You are on page 1of 1

Outstanding by DPM End

Days
Ref No. Description Date Passed Status
Shop Drawings
SMS-ELE-SPD-0002-03 L-2 Power 19-Jun-23 144
SMS-ELE-SPD-0024-02 Busway BB-SS3-01A 1600A & 18-Oct-23 23
SMS-ELE-SPD-0027-02 Busway BB-SS1-02 2500A & 1250A 14-Oct-23 27
SMS-ELE-SPD-0028-02 Busway BB-SS3-02 1600A 26-Oct-23 15
SMS-ELE-SPD-0034-03 L-3 Containment 18-Sep-23 53
SMS-ELE-SPD-0043-02 Blow up Electrical Room Plans 20-Jan-23 294 Received
SMS-ELE-SPD-0064-00 LFS-RS-1 Electrical Layout 9-Sep-23 62
SMS-ELE-SPD-0065-00 LFS-RS-2 Electrical Layout 9-Sep-23 62
SMS-ELE-SPD-0066-00 LFS-RS-6 Electrical Layout 9-Sep-23 62
SMS-ELE-SPD-0067-00 LFS-RS-3 Electrical Layout 10-Sep-23 61
SMS-ELE-SPD-0068-00 LFS-RS-4 Electrical Layout 10-Sep-23 61
SMS-ELE-SPD-0069-00 LFS-RS-5 Electrical Layout 10-Sep-23 61
SMS-ELE-SPD-0070-00 LFS-RS-7 Electrical Layout 10-Sep-23 61
SMS-ELE-SPD-0071-00 LFS-RS-8 Electrical Layout 13-Sep-23 58
SMS-ELE-SPD-0072-00 LFS-Street Ceilling lighting layput 10-Oct-23 31

(RFI) Request For Information

Electrification drawings of Lahore food street as per the


SMS-ELE-RFI-0011-00 14-Dec-22 331 Received
updated architectural layout are required for light point
wiring,digital signage points and material estimation

FOH spiritual and ablution area lighting layout in ACTLD


package for GL, L1, L2 and L3 is not updated as per the
SMS-ELE-RFI-0017-00 latest architectural layout. The lights are not matching 3-Jan-23 311 Received
the latest architectural layout and require
rearrangement. Kindly share updated lighting layout so
that point wiring shop drawings can also be updated.

Lighting design for Lahore food street elevations is not


avaiable in the shared reised Lahore food street drawings
SMS-ELE-RFI-0027-00 package.As per the tender elevaion drawings for Lahore 25-Jan-23 289 eleken@eleken.com
food street area.there are decorative lights in the
elevation windows. The revised design for these is
missing in the revised Lahore food street package.Kindly
share the updated lighting layout for firm working.
Rating for 110v DC battery chargers for all three
substations are not given in tender package.Kindly share
SMS-ELE-RFI-0033-00 1-Mar-23 254 eleken@eleken.com
information so that technical submittal for the same can
be submitted for approval.

Final electrical layout of Server room, Security Server


SMS-ELE-RFI-0034-00 22-May-23 172
room and security control room (including equipment
layout)is required to execute the work accordingly
As per the revised load schedule for Landlord SMDBs
received via email dated15 July 2023,the feeding
SMS-ELE-RFI-0036-00 3-Aug-23 99
information for Escalators and Travelators in
missing.Kundly provide updated feeding information for
As per the architechtural package of signages, there are
exterior totems and parking gates marked in the external
SMS-ELE-RFI-0037-00 16-Aug-23 86
area of the mall.There is no electrical provision for these
in electrical IFC drawings for these signages so that they

SDD (Schematic Design Drawing)


SMS-ELE-SDD-0009-00 USMDB Shop Drawings 31-Oct-23 10 (Courier)Mr.Waqas KHI
SMS-ELE-SDD-0004(Part-2)-04 SMDB-LL Shop Drawings 8-Nov-23 2 (Courier)Mr.Waqas KHI

Method Statement (MSS)


SMS-ELE-MSS-0009-00 Installation of SMDBs 4-Nov-23 6

Work Inspection Request(WIR)


Cable laying and termination for
SMS-ELE-WIR-0029-00 3-Apr-23 221
L1 lift connectional L2
SMS-ELE-WIR-0037-01 Installation of Cable Tray 24-Aug-23 78
SMS-ELE-WIR-0086-00 point wiring laying 5-Sep-23 66
SMS-ELE-WIR-0087-00 point wiring laying 5-Sep-23 66
SMS-ELE-WIR-0089-00 point wiring laying 5-Sep-23 66
SMS-ELE-WIR-0091-00 point wiring laying 5-Sep-23 66
SMS-ELE-WIR-0103-00 point wiring laying 19-Sep-23 52
SMS-ELE-WIR-0104-00 point wiring laying 19-Sep-23 52
SMS-ELE-WIR-0106-00 point wiring laying 6-Oct-23 35
SMS-ELE-WIR-0109-00 Installation of Cable Tray 19-Oct-23 22
SMS-ELE-WIR-0110-00 Laying of cable 19-Oct-23 22
SMS-ELE-WIR-0111-00 Cable tray 23-Oct-23 18
SMS-ELE-WIR-0113-00 Laying of cable(L-2, Zone 2,3,6 LV Cable) 4-Nov-23 6
SMS-ELE-WIR-0115-00 Installation of Cable Tray (GF Zone 4,5&6) 8-Nov-23 2
SMS-ELE-WIR-0116-00 Laying of cable (L-1 Zone 5&6) 8-Nov-23 2
SMS-ELE-WIR-0117-00 Laying of cable (L-1 Zone 2&3) 8-Nov-23 2

MIRs(Material Inspection Request)


SMS-ELE-MIR-0085-00 Cable tray & Accessories 5-Oct-23 36
SMS-ELE-MIR-0087-00 Distribution Board 16-Oct-23 25
SMS-ELE-MIR-0089-00 Isolators/Switch Disconnectors 16-Oct-23 25
SMS-ELE-MIR-0090-00 Earthing & Lighting Protection Material 17-Oct-23 24
SMS-ELE-MIR-0092-00 Cable tray 24-Oct-23 17
SMS-ELE-MIR-0093-00 Cable tray 27-Oct-23 14
SMS-ELE-MIR-0094-00 LV Switchgare SMDBs 28-Oct-23 13
SMS-ELE-MIR-0095-00 Cable tray 6-Nov-23 4
SMS-ELE-MIR-0096-00 Cable tray 8-Nov-23 2

Material Submittal
SMS-ELE-MSB-0029-03 Earth Braid 8-Nov-23 2

Site Instruction (SIN)

Referance to the drawings for the tolet area @3rd


DPM-MEP-SIN-43-00 28-Feb-23 255
Level,Zone-4 M/S Siemens provide the hand dryer power
provisions as per attached drawings

Area Clearance Work Inspection Request(WIR)


SMS-ELE-WIR-0001-00 Area clearance Inspection of BTD installation 4-Sep-23 67