SN Particular N0.

Length Breadth Height Area Quantities


(f.t.) (f.t) (ft) (Sq.ft)
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
1 Earthwork in excavation
1.1 column footing
F1 5 6 6 6.33 36 1139.4
F2 6 5.5 5.5 6.33 30.25 1148.895
F3 11 5 5 6.33 25 1740.75
Total 4029.045
1.2 Toe wall footing
1.2.1 Long Wall
Grid G-G 1 23 2 2.5 46 115
Grid F-F 1 33 2 2.5 66 165
Grid E-E 1 16 2 2.5 32 80
Grid D-D 1 57.5 2 2.5 115 287.5
Grid C-C 1 64 2 2.5 128 320
Grid B-B 1 22.5 2 2.5 45 112.5
Grid A-A 1 22.5 2 2.5 45 112.5
Toe wall 1 35 2 2.5 70 175

1.2.2 Short wall


Grid 1-1 1 13 2 2.5 26 65
Grid 2-2 1 17.5 2 2.5 35 87.5
Grid 3-3 1 52 2 2.5 104 260
Grid 4-4 1 35.33 2 2.5 70.66 176.65
Grid 5-5 1 52 2 2.5 104 260
Grid 6-6 1 30 2 2.5 60 150
Grid 7-7 1 20 2 2.5 40 100
Toe wall 1 22 2 2.5 44 110
Total 2576.65
Deduction the length coverd
1.3 by footing tie
F1 5 -6 2 2.5 -12 -150
F2 6 -5.5 2 2.5 -11 -165
F3 11 -5 2 2.5 -10 -275
Total -590.000
Total Excavation 6015.695
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
2 Earthwaork for filling
foundation trench by loose 1/5 th of exavation apx 1203.139
earth

lumn1 Column2 umn3 ColumnColumn5Column6 olumn7 Column8


(ft) (ft) (ft) (Sq.ft)
3.2 5" Sand filling
3.3 OnelayerFlat Brick Soiling
3.4 3mm Water Proofing
3.5 3" P.C.C.(1:3:6)
3.6 3/2" Floor Finish

Deduction
3.7 volume of tie beam
3.7.1 external beams 1 -327 1 1.5 -327 -490.5
3.7.2 internal beams 1 -101.19 1 1.5 -101.19 -151.785
Total earth filling -642.285

SN Particular N0. Length (fBreadth (feight (ft) (sq. ft.) Quantities


SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
a For PCC of footing
F1 5 6 6 0.25 36 45
F2 6 5.5 5.5 0.25 30.25 45.375
F3 11 5 5 0.25 25 68.75
Total 159.125
b For founadation of toe wall
(considering no pillars)
i Long Wall
Grid G-G 1 23 2 0.25 46 11.5
Grid F-F 1 33 2 0.25 66 16.5
Grid E-E 1 16 2 0.25 32 8
Grid D-D 1 57.5 2 0.25 115 28.75
Grid C-C 1 64 2 0.25 128 32
Grid B-B 1 22.5 2 0.25 45 11.25
Grid A-A 1 22.5 2 0.25 45 11.25
Toe wall 1 35 2 0.25 70 17.5
Total 136.75
ii Short wall
Grid 1-1 1 13 2 0.25 26 6.5
Grid 2-2 1 17.5 2 0.25 35 8.75
Grid 3-3 1 52 2 0.25 104 26
Grid 4-4 1 35.33 2 0.25 70.66 17.665
Grid 5-5 1 52 2 0.25 104 26
Grid 6-6 1 30 2 0.25 60 15
Grid 7-7 1 20 2 0.25 40 10
Toe wall 1 22 2 0.25 44 11
Total 120.915
c Deduction length of column
columns 22 -1.33 1.33 0.25 -1.7689 -9.72895
Total plain cement concrete 407.06105
SN Particular N0. Length (fBreadth (feight (ft) (sq. ft.) Quantities
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
(excluding reinforcement)
a. Column Footing
i. rectangular portion
F1 5 6 6 0.83 36 149.4
F2 6 5.5 5.5 0.83 30.25 150.645
F3 11 5 5 0.83 25 228.25

