SCHEDULE STOP LINE A

30 JANUARI 2019
No LIST PEKERJAAN KETERANGAN
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Rencana Pekerjaan Stop Line A :


1. Perbaikan frame conveyor transfer bagging line A = 4 jam (Mekanik/Fabrikasi)
2. Perbaikan belt conveyor transfer bagging line A = 6 jam (PT.SAT)
3. Penggantian belt conveyor wfg line A no.1 = 4 jam (Mekanik)
4. Penggantian bearing rotary feeder dryer line A = 4 jam (Mekanik)
5. Balancing IDF line A = 6 jam (PT.WIBON)

Rencana perbaikan konveyor metal line a :


- perbaikan dan penggantian bearing roll head drum conv metal detector
- ajust level papan luncur konv metal detector
- penggantian belt conv metal detector

Prepared by : Approved by: