EVALUATION
2.00 EARTHWORKS EXCAVATION
2.01 Excavate in soil for the Dam / Weir in
foundation works along its axis, rate to
include for storage if found reusable as per
the appropriat work drawings. m3 817 3,384.00 2,764,728.00
2.02 Ditto for rock excavation Provisional
quantity only (PQ) m3 245.1 4,000.00 980,400.00
2.03
Ditto for excavaion in rock for the trench and
toe key to foundation works.(PQ) m3 64.5 4,000.00 258,000.00
2.04 Drill in Rock for the anchorage of the dam to
solid weathered rock, holes of size 1.5M x
50mm Diameter in trench and toe key. (212
Nos holes) m3 0.63 5,000.00 3,150.00
2.05 Supply and place in position suitable sand /
cement slurry as hold‐down to anchor bars
in holes. m3 0.53 25,000.00 13,250.00
2.06 Ditto for the supply and place in position
anchor bars of size 20mm Diameter x 1.5M
long ton 0.8 561,330.00 449,064.00
Sub Total item 2.00 4,468,592.00
3.00 CONCRETE WORKS
3.01
Supply and place in position 50mm layer
Grade 20 concrete as blinding to foundation
works base slab to dam, rate to include for
adequate tapping to level m2 344 45,257.00 15,568,408.00
3.02 Ditto for blinding concrete in trench and the
toe key m2 94.6 45,257.00 4,281,312.20
3.03 Ditto for Grade 35 Concrete in Dam's trench
and the toe key m3 64.5 85,000.00 5,482,500.00
3.04 Ditto for grade 35 concrete to foundation
works to dam as per the appropriate work
drawing, rate to include for necessary
compaction m3 302.4 85,000.00 25,704,000.00
3.05 Ditto for grade 35 concrete in dam's wall and
spill weir m3 302.13 85,000.00 25,681,050.00
4.00 SHUTTERING FORMWORKS
4.01 Supply and place in position wrought
shuttering formworks to sides of concrete in
trench and toe key, rate to include for
removal m2 81.9 3,600.00 294,840.00
4.02 Ditto for shutters to sides of foundation base
to dam m2 90 3,600.00 324,000.00
4.03 Ditto for wrought shutters to sides of trench
and toe key to dam's spill weir, rate to
include for removal. m2 54.5 3,600.00 196,200.00
4.04 Ditto for smooth surface shutters to dam's
wall. m2 272.4 3,600.00 980,640.00
4.05 Ditto for smooth surface shutters to spillweir
section of dam m2 170.4 3,600.00 613,440.00
Sub Total item 4.00 2,409,120.00
5.00 REINFORCEMENT IN DAM
5.01 Supply and place in position high yield steel
reinforcement in dam's trench and toe key
as per the specification in the work
drawings. ton 5.064 380,000.00 1,924,320.00
5.02 Ditto for high yield steel reinforcement in
foundation works base slab to dam ton 11.87 380,000.00 4,510,600.00
5.03 Ditto for high yield steel reinforcement bars
in walls to dam ton 14.79 380,000.00 5,620,200.00
5.04 Ditto for high yield steel reinforcement bars
in dams spillweir ton 8.93 380,000.00 3,393,400.00
Sub Total Item 5.00 15,448,520.00
6.00 ABUTMENT WALLS TO SPILLWEIR
6.01 Supply and place in position grade 35
concrete in abutment walls to spillweir,
upstream section only. m3 2 85,000.00 170,000.00
6.02 Ditto for Grade 35 concrete in abutment
walls, downstream only. m3 8.4 85,000.00 714,000.00
6.03
Ditto for the supply and place in position
high yield reinforcement bars in upstream
and downstream abutment walls ton 0.66 380,000.00 250,800.00
6.04
Ditto for smooth surface shuttering
formwork to abutment walls (both upstream
and downstream) ate to include for removal m2 45.31 3,600.00 163,116.00
Sub total item 6.00 1,297,916.00
7.00 RETAINING WALL ‐ UPSTREAM OF DAM,
ALONG THE RIVER BANK
7.01 Excavate in soil along the left hand side of
the river bank to dam, rate to include for
carting away to spoil. m3 84.5 3,384.00 285,948.00
7.02 Ditto for rock excavation to foundation
works base slab to retaining wall. Provisional
Quantity only m3 25.35 4,000.00 101,400.00
7.03 Supply and place in position grade 20 as
blinding concrete to retaining wall footing,
rate to include for tapping m2 23.8 45,257.00 1,077,116.60
7.04 Ditto for grade 35 concrete in wall base
footing, rate to include for necessary
compaction m3 12.24 85,000.00 1,040,400.00
7.05 Ditto for grade 35 concrete in wall m3 32.64 85,000.00 2,774,400.00
7.06
Ditto for the supply and place in position
high yield reinforcement bars in wall footing. ton 0.961 380,000.00 365,180.00
7.07 Ditto for high yield reinforcement in
retaining wall. ton 2.6 380,000.00 988,000.00
7.08 Supply and place in position wrought surface
formwork to wall footng, rate to include for
removal m2 21.12 3,600.00 76,032.00
7.09 Ditto for shutters to retaining wal as per
item 7.08 m2 219.52 3,600.00 790,272.00
Sub Total item 7.00 7,498,748.60
8.00 INTAKE WORK CHAMBER
8.01 Excavate in soil for the foundation works to
Intake work chamber, rate to include for
carting away to spoil just as per the
necessary work drawings. m3 55.8 3,384.00 188,827.20
