SCHEDULE STP-A DAN STP-B

SOPO DEL OFFICE TOWER & LIFESTYLE

ID Task Name Duration Start Finish May 2016 June 2016


13 16 19 22 25 28 31 03 06 09 12 15 18 21
1 Start 0 days 20-05-16 20-05-16 20-05
2 STP A 29 days 20-05-16 17-06-16 20-05 17-06
3 Repair Struktur Dinding, Dak dan Balok 6 days 20-05-16 25-05-16 20-05 25-05
4 Tes Rendam I (Sebelum Coating) 9 days 20-05-16 28-05-16 20-05 28-05
5 Coating 16 days 23-05-16 07-06-16 23-05 07-06
6 Tes Rendam II (Setelah Coating) 12 days 30-05-16 10-06-16 30-05 10-06
7 Plester Proteksi 15 days 02-06-16 16-06-16 02-06 16-06
8 General Cleaning 12 days 06-06-16 17-06-16 06-06 17-06
9 STP B 29 days 20-05-16 17-06-16 20-05 17-06
10 Struktur Clarifier Basin 9 days 20-05-16 28-05-16 20-05 28-05
11 Urugan Ruang Basin 4 days 20-05-16 23-05-16 20-05 23-05
12 Pemasangan Tulangan Pelat 6 days 22-05-16 27-05-16 22-05 27-05
13 Screed Ruang Basin 7 days 22-05-16 28-05-16 22-05 28-05
14 Repair Struktur Dinding, Dak dan Balok 8 days 20-05-16 27-05-16 20-05 27-05
15 Tes Rendam I (Sebelum Coating) 12 days 20-05-16 31-05-16 20-05 31-05
16 Coating 11 days 23-05-16 02-06-16 23-05 02-06
17 Tes Rendam II (Setelah Coating) 12 days 29-05-16 09-06-16 29-05 09-06
18 Plester Proteksi 10 days 05-06-16 14-06-16 05-06 14-06
19 General Cleaning 8 days 10-06-16 17-06-16 10-06 17-06
20 Finish 0 days 17-06-16 17-06-16 17-06