ii. Trapezoidal portion


F1 5 6 6 1 78.75
F2 6 5.5 5.5 1 81.5
F3 11 5 5 1 127.4166667
Total 815.9616667
b. Column
Foundation column 22 1.33 1.33 2.5 1.7689 97.2895
Ground floor 22 1.33 1.33 8.5 1.7689 330.7843
First floor 17 1.33 1.33 8.5 1.7689 255.60605
Second floor 8 1.33 1.33 8.5 1.7689 120.2852
Total 803.96505
c. Beams
i. Footing beam + plinth beam
Grid G-G 2 15.33 1 1.5 15.33 45.99
Grid F-F 2 32.33 1 1.5 32.33 96.99
Grid E-E 2 15.33 1 1.5 15.33 45.99
Grid D-D 2 56.83 1 1.5 56.83 170.49
Grid C-C 2 63.33 1 1.5 63.33 189.99
Grid B-B 2 21.83 1 1.5 21.83 65.49
Grid A-A 2 21.83 1 1.5 21.83 65.49
Grid 1-1 2 13.67 1 1.5 13.67 41.01
Grid 2-2 2 13.67 1 1.5 13.67 41.01
Grid 3-3 2 47.17 1 1.5 47.17 141.51
Grid 4-4 2 30.67 1 1.5 30.67 92.01
Grid 5-5 2 52.67 1 1.5 52.67 158.01
Grid 6-6 2 30.67 1 1.5 30.67 92.01
Grid 7-7 2 20.67 1 1.5 20.67 62.01

ii. First Floor


(Excluding slab volume)
Grid G-G 1 22.08 1 1 22.08 22.08
Grid F-F 1 32.33 1 1 32.33 32.33
Grid E-E 1 18.33 1 1 18.33 18.33
Grid D-D 1 59.83 1 1 59.83 59.83
Grid C-C 1 63.33 1 1 63.33 63.33
Grid B-B 1 21.83 1 1 21.83 21.83
Grid A-A 1 21.83 1 1 21.83 21.83
Grid 1-1 1 13.67 1 1 13.67 13.67
Grid 2-2 1 23.17 1 1 23.17 23.17
Grid 3-3 1 47.17 1 1 47.17 47.17
Grid 4-4 1 34.42 1 1 34.42 34.42
Grid 5-5 1 52.67 1 1 52.67 52.67
Grid 6-6 1 52.67 1 1 52.67 52.67
Grid 7-7 1 20.67 1 1 20.67 20.67

iii. 2nd Floor


(Excluding slab volume)
Grid F-F 1 18.33 1 1 18.33 18.33
Grid E-E 1 18.33 1 1 18.33 18.33
Grid D-D 1 59.83 1 1 59.83 59.83
Grid C-C 1 63.33 1 1 63.33 63.33
Grid B-B 1 21.83 1 1 21.83 21.83
Grid 2-2 1 23.17 1 1 23.17 23.17
Grid 3-3 1 41.42 1 1 41.42 41.42
Grid 4-4 1 34.42 1 1 34.42 34.42
Grid 5-5 1 44.67 1 1 44.67 44.67
Grid 6-6 1 30.67 1 1 30.67 30.67
Grid 7-7 1 12.67 1 1 12.67 12.67

iv. 3rd Floor


(Excluding slab volume)
Grid E-E 1 18.33 1 1 18.33 18.33
Grid D-D 1 59.83 1 1 59.83 59.83
Grid C-C 1 63.33 1 1 63.33 63.33
Grid 4-4 1 34.42 1 1 34.42 34.42
Grid 5-5 1 44.67 1 1 44.67 44.67
Grid 6-6 1 30.67 1 1 30.67 30.67
Total 2411.92
d. Slab
(Excluding slab volume)
First Floor 1 0.5 2635.34 1317.67
2nd Floor 1 0.5 2140.08 1070.04
3rd Floor 1 0.5 836.76 418.38