8.02 Ditto for rock excavation m3 16.74 4,000.00 66,960.00
8.03 Supply and place in position grade 20
concrete as blinding to foundation base slab
to Intake chamber m2 30.25 45,257.00 1,369,024.25
8.04 Ditto for grade 35 concrete in base slab to
Intake chamber, rate to include for
necessary compaction m3 11.7 85,000.00 994,500.00
8.05 Ditto for grade 35 in walls to chamber m3 32.4 85,000.00 2,754,000.00
8.06 Ditto for grade 35 concrete in roof slab to
chamber m3 5.81 85,000.00 493,850.00
8.07 ditto for the supply and place in position
high yield steel reinforcement basis in base
slab to chamber ton 0.92 380,000.00 349,600.00
8.08
Ditto for high yield bars in walls of chamber ton 2.55 380,000.00 969,000.00
8.09 Ditto for high yield reinforcement bars in
roof slab of chamber ton 0.456 380,000.00 173,280.00
8.10 ditto for side shutters to base of chamber,
rate to include for removal m2 8.64 3,600.00 31,104.00
8.11 Ditto for shutters of walls of chamber,
internal sides only m2 73.6 3,600.00 264,960.00
8.12 Ditto for shutters to walls of chamber,
external sides only. m2 88.32 3,600.00 317,952.00
8.13 Ditto for smooth surface shutters to soffit of
roof slab to chamber m2 19.36 3,600.00 69,696.00
8.14 Ditto for sides shutters to roof slab of
chamber m2 5.28 3,600.00 19,008.00
Sub total Item 8.00 8,061,761.45
9.00 PEDESTRIAN WALKWAY BRIDGE ‐ DAM TO
INTAKE WORK CHAMBER
9.01 Supply and place in position grade 35
concrete in U‐beam precast concrete size
300 x 1000 x 1800mm as per the appropriate
work drawing. m3 0.41 85,000.00 34,850.00
9.02 Ditto for high yield stel reinforcement bars in
U‐beam ton 0.1 380,000.00 38,000.00
9.03
Ditto for sides and soffit shutters to U‐beam. m2 3.48 3,600.00 12,528.00
Sub Total Item 9.00 85,378.00
10.00 MISCELLANEOUS ITEMS
THE DAM
10.01 Supply and place in position as per the
specification in accordance with the
appropriate wotk drawings Expansion Joint
Sevitite type XJ size 13 x 140mm. M 82 10,000.00 820,000.00
10.02 Ditto for Servitite CJ type size 13 x 150mm as
construction joint in dam M 12.5 12,000.00 150,000.00
10.03
Allow for the supply and installation of steel
pipe size 250mm diameter or High Density
Plastic pipe or similar as silt desilting /
dewatering through the dam, rate to include
for the necessary pipe fittings M 11 150,000.00 1,650,000.00
10.04 Ditto for chute blocks downstream side of
the dam, infrnt of the spillweir. Size of
trianglarly shaped blocks 400 x 500 x
2000mm. nos 5 20,000.00 100,000.00
10.05
Allow for the installation of 250mm
diameter Steel pipe or High Density plastic
pipe Provisional Quantity, rates inclusive of
excavation for pipe laying and backfilling
with fittings and appurtenances m 30 150,000.00 4,500,000.00
Sub total Item 10.00 7,220,000.00
11.00 INTAKE CHAMBER
11.01
Supply and place in steelwork ladder of size
400 x 4600mm x 300mm rungs, rate to
include for coating with approved anti ‐rust
paints with one coat of prime and two coats
of marine bitumonous paint. no 1 250,000.00 250,000.00
11.02 Ditto for the supply and installation of
penstock gates, each of size 250mm nominal
diameter as per the appropriate
specification in accordance to the working
drawings nos 4 300,000.00 1,200,000.00
11.03
Ditto for the supply and place in position
Servitite CJ types as construction joint to
base slab of chamber nos 17.6 12,000.00 211,200.00
11.04 Ditto for Servitite CJ as joints in walls size 13
x 150mm no 9.2 12,000.00 110,400.00
11.05
Allow for 250mm diameter holes in walls of
chamber for raw water inlet and outlet nos 5 5,000.00 25,000.00
Sub Total Item 11.00 1,796,600.00
12.00 BANK RETAINING WALL
12.01 Allow for the supply and place in position
Constrction Joint Servitite type CJ in wall and
base slab to retaining wall. Size 13 x 150mm
refers. m 30.4 12,000.00 364,800.00
Sub total item 12.00 364,800.00
13.00 BOULDERS TO UPSTREAM BASE OF DAM /
WEIR
13.01
Supply and place in position rock boulders of
size 200 to 300mm as per the appropriate
working drawings upstream face only m3 160 50,000.00 8,000,000.00
Sub total Item 13.00 8,000,000.00
SUMMARY
1.00 SITE CLEARANCE 422,400.00
2.00 EARTHWORKS EXCAVATION 4,468,592.00
3.00 CONCRETE WORKS 76,717,270.20
4.00 SHUTTERING FORMWORKS 2,409,120.00
5.00 REINFORCEMENT IN DAM 15,448,520.00
6.00 ABUTMENT WALLS TO SPILLWEIR 1,297,916.00
7.00 RETAINING WALL ‐ UPSTREAM OF DAM,
ALONG THE RIVER BANK 7,498,748.60
8.00 INTAKE WORK CHAMBER 8,061,761.45
9.00 PEDESTRIAN WALKWAY BRIDGE ‐ DAM TO
INTAKE WORK CHAMBER 85,378.00
10.00 MISCELLANEOUS ITEMS 7,220,000.00
11.00 INTAKE CHAMBER 1,796,600.00
12.00 BANK RETAINING WALL 364,800.00
13.00 BOULDERS TO UPSTREAM BASE OF DAM /
WEIR 8,000,000.00
GRAND TOTAL 153,859,772.19