Activit Activity Name DISCIPLINERemaining Duration Start Finish Method Statement status date of submit ITP Submittal status

ELECTRICAL Energy Center 2


UNDERGROUND
Lay Electrical Containments (Underground) E 16 29-Mar-23 26-Apr-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0013-01 Code=B
1ST & 2ND FIX
Electrical 1st & 2nd fix - Electrical Containments E 16 11-Jul-23 29-Jul-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0013-01 Code=B
Electrical 1st & 2nd fix - Cable Pulling SWG to Generators E 16 30-Jul-23 16-Aug-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0001-00 Code=B
Electrical 1st & 2nd fix - Low current systems E 16 30-Jul-23 16-Aug-23 UNDER REVIEW KAIG3-ITP-GN-LC-0002-01 Code=B
Electrical 1st & 2nd fix - Cable Pulling SWG to Boilers E 16 17-Aug-23 4-Sep-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0001-00 Code=B
Electrical 1st & 2nd fix- Fire Detection & Alarm System E 16 17-Aug-23 4-Sep-23 KAIG3-MS-GN-LC-0001-01 Code=B KAIG3-ITP-GN-LC-0001-00 Code=B
KAIG3-ITP-GN-E-0011-00
E 16 KAIG3-MS-GN-E-0013-00 Code=B KAIG3-ITP-GN-E-0012-00
Code=B
Electrical 1st & 2nd fix - Lighting points, controls and switches 5-Sep-23 24-Sep-23
Electrical 1st & 2nd fix - Cable Pulling SWG to Heat Exchanger E 16 5-Sep-23 24-Sep-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0001-00 Code=B
Electrical 1st & 2nd fix - Cable Pulling SWG to Ice Storage Tank E 16 25-Sep-23 12-Oct-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0001-00 Code=B
Electrical 1st & 2nd fix - Cable Pulling SWG to Chillers E 16 14-Oct-23 31-Oct-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0001-00 Code=B
Electrical 1st & 2nd fix - Cable Pulling SWG to Chillers Pumps E 16 1-Nov-23 19-Nov-23 KAIG3-MS-GN-E-0006-00 Code=B KAIG3-ITP-GN-E-0001-00 Code=B
FINAL FIX & EQUIPMENT
MEP Equipment - Electrical LV panels installation E 16 30-Jul-23 16-Aug-23 KAIG3-MS-GN-E-0008-00 Code=B KAIG3-ITP-GN-E-0004-00 Code=B
MEP Final Fix - Low current systems E 16 26-Sep-23 14-Oct-23 UNDER REVIEW 1/3/2023 KAIG3-ITP-GN-LC-0002-01 Code=B
MEP Final Fix - Small power outlets and points E 16 15-Oct-23 1-Nov-23 KAIG3-MS-GN-LC-0009-00 Code=B NO ITP

E 16 kAIG3-MS-GN-E-0006-00 SUPERSEADED it change to LV KAIG3-ITP-GN-E-0001-00 SUPERSEADED


and MV Cable
MEP Equipment - Electrical Bus bar 2-Nov-23 20-Nov-23
LV Switchboards, Transformers & Feeders E 16 21-Nov-23 9-Dec-23 KAIG3-MS-GN-LC-0016-00 Code=B KAIG3-ITP-GN-E-0016-00 Code=B
MEP Equipment - Electrical Central Battery System E 16 10-Dec-23 27-Dec-23 KAIG3-MS-GN-LC-0012-00 Code=B KAIG3-ITP-GN-E-0005-00 Code=B
MEP Final Fix - Fire Detection & Alarm System E 16 28-Dec-23 15-Jan-24 KAIG3-MS-GN-LC-0001-01 Code=B KAIG3-ITP-GN-LC-0001-00 Code=B
SWITCHBOARDS
MV Switchboards & Feeders SET 1 E 16 12-Sep-23 1-Oct-23 KAIG3-MS-GN-LC-0015-00 Code=B KAIG3-ITP-GN-E-0004-00 Code=B
