.000 0.748 0.450 8.415
Less Footings & Columns -5 2.737 0.748 0.450 - 4.606
sec- 15 upto FFL 5 4.540 0.345 1.060 8.301
Over Footings slopes (F5) 5 1.308 0.345 0.200 0.451
Over Footings slopes (F3) 5 0.970 0.345 0.263 0.439
Sec-12 Steps 24 5.000 0.575 0.300 20.700
Less Footings & Columns -24 2.100 0.575 0.300 - 8.694
Sec-12 upto FFL 24 4.540 0.345 1.360 51.124
Over Footings Slopes (F3) 24 1.640 0.345 0.175 2.376
Sec-16 Steps 4 5.000 0.748 0.460 6.882
Less Footings & Columns -4 2.100 0.748 0.460 - 2.890
Sec-16 upto FFL 4 4.540 0.345 1.060 6.641
Over Footings Slopes (F3) 4 1.640 0.345 0.175 0.396
Sec-6 Steps 1 9.000 0.575 0.225 1.164
Less Footings & Columns -1 2.737 0.575 0.225 - 0.354
Sec-6 upto FFL 1 8.540 0.345 1.135 3.344
Over Footings slopes (F5) 1 1.308 0.345 0.200 0.090
Over Footings Slopes (F3) 1 0.970 0.345 0.263 0.088
Sec-1 & 2 steps 8 8.230 0.575 0.225 8.518
Less Footings & Columns (F4) -4 1.500 0.575 0.225 - 0.776
Less Footings & Columns (F6) -3.0 2.400 0.575 0.225 - 0.932
Less Footings & Columns (F7) -2 2.000 0.575 0.225 - 0.518
Sec-1 upto FFL 8 7.810 0.345 1.135 24.466
Over Footings Slpoes (F6) 3 1.940 0.345 0.138 0.277
Over Footings Slpoes (F4) 4 1.120 0.345 0.138 0.213
B/w footings slopes 8 4.750 0.345 0.450 5.900
Sec-3 Steps 1 62.420 0.575 0.225 8.076
Less Footings & Columns (F4) -6.5 1.500 0.575 0.225 - 1.261
Less Footing & Columns (F5) -0.5 3.075 0.575 0.225 - 0.199
Sec-3 upto FFL 1 59.725 0.345 1.510 31.114
Less Footings Tapper (F4) -13 0.560 0.345 0.075 - 0.188
Less Footings Tapper (F5) -1 1.508 0.345 0.200 - 0.104
Sec-4 Steps 1 12.420 0.575 0.225 1.607
Less Columns & Footings (F4) -1.5 1.500 0.575 0.225 - 0.291
Less Columns & Footings (F5) -0.5 3.075 0.575 0.225 - 0.199
Sec-4 upto FFL 1 11.620 0.345 1.510 6.053
Sec-5 Steps 1 20.500 0.575 0.225 2.652
Less Columns & Footings (F4) -1.5 1.500 0.575 0.225 - 0.291
Less Columns & Footings (F5) -1 3.300 0.575 0.225 - 0.427
Sec-5 upto FFL 1 19.240 0.345 1.585 10.521
Sec-13 Steps 1 10.000 0.518 0.300 1.554
Less Column Footings 2 1.195 0.518 0.300 0.371
Sec-13 upto FFL 1 9.540 0.345 1.405 4.624
Trenches
Long sides along Walls 2 160.000 0.230 1.815 133.584
LongSides external 2 160.000 0.345 0.475 52.440
2 160.000 0.230 0.900 66.240
Short Sides along walls 2 42.000 0.230 1.815 35.066
10 29.870 0.460 0.475 65.266
10 29.870 0.230 0.900 61.831

Service Bay Internal Walls Steps 24 8.500 0.518 0.300 31.702


Service Bay Internal Walls upto FFL 24 8.500 0.230 1.910 89.617

For Drain 2 150.000 0.345 0.750 77.625


For Boundary Wall in Foundation 1 160.000 0.230 0.900 33.120
-
879.196 M3
3 Re Inforcement As Per BBS prepared by Unit#04 Dwgs 170.00 Ton

4 RCC (1:2:4) in Footings a)


F2 Straight Portion 15 3.30 3.30 0.20 32.67
Tapper 15 3.30 3.30 34.06
F5 Straight Portion 15 3.08 3.08 0.20 28.37
Tapper 15 3.08 3.08 24.74
F6 Straight Portion 1 2.40 2.40 0.20 1.15
Tapper 1 2.40 2.40 1.09
F3 Straight Portion 13 2.10 2.10 0.20 11.47
Tapper 13 2.10 2.10 4.99
F3 Straight Portion -
-
Footing F5 -
Tapper Portion -
Footing F6 -
-
Footing F4 -
-
Footing F7 & F7' (Bridge Footing) 16 2.10 2.70 0.60 54.43
-
Vertical Member of Bridge Footings -
Horizontal Member of Bridge Footing -