Deduction
Staircase -2 12 14 0.5 168 -168
Total 2638.09
e. RCC lintel
D1,W2, 4 4 0.75 0.5 3 6
SD,W3 10 5 0.75 0.5 3.75 18.75
D2,D3,W1 35 3 0.75 0.5 2.25 39.375
W4 16 6 0.75 0.5 4.5 36
W5 4 8 0.75 0.5 6 12
Total 112.125
f. Staircase
Steps I 2 6.5 5.5 0.58 35.75 41.47
Steps II 1 2.5 5 0.58 12.5 7.25
Landing 2 5 5.5 0.5 27.5 27.5
Total 76.22
Total RCC work 6858.281717
SN Particular N0. Length (fBreadth (feight (ft) (sq. ft.) Quantities
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
a. For footing @0.6% 815.9617 10.8686094
b. For column @ 1.5% 803.9651 26.77203617
c. For beams @ 1.2% 2411.92 64.2535488
d. For roof slab @ 1% 2638.09 58.565598
e. For stair and lintel @ 0.8% 6970.407 123.7944233
Total 284.2542157
SN Particular N0. Length (fBreadth (feight (ft) (sq. ft.) Quantities
7 Brickwork in cement mortar(1:6)
in foundation and plinth
Long Wall
Grid G-G 1 21.5 0.75 2.5 16.125 40.3125
Grid F-F 1 14.75 0.75 2.5 11.0625 27.65625
Grid E-E 1 14.75 0.75 2.5 11.0625 27.65625
Grid D-D 1 13.75 0.75 2.5 10.3125 25.78125
Grid C-C 1 37.25 0.75 2.5 27.9375 69.84375
Grid A-A 1 21.25 0.75 2.5 15.9375 39.84375
Toe wall 1 34 0.75 2.5 25.5 63.75

Short wall
Grid 1-1 1 14.25 0.75 2.5 10.6875 26.71875
Grid 2-2 1 17.75 0.75 2.5 13.3125 33.28125
Grid 3-3 1 22.5 0.75 2.5 16.875 42.1875
Grid 4-4 1 19.25 0.75 2.5 14.4375 36.09375
Grid 5-5 1 38.25 0.75 2.5 28.6875 71.71875
Grid 6-6 1 31.25 0.75 2.5 23.4375 58.59375
Grid 7-7 1 21.25 0.75 2.5 15.9375 39.84375
Toe wall 1 26 0.75 2.5 19.5 48.75

Deduction length of column


Column 22 -1 1 2.5 -1 -55
Total brickwork infoundation and plinth 597.03125
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
8 2.5cm thk D.P.C. (1:2:4)
Long Wall
Grid G-G 1 21.5 0.75 16.125 16.125
Grid F-F 1 14.75 0.75 11.0625 11.0625
Grid E-E 1 14.75 0.75 11.0625 11.0625
Grid D-D 1 13.75 0.75 10.3125 10.3125
Grid C-C 1 37.25 0.75 27.9375 27.9375
Grid A-A 1 21.25 0.75 15.9375 15.9375
Toe wall 1 34 0.75 25.5 25.5

Short wall
Grid 1-1 1 14.25 0.75 10.6875 10.6875
Grid 2-2 1 17.75 0.75 13.3125 13.3125
Grid 3-3 1 22.5 0.75 16.875 16.875
Grid 4-4 1 19.25 0.75 14.4375 14.4375
Grid 5-5 1 38.25 0.75 28.6875 28.6875
Grid 6-6 1 31.25 0.75 23.4375 23.4375
Grid 7-7 1 21.25 0.75 15.9375 15.9375
Toe wall 1 26 0.75 19.5 19.5

