OCS-UGC01 follow up sheet based on Interface item number as per Meeting held on 1

S.no Interface Item Number Discussion Point

Requirements / details and location of


1 T1.2- OH/UG-05 the Neutral Section

Design the Type of Drop Arm and shall fix


2 T1.2- OH/UG-07 in accordingly

Design and furnish the span of Drop


3 T1.2- OH/UG-08 Arms of OHE.

Obligatory drop arm to be furnished (if


4 T1.2- OH/UG-09 any)

5 T1.2- OH/UG-10 Loading on Drop Arm

KM No. / Drop Arm No. of drop arm


6 T1.2- OH/UG-11 location

Necessary details of earthing (Tunnel


7 T1.2- OH/UG-12(M) Earth Conductor (TEC) and associated
earthing).
Details of OHE Structure earthing
8 T1.2- OH/UG-14(M) including location.

9 T1.3- OH/UG-05 Obligatory catenary / OCS locations.

Design and provide necessary details of


10 T1.3- OH/UG-06(M) earthing (Tunnel Earth Conductor (TEC).

Details of connecting link terminal


11 T1.3- OH/UG-07 locations.

ISF Summary : From UGC-01 To OCS-11A (As on 20.Feb.2019)


Sl No ISF Number Date

1 IS/UGC01/PKG11/00001 31-May-18

2 IS/UGC01/PKG11/00002 9-Jul-18

3 IS/UGC01/PKG11/00003 26-Jul-18

4 IS/UGC01/PKG11/00004 30-Jul-18
5 IS/UGC01/PKG11/00005 1-Sep-18

6 IS/UGC01/PKG11/00006 10-Sep-18

7 IS/UGC01/PKG11/00007 10-Sep-18

8 IS/UGC01/PKG11/00008 20-Sep-18

9 IS/UGC01/PKG11/00009 20-Sep-18

10 IS/UGC01/PKG11/00010 1-Oct-18

11 IS/UGC01/PKG11/00011 29-Sep-18

IS/UGC01/PKG11/00011 (Rev 1 2-Nov-18

12 IS/UGC01/PKG11/00012 29-Sep-18
13 IS/UGC01/PKG11/00013 29-Sep-18

14 IS/UGC01/PKG11/00014 12-Sep-18

15 IS/UGC01/PKG11/00015 18-Sep-18

16 IS/UGC01/PKG11/00016 18-Sep-18

17 IS/UGC01/PKG11/00017 10-Sep-18

18 IS/UGC01/PKG11/00018 5-Oct-18

19 IS/UGC01/PKG11/00019 1-Oct-18

20 IS/UGC01/PKG11/00020 12-Oct-18

21 IS/UGC01/PKG11/00021 24-Oct-18

22 IS/UGC01/PKG11/00022 1-Nov-18

23 IS/UGC01/PKG11/00023 30-Nov-18

24 IS/UGC01/PKG11/00024 10-Dec-18

25 IS/UGC01/PKG11/00025 18-Dec-18
26 IS/UGC01/PKG11/00026 27-Dec-18

27 IS/UGC01/PKG11/00027 27-Dec-18

28 IS/UGC01/PKG11/00028 29-Dec-18

29 IS/UGC01/PKG11/00029 29-Dec-18

IS/UGC01/PKG11/00029-R01 25-Jan-19

IS/UGC01/PKG11/00029-R02 12-Feb-19
30 IS/UGC01/PKG11/00030 7-Jan-19
31 IS/UGC01/PKG11/00031 22-Jan-19

32 IS/UGC01/PKG11/00032 22-Jan-19

33 IS/UGC01/PKG11/00033 26-Jan-19

34 IS/UGC01/PKG11/00034 30-Jan-19
35 IS/UGC01/PKG11/00035 14-Feb-19

MOM Follow Up
Follow up from POS
S. NO. Dept. Discussion Point

1 POS Typical Bracket Drawing


POS
2 Feeder of ACDB

3 POS Transformer Capacity

4 POS and UGC-01 HT- side Earthing layout ASS room

Follow up from OCS


S. NO. Dept. Discussion Point
Overhead Catenary System
1 OCS

Tunnel cross section drawing with load


2 OCS details.

3 OCS No.of ROCS support considered


ace item number as per Meeting held on 14-Feb-2019
Action Action Date

We have to provide the exact chainage


requirements after finalaization of Depends on PSS
Simulation study by PSS.

We have to Provide the details by 1- 5-Mar-19


Mar-2019

We have to Provide the details by 1- 5-Mar-19


Mar-2019

We have to Provide the details by 1- 5-Mar-19


Mar-2019

We have to Provide the details by 1- 5-Mar-19


Mar-2019

We have to provide these details by end 5-Mar-19


of 2019

We have to Provide the details by 19- 25-Feb-19


Feb-2019
We have to Provide the details by 19-
Feb-2019 25-Feb-19

We have to provide the details by 1-Mar 25-Feb-19


2019.

We have to provide the details by 1- 1-Mar-19


Mar-2019

We have to provide the details of


connecting link terminal locations by 19- 1-Mar-19
Feb-2019

UGC-01 To OCS-11A (As on 20.Feb.2019)


Desciption Status Remarks
UGC01 shared Architectural and MEP Response to our ISF - OCS-
Preliminary Drawings for review and UGC01-ISF-0002-R00
comments.

UGC01 shared station electrical load for Response to our ISF - OCS-
UGC01-ISF-0002-R00
finalization of transformer sizing of all We replied by OCS-UGC01-ISF-
four station under them. 0016-R00

UGC01 requested information required


for development of Definitive and
combined service drawings.

UGC01 submitted the structural


earthing system drawings for one
station (SVB) for PST teams review and
confirmation.
UGC-01 requested some information
required for development of Definitive
and combined service drawings for
Cuffe Parede station - Coss over.

They requested us to varify ASS room


layout and to provide equipment foot We Responded by - OCS-
prints and equipment static and UGC01-ISF-0004-R00,OCS-
dynamic load of all three station UGC01-ISF-0005-R00, OCS-
Vidhyabhawan station, Church gate UGC01-ISF-0006-R00
station, and Hutatma Chowk station.

UGC01 shared SVB & SGC DD general


arrangement drawing as per our
requirment in technical rooms for
Vidhyabhawan station, Church gate
station. Also requested for structural
openings for cabel entries/exit in
station for UGC-01.

UCG01 requested us to confirm the


pipes/sleeves numbers and sizes as
shown in drawaings in Vidhyabhawan
station.

UGC01 shared CSD & SEM drawings for Response to our ISF - OCS-
cuffe Parade Station. Launching area- UGC01-ISF-0002-R00
GL, 20-24 for Cuffe parade station.

UGC01 shared NATM lining for NATM


tunnel before cuffe parade station and
requested our inputs.
UCG01 shared CSD &SEM drawings for Response to our ISF - OCS-
vidhan bhawan Base Slab. UGC01-ISF-0002-R00
UCG01 shared CSD &SEM drawings for Response to our ISF - OCS-
vidhan bhawan Base Slab. UGC01-ISF-0002-R00

UCG01 shared Temporary Equipment


Routing drawings for bringing all heavy
equipments from street level to
respective equipment location in the
station box for church gate station.
UCG01 shared Temporary Equipment
Routing drawings for bringing all heavy
equipments from street level to
respective equipment location in the
station box for Vidhan bhawan station.