MV Switchboards & Feeders SET 2 E 16 3-Oct-23 21-Oct-23 KAIG3-MS-GN-LC-0015-00 Code=B KAIG3-ITP-GN-E-0004-00 Code=B
MV Switchboards & Feeders SET 3 E 16 23-Oct-23 9-Nov-23 KAIG3-MS-GN-LC-0015-00 Code=B KAIG3-ITP-GN-E-0004-00 Code=B
Cable Termination & Testing(LOW VOLATAGE) 20-Nov-23 7-Dec-23 kAIG3-MS-GN-E-0006-00 Code=B 1/2/2023 KAIG3-ITP-GN-E-0001-00 Code=B
Cable Installation,Termination & Testing(LOW CURRENT) UNDER REVIEW KAIG3-ITP-GN-LC-0003-00 Code=B
Cable Termination & Testing(Medium VOLATAGE) NO MS KAIG3-ITP-GN-E-0014-00 Code=B
GENERATOR SETS
Generator test & Inspections E 6 17-Aug-23 23-Aug-23 NO MS 10/2/2023 NO ITP
Generator & connections SET 1 E 16 24-Aug-23 11-Sep-23 KAIG3-MS-GN-LC-0007-00 Code=B KAIG3-ITP-GN-E-0009-00 Code=B
Generators & connections SET 2 E 16 12-Sep-23 1-Oct-23 KAIG3-MS-GN-LC-0007-00 Code=B KAIG3-ITP-GN-E-0009-00 Code=B
Generators & connections SET 3 E 16 2-Oct-23 19-Oct-23 KAIG3-MS-GN-LC-0007-00 Code=B KAIG3-ITP-GN-E-0009-00 Code=B
Generators & connections SET 4 E 16 21-Oct-23 7-Nov-23 KAIG3-MS-GN-LC-0007-00 Code=B KAIG3-ITP-GN-E-0009-00 Code=B
Generators & connections SET 5 E 16 23-Oct-23 9-Nov-23 KAIG3-MS-GN-LC-0007-00 Code=B KAIG3-ITP-GN-E-0009-00 Code=B
Generators & connections SET 6 E 16 11-Nov-23 28-Nov-23 KAIG3-MS-GN-LC-0007-00 Code=B KAIG3-ITP-GN-E-0009-00 Code=B
Generator control boards for crescent 1 & 2 E 16 29-Nov-23 17-Dec-23 NO MS 10/2/2023 KAIG3-ITP-GN-E-0009-00 Code=B
Generators pre start up connections & tests E 8 18-Dec-23 26-Dec-23 NO MS 10/2/2023 NO ITP
TOILETS
PIPELAYING
Fix drainage pipes M 16 14-Aug-23 31-Aug-23
Fix potable water pipes M 16 2-Sep-23 19-Sep-23
CONTAINMENTS
Fix Electrical Containments E 16 20-Sep-23 9-Oct-23
PLASTER & SCREED
Screed A 10 10-Oct-23 21-Oct-23
Plaster walls A 16 22-Oct-23 8-Nov-23
WATERPROOFING
Apply waterproofing C 10 9-Nov-23 20-Nov-23
Leak test C 6 21-Nov-23 27-Nov-23
FLOORING
Lay floor tiles A 16 17-Dec-23 3-Jan-24
SPECIALITIES
Install Countertops A 16 4-Jan-24 22-Jan-24
Build cabinets A 16 4-Jan-24 22-Jan-24
WALL FINISHES
Fix Wall tiles A 16 28-Nov-23 16-Dec-23
FINAL FIX & EQUIPMENT
Fix plumbing & sanitary wares M 16 23-Jan-24 10-Feb-24
ACCESSORIES
Install Toilet Accessories A 16 11-Feb-24 29-Feb-24
PERIMETER WALL
Build footing & Columns (Access) C 16 29-Dec-22 16-Jan-23
WESTERN AREA
QC hod points C 4 22-Oct-22 25-Oct-22
Backfilling C 10 26-Oct-22 6-Nov-22
External blockwork - Layout A 3 9-Nov-22 12-Nov-22
External blockwork - QC hold points A 3 13-Nov-22 15-Nov-22
External blockwork - Lay blocks Part 1 A 10 16-Nov-22 27-Nov-22
External blockwork - Lay blocks Part 2 A 10 28-Nov-22 8-Dec-22
External blockwork - Lay blocks Part 3 A 10 10-Dec-22 20-Dec-22
External blockwork - QC hold points on Interfaces A 3 21-Dec-22 24-Dec-22
External blockwork - Interfaces, etc. A 4 25-Dec-22 28-Dec-22
Apply waterproofing to foundations C 10 29-Dec-22 9-Jan-23
Cement Plaster - Layout A 3 10-Jan-23 12-Jan-23