Deduction length of column


Column 22 -1 1 -1 -22
Door opening MD -1 4 0.75 3 -3
Opening SD -3 6 0.75 4.5 -13.5
Total DPC 222.3125
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
9 Brickwork in super structure
a. Ground Floor
Grid G-G 1 19.42 0.75 8.5 14.565 123.8025
Grid F-F 1 12.67 0.75 8.5 9.5025 80.77125
Grid E-E 1 12.67 0.75 8.5 9.5025 80.77125
Grid D-D 1 24.34 0.75 8.5 18.255 155.1675
Grid C-C 1 40.68 0.75 8.5 30.51 259.335
Grid A-A 1 8 0.75 8.5 6 51
Off Grid 1 8 0.75 8.5 6 51
Grid 1-1 1 13.67 0.75 8.5 10.2525 87.14625
Grid 2-2 1 17.17 0.75 8.5 12.8775 109.45875
Grid 3-3 1 43.18 0.75 8.5 32.385 275.2725
Grid 4-4 1 32.51 0.75 8.5 24.3825 207.25125
Grid 5-5 1 48.68 0.75 8.5 36.51 310.335
Grid 6-6 1 29.34 0.75 8.5 22.005 187.0425
Grid 7-7 1 19.34 0.75 8.5 14.505 123.2925
Off Grid 1 26 0.75 8.5 19.5 165.75
Half brick Wall 1 68.25 0.375 8.5 25.59375 217.546875
Total 2484.943125
b. First Floor
Grid F-F 1 18.33 0.75 8.5 13.7475 116.85375
Grid E-E 1 15.67 0.75 8.5 11.7525 99.89625
Grid D-D 1 27.34 0.75 8.5 20.505 174.2925
Grid C-C 1 40.68 0.75 8.5 30.51 259.335
Grid B-B 1 19.17 0.75 8.5 14.3775 122.20875
Off Grid 1 14 0.75 8.5 10.5 89.25
Grid 2-2 1 22.17 0.75 8.5 16.6275 141.33375
Grid 3-3 1 38.84 0.75 8.5 29.13 247.605
Grid 4-4 1 38.84 0.75 8.5 29.13 247.605
Grid 5-5 1 42.01 0.75 8.5 31.5075 267.81375
Grid 6-6 1 31.335 0.75 8.5 23.50125 199.760625
Grid 7-7 1 12.67 0.75 8.5 9.5025 80.77125
Off Grid 1 10.5 0.75 8.5 7.875 66.9375
Half brick Wall 1 45.25 0.375 8.5 16.96875 144.234375
Total 2257.8975
c. Second Floor
Grid E-E 1 12.67 0.75 8.5 9.5025 80.77125
Grid D-D 1 24.34 0.75 8.5 18.255 155.1675
Grid C-C 1 24.34 0.75 8.5 18.255 155.1675
Grid 4-4 1 13.67 0.75 8.5 10.2525 87.14625
Grid 5-5 1 29.34 0.75 8.5 22.005 187.0425
Grid 6-6 1 29.34 0.75 8.5 22.005 187.0425
Half brick Wall 2 9.5 0.375 8.5 3.5625 60.5625
Total 912.9
d. Deduction For Opening
D1,W2, -4 4 0.75 7 3 -84
SD,W3 -8 5 0.75 7 3.75 -210
D2,W1 -29 3 0.75 7 2.25 -456.75
W4 -16 6 0.75 7 4.5 -504
W5 -4 8 0.75 7 6 -168
D3 -6 3 0.375 7 1.125 -47.25
SD -2 5 0.375 7 1.875 -26.25
Total -1496.25
e. Deduction for lintels
D1,W2, -4 4 0.75 0.5 3 -6
SD,W3 -10 5 0.75 0.5 3.75 -18.75
D2,D3,W1 -35 3 0.75 0.5 2.25 -39.375
W4 -16 6 0.75 0.5 4.5 -36
W5 -4 8 0.75 0.5 6 -12
Total (112.13)
Total Superstructure brickwork 4,047.37
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
Plaster work in 1:4 C/S mortar
11 Walls
A. Ground Floor