UGC01 Shared ASS-1 and ASS -2


Equipment Layout for Church gate
Station.

UGC01 Shared ASS-1 and ASS -2


Equipment Layout for Hutatma Chowk
Station

UGC01 Shared ASS-1 and ASS -2


Equipment Layout for Cuffe Parade
Station

UGC01 Shared ASS-1 and ASS -2


Equipment Layout for Vidhya Bhawan
Station.
UGC01 Shared total power load of the Response to our ISF - OCS-
Vidhya bhawn Station. UGC01-ISF-0002-R00

UGC01 shared Undercroft level cabel


Tray layout of Vidhan Bhawan station.

UGC01 shared Undercroft level &


Platform level cabel Tray layout of
Church gate station and Hutatma
chowk station.

Response to our ISF - OCS-


UGC01 Shared total power load of the UGC01-ISF-0002-R00
Church gate & Hutatma Chowk station. We replied by OCS-UGC01-ISF-
0013-R00

UGC01 shared CSD & SEM drawings for Response to our ISF - OCS-
cuffe Parade Station NATM side (GL C12 UGC01-ISF-0002-R00
to C6)
UGC01 shared total electrical load the Response to our ISF - OCS-
cuffe parade station. UGC01-ISF-0002-R00

UGC-01 shared OTE Duct Design Details


and provided the locations of ROCS in
the station area for fixing of OTE in
SVB,SCG & SHC.

UCG-01 replied to our ISF (ISF-OCS- They Replied to our ISF - ISF-
UGC01-ISF-0011-R00) provided out OCS-UGC01-ISF-0011-R00
Urgent input requirments
UGC-01 shared Equipment delievery
routing drawings (CAD & PDF) for
bringing all heavy equipment from
street level to Respective locations for
Cuffe Parade station.

UGC-01 shared Equipment delievery


routing drawings (CAD & PDF) for
bringing all heavy equipment from
street level to Respective locations for
Hutatma chowk station.

UGC-01 shared Station ASS Room


Equipment Layout Drawings.

Discussed during technical


meeting held on 8-Jan-2019.
UGC-01 shared Fire protection Scheme Revised ISF no. R01 sent by
for Transformer in ASS-1 & ASS-2. UGC-01 on 25 -Jan 2019.
We repled by OCS-UGC01-ISF-
0015-R00

UGC-01 proposed trolley mounted 22.5


Kg carbon dioxide type fire extinguisher We repled by OCS-UGC01-ISF-
for transformer fire protection in ASS-1 0015-R00
& ASS-2 rooms.

UGC-1 Requested us to provide the Response to our ISF - OCS-


requirements as required for UGC01-ISF-0015-R00
Firefighting/Fire protection/Gas We replied by ISF - OCS-
suppression/Gas flooding system UGC01-ISF-0015-R01
including ASS room Fire rated door. Etc.
UGC-01 requested some design
information mentioned below-
1. Specify the cable routing and section
needed at the interface between Tunnel
and Stations.
2. Specify the size and space in the
Tunnel for
the HV and other associated cable
containments/brackets/trunking
/trench.
3. Specify the cable route (including all
details) in Tunnel for 33KV, 25KV,
traction return cable.
4. Specify the Structural openings for
cable
entries/exit in the stations/Tunnels.
5. Provide the location of cable
crossings
in the tunnel.
6. Provide the LV Power requirements of
OCS equipment in ASS room.
UGC-01 requested some design
information mentioned below-
1. Provide the Tunnel Rigid Catenary
System
fixing design details including locations
and loads.
2. Provide the details of height of
contact wire
and minimum electrical clearance.
3. Provide the requirements/details of
the
neutral section in order to
adjust/modify the vertical alignment of
the Tunnels at the neutral section
locations.
4. Provide fixing details of beam to
support rigid
overhead contact system for Tunnel
launching shaft area.
5. Provide the type of drop arm and its
base fixing
arrangement.
6. Provide the span of drop arms of
OHE.
7. Provide the details of obligatory drop
arm, if
any.
8. Provide the details of loading on
drop arm.
9. Provide the details of KM No./Drop
Arm No. of
drop arm locations.
10. Provide the details of earthing
(Tunnel
earth conductor (TEC) and associated
earthing)
11. Provide the details and location of
OHE
Structural earthing.

UGC-01 requested some design


information mentioned below-
1. Provide the station Rigid Catenary
System
fixing design details, including locations
and loads.
2. Provide the details of height of
contact
wire and minimum electrical clearance.

UGC-01shared SCP, SVB & SCG


Temporary openings details.
UGC-01 shared maximum demand of Response to ourISF (OCS-
MEP & other systems in SCP, SVB, SCG & UGC01-ISF-0016-R00) dated
SHC 28th Jan’19,
UGC-01 shared SOD which was issued
by the Engineer through letter GCC-
UGC01-LET-000815-A00
dated 28th Nov 2018

OM Follow Up
ow up from POS
Action Action Date
We have to share the Typical bracket 22-Jan
drawing.
POS have to share the SLD to UGC-01for 22-Jan
the reference and records.
We have received the Total load, UGC-
01 reuested to confirm the transformer 21-Jan
rating.

We requested separate MET with risers


for battery and battery charger will be
shared with LV system MET.
Rest separate riser with MET shall be
provided to transformer, neutral and HT
are acceptable to UGC-01.

ow up from OCS
Action Action Date

OCS will confirm the numbers of


hangers, penetration depth on OTE 8-Feb
duct.
POS have yo share the latest drawing. 22-Jan
We stated that no. of ROCS support
considered (For OTE ducts) based on
total station Box length divided by 7
Meters, and the exect location will be End March
shared after the design and GC
concurrence
OCS-UGC02 follow up sheet based on Interface item number as per 14-Feb-2019

Interface Item Number Discussion Point Action


S.no
Cable containments / UGC 02 was shared the CST Cable
trunking / brackets for HV & Containments DD Stage drawings to
other associated cable us.We have to review & comments on
1 T2.1- PS/UG-06(M) routing. 22.01.2019.

Requirements / details and We have to provide the exact chainage


2 T2.2- OH/UG-05 location of the Neutral requirements after finalaization of
Section Simulation study by PSS.

Design the Type of Drop Arm We have to Provide the details by 1-Mar-
3 T2.2- OH/UG-07 and shall fix in accordingly 2019

Design and furnish the span We have to Provide the details by 1-Mar-
4 T2.2- OH/UG-08 of Drop Arms of OHE. 2019

Obligatory drop arm to be We have to Provide the details by 1-Mar-


5 T7.2- OH/UG-09 furnished (if any) 2019

We have to Provide the details by 1-Mar-


6 T2.2- OH/UG-10 Loading on Drop Arm 2019

KM No. / Drop Arm No. of We have to provide these details by end


7 T2.2- OH/UG-11 drop arm location of 2019

Necessary details of earthing We have to Provide the details by 19-


8 T2.2- OH/UG-12(M) (Tunnel Earth Conductor (TEC) Feb-2019
and associated earthing).

Details of OHE Structure We have to Provide the details by 19-


9 T2.2- OH/UG-14(M) earthing including location. Feb-2019

Obligatory catenary / OCS We have to provide the details by 1-Mar


10 T2.3- OH/UG-05 locations. 2019.
Design and provide necessary We have to provide the details by 1-Mar
11 T2.3- OH/UG-06(M) details of earthing (Tunnel 2019.
Earth Conductor (TEC).

