PROJECT
Project Plan
Development of Gitagum Potable
Water System - JAVESCO Project
Author: MARK ROGER R. HUBERIT II
Creation Date: 4/13/18
Last Revised: 4/13/18
Version: 0
0
TABLE OF CONTENTS
INTRODUCTION........................................................................................................................................................................2
PURPOSE OF PLAN.......................................................................................................................................................................2
BACKGROUND INFORMATION/AVAILABLE ALTERNATIVES...................................................................................................... 2
PROJECT APPROACH......................................................................................................................................................... 16
PHASE 1: NEW WATER DISTRIBUTION NETWORK ............................................................................................................. 17
PHASE 2: EXPANSION OF SERVICE COVERAGE.................................................................................................................. 20
PHASE 3: SEPTAGE MANAGEMENT PROGRAM................................................................................................................... 21
GOALS AND OBJECTIVES..................................................................................................................................................24
BUSINESS GOALS AND OBJECTIVES (BUSINESS OPERATION)............................................................................................24
PROJECT GOALS AND OBJECTIVES (PROJECT IMPLEMENTATION).....................................................................................24
SCOPE.......................................................................................................................................................................................25
SCOPE DEFINITION............................................................................................................................................................ 25
PROJECT BUDGET................................................................................................................................................................27
RISK ASSESSMENT............................................................................................................................................................ 28
INITIAL PROJECT RISK ASSESSMENT.........................................................................................................................................29
MILESTONES...................................................................................................................................................................... 32
ASSUMPTIONS........................................................................................................................................................................33
PROJECT ASSUMPTIONS.................................................................................................................................................... 33
CONSTRAINTS........................................................................................................................................................................34
PROJECT CONSTRAINTS.................................................................................................................................................... 34
RELATED PROJECTS.......................................................................................................................................................... 34
CRITICAL PROJECT BARRIERS........................................................................................................................................... 34
PROJECT MANAGEMENT APPROACH............................................................................................................................35
PROJECT TIMELINE............................................................................................................................................................ 35
PROJECT ROLES AND RESPONSIBILITIES........................................................................................................................... 35
ISSUE MANAGEMENT......................................................................................................................................................... 37
COMMUNICATIONS PLAN.................................................................................................................................................... 38
ATTACHMENTS/APPENDICES............................................................................................................................................40
APPROVALS.............................................................................................................................................................................41
Sign-off Sheet............................................................................................................................................................................41
1
INTRODUCTION
Purpose of Plan
The Development of Gitagum Potable Water System JAVESCO Project Plan will
provide an improved and efficient water system for Gitagum, Misamis Oriental.
As the water system shall be more responsive to the needs of the growing
population, it shall also complement the initiatives of the City Government
making it a strong driving force for growth. Additionally, the Plan will serve as an
agreement between the following JAVESCO Project Management Team and
Project Task Force Team of Gitagum Local Government Unit
Project Overview
Business and project goals and objectives
Scope and expectations
Roles and responsibilities
Assumptions and constraints
Project management approach
Table of Organization
Safety and Health
Temporary Facilities
Quality and Methodology
Schedule
Procurement
Risk Assessment
Budget
Communication Plan
HISTORICAL BACKGROUND
The name of the municipality of Gitagum can be traced back to the time when
the area was still a settlement for non-Christian natives. History says that these
natives who got sick at that time called on a quack doctor to help them get well.
This doctor treated them with leaves of a plant called the tagum-tagum which
abundantly grows in the place. These leaves cured them of the illness and thus
they named the town after the miraculous plant.
2
Gitagum, officially the Municipality of Gitagum, is a 5th class municipality in
the province of Misamis Oriental, Philippines. According to the 2015 census, it
has a population of 16,373 people.
DEMOGRAPHY
WATER RESOURCES
Surface and underground water resources are equally important in agricultural and
industrial activities. Water resources in Gitagum include underground water, springs,
creeks and rivers that cover particular portions of land area of the locality.
The Water District has not seen yet the possibility of bulk water supply since the
operation is still sustainable, only that they can’t provide water to other areas that3
expanded recently but ensured that their expansion project can solve the problems in
water shortage. However, at present, they see high iron content in well water and
becoming one of the water quality issues.
The present water system and level of service of the MWD has many serious
deficiencies, as follows:
1. Low pressure prevails over most of the distribution system;
2. The existing deep well pumping facilities operate inefficiently;
3. Leaking pipes laid in populated drains are a potential source of
contamination;
4. There is a lack of blow-off or draining valves to drain the distribution
system and maintain clean water especially at end cap locations;
5. There is a lack of flowmeter so production data is estimated.
Consequently, the Non-revenue water percentage is not accurate.