Plinth Beam -
-
Beams over Trench in LT Room -
-
Boundary Wall Footings -

210.00 M3

b) Diaphragm
D1 External Back
D3 External Front (Sec 6-6) 7 11.300 0.230 0.300 5.458
Vertical Supports Sec 5'-5' 14 0.300 0.230 1.800 1.739
Bottom Beam Straight Portion 7 9.540 0.230 0.300 4.608
Both Sides Corner 14 0.230 0.800 0.800 2.061
D3 External Back
D3 External Front (Sec 6-6) 14 11.300 0.230 0.300 10.916
Vertical Supports Sec 5'-5' 28 0.300 0.230 1.800 3.478
Bottom Beam Straight Portion 14 9.540 0.230 0.300 9.216
Both Sides Corner 28 0.230 0.800 0.800 4.122
D2 Internal
Arc Beam Sec 8-8 15 11.300 0.180 0.300 9.153
Vertical Supports Sec 5-5 30 0.180 0.300 1.800 2.916
Bottom Beam Straight Portion Sec 3-3 15 10.000 0.180 0.300 8.100
Both Sides Corner 30 0.230 0.800 0.800 4.416
-
66.181 M3

c) Valley Beams
VB1 6.5 16.000 0.280 0.750 21.840
Valley Wings (Including Gutters) 6.5 16.460 0.580 0.090 5.585
VB2 21 16.000 0.180 0.750 45.360
Valley Wings (Including Gutters) 42 16.460 0.580 0.090 36.087
-
108.872 M3

d) Shells
Shell Slab 12.5 11.300 33.000 0.077 358.916
-
358.916 M3

e) Beams & Lintels


Long Spans 1 140.000 0.255 0.780 27.846
Cross Beams 4 9.000 0.255 0.780 7.160
Godown Long Beams 1 22.000 0.255 0.780 4.376
-
39.382 M3

f) Flat Roof
Extention of Unit# 04 1 Area 255.000 0.180 45.900

-
45.900 M3

g) Retaining Walls
UGWT Walls 2 10.000 0.300 4.500 27.000
2 5.000 0.300 4.500 13.500
-
-
-
40.500 M3

5 RCC (1:1.5:3) in Columns


C1 Upto Plinth Beam 3 0.46 0.46 1.10 0.70
C1 Upto Beam Soffit 35 0.46 0.46 7.90 58.51
C3 1st Pour 3 0.46 0.46 1.10 0.70
C3 2nd Pour 5 0.46 0.46 3.60 3.81

C2 (Area=.225) 12 0.23 7.90 21.33


-
85.04 M3

6 Masonary in Foundation
External Walls -
Long Walls Steps 1 130.000 0.805 0.450 47.093
Upto FFL 1 130.000 0.345 2.500 112.125
Extention Unit# 4
Common Wall 1 32.000 0.575 0.225 4.140
1 32.000 0.345 2.500 27.600
For Boundary Wall in Foundation 1 160.000 0.230 0.900 33.120
-
224.078 M3

7 Horizontal DPC
External Walls -
Long Walls Steps 2 130.000 0.345 89.700
Internal walls
Extention of Unit# 04 2 32.000 0.345 22.080
-
111.780 M2
Epoxy Anchorage 31 40.000 200.000 248,000.000

8 Vertical DPC
External Walls -
Long Walls Steps 1 130.000 0.450 58.500
1 32.000 0.450 14.400
-
72.900 M2

9 Masonary in Superstructure
a) External Walls 230mm -
Long Walls 1 130.000 0.225 6.500 190.125
b) Extention of Unit# 04 230mm 1 32.000 0.225 6.500 46.800
10 6.000 0.225 1.800 24.300
-
261.225 M3

c) New Plot Boundary Wall 115mm 1 160.000 0.115 2.300 42.320


-
42.320 M3

10 Plaster work
External Walls 345mm -
Long Walls 1 132.000 6.500 858.000
Extention Unit#4 1 40.000 6.500 260.000
Slabs Plaster of Ext. Unit# 04 1 Area 250.000 250.000
Plater in Diaphragm 10 6.000 1.800 108.000
Boundary wall Plaster Work Int. Side 1 160.000 2.135 341.600
-
1,817.600 M2

11 Deep Struck Pointing


External Walls 345mm -
Long Walls 1 120.000 6.500 780.000
Short Walls 1 32.000 6.500 208.000
Plaster in Diaphragms 10 6.000 1.800 108.000
-
1,096.000 M2

21,22 Flooring
Internal Floor Shells 1 35.00 40.00 1,400.00
Ext. Unit# 4 1 Area 250.00 250.00
1,650.000 M2

43 a) Paver
New Plot 1 Area as per Autocad 1,700.00 1,700.00
1,700.000 M2
43 b) Kerb Stone
Arround New Buildings 1 Length 128.00 128.00
128.000 Rm

4 Stairs
1st Flight 1 4.50 1.50 0.18 1.22
2nd Flight 1 3.30 1.50 0.18 0.89
Landing 1 1.58 3.00 0.18 0.86
Steps 13 0.18 0.17 1.50 0.60
-
3.562 M3
House No. 11, St# 08, F-7/3, Islamabad
Construction of H.No. 11