Details of connecting link We have to provide the details by 1-Mar


12 T2.3- OH/UG-07 terminal locations. 2019.

ISF Summary : From UGC-02 To OCS-11A (As on 20.Feb.2019)


Sl No ISF Number Date Desciption
1 ISF/UCG02/OCS/00001 To check
UCG02 shared definitive design drawings
2 ISF/UCG02/OCS/00002 9-Nov-18 Architectural drawings for CST (PDF
CADD)

UCG02 shared definitive design drawings


3 ISF/UCG02/OCS/00003 18-Nov-18 Architectural drawings for Grant road
station (PDF CADD)

UCG-02 shared the CRD-GFC Drawings-


4 ISF/UCG02/OCS/00004 26-Nov-18 Equipment Delievery route drawings for
CST stations(PDF and CSD)

UCG-02 shared the CRD-GFC Drawings-


5 ISF/UCG02/OCS/00005 26-Nov-18 Equipment Delievery route drawings for
Grant road station (PDF and CSD)

UCG02 shared definitive design drawings


6 ISF/UCG02/OCS/00006 20-Nov-18 SEM drawings for CST (PDF CAD)

UGC-02 Shared the total Electrieal Power


Load (signed off by GC experts) of CST,
7 ISF/UCG02/OCS/00007 14-Dec-18 Kalbadevi, Girgaon and Grant Road
Stations.

UGC-02 shared the alignment drawing


8 ISF/UCG02/OCS/00008 26-Dec-18 Rev 5.1
UGC-02 shared Revised SEM Drawings of
9 Email 10-Jan-19 CST Station.
UGC-02 Shared latest Architectural GAD
10 Email 12-Jan-19 Drawings for CST, Grant Road, Girgaon
and Kalbadevi stations
UGC-02 shared Tunnel Services (Space
Proofing Drawings) and Tunnel Segment
Drawings for T1 Drive(from CST to
Kalbadevi station), T2 Drive (from
11 Email 12-Feb-19 Kalbadevi to Girgaon station), T3 Drive
(Girgaon to Grant Road station) and T4
Drive (from Grant Road to Mumbai
Central stations)

UGC-02 shared Revised SEM –DD Stage


12 Email 18-Feb-19 drawings for CST Station

MOM Follow Up
Follow up from POS
S. NO. Dept. Discussion Point Action
Discussed and size of the pull pit has
been agreed. UGC 02 informed to
maintain a clearance of 700 mm from
the wall. POS team to check as per
1 POS Pull Pit Drawing comment of UGC 02.

UGC-02 and OCS contractor jointly


2 POS Hoisting Hook Drawing signed off. Final hook location to
shared by OCS.

3 POS Earthing Layout

Team have to share the ACDB & DCDB


Load in all ASS to UGC-02
4 POS ACDB and DCDB Load

Follow up from OCS


S. NO. Dept. Discussion Point Action
A. Architecture layout of CST, Grant
Road & Girgaon have been shared
during meeting.
B. Latest SEM drawing & OTE duct
1 OCS ROCS input requirement layout drawings of CST station have
been shared during meeting.
OCS team to respond.
The drawing has been discussed and
2 OCS Typical bracet drawing interfaced, the size of the bracket to be
finalized at later stage.
er 14-Feb-2019

Action Date

22-Jan-19

Depends on PSS

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19
1-Mar-19

1-Mar-19

20.Feb.2019)
Status Remarks

Reply to our ISF -


OCS-UGC02-ISF-
0002-R00

Reply to our ISF -


OCS-UGC02-ISF-
0002-R00

Reply to our ISF -


OCS-UGC02-ISF-
0002-R00
Action Date Remarks

All the pull pits


31-Jan-19 are made keeping
gap for drain
(300mm) and
retaining wall. No
infringement in
SOD.

15-Feb-19

Transformer
Neutral earthing
to be concluded

63 A for ACBD 3
phase supply. No
requirement for
DCDB 45283.14

Action Date Remarks


OCS-UGC03 follow up sheet based on Interface item number as per 14-Feb-2019
S.no Interface Item Number Discussion Point Action

We have to provide the exact


Requirements / details and chainage requirements after
1 T3.2- OH/UG-05 location of the Neutral Section finalaization of Simulation study by
PSS.

Design the Type of Drop Arm We have to Provide the details by 1-


2 T3.2- OH/UG-07 and shall fix in accordingly Mar-2019

Design and furnish the span of We have to Provide the details by 1-


3 T3.2- OH/UG-08 Drop Arms of OHE. Mar-2019

Obligatory drop arm to be We have to Provide the details by 1-


4 T3.2- OH/UG-09 furnished (if any) Mar-2019

We have to Provide the details by 1-


5 T3.2- OH/UG-10 Loading on Drop Arm Mar-2019

KM No. / Drop Arm No. of drop We have to provide these details by


6 T3.2- OH/UG-11 arm location end of 2019

Necessary details of earthing We have to Provide the details by 19-


7 T3.2- OH/UG-12(M) (Tunnel Earth Conductor (TEC) Feb-2019
and associated earthing).

Details of OHE Structure We have to Provide the details by 19-


8 T3.2- OH/UG-14(M) earthing including location. Feb-2019

Obligatory catenary / OCS We have to provide the details by 1-


9 T3.3- OH/UG-05 locations. Mar 2019.
Design and provide necessary We have to provide the details by 1-
10 T3.3- OH/UG-06(M) details of earthing (Tunnel Mar 2019.
Earth Conductor (TEC).

Details of connecting link We have to provide the details by 1-


11 T3.3- OH/UG-07 terminal locations. Mar 2019.

ISF Summary : From UGC-03 To OCS-11A (As on 20.Feb.2019)


Sl No Reference Date Desciption

UGC-03 shared Cncourse level key


1 Received on 8-Sep-18 plan and platform level key plan for
Science meuseum and station Worli.

2 Received on 21-Sep-18 UGC-03 shared Electrical load schedua

UGC-03 Shared Fire


3 Received on 22-Sep-18 compartmentation plan.
UGC-03 shared Temporary and
Permanent land pland, and
concourse level key plan, top of the
box level plan and some other PDF
4 Received on 24-Sep-18 and CAD drawings for Mumbai
central

UGC-03 shared Temporary and


Permanent land pland, and
concourse level key plan, top of the
box level plan and some other PDF
5 Received on 24-Sep-18 and CAD drawings For Mahalaxmi
station.

UGC-03 shared comments by their


6 Received on 16-Jan-19 DDC on Pull Pit drawings.
UGC-03 shared base slab drawing for
7 Received on 22-Jan-19 our clearance
8 Received on 22-Jan-19 UGC-03 shared SEM drawings.
UGC-03 shared Electrical load of all
9 Received on 20-Feb-19 station for transformer sizing

MOM Follow Up
Follow up from POS
S. NO. Dept. Discussion Point Action
OCS to provide technical details
required for short circuit
1 POS Transfomer Rating details calculation on secondary side.