6. Water supply is seldom treated or disinfected due to poor
maintenance of each water chlorination treatment unit.
There is a need for additional fire hydrants within the identified location by the
LGU of Gitagum. Should there be fire incidences, it may be easier to tap these
hydrants especially during rush emergency situations.
Project Approach
Below is the major program of works to be implemented upon the commencement of the
project:
a) Pipelaying for the new water system
b) Gitagum River water sourcing;
c) Electro-Mechanical (pump/motor) replacement and necessary upgrading;
d) Meter Set assembly improvement
e) Chlorination treatment unit replacement
f) Variable Frequency Drive and Control improvement to maintain
continuous satisfactory dynamic pumping water supply and pressure
g) Pump Station building refurbishment
Commercial losses can amount to a higher volume of water than physical losses
and often have a greater value, since reducing commercial losses increases
revenue, whereas physical losses reduce production costs. For any profitable
utility, the water tariff will be higher than the variable production cost—
sometimes up to four times higher. Thus, even a small volume of commercial
loss will have a large financial impact.
By addressing the physical and commercial line losses, the total NRW is
effectively reduced.
The following recommended steps are important in achieving the desirable low
level of NRW:
a) Pipe replacement;
b) District Metering Area (DMA) methodology;
c) Relocation of Service Connections for avoidance of illegal tapping and
tampering of water meter;
d) Water Meter replacement program of defective and under registering service
connections;
After the completion of above expansion priority areas within a fifteen (15) years
period from the commencement of the Agreement, service coverage of operation
of JAVESCO shall have expanded to a total of 11 Barangays with approximately
20,469 service connections. These household and commercial connections
shall be the result of upgrading and expanding the water system.
Septage or septic tank sludge refers to the partially treated sludge stored in
a septic tank. It is one type of fecal sludge. Septage is a by-product from the
pretreatment of household wastewater in a septic tank where it accumulates
over time. Septage is pumped out of a septic tank or onsite sewage facility with
a vacuum truck. The septic tanks can be residential or non-residential. Non-
residential sources can include wastewater from commercial/industrial
development, grease interceptor as well as other sources such as portable
toilet, Recreational Vehicle (RV) and boat waste. ii
GOALS AND
OBJECTIVES
9
The business goals and objectives for this project will focus on implementing the
development of potable water system of Gitagum that:
SCOPE
Scope Definition
The Project will set and upgrading the existing water system:
A. Water Source – It is important to determine the water source that will
supply the target population to be served. This source needs to be
geographically close to the area to be supplied to lessen the capital
expenditure needed to tap the water source. It will also help if the water it
produces is potable which means that it passes the Philippine Standards
for Drinking Water. In summary, drinking water should be free of bacteria
and has acceptable levels of minerals. In addition, it should be free of
harmful chemicals such as lead, cyanide and mercury. Should the water
from the source fail in these aspects, water treatment needs to be
conducted which may include chlorination and even setting-up of
multimedia filters and other treatment facilities to address water quality
issues. For a more complete discussion of the standards acceptable for
drinking water, one may check the Department of Health (DOH)
Administrative Order No. 2007-0012 or more commonly known as the
Philippine National Standards for Drinking Water 2007.
10
The water source that shall be tapped is projected to be the Bitanagan
River.
B. The Total Demand, Density of Households and Pipeline Distribution
Network – The number of households will also determine the feasibility of
setting-up a Level III Water System. By NEDA’s definition, a Level III
Water System is: “a system with a source, a reservoir, a piped distribution
network and household taps. It is generally suited for densely populated
areas.” Normally, it is feasible to set-up a water system in an area with a
dense household count of about one thousand (1,000) houses. The
density helps maximize the use of the pipelines. If the houses are too far
away from each other, it also becomes more expensive to lay the
pipelines.
In the case of Gitagum, the identified area has total household count of
more than 16,453 houses. Hence, there is a large customer base that can
benefit from the improved water supply. This household count will serve
as the basis for determining the water supply demand volume.
C. Existing Water System Assets – New water assets and equipment shall
be installed in order to provide sufficient water for the City. These assets
shall be calibrated and matched in order to meet the increasing water
demand of the consumers.
D. Affordability of the Water Rates – The economic situation of the city will
also be assessed based on its income classification. This will be a factor
in determining the water rate as the capacity of the constituents to pay will
be considered. If the water rates are too high, the consumers may not be
motivated to connect to the water service as they will be unable to pay
anyway. It will also help to remember that the daily minimum wage in
Region area is at Three Hundred Forty Pesos (P340.00). Per the Primer
on Tariff Setting and Regulation issued by NWRB, the minimum charge of
the water utility for residential customers must not exceed 5% of the
monthly salary of the minimum wage worker. With a daily minimum wage
of P340.00, a minimum wage worker would earn P8,840.00 per month
(computed as P340.00 X 26 days). Five percent of the monthly minimum
wage would be equivalent to P442.00. Therefore, the water rate in this
11
feasibility study should not exceed P442.00 for the minimum 10 cubic
meters of residential customers.