Dated: - 18-Nov-22 Friday


Total Required
Done Remaining Work Done
Sr# Activities Unit Estimated Productivity/Week to Status Progress %age
Qty Quantity this Week
Qty meet target

Basement Floor

1 Tile Fixing m3 45 15 30 5 10 On Track 33.33%


2 Fixing of CP fittings in Wash Rooms m 3
6,000 4,735 1,266 211 No Progress 78.91%
3 Walls & Ceiling Paint m 3
247 247 - - Completed 100.00%
4 Doors Fixing m 3
160 143 17 9 No Progress 89.19%
5 Electrical Fittings m 3
146 146 - - Completed 100.00%
6 Diaphragm Concrete m3 73 73 - - Completed 100.00%
7 Shells Concrete m3 415 415 - - Completed 100.00%
8 Trenches - - -
a) PCC (1:4:8) m3 85 85 - - Completed 100.00%
b) Masonry m3 270 270 - - Completed 100.00%
c) Plaster m 2
1,353 927 426 229 No Progress 68.51%
d) Slab m 3
65 39 26 14 No Progress 60.00%
9 Brick work in S.S m 3
800 360 440 237 No Progress 44.96%
10 Plinth Beams m3 120 111 9 5 No Progress 92.52%
11 Flooring - -
i PCC under Shells m 3
650 630 20 11 650 On Track 96.97%
ii Terrazo Topping Shell m2 6,000 2,774 3,226 1,737 6000 On Track 100.00%
iii PCC in Service Bays m3 130 - 130 70 130 On Track 100.00%
iv Terrazo in Services Bay m 2
450 - 450 242 450 On Track 100.00%
v Simple Floor m 2
451 - 451 243 200 In Lag 44.40%
vi Tile work m 2
400 - 400 215 300 On Track 75.00%
12 Service Bay Slab m3 243 90 153 (358) On Track 36.91%
13 Service Bay Beams m3 50 16 34 18 No Progress 32.00%
14 Plaster Work m2
8,000 1,850 6,150 3,311 No Progress 23.13%
15 Bracing Beams m3 47 30 17 9 No Progress 62.93%
16 Water Proofing (Nos of Shells) Nos 30 16 14 8 No Progress 53.33%
Syntronics Limited
Note:- Report is prepared by considering 28th of February as Finish date of the project.
Construction of Unit# 05 & O6

Unit#06 Till Date: - 7-Feb-22 Monday

Required
Done Remaining Work Done
Sr# Activities Unit Ttl Qty Productivity/Week to Status Progress %age
Qty Quantity this Week
meet target
1 PCC under Footings m3 45 45 - - Completed 100.00%
2 Filling m3 6,500 3,877 2,623 525 No Progress 59.64%
3 Footings Concrete m3 247 247 - - Completed 100.00%
4 Colmns Concrete m3 160 160 - - Completed 100.00%
5 Valley Beams Concrete m3 146 146 - - Completed 100.00%
6 Diaphragm Concrete m3
73 73 - - Completed 100.00%
7 Shells Concrete m3 415 415 (0) (0) Completed 100.10%
8 Trenches - - -
a) PCC (1:4:8) m3 85 60 25 5 No Progress 70.59%
b) Masonry m 3
270 146 125 25 No Progress 53.89%
c) Plaster m 2
1,353 906 447 89 No Progress 66.95%
d) Slab m3 65 32 33 7 No Progress 49.15%
9 Brick work in S.S m3 1,050 406 644 129 No Progress 38.68%
10 Plinth Beams m 3
120 112 8 2 No Progress 92.99%
11 Flooring -
i PCC under Shells m3 650 291 359 72 No Progress 44.77%
ii Terrazo Topping Shell m 2
6,000 - 6,000 1,200 No Progress 0.00%
iii PCC in Service Bays m 3
130 - 130 26 No Progress 0.00%
iv Terrazo in Services Bay m 2
450 - 450 90 No Progress 0.00%
v Simple Floor m2 451 - 451 90 No Progress 0.00%
vi Tile work m2 400 - 400 80 No Progress 0.00%
12 Services Bay Columns m 2
40 19 21 4 No Progress 48.65%
13 Service Bay Slab m 3
243 16 227 45 No Progress 6.67%
14 Service Bay Beams m3 41 13 28 6 No Progress 32.46%
15 Plaster Work m2
8,000 1,046 6,954 1,391 No Progress 13.08%
16 Bracing Beams m3
47 35 12 2 No Progress 75.01%
Payment Summary
Dated:- 21-Feb-22
Total Contract amount= 295,000,000.00
Less 5% Retention= (14,750,000.00)
Less Mobilization Advance = (41,250,000.00)
Net Amount = 239,000,000.00
Less 1st IPC = (8,337,718.00)
Less 2nd IPC = (9,775,768.00)
Less 3rd IPC = (8,599,531.00)
Less steel @115,000/Ton (3,450,000.00)
Less Cement @550/Bag (8,800,000.00)
Less steel @115,000/Ton (49,489,100.00)
Less Cement @550/Bag (17,600,000.00)
Remaining Payable = 132,947,883.00