UGC-03 Shared Latest


2 POS
Architectural Drawings Architectural Drawings of all
Shared station to OCS contractor. OCS to
Reply on drawings.
UGC-03 Proposed the Cable
bracket length as 600 mm for
3 POS
Cable tray in Undercroft both 33kV and 25kV, OCS
level contractor to respond on the
same.

Details of shaft have been shared


during the meeting to OCS
contractor by UGC 03. OCS to
4 POS Cable Shaft of SSM
confirm the size of shaft which
will carry cables from RSS to
Undercroft.
Team have to share the ACDB &
DCDB Load in all ASS to UGC-03
5 POS ACDB and DCDB Load
er 14-Feb-2019
Action Date

Depends on PSS

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19

1-Mar-19
1-Mar-19

1-Mar-19

Feb.2019)
Status Remarks

Reply on our ISF -


OCS-UGC03-ISF-
0002-R00

Reply on our ISF -


OCS-UGC03-ISF-
0002-R00

Response to our ISF


- OCS-UGC03-ISF-
0011-R02

Action Date Remarks


Details shared via
email dated Feb 1.

Related to OCS

Details shared via


email dated Feb 1.

Details shared via


email dated Feb 1.

63 A is required for
ACDB. No
requirement for
DCDB. Muthuvel sir
to share.
ISF Summary : From UGC-04 To OCS-11A (As on 20.Feb.201
Sl No ISF Number Date

1 UGC04-OCS-ISF-00001-R00 20-Sep-18

2 UGC04-OCS-ISF-00002-R00 26-Sep-18

3 UGC04-OCS-ISF-00003-R00 26-Sep-18

4 UGC04-OCS-ISF-00004-R00 26-Sep-18

5 UGC04-OCS-ISF-00005-R00 26-Sep-18

6 UGC04-OCS-ISF-00006-R00 To Check

7 UGC04-OCS-ISF-00007-R00 3-Oct-18

8 UGC04-OCS-ISF-00008-R00 3-Nov-18

9 UGC04-OCS-ISF-00009-R00 20-Nov-18

10 UGC04-OCS-ISF-00010-R00 24-Nov-18

11 UGC04-OCS-ISF-00011-R00 To Check
12 UGC04-OCS-ISF-00012-R00 4-Dec-18

13 UGC04-OCS-ISF-00013-R00 29-Jan-19

14 UGC04-OCS-ISF-00014-R00 29-Jan-19

MOM Follow Up
Follow up from POS
S. NO. Dept. Discussion Point

Transformer Loading
1 POS Details

Architectural layout
2 POS (Dadar)

3 POS ACDB DCDB Load

Follow up from OCS


S. NO. Dept. Discussion Point
ROCS Input design
1 OCS Requirments

2 OCS 33 kv cables, control


cables, TEC, OPC, ROCS
support(Tentative)

Tunnel segment
3 OCS drawing

4 OCS Tunnel CSD


mary : From UGC-04 To OCS-11A (As on 20.Feb.2019)
Desciption Status Remarks

They accepeted old IS. Information

UGC-04 shared BIM 3d Model, latest rivision of Reply to our ISF - OCS-
architechtural and structural drawings, and Electrical UGC04-ISF-0002-R00
load.

UGC-04 shared NATM drawings.

UGC-04 shared Tunnel section Drawings and Earthing


bonding drawing.

UGC-04 shared ASS Equipment layout and some other Reply to our ISF - OCS-
details. UGC04-ISF-0005-R00

UGC04 required confirmation from our side regarding the We Replied by ISF - OCS-
pull-pit UGC04-ISF-0010-R00

UGC04 required confirmation from our side regarding the We Replied by ISF - OCS-
pull-pit changes. UGC04-ISF-0010-R00

UGC04 required confirmation from our side regarding


ROCS length confirmation in station area.

UGC04 required confirmation from our side regarding We Replied by ISF - OCS-
ROCS length and anchoring in purpose. UGC04-ISF-0007-R00
UGC-04 shared drawings which are part of Definitive
Design submission for Siddhivinayak station.

UGC-04 shared Tunnel Segment drawing for dimple


Location identification.

UGC 04 will share revised


UGC-04 shared Dadar station ASS1 and ASS 2 Layout. arch layout again.

MOM Follow Up
Follow up from POS
Action Action Date Remarks
POS team has shared the transformer details comments
to Interface team, We have to forward to UGC-04 No action from POS

UGC-04 shared Architectural layout of Dadar station


during the meeting held on 29-01-2019 by ISF-14 POS Revised equipment layout
team to share the layout as per this rivision. shared by OCS to UGC04.
UGC04 informed again
change in arch layout.

We have to to share the ACDB & DCDB Load in ASS to 63 A is required for ACDB.
UGC-04 No requirement for DCDB.

Follow up from OCS


Action Action Date Remarks
UGC-04 has already shared the ROCS inputs, OCS team
to respond.
Typical Drawings will be discussed in the same Meeting.

UGC-04 shared the tunnel segment drawing in meeting


held on 29 Jan by ISF 15 OCS team to reply.

UGC-04 shared Tunnel CSD with us, we have to check and


confirm the requirment fulfilment.
ISF Summary : From UGC-05 To OCS-11A (As on 20.Feb.20
Sl No ISF Number Date Desciption

UGC05 shared Architectural (AR) PD


1 UGC05-OCS-ISF-0001-R00 15-Jun-18 (ACAD &PDF) drawings to us on 15 june
2018 in person.

MMRC splited the Tender in to Package


11A & 11B. Hence UGC05 needs the
clarity on split up of activities under
2 UGC05-OCS-ISF-0002-R00 20-Jul-18 UGC's Section VI. Appendix 19 Design &
Construction Interface management,
Indicative Interface sheet (IS) Serial No.
08 & 09.

UGC05 shared vorede Tunnel segment &


lining details Drawing Approved CRD
3 UGC05-OCS-ISF-0003-R00 23-Jul-18 (ACAD &PDF) Drawings to us on 23 july
2018

UGC-05 requested us to provide scope


4 UGC05-OCS-ISF-0004-R00 1-Sep-18 of work and update sheet.

UGC05 requested to provide our


preliminery design on their PD design
5 UGC05-OCS-ISF-0005-R00 1-Sep-18 information. They want us to Review on
their drawings.

UGC-05 shared Equipment delivery


6 UGC05-OCS-ISF-0006-R00 12-Sep-18 route layout drawings of Vidhyanagri
and dharavi.

UGC-05 shared interface management


7 UGC05-OCS-ISF-0007-R00 18-Sep-18 program to us in person.
UGC05 shared ASS1 & ASS2 Equipment
layout (CSD) with Trasformer lifting hook
8 UGC05-OCS-ISF-0008-R00 29-Sep-18 arrangement to us on the basis of
meeting on 11- sept-2018.