a. Grid G-G 1 20.75 0.083 8.5 1.72225 14.639125
Grid F-F 1 14 0.083 8.5 1.162 9.877
Grid E-E 1 14 0.083 8.5 1.162 9.877
Grid D-D 1 27 0.083 8.5 2.241 19.0485
Grid C-C 1 46 0.083 8.5 3.818 32.453
Grid A-A 1 8 0.083 8.5 0.664 5.644
Off Grid 1 8 0.083 8.5 0.664 5.644
Grid 1-1 1 15 0.083 8.5 1.245 10.5825
Grid 2-2 1 18.5 0.083 8.5 1.5355 13.05175
Grid 3-3 1 48.5 0.083 8.5 4.0255 34.21675
Grid 4-4 1 36.5 0.083 8.5 3.0295 25.75075
Grid 5-5 1 54 0.083 8.5 4.482 38.097
Grid 6-6 1 32 0.083 8.5 2.656 22.576
Grid 7-7 1 22 0.083 8.5 1.826 15.521
Off Grid 1 26 0.083 8.5 2.158 18.343
Half brick Wall 1 68.25 0.083 8.5 5.66475 48.150375
Total 323.47175
First Floor
b. Grid F-F 1 17 0.083 8.5 1.411 11.9935
Grid E-E 1 17 0.083 8.5 1.411 11.9935
Grid D-D 1 30 0.083 8.5 2.49 21.165
Grid C-C 1 46 0.083 8.5 3.818 32.453
Grid B-B 1 20.5 0.083 8.5 1.7015 14.46275
Off Grid 1 14 0.083 8.5 1.162 9.877
Grid 2-2 1 23.5 0.083 8.5 1.9505 16.57925
Grid 3-3 1 41.5 0.083 8.5 3.4445 29.27825
Grid 4-4 1 41.5 0.083 8.5 3.4445 29.27825
Grid 5-5 1 46 0.083 8.5 3.818 32.453
Grid 6-6 1 32 0.083 8.5 2.656 22.576
Grid 7-7 1 14 0.083 8.5 1.162 9.877
Off Grid 1 10.5 0.083 8.5 0.8715 7.40775
Half brick Wall 1 45.25 0.083 8.5 3.75575 31.923875
Total 281.318125
Second Floor
c. Grid E-E 1 14 0.083 8.5 1.162 9.877
Grid D-D 1 27 0.083 8.5 2.241 19.0485
Grid C-C 1 27 0.083 8.5 2.241 19.0485
Grid 4-4 1 15 0.083 8.5 1.245 10.5825
Grid 5-5 1 32 0.083 8.5 2.656 22.576
Grid 6-6 1 32 0.083 8.5 2.656 22.576
Half brick Wall 2 14.5 0.083 8.5 1.2035 20.4595
Total 124.168
Deduction For Opening
d. D1,W2, -4 4 0.083 7 0.332 -9.296
SD,W3 -8 5 0.083 7 0.415 -23.24
D2,W1 -29 3 0.083 7 0.249 -50.547
W4 -16 6 0.083 7 0.498 -55.776
W5 -4 8 0.083 7 0.664 -18.592
D3 -6 3 0.083 7 0.249 -10.458
SD -2 5 0.083 7 0.415 -5.81
Total -173.719
Deduction for lintels
e. D1,W2, -4 4 0.083 0.5 0.332 -0.664
SD,W3 -10 5 0.083 0.5 0.415 -2.075
D2,D3,W1 -35 3 0.083 0.5 0.249 -4.3575
W4 -16 6 0.083 0.5 0.498 -3.984
W5 -4 8 0.083 0.5 0.664 -1.328
Total -12.4085
Ceilings
B. Ground Floor 1 0.083 2635.34 218.73322
First Floor 1 0.083 2140.08 177.62664
Second Floor 1 0.083 836.76 69.45108
Total 465.81094
Total cement plaster waork 1008.641315
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
Flooring Work
12 50mm thick screeding work
12.1 Ground Floor 1 0.167 2513.00 419.671
First Floor 1 0.167 2635.34 440.10178
Second Floor 1 0.167 2140.08 357.39336
Roof level 1 0.167 836.76 139.73892
Total 1356.91

