Civil Aviation Authority of Nepal

Gautam Buddha Airport Upgrading Component


BILL OF QUANTITY
STRUCTURE WORKS FOR DHAPAKHEL RESIDENCE
Contract No:

S. N. Description of Items Unit Quantity Rates Amounts

A Main Building 10,247,419.77

Excavate in soft/med. hard mixed soil, depth less than 1.5m


& dispose unsuitable and excess materials, including cost of
1 trench backfill, all complete as per drg, specification and cft 9628.37 25.00 240709.14
instruction of the Engineer.
2 Mix gravel filling cft 562.89 130.00 73176.16
Boulder packing in foundation with consolidation all complete
2 as per drawing, specification and instruction of the Engineer. cft 1125.79 130.00 146352.31

PCC lining(1:2:4) in foundation, including cost of placing &


3 removal of side forms, all complete as per drawig, cft 919.97 450 413984.88
specification and instruction of the Engineer.
Provide and place Structural Concrete Class 25 (excluding
formwork and reinforcement bars) for any section, in any
4 height & location all complete as per drawing, specification cft 5459.49 650 3548667.40
and instruction of the Engineer.
Provide, place and remove rough formworks to all concrete
works of any section, at any height & location, all complete
5 as per drawing, specification and instruction of the Engineer. sft 13409.14 100 1340914.15

Provide/ fabricate and lay high tensile Fe-415 (Tor-


reinforcement) bars at any height & location all complete as
6 per drawing, specification and instruction of the Engineer. kgs 20476.99 120 2457238.39

7 Brick Works
1st class chimney brick walls set in 1:4 cement mortar for
a) foundation, plinth all complete with scaffoldings and as per cft 2112.53 481.314 1016789.57
drawing, specification and instruction of the Engineer.
Half brick wall (for partition and claddings) set in 1:4 cement
mortar including cost of M15 concrete tie with 1- 8 dia
b) horizontal bar & side forms at every 6th brick course, all sft 4007.22 150 601083.00
complete with scaffolding and as per drg, spec and
instruction of the Engineer.
12/15mm coat neat cement plaster of mix 1:4 in ceilling
8 (external/internal) all complete with scafolding and as per m2 16340.19 25 408504.78
specification and instruction of the Engineer.

B Water Tank 80,000.00

Prepared by: Checked by: Approved by:


Earthwork in excavation
S.N Description Nos L(ft) B(ft) H(ft) Qty Total Qty Remarks
Earthwork in excavation 9628.37
1 Footing 8158.31
1.1 Strip footing
SF1 1 21.25 8.5 6.50 1174.06
SF2 1 25.75 9 6.50 1506.38
1.2 Isolated footing
F1 2 8 8 6.50 832.00
` F2 1 9 9 6.50 526.50
F3 1 8 8 6.50 416.00 Bearing of 1'
for
F4 1 8.75 8.75 6.50 497.66 excavation
F5 1 10.25 10.25 6.50 682.91
F6 1 9 9 6.50 526.50
F7 1 8.75 8.75 6.50 497.66
F8 1 8.5 8.5 6.50 469.63
F9 1 9.5 9.5 6.50 586.63
F10 1 8.25 8.25 6.50 442.41
2 Footing Trench 1470.05
A1-A2 1 8.25 2 6.50 107.25
` A2-A3 1 6.25 2 6.50 81.25
B1-B2 1 7.25 2 6.50 94.25
B2-B3 1 5.125 2 6.50 66.63
C2-C3 1 10.75 2 6.50 139.75
D2-D3 1 10.375 2 6.50 134.88
E1-E2 1 7.75 2 6.50 100.75
E2-E3 1 5.875 2 6.50 76.38
1A-1B 1 4.875 2 6.50 63.38 Trench
width only
1B-1C' 1 1.292 2 6.50 16.80 no extra
1C'-1D 1 1 2 6.50 13.00 bearing
1D-1E 1 7 2 6.50 91.00
2A-2B 1 3.875 2 6.50 50.38
2B-2D 1 11.872 2 6.50 154.34
Mix Gravel filling
S.N Description Nos L(ft) B(ft) H(ft) Qty Total Qty Remarks
Mix Gravel Filling 562.89
1 Footing 449.81
1.1 Strip footing
SF1 1 19.75 7 0.50 69.13
SF2 1 24.25 7.5 0.50 90.94
1.2 Isolated footing
F1 2 6.5 6.5 0.50 42.25
` F2 1 7.5 7.5 0.50 28.13 Projection
F3 1 6.5 6.5 0.50 21.13 3" beyond
F4 1 7.25 7.25 0.50 26.28 foundation
for filling
F5 1 8.75 8.75 0.50 38.28
F6 1 7.5 7.5 0.50 28.13
F7 1 7.25 7.25 0.50 26.28
F8 1 7 7 0.50 24.50
F9 1 8 8 0.50 32.00
F10 1 6.75 6.75 0.50 22.78
2 Footing Trench 113.08
A1-A2 1 8.25 2 0.50 8.25
` A2-A3 1 6.25 2 0.50 6.25
B1-B2 1 7.25 2 0.50 7.25
B2-B3 1 5.125 2 0.50 5.13
C2-C3 1 10.75 2 0.50 10.75
D2-D3 1 10.375 2 0.50 10.38
E1-E2 1 7.75 2 0.50 7.75
E2-E3 1 5.875 2 0.50 5.88
1A-1B 1 4.875 2 0.50 4.88 Filling on 2'
1B-1C' 1 1.292 2 0.50 1.29 whole
1C'-1D 1 1 2 0.50 1.00 portion
1D-1E 1 7 2 0.50 7.00
2A-2B 1 3.875 2 0.50 3.88
2B-2D 1 11.872 2 0.50 11.87
Boulder Filling
S.N Description Nos L(ft) B(ft) H(ft) Qty Total Qty Remarks
Boulder Filling 1125.79
1 Footing 899.63
1.1 Strip footing
SF1 1 19.75 7 1.00 138.25
SF2 1 24.25 7.5 1.00 181.88
1.2 Isolated footing
F1 2 6.5 6.5 1.00 84.50
` F2 1 7.5 7.5 1.00 56.25 Projection
F3 1 6.5 6.5 1.00 42.25 3" beyond
F4 1 7.25 7.25 1.00 52.56 foundation
for filling
F5 1 8.75 8.75 1.00 76.56
F6 1 7.5 7.5 1.00 56.25
F7 1 7.25 7.25 1.00 52.56
F8 1 7 7 1.00 49.00
F9 1 8 8 1.00 64.00
F10 1 6.75 6.75 1.00 45.56
2 Footing Trench 226.16
A1-A2 1 8.25 2 1.00 16.50
` A2-A3 1 6.25 2 1.00 12.50
B1-B2 1 7.25 2 1.00 14.50
B2-B3 1 5.125 2 1.00 10.25
C2-C3 1 10.75 2 1.00 21.50
D2-D3 1 10.375 2 1.00 20.75
E1-E2 1 7.75 2 1.00 15.50
E2-E3 1 5.875 2 1.00 11.75
1A-1B 1 4.875 2 1.00 9.75 Filling on 2'
1B-1C' 1 1.292 2 1.00 2.58 whole
1C'-1D 1 1 2 1.00 2.00 portion
1D-1E 1 7 2 1.00 14.00
2A-2B 1 3.875 2 1.00 7.75
2B-2D 1 11.872 2 1.00 23.74
Boulder Filling
S.N Description Nos L(ft) B(ft) H(ft) Qty Total Qty Remarks
Boulder Filling 919.97
1 Footing 296.88
1.1 Strip footing
SF1 1 19.75 7 0.33 45.62
SF2 1 24.25 7.5 0.33 60.02
1.2 Isolated footing
F1 2 6.5 6.5 0.33 27.89
` F2 1 7.5 7.5 0.33 18.56 Projection
F3 1 6.5 6.5 0.33 13.94 3" beyond
F4 1 7.25 7.25 0.33 17.35 foundation
for filling
F5 1 8.75 8.75 0.33 25.27
F6 1 7.5 7.5 0.33 18.56
F7 1 7.25 7.25 0.33 17.35
F8 1 7 7 0.33 16.17
F9 1 8 8 0.33 21.12
F10 1 6.75 6.75 0.33 15.04
2 Footing Trench 74.63
A1-A2 1 8.25 2 0.33 5.45
` A2-A3 1 6.25 2 0.33 4.13
B1-B2 1 7.25 2 0.33 4.79
B2-B3 1 5.125 2 0.33 3.38
C2-C3 1 10.75 2 0.33 7.10
D2-D3 1 10.375 2 0.33 6.85
E1-E2 1 7.75 2 0.33 5.12
E2-E3 1 5.875 2 0.33 3.88
1A-1B 1 4.875 2 0.33 3.22 Filling on 2'
1B-1C' 1 1.292 2 0.33 0.85 whole
1C'-1D 1 1 2 0.33 0.66 portion
1D-1E 1 7 2 0.33 4.62
2A-2B 1 3.875 2 0.33 2.56
2B-2D 1 11.872 2 0.33 7.84
59.81115
34092.36
113.4547
0
0
S.N Description Area Total Area
1 TERMINAL BULIDING
1.1 PHASE 1 47509.215
1.1.1 Basement 9758
1.1.2 Ground Floor 18773.87
1.1.3 First Floor 10346.29
1.1.4 Second Floor 5173.145 50% of FF
1.1.5 Kerb area 3457.91
1.2 PHASE 2 19284.5
1.2.1 West portion 9642.25
1.2.2 East portion 9642.25

2 APRON AREA 68647.86


PHASE 1 24083.39
PHASE 2 - West 22748.53
PHASE 2 - East 11125.94
Equipment yard 10690
3 Taxiway 39824
4 Car park and other areas 36398
Void FF
1 591.93

2 1487.06
3 2201
4 2058.14
5 1497.38
6 592.07
8427.58

4395