UGC05 have shared NATM drawings to


9 UGC05-OCS-ISF-0009-R00 12-Sep-18 us , They requested OCS input within 7
days.

UGC05 have shared E&M Equipment


10 UGC05-OCS-ISF-0010-R00 10-Oct-18 Electrical Load to us. They requested
OCS input within 7 days.

UCG05 have shared Final inner Dia of


11 UGC05-OCS-ISF-0011-R00 10-Oct-18 the Tunnel and E7M service details to
us.

UCG05 shared the Approed Interface


Management Plan & Program (IMP &
12 UGC05-OCS-ISF-0012-R00 23-Oct-18 IMPG) to us. They requested us to
provide the same ASAP.

UGC05 shared undercraft E&M service


of BKC station and requsted us to
13 UGC05-OCS-ISF-0013-R00 24-Oct-18 provide our undercrafe floor cabels
routing.

UGC5 shared Dharavi, BKC, Vidhyanagri


14 UGC05-OCS-ISF-0014-R00 6-Nov-18 stations Undercrafe Floor CSD to us.

UGC05 requested to provide our IMP of


15 UGC05-OCS-ISF-0015-R00 20-Nov-18 Preliminery & Definitive Design
Exchange informatioin provision dates.
UGC05 shared Equipment Delivery
Route layout drawings of BKC &
16 UGC05-OCS-ISF-0016-R00 20-Nov-18 Santacruz Metrstation to us. Requested
to review and provide observation in 7
days.

UGC05 shared undercraft E&M service


of Vidhyanagri station and requsted us
17 UGC05-OCS-ISF-0017-R00 20-Nov-18 to provide our undercrafe floor cabels
routing.

UGC05 shared Santacruz station


Undercrafe floor CSD to us and
18 UGC05-OCS-ISF-0018-R00 20-Nov-18 requested to provide observation in 7
days.

They are having some Issues in OHE


clearances. They want a possible
19 UGC05-OCS-ISF-0019-R00 25-Dec-18 solution with adjustment of bracket
length or locations.

UGC-05 shared ROCS Design information


20 UGC05-OCS-ISF-0020-R00 24-Dec-18 as per our ISF- OCS-UGC05-ISF-0011-R00

UGC-05 shared the track crossing sleeve


21 UGC05-OCS-ISF-0021-R00 10-Jan-19 and cable pull-pit detailed layout of
Vidhya nagri station

UGC-05 requested us to provide the


location of transformer lifting hook and
travelling Road map of transformer from
street level to ASS room throught
considered access route of MEP
22 UGC05-OCS-ISF-0022-R00 8-Feb-19 equipment lowering drawing details
provided to you for all the UGC-05
uderground stations through ISF UGC05-
OCS-ISF-0006-R00 Dt. 12-Sept-2019
&UGC05-OCS-ISF-0016-R00 Dt. 20-Nov-
2018.

UGC-05 shared PSD fixing details and


23 UGC05-OCS-ISF-0023-R00 8-Feb-19 OTE cutouot details to us.
MOM Follow Up
Follow up from POS
S. NO. Dept. Discussion Point Action

Follow up from OCS


S. NO. Dept. Discussion Point Action
UGC-05 contractor has provided
chainages wheredeeviation is occuring
1 OCS Tunnel clearance Issue in circular tunnel. OCS to Confirm
clearance
S-11A (As on 20.Feb.2019)
STATUS Remarks

Information

OCS-UGC05-ISF-0004-R00, OCS-UGC05-ISF- UGC05-OCS-ISF-0003-R00,


0006-R00 , OCS-UGC05-ISF-0007-R00 UGC05-OCS-ISF-0001-R00

Attachment missing in share point.


Reply to our Isf - OCS-UGC05-ISF-0003-R00

Reply to our Isf - OCS-UGC05-ISF-0003-R00

UGC05-OCS-ISF-0012-R00
Attachment missing in share point.

Attachment missing in share point.

Reply to our Isf - OCS-UGC05-ISF-0003-R00

Attachment missing in share point.

Response to our ISF - OCS-UGC05-ISF-0011-


R00

UGC05-MEP-SVN-1381-002 drawing
checked. Requriement are fulfilled. Similar
size pull pit are required on other side of the
platform.

Lifting hook details will be shared by Mar 8


by installation team. Interface team to follow
up. No requirement of submitting a road
map.
Action Date

Action Date

1-Feb-19
ISF Summary : From UGC-06 To OCS-11A (As on 20.Feb.
Sl No ISF Number Date

1 P06/OCS/ISF/0001/R00 9-Jun-18

2 P06/OCS/ISF/0002/R00 8-Aug-18

3 P06/OCS/ISF/0003/R00 8-Aug-18

4 P06/OCS/ISF/0004/R00 24-Aug-18

5 P06/OCS/ISF/0005/R00 25-Aug-18

6 P06/OCS/ISF/0006/R00 28-Aug-18

7 P06/OCS/ISF/0007A/R00 31-Aug-18

8 P06/OCS/ISF/0007B/R00 31-Aug-18

9 P06/OCS/ISF/0007C/R00 31-Aug-18

10 P06/OCS/ISF/0008/R00 11-Sep-18

11 P06/OCS/ISF/0009/R00 11-Sep-18
12 P06/OCS/ISF/0010/R00 (Hold) 11-Sep-18

13 P06/OCS/ISF/0011/R00 (Hold) 11-Sep-18

14 P06/OCS/ISF/0012A/R00 13-Sep-18

15 P06/OCS/ISF/0012B/R00 13-Sep-18

16 P06/OCS/ISF/0012C/R00 13-Sep-18

17 P06/OCS/ISF/0013/R00 14-Sep-18

18 P06/OCS/ISF/0014/R00(Hold) 14-Sep-18

19 P06/OCS/ISF/0015/R00(Hold) 15-Sep-18

20 P06/OCS/ISF/0016/R00(Not Releven 15-Sep-18

21 P06/OCS/ISF/0017/R00 17-Sep-18

22 P06/OCS/ISF/0018/R00 17-Sep-18

23 P06/OCS/ISF/0019/R00 20-Sep-18

24 P06/OCS/ISF/0020/R00 11-Jan-19

25 P06/OCS/ISF/0021/R00 15-Jan-19

26 P06/OCS/ISF/0022/R00 17-Jan-19

27 P06/OCS/ISF/0023/R00 24-Jan-19

28 P06/OCS/ISF/0024/R00 25-Jan-19

P06/OCS/ISF/0024/R01 30-Jan-19
P06/OCS/ISF/0024/R02 13-Feb-19

29 P06/OCS/ISF/0025/R00 28-Jan-19

30 P06/OCS/ISF/0026/R00 29-Jan-19

31 P06/OCS/ISF/0027/R00 29-Jan-19

32 P06/OCS/ISF/0028/R00 30-Jan-19

Email 16-Jan-19

Email 30-Jan-19

Email 7-Feb-19

Email 12-Feb-19

Email 12-Feb-19

33 P06/OCS/ISF/0029/R00 14-Feb-19

MOM Follow Up
Follow up from POS
S. NO. Dept Discussion Point

1 POS
UGC 06 latest
equipment layout.
2 POS Hoisting Hook drawing

3 POS
Typical Bracket
Drawing

4 POS Cable tray drawings


ummary : From UGC-06 To OCS-11A (As on 20.Feb.2019)
Desciption STATUS
UGC-06 shared Architectural (AR) & Structural (ST) (ACAD & PDF)
drawings to us on 30.May.2018 in person. UGC-06 requested us
to give their comments by 15.Jul.2018.

