You are on page 1of 6

63660

China : Liaoning Medium Cities Infrastructure Project


 Procurement Plan (October 2010 – December 2012)

I. General

1. Project information:
Country: China
Borrower: People’s Republic of China
Project Name: Liaoning Medium Cities Infrastructure Project
Project ID: P 099992
Project Implementing Agency (PIA):
Liaoning Urban Construction and Renewal Project Office (LUCRPO) will
coordinate and supervise all procurement activities. The PIAs for each project
component are described as follows:
No. Project Sub-component PIA
1 Liaoyang Sub-component PMO under the Urban Construction Bureau
2. Jinzhou Sub-component PMO under the Municipal Construction Committee
3 Benxi Sub-component PMO under the Municipal Construction Committee
4 Panjin Sub-component PMO under the Urban Construction Bureau
5 Fushun Sub-component PMO under the Municipal Construction Committee

2. Bank’s approval Date of the procurement Plan: XXXXXXXXX


3. Date of General Procurement Notice: April 6, 2006
4. Period covered by this procurement plan: October 2010-December 2012

II. Goods and Works and non-consulting services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the


Bank as stated in Appendix 1 to the Guidelines for Procurement:
Prior Review Thresholds Proposed (USD)

Goods ≥ 0.5 million


Works ≥ 5 million

2. Prequalification: Not applied.


3. Any Other Special Procurement Arrangements: Not applied in 2010-2012.
4. Procurement Packages with Methods and Time Schedule
Domestic Estimated
Contract Procurement Review Expected
Preference Construction
Estimated Cost
Prequalification by Bid- Period
Ref. No. (Description) Method Category (yes/no)
(yes/no) Bank Opening (months)
(Million (Million (Prior /
      Date  
RMB) USD) Post)
Benxi                    
Goods
BPT21 Bus stop signs & Bus Shelters 10.81 1.58 ICB NO NO Prior March ,2011 12
(G)
Xihu Road Houhu Section,
BRI14 Jiefang 2 Road, Xincheng road 35.13 5.14 NCB CW NO NO Prior May ,2011 12
North Section
Fushun                    

FTM23 Traffic Signal Control System 7.08 1.06 ICB G NO NO Prior April,2011 6

Qianjin Road,Shiyidao
Street,Shisidao Street,Fumin
FRM14 Road,Zhonghe Road,Jiudao 41.84 6.24 NCB CW NO NO Prior Feb, 2011 12
Street,Erdao Street,Sidao
Street,Qidao Street,Badao Street
Yongshou Road,Fengxiang
Road,Wangqing Street,Huncun
FRM15 33.1 4.93 NCB CW NO NO Post Feb, 2011 12
Street,Meihe Road,Jiangjunsan
Street,Xinhuasan Street

Heishan Street,Huanren
FRM16 Road,West Section of Leifeng 34.33 5.12 NCB CW NO NO Prior March,2011 12
Road,Zhangwu Road
Nanhuayuan Street,Suiyang
Road,Rengonghe
FRM17 37.14 5.54 NCB CW NO NO Prior March,2011 12
Zroad,Hudongyi Street,Ningan
Road,Meidu Road

FRM18 Pannan Road 33.6 5.01 NCB CW NO NO Prior April,2011 12


Domestic Estimated
Contract Procurement Review Expected
Preference Construction
Estimated Cost
Prequalification by Bid- Period
Ref. No. (Description) Method Category (yes/no)
(yes/no) Bank Opening (months)
(Million (Million (Prior /
      Date  
RMB) USD) Post)
Liaoyang                    
milling machine(0.5m),

cold recycling machine(2M),


LRM22 9.60 1.43 ICB G NO NO Prior April, 2011 6
Mud-sucking truck,
14M Cherry Picker Truck

CCTV and cables, Command


LTM21 Centre Upgrading, GD system, 15 2.2 ICB G NO NO Prior Feb, 2011 12
ATC and signals