3mm thick Punning work


12.2 Ground Floor 2513.00 2513.00
First Floor 2635.34 2635.34
Second Floor 2140.08 2140.08
Roof level 836.76 836.76
Total 8125.18
SN Particular N0. Length Breadth Height Area Quantities
(ft) (ft) (ft) (Sq.ft)
Woodwork in Frame
Doors D1 1 0.33 0.25 28.00 0.0825 2.31
13 Doors D2 13 0.33 0.25 17.00 0.0825 18.2325
Doors D3 6 0.33 0.25 16.50 0.0825 8.1675
Door SD 6 0.33 0.25 26 0.0825 12.87
Window W1 16 0.33 0.25 16.00 0.0825 21.12
Window W2 9 0.33 0.25 20.00 0.0825 14.85
Window W3 11 0.33 0.25 22.00 0.0825 19.965
Window W4 4 0.33 0.25 24.00 0.0825 7.92
Window W5 3 0.33 0.25 24.00 0.0825 5.94
Total Woodwork in opening frames 111.38
Remarks

Remarks

Cu. ft.

L=21+2/2+2/2
L=31+2
L=14+2
L=55.5+2
L=62+2
L=20.5+2
L=20.5+2
L=15+9.5+10.5=35

L=15-2
L=19.5-2
L=54-2
L=37.33-2
L=54-2
L=32-2
L=22-2
L=15.5+8.5=22
Cu. ft.

Cu. ft.
Cu. ft.
Remarks

Cu. ft.

Column9
L=c-c perimeter
L= n sum - n × 1.33
Cu. ft.

Remarks
Remarks

Cu. ft.

L=21+2/2+2/2
L=31+2
L=14+2
L=55.5+2
L=62+2
L=20.5+2
L=20.5+2
L=15+9.5+10.5=35
Cu. ft.

L=15-2
L=19.5-2
L=54-2
L=37.33-2
L=54-2
L=32-2
L=22-2
L=15.5+8.5=22
Cu. ft.

Cu. ft.
Remarks
Remarks
top area = 1.5×1.5
base area= 6×6
V=h(1.5²+1.5×6+6²)/3

Cu. ft.

deducting tie beams *2


upto botoom of beam

Cu. ft.

L=14+1.33
L=31+1.33
L=14+1.33
L=55.5+1.33
L=62+1.33
L=20.5+1.33
L=20.5+1.33
L=15-1.33
L=15-1.33
L=48.5-1.33
L=32-1.33
L=54-1.33
L=32-1.33
L=22-1.33

L=14+1.33+6.75
L=31+1.33
L=14+1.33+3
L=55.5+1.33+3
L=62+1.33
L=20.5+1.33
L=20.5+1.33
L=15-1.33
L=15-1.33+9.5
L=48.5-1.33
L=32-1.33+3.75
L=54-1.33
L=54-1.33
L=22-1.33

L=17+1.33
L=14+1.33+3
L=55.5+1.33+3
L=62+1.33
L=20.5+1.33
L=15-1.33+9.5
L=33.5-1.33+9.25
L=32-1.33+3.75
L=46-1.33
L=32-1.33
L=14-1.33

L=14+1.33
L=55.5+1.33
L=27+1.33
L=15-1.33
L=32-1.33
L=32-1.33
Cu. ft.

Cu. ft.

Cu. ft.

Cu. ft.
Cu. ft.
Remarks
Remarks

1cu.Ft =2.22 Quintal

Quintal
Remarks

L=14+0.75+6.75
L=14+0.75
L=14+0.75
L=13+0.75
L=36.5+0.75
L=20.5+0.75
L=11+12.25+10.75

L=15-0.75
L=15-0.75+3.5
L=18.5-0.75+4.75
L=17-0.75+3
L=39-0.75
L=32-0.75
L=22-0.75
L=10.5+15.5

Cu. ft.
Remarks

L=14+0.75+6.75
L=14+0.75
L=14+0.75
L=13+0.75
L=36.5+0.75
L=20.5+0.75
L=11+12.25+10.75

L=15-0.75
L=15-0.75+3.5
L=18.5-0.75+4.75
L=17-0.75+3
L=39-0.75
L=32-0.75
L=22-0.75
L=10.5+15.5

Sq. ft.
Remarks

L=14+6.75-1.33
L=14-1.33
L=14-1.33
L=27-2.66
L=46-1.33*4
L=8
L=8
L=15-1.33
L=15-1.33+3.5
L=48.5-1.33*4
L=33.5-1.33*3+3
L=54-1.33*4
L=32-1.33*2
L=22-1.33*2
L=10.5+15.5
L=47+10.75+10.5
Cu. ft.

L=17+1.33
L=14-1.33+3
L=27-2.66+3
L=46-1.33*4
L=20.5-1.33
L=14
L=15-1.33+3.5+5
L=41.5-1.33*2
L=41.5-1.33*2
L=46-1.33*3
L=17+15-1.33/2
L=14-1.33
L=10.5
L=9.5*2+15.5+10.75
Cu. ft.

L=14-1.33
L=27-1.33*2
L=27-1.33*2
L=15-1.33
L=32-1.33*2
L=32-1.33*2
L=7+7.5
Cu. ft.