UGC 06 shared Temporary Equipment Lowering Cutout


(Transmittal, ACAD & PDF) drawings for SC1, SSR and SC2 stations Replied OCS-UGC06-ISF-0002-R00 ,
to us on 08 August 2018 and want us to share our requirments
and list of OCS equipments and their sizes and weight by 20-Aug- OCS-UGC06-ISF-0003-R00
18.

UGC 06 shared Approved Tunnel Segment Drawing (CRD)( ACAD,


PDF) for complete alignment to Alstom on 06 August 2018 in CD.

UGC06 received design state input from us and want to know


that these are the latest drawing to incorporate our requirments Shared OCS-UGC06-ISF-0005-R00
and also want to get cabel route section earthing layout and
equipment layout for some sections.

UGC06 said that Interfacing scope generated by us is not in line


with the scope defined in contract and wants the interfacing
scope to be separated & specific for OHE/OCS applicable for Reply to OCS-UGC06-ISF-0001-R00
them and duly signed off by GC/MAPPLE & Alstom. (Reply to
OCS-UGC06-ISF-0001-R00)

UGC06 shared Elctrical load details of Domestic station ,Sahar Received


road station and International Station.

UGC06 sent segregated Domestic Station (SC1)status 'C' from


GC/MPPLE - ASS rooms layout from the list of drawings sent to us We replied by OCS-UGC06-ISF-0005-
previously for our review and comments. Requested us to give R00
our comments by 10-sept-18.

We replied by OCS-UGC06-ISF-0005-
UGC06 sent segregated Sahar Road Station (SSR) status 'C' from R00
GC/MPPLE - ASS rooms layout from the list of drawings sent to us Sahar Road is signed off, as GC
previously for our review and comments. Requested us to give requested for some modification, Rest
our comments by 10-sept-18. drawings are pending for sign off.

UGC06 sent segregated International Station (SC2) status 'C' from Sahar Road is signed off, as GC
GC/MPPLE - ASS rooms layout from the list of drawings sent to us requested for some modification, Rest
previously for our review and comments. Requested us to give drawings are pending for sign off.
our comments by 10-sept-18.

UGC06 shared Electrical drawings (MEP-design calculation for


domestic station) with status 'C' to us.
UGC06 shared Electrical drawings (MEP-design calculation for
Sahar Road station) with status 'C' to us.
UGC06 shared Definitive Stage Architectural drawing of SC1 and Reply to our ISF OCS-UGC06-ISF-0004-
SC2 to us. R01
UGC06 shared Definitive Stage Architectural drawing of Sahar Reply to our ISF OCS-UGC06-ISF-0004-
Road to us. R01
UGC06 shared equipment routing layout (ACAD & PDF) of
Domestic Station (SC1) to us.
UGC06 shared equipment routing layout (ACAD & PDF) of Sahar
Road Station (SSR) to us.
UGC06 shared equipment routing layout (ACAD & PDF) of
International Station to us.

UGC06 shared Architectural drawings(BIM) of Domestic Station, Reply to our ISF OCS-UGC06-ISF-0004-
Sahar road station &International Station (SC2) to us. R01

UGC06 shared PD structural drawings (BIM) of Domestic station, Reply to our ISF OCS-UGC06-ISF-0004-
Sahar road station & international station to us. R01
UGC06 shared electrical drawings (MEP-Design for International
station to us.
UGC06 shared approved "status C" Interface Management Plan to Information
us
UGC06 shared Sahar Rod Station- E&M CSD Drawings(Undercroft
level)& International station - E&M CSD Drawings (undercroft
level) to us.
UGC06 Shared Construction program of Base slab (tentative) for
all 3 stations to us.
UGC-06 shared preliminary design submission of Tunnel E&M
drawings.
Response to our ISF OCS-UGC06-ISF-
UGC-06 shared our Urgent ROCS requirments. 0010-R00

Drawing to be updated as per revised


UGC-06 shared E&M DD stage drawings of SC1, SSR &SC2. equipment layout. Revised equipment
layout jointly signed off on Feb 25,
2019. The same needs to updated by
UGC 06.

UGC-06 shared E&M DD stage drawings of SC1, SSR &SC2.


UGC-06 shared CSD-Acad drawings (E&M –DD-stage) Status-B on Comments shared with Muthuvel Sir
15-Jan-2019 to Ocs SC1, SSR, SC2 via email dated Feb
The clearance from rail level to soffit of OTE Duct as 4880 mm(As
per GC) for all station of UGC-06.As per SOD the dimension from
rail level to soffit of OTE Duct as 4838 mm.

UGC-06 revised PSD layout. Based on revised drawing for


clearance from top of rail level to Soffit of OTE i.e. 4868 mm is
enclosed with the ISF, they requested us to review the drawing.
UGC-06 revised the clearance to 4880 mm for all UGC-06 Response to our ISF OCS-UGC06-ISF-
stations. 0016-R00
Casting schedual of SC1, SSR and SC2.

ASS room Layout for SC1, SSR and SC2. UGC-06 requested Alstom Hook locations to be marked by Mr.
Bhagwan Singh & Mr. Manish in latest
to Mark Hook location in Achitectural drawings. Architectural drawings.

1. Drawing for SSR signed off.


2. For SC1 under preparation.
Cable entry into the station box, (SC1, SC2, SSR) for 25 kV. 3. SC2 no 25 kV cable arrangement
required.

UGC-06 shared in CD. P06/OCS/ISF/0003/R00,


P06/OCS/ISF/0010/R01, P06/OCS/ISF/0011/R00,
P06/OCS/ISF/0017/R00, P06/OCS/ISF/0019/R00,
P06/OCS/ISF/0020/R00, P06/OCS/ISF/0021/R00,
P06/OCS/ISF/0022/R00, P06/OCS/ISF/0023/R00

UGC-06 shared OTE-Duct drawings for our review.


UGC-06 shared ACAD & .pdf drawings for ASS1 &
ASS2 and would like to have these hook locations marked in the Hook locations to be marked by Mr.
Bhagwan Singh & Mr. Manish in latest
Drawings-DD Stage ( Status C – enclosed) for all 3 stations by 06- Architectural drawings.
02-2019

UGC-06 shared Electrical Load Details PD Stage ( Status –C ) to us Response to our ISF OCS-UGC06-ISF-
on 28-08-2018. Electrical Load Details DD Stage (Advance copy ) 0013-R01
presently shared by writing on our ISF OCS-UGC06-ISF-0013-R01

UGC-06 shared all equpiment layouts and CCF, by writing on our Response to our ISF - OCS-UGC06-ISF-
ISF- OCS-UGC06-ISF-0015-R00 0015-R00
UGC-06 shared type of tripping and protection for SSR, by writing Response to our ISF OCS-UGC06-ISF-
on our ISF OCS-UGC06-ISF-0016-R00 0016-R00
UGC-06 shared type of tripping and protection for SSR,as a reply Response to our ISF OCS-UGC06-ISF-
to our ISF OCS-UGC06-ISF-0016-R00 0016-R00

MOM Follow Up
Follow up from POS
Action Action Date
UGC 06 had revised their Equipment layout drawing as per
meeting held on Oct 30, 2018 and received 'C' on their
architectural layout DD drawings and MEP PD drawings.
Latest equipment layout have been discussed with UGC 06 All equipment layouts have been
and they have agreed to accept the changes, after GC
provides 'C' status of PD drawings of OCS contractor. signed off on feb 25.
UGC-06 contractor has already shared the architectural
drawing with hook position marked on ACAD DD drawings.
POS team to judge the suitablity if the location of these Hoisting hook location to be provided
by Installation Manager/Engineer.
hooks are OK and is adviced to change/indicate as requried
by them
The bracket drawing has been discussed and interfaced.