Qingnian Street, Jiefang


LRM14 31.81 4.74 NCB CW NO NO Post Feb, 2011 12
Road,Laodong Street
Shuguang Road, Erdao Street,
LRM15 Sandao Street, Bus Stops and 26.71 3.98 NCB CW NO NO Post March,2011 12
passenger waiting sheds
LRM16 Greening for Nanhuan Road 27.65 4.12 NCB CW NO NO Post Feb, 2011 6
October,
LPT12 Liaohua Bus parking lots 3 0.44 NCB CW NO NO Post 12
2010
Zhongxin road, Beixin street,
LRI17 10.45 1.53 NCB CW NO NO Post May, 2011 12
Dongxing road
Domestic Estimated
Contract Procurement Review Expected
Preference Construction
Estimated Cost
Ref. Prequalificati by Period
(Description) Method Category (yes/no) Bid-Opening
No. on (yes/no) Bank (months)
(Million (Million (Prior /
      Date  
RMB) USD) Post)
Jinzhou                    

Traffic signals maintenance


car, CCTV and cables, RLR
JTM21 system, GD System, 26.44 3.87 ICB G NO NO Prior March, 2011 12
Information Screen

ATC and signals


Shengli Bus Terminal, Xinzhi
JPT12 Street Bus Interchange, 2.7 0.4 NCB CW NO NO Post March, 2011 10
Nanshan Bus Interchange
Zhongyang Street,
JRI18 Zhongyang North Street, 63.63 9.32 NCB CW NO NO Prior March, 2011 12
Jinxing Road
JRM18 Shifu Road, Shifu West Road 6.01 0.88 NCB CW NO NO Post March, 2011 10
JRM19 Mingde Street 6.19 0.91 NCB CW NO NO Post March, 2011 10
Beian Road, Beizhen Road,
Anda Street, Taifeng Road,
Hubei Road, Jingdong Street,
Weidong Street, Fukang
JRM15 Road, Jinyuan Road, Hechun 51.05 7.47 NCB CW NO NO Prior March, 2011 12
Road, Zhaodong Street,
Kuanggong Street, Jinxi
Street, Jiangxi Street,
Zhonghuan south Road
Domestic Estimated
Contract Procurement Review Expected
Preference Construction
Estimated Cost
Ref. Prequalification Bid- Period
(Description) Method Category (yes/no) by Bank
No. (yes/no) Opening (months)
(Million (Million (Prior /
      Date  
RMB) USD) Post)
Panjin                    
ATC and signals, RLR system, March,
PTM21 45.81 6.71 ICB G NO NO Prior 12
CCTV 2011
Command Centre Integrated
Platform, Command Centre
and Computer Room, Wireless
Intercom Command System,
March,
PTM22 Command Centre Upgrading, 35.22 5.16 ICB G NO NO Prior 12
2011
GD System, Urban entrance-
exit management system, 122
police system, Traffic flow
monitoring system
March,
PTM24 Guardrail 5 0.73 ICB G NO NO Prior 6
2011
III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated
in Appendix 1 to the Guidelines Selection and Employment of Consultants:
Prior Review Thresholds Proposed (USD)

Consulting Service ≥0.2 million for firm, ≥0.05 million for individuals, all SSS

2. Short list comprising entirely of national consultants: Short list of consultants for
services, estimated to cost less than US$ 300,000 or equivalent per contract, may
comprise entirely of national consultants in accordance with the provisions of paragraph
2.7 of the Consultant Guidelines.
3. Any Other Special Selection Arrangements: No.

4. Consultancy Assignments with Selection Methods and Time Schedule

1 2 3 4 5 6 7

Ref. No. Description of Estimated Selection Review Expected Comments


Assignment Cost (USD) Method by Bank Proposals
(Prior / Submission
Post) Date
LUCRPO
IDTS1 Enforcement of 300,000 QCBS Prior May 1, 2011
traffic and
parking
strategies
Management,
training & study
tour
IDRI2 Transport 250,000 QCBS Prior May 1, 2011
Planning
IDRM1 Preventative 120,000 CQS Post May 1, 2011
road
Maintenance
planning training
& study tour
IDPT1 Bus Priority 140,000 CQS Post May 1,2011
training & study
tour