Cu. ft.

Cu. ft.
Cu. ft.
Remarks

L=14+6.75
L=14
L=14
L=27
L=46
L=8
L=8
L=15
L=15+3.5
L=48.5
L=33.5+3
L=54
L=32
L=22
L=10.5+15.5
L=47+10.75+10.5
Cu. ft.

L=17
L=14+3
L=27+3
L=46
L=20.5
L=14
L=15+3.5+5
L=41.5
L=41.5
L=46
L=17+15
L=14
L=10.5
L=9.5*2+15.5+10.75
Cu. ft.

L=14
L=27
L=27
L=15
L=32
L=32
L=7+7.5
Cu. ft.

Cu. ft.

Cu. ft.

Cu. ft.
Cu. ft.
Remarks

Cu. ft.

Sq. ft.
Remarks

Cu. ft.
Project : Cost Estimation of Residential Building
Owner :
Location : Khushibu, Kathmandu

Table : Cost Estimation

S. No Description Quantity Unit


A Cost Up To Plinth level
1 : Earthwork in excavation L=14+0.75+6.75 cft
2 : Earthwork in filling
2.1 : Filling in room areas L=15-0.75+3.5 cft
3 : Flat Brick soling
3.1 : In Foundation / floor areas - sft
4 : Plain Cement Concrete
4.1 : In foundation 136.75 cft
4.2 : In room areas (9.73) cft
6 : Reinforced Concrete
6.1 : PCC for RCC
Foundation L=32-2 cft
Column - cft
Tie beam V=h(1.5²+1.5×6+6²)/3 cft
6.2 : Formworks 47.17 sft
6.3 : Steel Reinforcement 21.83 kg
7 : Sand filling - cft
8 : Polythene sheet laying as vapour barier - sft
9 : Brickwork in foundation 1,206.00 cft

B Cost Above Tie Beam


1: Reinforced Cement Concrete
1.1 : PCC for RCC
Columns (M20) Remarks cft
Beam (M15) Err:509 cft
Slab (M15) Err:509 cft
1.2 : Formworks - sft
1.3 : Steel Reinforcement Err:509 kg
: Columns Err:509
: Beam Err:509
: Slab 87.15
2: Brickwork
2.1 : 9" thick (1:6 c/m) 247.61 sft
2.2 : 4" thick (1:4 c/m) 199.76 sft
2.3 : Brick cornice - rft
3: Plaster
3.1 : Internal Plaster (36.00) sft
3.2 : External Plaster - sft

C Finishing Works
1 : Flooring Works
1.1 : Screeding - sft
1.2 : Punning 0.66 sft
1.3 PCC 1.54 cft
1.4 Brick soling - sft
2 : Plaster of Paris 4.48 sft
3 : Doors and Windows
3.1 : Wooden Door Frame 32.45 cft
3.2 : Flush Door Shutter 7.41 sft
3.3 : Aluminium Windows sft
3.4 : Rolling Shutter sft
4 : Painting
4.1 : Plastic Emulsion Paint 1.16 sft
4.2 : Exterior Paint (Biofine) sft
4.3 : Enamel Paint on door frame sft
4.4 : Chopara Polish sft

Total Cost of Civil Works (A+B+C)

D Electircal works 10 % of Civil Cost

Total Cost of Construction of Bldg

Note :
Total Building Area 2,165.00 sft
Cost Per Sft #VALUE! NRs.

paid to contractor
remaining cost for contractor
Rate Amount

4.00 #VALUE!

12.00 #VALUE!

4.00 -

9.00 1,230.75
9.00 (87.56)

27.00 #VALUE!
27.00 -
27.00 #VALUE!
- -
-
28.50 -
2.50 -
11.00 13,266.00

Sub Total = #VALUE!

27.00 #VALUE!
27.00 Err:509
27.00 Err:509
27.00 -
Err:509
Err:509
Err:509
-

11.00 2,723.66
9.00 1,797.85
30.00 -
5.00 (180.00)
8.00 -

Sub Total = #VALUE!

4.00 -
4.00 2.66
9.00 13.82
4.00 -
6.00 26.89

-
-
-
-

12.00 13.94
22.00 -
12.00 -
15.00 -

Sub Total = 57.31