Drawings revised and updated as per


We shared our typical cable arrangement and Sahar Road UGC drawings. Sahar road drawings
cable tray drawings, but UGC 06 adviced to review their CSD has been signed off on Feb 25, 2019.
DD drawings with status 'B'.
Remarks

P06/OCS/
ISF/0001/
R00

P06/OCS/
ISF/0001/
R00

P06/OCS/
ISF/0001/
R00
Satish sir to update
OCS-UGC07 follow up sheet based on Interface item number as per Meeting with GC 14
S.no Interface Item Number Discussion Point
Cable route inside the Ramp & entry to the
Ramp Zone for 33 kV, 25 kV & traction return
1 T7.1- PS/UG-04(N1) cables etc.

Request the type of tripping and protections


2 T7.1- PS/UG-14(M) required for MDB at ASS LV side

Locations of cable crossings in the station /


3 T7.1- PS/UG-14(N1) tunnel

LV power requirements of our equipment in


4 T7.1- PS/UG-14(N2) ASS rooms

Fixings to support Rigid Overhead Contact


5 T7.2- OH/UG-01(M) System

Fixing Design details for rigid catenary system


6 T7.2- OH/UG-02 for tunnel.

Height of contact wire and minimum


7 T7.2- OH/UG-03 electrical clearances needed.

Design the OHE according to the gradients


8 T7.2- OH/UG-04 and curves.

Requirements / details and location of the


9 T7.2- OH/UG-05 Neutral Section

Design all required fixings of beam to support


10 T7.2- OH/UG-06(A) Rigid Overhead Contact system for Tunnel
Launching area.
Design the Type of Drop Arm and shall fix in
11 T7.2- OH/UG-07 accordingly
Design and furnish the span of Drop Arms of
12 T7.2- OH/UG-08 OHE.

13 T7.2- OH/UG-09 Obligatory drop arm to be furnished (if any)

14 T7.2- OH/UG-10 Loading on Drop Arm


15 T7.2- OH/UG-11 KM No. / Drop Arm No. of drop arm location

Necessary details of earthing (Tunnel Earth


16 T7.2- OH/UG-12(M) Conductor (TEC) and associated earthing).

Details of OHE Structure earthing including


17 T7.2- OH/UG-14(M) location.

Drawings showing the locations, cable ducts


18 T7.3- OH/UG-04 and sizes of openings for passage of cables
including routings.

19 T7.3- OH/UG-05 Obligatory catenary / OCS locations.

20 T7.3- OH/UG-07 Details of connecting link terminal locations.

ISF Summary : From UGC-07 To OCS-11A (As on 14.Feb.2


Sl No ISF Number Date

1 UGC07-OCS-ISF-0002-R00 11-Sep-18

2 UGC07-OCS-ISF-0008-R00 11-Dec-18

3 UGC07-OCS-ISF-0009-R00 24-Dec-18

4 UGC07-OCS-ISF-0011-R00 28-Jan-19

5 UGC07-OCS-ISF-0013-R00 1-Feb-19

MOM Follow Up
Follow up from POS
S. NO. Dept Discussion Point
Equipment and earthing layout of all three
1 POS stations.

Pullpit drawings of MIDC, Seepz and Marol


2 POS naka

Cable routing of 25kV and 33kV at Ramp


3 POS area.

4 POS Station wise Electrical Load

5 POS Tunnel segment Drawings

Follow up from OCS


S. NO. Dept Discussion Point

ROCS typical arrangement Drawings for


1 OCS Bored tunnel.

2 OCS RAMP/FOCS Arrangement

3 OCS ROCS Typical arrangement at station.

4 OCS Tunnel segment Drawings


m number as per Meeting with GC 14-Feb-2019
Action Action Date
Technical discussion happened on 10-
Jan-2019 on the same topic, We have to
share the revised drawings by 6-Feb- 6-Feb-19
2019.

Interface team will raise ISF requesting


the type of tripping and protections 2-Feb-19
required to UGC-07 by 2-Feb-2019.

UGC-07 replied on 24.12.2018 to revise


the drawing, we have to revise and 5-Feb-19
share to UGC-07 by 5-Feb-2019

We have to share the LV load 2-Feb-19


requirement by 2-Feb-2019
UGC-07 Shared tunnel Segment and
lining drawings to us on 1-Feb-2019. We 4-Feb-19
have to respond on that.

We shared the basic details through


mail and UGC-07 responded back. We 6-Feb-19
have to resend the details as per the
Segment details.

We have to revise and share to UGC-07 12-Feb-19


by 12-Feb-2019

UGC-07 shared the aligment drawing


Rev.5 & 5.1 to us, we have to revise and 12-Feb-19
share to UGC-07 by 12-Feb-2019.

We have to provide the exact chainage


requirements after finalaization of Depends on PSS
Simulation study by PSS.

UGC-07 Shared tunnel Segment and


lining drawings to us on 1-Feb-2019. We 1-Mar-19
have to respond as per that.
We have to Provide the details by 1- 1-Mar-19
Mar-2019
We have to Provide the details by 1- 1-Mar-19
Mar-2019
We have to Provide the details by 1- 1-Mar-19
Mar-2019
We have to Provide the details by 1- 1-Mar-19
Mar-2019
We have to provide these details by end 1-Dec-19
of 2019

We have to Provide the details by 19- 19-Feb-19


Feb-2019

We have to Provide the details by 19- 19-Feb-19


Feb-2019

UGC-07 replied on our typical cable


crossing details on 24.12.2018 to revise 5-Feb-19
the drawing. We have to revise and
share to UGC-07 by 5-Feb-2019.

We have to provide the details by 1-Mar 1-Mar-19


2019.
We have to provide the details of
connecting link terminal locations by 19-Feb-19
19-Feb-2019

m UGC-07 To OCS-11A (As on 14.Feb.2019)


Interface Item Number Remarks
Desciption STATUS Reference

Received MIDC station BIM 3D model Received


and latest architectural drawing

Horizintal and Vertical alignment Rev


5.1 station SEEPZ to ramp till contract
boundary.

UGC-07 commented on OCS shared Replied to the


drawings "Typical dtails for track comment via email
crossing." dated Feb 22.

UGC-07 requested ROCS/FOCS


mouonting arrangement at Ramp area.

Response to our ISF -


UGC-07 shared Transformer load OCS-UGC07-ISF-
details. 0014-R00

MOM Follow Up
Follow up from POS
Action Action Date Remarks
We have received 'C' status on Shared the approved
equipment layout, same will be share layout along with DSR
with UGC-07. CCF can be signed off. in which 'C' status is
13-Feb-19 provided.