Cement Plaster - QC hold points A 3 14-Jan-23 16-Jan-23
External blockwork - Lay blocks Part 4 A 10 17-Jan-23 28-Jan-23
Cement Plaster - Plaster walls Part 1 A 10 17-Jan-23 28-Jan-23
Cement Plaster - Plaster walls Part 2 A 10 29-Jan-23 8-Feb-23
EASTERN AREA
QC hod points C 4 28-Nov-22 1-Dec-22
Backfilling C 10 3-Dec-22 13-Dec-22
External blockwork - Layout A 3 17-Dec-22 19-Dec-22
External blockwork - QC hold points A 3 20-Dec-22 22-Dec-22
External blockwork - Lay blocks Part 1 A 10 24-Dec-22 3-Jan-23
External blockwork - Lay blocks Part 2 A 10 4-Jan-23 15-Jan-23
External blockwork - Lay blocks Part 3 A 10 16-Jan-23 26-Jan-23
External blockwork - QC hold points on Interfaces A 3 28-Jan-23 30-Jan-23
External blockwork - Interfaces, etc. A 4 31-Jan-23 4-Feb-23
External blockwork - Lay blocks Part 4 A 10 5-Feb-23 15-Feb-23
Apply waterproofing to foundations C 10 16-Feb-23 28-Feb-23
Cement Plaster - Layout A 3 1-Mar-23 4-Mar-23
Cement Plaster - QC hold points A 3 5-Mar-23 7-Mar-23
Cement Plaster - Plaster walls Part 1 A 10 8-Mar-23 19-Mar-23
Cement Plaster - Plaster walls Part 2 A 10 20-Mar-23 3-Apr-23
SOUTH & NORTH AREA
QC hod points C 4 4-Jan-23 8-Jan-23
Backfilling C 10 9-Jan-23 19-Jan-23
External blockwork - Layout A 3 23-Jan-23 25-Jan-23
External blockwork - QC hold points A 3 26-Jan-23 29-Jan-23
External blockwork - Lay blocks Part 1 A 10 30-Jan-23 9-Feb-23
External blockwork - Lay blocks Part 2 A 10 11-Feb-23 21-Feb-23
External blockwork - Lay blocks Part 3 A 10 23-Feb-23 6-Mar-23
External blockwork - QC hold points on Interfaces A 3 7-Mar-23 9-Mar-23
External blockwork - Interfaces, etc. A 4 11-Mar-23 14-Mar-23
External blockwork - Lay blocks Part 4 A 10 15-Mar-23 27-Mar-23
Apply waterproofing to foundations C 10 16-Mar-23 29-Mar-23
Cement Plaster - Layout A 3 29-Mar-23 3-Apr-23
Cement Plaster - QC hold points A 3 29-Mar-23 3-Apr-23
Cement Plaster - Plaster walls Part 1 A 10 3-Apr-23 18-Apr-23
Cement Plaster - Plaster walls Part 2 A 10 6-Apr-23 25-Apr-23
REMAINING ACCESS
QC hod points C 4 9-Jan-23 12-Jan-23
Backfilling C 10 14-Jan-23 24-Jan-23
External blockwork - Layout A 3 28-Jan-23 30-Jan-23
External blockwork - QC hold points A 3 31-Jan-23 2-Feb-23
External blockwork - Lay blocks Part 1 A 10 4-Feb-23 14-Feb-23
External blockwork - Lay blocks Part 2 A 10 15-Feb-23 27-Feb-23
External blockwork - Lay blocks Part 3 A 10 28-Feb-23 11-Mar-23
External blockwork - QC hold points on Interfaces A 3 12-Mar-23 14-Mar-23
External blockwork - Interfaces, etc. A 4 15-Mar-23 19-Mar-23
External blockwork - Lay blocks Part 4 A 10 20-Mar-23 3-Apr-23
Apply waterproofing to foundations C 10 21-Mar-23 4-Apr-23
Cement Plaster - Layout A 3 4-Apr-23 9-Apr-23
Cement Plaster - QC hold points A 3 4-Apr-23 9-Apr-23
Cement Plaster - Plaster walls Part 1 A 10 9-Apr-23 27-Apr-23
Cement Plaster - Plaster walls Part 2 A 10 12-Apr-23 30-Apr-23