Cemfis India Pvt Ltd

CONCRETE POUR CARD


DATE ……………………………………..
CARD NO ………………………………..
NAME OF CUSTOMER ............................
NAME OF WORK .....................................
WORKSITE :...............................................
GRADE OF CONCRETE ...........................
LOCATION OF CONCRETING ...........................
REFERENCE DRAWING ………………………

APPROVING AUTHORITY ENGINEER CONSULTANT CLINET


INSPECTION ITEMS PIOR TO CONCRETEING
REINFORCEMENT
1) SPACING
2) BAR DIA
3) FREE FORM RUSTING
4) SATISFYING THE DRAWING

SHUTTERING
1) OILED AND READY TO USE
2) POSITIONING
3) MINIMUM COVER
MAINTAINED
4) LEVEL

INSPECTION ITEMS DURING CONCRETEING

TIME OF COMMENCE ______________________

`1) CONCRETE QUALITY


2) TEST CUBE MOULDS READY
3) VIBRATION PROPERLY DONE
4) LEVEL MAINTIAINED
5) CONRETE QUANTITY

TIME OF COMPLETION ______________________

POST CONCRETING INSPECTION

1) SURFACE
2) LEVEL
3) SHUTTERING CLEANING AND
READY FOR USE AGAIN

__________________ ___________________ ____________________

SITE ENGINEER CONSULTANT CLINET