UGC-07 has replied on shared Pull pit Replied via email on


drawings,team has to review and reply 7-Feb-19 feb 22
on the same.
Discussion held on same point, team In progress. But
has to revise the drawings. temperorary
12-Feb-19 arrangement shared
via email on feb 22.

We recived Electrical load, We have to


confirm the Transformer rating to UGC- 7-Feb-19 Need to reply Saitsh sir
07
UGC-07 shared the Tunnel segment
drawings, team has to reply on that. No reply required to be
15-Feb-19 shared. We
acknowledge the
receipt of drawing.

Follow up from OCS


Action Action Date Remarks
OCS to provide the ROCS typical
arrangement Drawing for board tunnel. 13-Feb-19

ROCS/FOCS Arrangement Drawing


along with transition element along the 7-Feb-19
RAMP section will be shared by OCS
Contractor.
UGC-07 shared the station cross section
for MIDC and Sheepz, OCS team have to 13-Feb-19
Respond on that.

UGC-07 shared the Tunnel segment


drawings, team has to reply on that. 15-Feb-19
ISF Summary : From RST To OCS-11A (As on 20.Feb.2019)
Sl No ISF Number Date

1 ISF_RST-OCS-ISF-0001-R01 28-Dec-18

2 ISF_RST-OCS-ISF-0002-R01 28-Dec-18

3 ISF_RST-OCS-ISF-0003-R01 28-Dec-18
om RST To OCS-11A (As on 20.Feb.2019)
Desciption Remarks

RST contractor requested Details of gradient of


OCS to obtain smooth current collection

RST contractor requested OCS details incl material


properties of contact wire to design Pantograph
incl dimensions of collector strip

RST contractor requested Details of location,


configuration and length of neutral sections
ISF Summary : From PSS To OCS-11A (As on 20.Feb.2019)
Sl No ISF Number Date

1 PSS-OCS-ISF-0001-R00 8-Aug-18

2 PSS-OCS-ISF-0002-R00 24-Oct-18

3 PSS-OCS-ISF-0003-R00 13-Dec-18

PSS-OCS-ISF-0004-R00 (Old)
4 31-Dec-18
(Received on 02.01.2019)

PSS-OCS-ISF-0004-R00 2-Jan-19

5 PSS-OCS-ISF-0005-R00 18-Jan-19

6 PSS-OCS-ISF-0006-R00 21-Jan-19

7 PSS-OCS-ISF-0007-R00 21-Jan-19

8 PSS-OCS-ISF-0008-R00 31-Jan-19
9 PSS-OCS-ISF-0009-R00 31-Jan-19

10 PSS-OCS-ISF-0010-R00 7-Feb-19
y : From PSS To OCS-11A (As on 20.Feb.2019)
Desciption Remarks
They shared the input data Requirements for
RSS/FP/SP/SSP etc

They shared max Demand of eacg ASS and


Dmand Calculations indicating the total
connected load. Transformer Sizing calculations
also.

They requested length of cable for aarey,


Dharavi and science museum locations as per
requirments.

PSS Contractor shared Copy of Equipment


layout submitted to GC for SSPs at CST Metro,
BKC, Sahar Raod and Achayara Atre Chowk
stations; SPs at Waroli and CSIA Domestic
Stations; FP at science museum and dharavi
stations.(With PDF files.)

PSS Contractor shared Copy of Equipment


layout submitted to GC for SSPs at CST Metro,
BKC, Sahar Raod and Achayara Atre Chowk
stations; SPs at Waroli and CSIA Domestic
Stations; FP at science museum and dharavi
stations.(With CAD files.)

PSS contractor Shared 25 KV SLD with us.

PSS contractor Shared -


1.Overall SLD for Dharavi and Science Museum
RSS
2.Overall Equipment layout for Dharavi and
Science Museum RSS
3.Cable Trench Layout inside and outside RSS
for Dharavi & Science museum

PSS contrator shared IO List for ASS equiments,


and asked us to confirm that all ASS equipments
such as 33kV GIS,ACDB,DCDB etc shall have
provision for sufficient potential free contacts
for remote monitoring (RTU) as per IO list.

1. Earthing & bonding (E&B) plan and return


current conduction concepts
2. 33kV Cable network Cable data (e. g.
electrical cross sections, material of conductors,
anatomy of cable shields, earthing
details), distances between conductors of
power supply and TEL/SIG etc
PSS contractor shared traction sectioning
diagram (GPDS) for our reference and checking
our requirments.

PSS contractor requested some inputes to


finalize cable lying for 33 kV cable ASS to ASS
and RSS to ASS
ISF Summary : From DPT DDC To OCS-11A (As on 20.feb.2019)
Sl No Reference Date

1 Mail Received on 16-Oct-18

2 Mail Received on 17-Nov-18

3 Mail Received on 27-Dec-18

4 Mail Received on 27-Dec-18

5 Mail Received on 27-Dec-18

6 Mail Received on 27-Dec-18

7 Mail Received on 27-Dec-18

8 Mail Received on 28-Dec-18

9 Mail Received on 3-Jan-19

10 Mail Received on 3-Jan-19

11 Mail Received on 3-Jan-19

12 Mail Received on 14-Jan-19

13 Mail Received on 21-Jan-19


DDC To OCS-11A (As on 20.feb.2019)
Desciption Remarks

Depot Shared ASS-2 & Compressor room ground floor


plan, Maintenance wrokshop & central store Building
ground floor plan, First floor plan, Terrace floor part
plan A, Roof plan Part plan A and some other
drawings.

Depo shared Depot Revised SSP Location.


Depot Shared The Autocad Drawings for Auto wash
plant, Dpot as we requested in meeting held on 27
dec.
Depot Shared Master plan R-A
Depot shared Architectural drawing for stabling Shed-
1
Depot shared Architectural drawing for stabling Shed-
2
Depot shared GAD drawings for Underpass.
Depot shared some missing Architectural drawing for
stabling Shed-2
Depot shared CAD and PDF drawings for AAREY
station building.
Depot shared PFA Stabling Shed - 2 drawings.

Depot shared CAD and PDF drawings of covered shed


stabling lines (20 lines) Zone-2 in Aarey Depot.

GC shared Aarey station building OCS requirments:


1.Architectural GA of Platform Level
2.Structural GA of Platform Level [Aarey Station
OCS.dwg]
3.Architectural GA of Concourse Level
4.Structural GA of Concourse Level [Aarey Station
OCS.dwg]
5. Section FF'(Cross section with portal frame)[Aarey
Station OCS.dwg]
6.Section BB'(Typical Cross Section)[Aarey Station
OCS.dwg]
7.Section EE'(Longitudinal section)[Aarey Station
OCS.dwg]
Requested us to provide clearance.

GC shared Aarey station OCS arrangement Developed


by GC
ISF Summary : From STPT To OCS-11A (As on 20.Feb.2019)
Sl No ISF Number Date Description
STPT confirms that Axle Counters will be used in
1 STPT-OCS-ISF-0001-R00 15-Feb-19 Mumbai Metro Line 3
019)
Remarks