The residents at Gitagum are used to sourcing water from the water
district, water associations, Level 2 and Level 1 water systems. If they use
their own shallow wells and through jetmatic pumps, they get charged
additional electrical bill. Additional electrical bill for operating the jetmatic
pump may be around P1,000 to as high as P3,000.00 per month. With
this high water cost, the residents interviewed during the study were
definitely more open to a more affordable water service provider.
Hence, the Clean Water Act of 2004 specified that LGUs should have a
Septage Management Facility in place by Year 2020. With none in place
yet in Mati City, it is high time that the Gitagum should plan for this.
PROJECT BUDGET
12
13
Risk Assessment
14
Initial Project Risk Assessment
OPERATIONS
15
COMMERCIAL
DESIGN
16
RISK LEVEL LIKEHOOD MITIGATION STRATEGY /
RISK
L/M/H PROBABILITY ACTION PLAN
Late approval of RFA / RFI High Certainty If approval does not come out
after 14 days, write formal EOT
letter. And notice of delay.
Late approval of Design for High Certainty Do not start works at site for
Value Engineering client to be force to issue
approval. Submit follow-up
letter for approval can be used
for EOT Claim.
SUPPLIER
RISK LEVEL LIKEHOOD MITIGATION STRATEGY /
RISK
L/M/H PROBABILITY ACTION PLAN
Delay in delivery of pipes, Submit delivery schedule of
fitting and valves element precast 1 month in advance
ENVIRONMENTAL/SOCIAL
RISK LEVEL LIKEHOOD MITIGATION STRATEGY /
RISK
L/M/H PROBABILITY ACTION PLAN
17
Milestones
The following represent key project milestones, with estimated completion dates:
2 Phase 2 (3 barangays):
Setting-up of a new water
system in the Barangays
Pangayawan, Burnay, and 2024 to 2029
Gregorio Pelaez (Lagutay)
establishment of a Septage
Management Facility.
3 Phase 3 (3 barangays):
Setting-up of a new water
system in the Barangays 2030 to 2033
Carlos P. Garcia, Ulab, and
Kilangit.
4 Implementation of Septage
Management Program
2025
(compliance to Clean Water
Act of 2004)
5 Maintenance of the Water
2033 onwards
System Assets
18
ASSUMPTIONS
Project Assumptions
Management will ensure that project team members are available as needed
to complete project tasks and objectives.
All project participants will abide by the guidelines identified within this plan.
The Project Plan may change as new information and issues are revealed.
CONSTRAINTS
Project Constraints
Unlike risks, critical project barriers are insurmountable issues that can be
destructive to a project’s initiative. In this project, the following are possible
critical barriers:
19
PROJECT MANAGEMENT APPROACH
The information contained within the Project Plan will likely change as the
project progresses. While change is both certain and required, it is important to
note that any changes to the Project Plan will impact at least one of three critical
success factors: Available Time, Available Resources (Financial, Personnel), or
Project Quality. The decision by which to make modifications to the Project Plan
(including project scope and resources) should be coordinated using the
following process:
Step 2: The Project Manager will review the change and determine the
associated impact to the project and will forward the issue, along
with a recommendation, to the Steering Committee for review and
decision.
21
Communications Plan
This plan provides a framework for informing, involving, and obtaining buy-in
from all participants throughout the duration of the project.
Project Proponents
Steering Committee
Project Manager
User Group Participants
Subject Matter Experts
22
Middle-Out Full support at all levels, where the changes will have to be
implemented, is important to sustainable improvement. At this level (as
with all levels), there must be an effort to find and communicate the
specific benefits of the changes. People need a personal stake in the
success of the project management practices.
Website Use User Group Participants and Subject Matter Experts may be
updated monthly at the discretion of the Project Manager. Information will
be posted to the project’s website.
23
ATTACHMENTS/APPENDICES
24
APPROVALS
Sign-off Sheet
I have read the above Project Plan and will abide by its terms and conditions
and pledge my full commitment and support for the Project Plan.
Project Sponsor:
Date
Project Manager:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
25
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
Steering Committee:
Date
26
i
The Manager’s Non-Revenue Water Handbook, Farley, Malcolm, et.al. 2008
i
http://wikimapia.org/#lang=en&lat=15.283688&lon=121.011314&z=13&m=b&search=%20city
iii
https://en.wikipedia.org/wiki/Septage
iiiiv
https://www.britannica.com/technology/wastewater-treatment/Sludge-treatment-and-disposal