USULAN PEMBIAYAAN
1 BIAYA LANGSUNG
NO POSISI SATUAN VOLUME HARGA JUMLAH (Rp)
SATUAN (Rp)
A TENAGA AHLI (*sertifikasi)
1 Ahli Sipil Struktur *) Orang-Bulan 3 10,000,000 30,000,000
2 Ahli Elektrikal Mekanikal *) Orang-Bulan 3 10,000,000 30,000,000
3 Ahli Plumbing/PAB/PAK Orang-Bulan 1.5 8,000,000 12,000,000
72,000,000
B ASISTEN (Sub Profesional Staff)
1 Drafter Sipil Struktur Orang-Bulan 3 7,000,000 21,000,000
2 Drafter Elektrikal Mekanikal Orang-Bulan 3 7,000,000 21,000,000
3 Drafter Plumbing/PAB/PAK Orang-Bulan 3 7,000,000 21,000,000
63,000,000
C TENAGA PENDUKUNG
1 Admin Percetakan/Dokumentasi Orang-Bulan 3 1,500,000 4,500,000
4,500,000
*)tenaga ahli ME masih dalam konfirmasi
2 BIAYA LANGSUNG NON PERSONIL
NO URAIAN SATUAN VOLUME HARGA JUMLAH (Rp)
SATUAN (Rp)
A OPERASIONAL KANTOR selama 2 BULAN
1 Pemakaian utilitas (air,listrik,ruang,ATK) bulan *) 2 500,000 1,000,000
2 Komputer printer unit/bulan 4 500,000 4,000,000
3 Fotocopy perawatan unit/bulan 2 500,000 2,000,000
4 Internet/wifi/komunikasi unit/bulan 1 1,000,000 2,000,000
9,000,000
B TRANSPORTASI DAN PEMAPARAN selama 2 BULAN
1 Paparan dan lump sum ritasi/bulan 1 2,000,000 4,000,000
2 Transportasi ritasi 3 1,500,000 4,500,000
8,500,000
C PELAPORAN
1 Laporan Kemajuan, draft output Buku 3 500,000 1,500,000
2 Laporan Kajian (Geoteknik, Geodesi, Struktur) Buku 3 500,000 1,500,000
3 Album Gambar A2,A3 Buku 6 500,000 3,000,000
4 Laporan Akhir+Album Final (Termasuk CD) Buku 9 1,000,000 9,000,000
15,000,000
REKAP PEMBIAYAAN
NO URAIAN JUMLAH (Rp.)
1. BIAYA LANGSUNG
A TENAGA AHLI 72,000,000
B TENAGA ASISTEN AHLI 63,000,000
C TENAGA PENDUKUNG 4,500,000
SUB TOTAL - 1 139,500,000
2. BIAYA LANGSUNG NON PERSONIL
A OPERASIONAL KANTOR selama 2 BULAN 9,000,000
B TRANSPORTASI DAN PEMAPARAN selama 2 BULAN 8,500,000
C PELAPORAN 15,000,000
SUB TOTAL - 2 32,500,000
SUB TOTAL 1+2 172,000,000