Surface Mapping and Electrical Resistivity To

WORK SCHEDULE
No ACTIVITY Days
10
1 2 3 4 5 6 7
A. Preparation & Mob-Demobilization
1 Work Order/Contract 2
2 Preparation at Warehouse 3
3 Mobilization Team (BDO-KDI) 1
4 Preparation at site (Orientation, Safety Induction, 3
Commisioning, etc)
6 Demobilisasi Team 1

B. Field Work
1 Production BM & GCP 3
2 Installation BM & GCP 3
3 Measure and Tie BM & CP 4
4 Quality Control of Geodetic Survey 1
5 Photogrammetry Acquisition 8
6 Quality Control Aerial Survey 1
7 Resistivity Measurement 8
8 Quality Control of ERT Survey 1

B. Studio Processing & Reporting


1 Rendering Data & 3D Model 15
2 Vectorization and Digitation 6
3 ERT Processing & Forward Modelling 6
4 Finishing 5
5 Topographic & Geophysical Reporting 4
al Resistivity Tomography Survey for WAM IUP, Kendari, South East Sulawesi

DURATION
10 20 30 40
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
Sulawesi

REMARK
40
34 35 36 37 38 39 40

Refference
Investarization

Monument & Premark