You are on page 1of 26

12/19/2018 Student Test Report | TestMent

 / Report / Test Report

 Dashboard Test report of TEST-03 Subjectwise ESE - Paper 2 - CE


(../studentpanel/page.php?
page=dashboard&view=overview)
Score Overview Subject wsie Question wise Time wise

Compare with Toppers Solution Difficulty Level Rank


 My Tests
(../studentpanel/page.php?
page=product&view=product_list)
Subject: CE
Language: English

 My Results
(../studentpanel/page.php? Q.1
page=report&view=overall_report)
For completing a task, Rohan takes no less than 30 minutes, sometimes as
much as 50 minutes, 40 minutes are most frequent than any other time, if this
performance were on activity in a PERT project, its variance will be
✉ Message
(../studentpanel/page.php?
page=message&view=message_list)

 Documents
(../studentpanel/page.php?
page=doc&view=doc_list)

 News & Updates


(../studentpanel/page.php?
page=news&view=news_list)
Solution

 Bookmarked Correct
Questions
Your Ans b
(../studentpanel/page.php?
page=bookmarkq&view=q_list) Correct Ans b

Time (Secs) 50

 Bookmark

Q.2

Which of the following statement(s) is/are correct?

I.Activities on PERT network usually follow -distribution

II. -distribution curve may be left skewed or right skewed.

Only I is correct

Only II is correct

Both are correct

None of these

Solution
https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 1/26
12/19/2018 Student Test Report | TestMent

Correct

Your Ans c

Correct Ans c

Time (Secs) 15

 Bookmark

Q.3

Which of the following statement(s) is/are correct about following figure?

I.Normal distribution curve is symmetrical about the mean of the distribution.

II.Shaded area of the curve between is 68.27% of


total area

III.Shaded area of the curve between is 95.46%


of total area

IV.Shaded area of the curve between is 99.7% of


total area

I, II and III

II, III and IV

I, III and IV

I, II, III and IV

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 58

 Bookmark

Q.4

P, Q, R and S are the four activities along unique critical path of a AOA network
of activities. Their characteristics are as under

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 2/26
12/19/2018 Student Test Report | TestMent

What is the possible range of project duration (in days).

29.256 to 40.744

23.512 to 46.488

17.768 to 52.232

25.32 to 40.48

Solution

InCorrect

Your Ans a

Correct Ans c

Time (Secs) 137

 Bookmark

Q.5

A bulldozer moves soil on both way trip at speed of 2.5 kmph. For a haul
distance of 45 meter, the time required for loading, shifting and turning for both
way trip is 1 min. Considering operation factor as 50 min/hr, calculate per hour
output (in m3) of bulldozer. Net mould board capacity is 2.5 m3.

79.11

115.74

39.556

57.87

Solution

Unattempted

Your Ans

Correct Ans a

Time (Secs) 66

 Bookmark

Q.6

Calculate number of trips a bulldozer has to make to remove 100 m3 of soil


material

Operation factor = 50 min/hr

Output = 60 m3/hr

Net mould board capacity = 2.5 m3

Haul distance = 45 meter

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 3/26
12/19/2018 Student Test Report | TestMent
Pushing speed = 2.5 kmph

Returning speed = 5.5 kmph

80

34

40

48

Solution

Unattempted

Your Ans

Correct Ans c

Time (Secs) 173

 Bookmark

Q.7

On an embankment dam, sheep foot roller is used. Determine the quantity of


material compacted if roller travels at 4 kmph, time of rolling is 40 min, length of
drum is 2.5 m, fraction of overlap is 1/8, layer thickness is 0.4 m and number of
passes are 6. Assume only one drum is being used.

50

60

55

65

Solution

Unattempted

Your Ans

Correct Ans c

Time (Secs) 29

 Bookmark

Q.8

A construction company has just bought a new excavator for Rs 27,00,000. The
salvage value of excavator after seven years is Rs 7,20,000. Using the sum of
the year’s digits method, what is the book value of the excavator at the end of
fourth year?

Rs 13,67,485

Rs 11,26,385

Rs 11,44,285

Rs 14,36,785

Solution

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 4/26
12/19/2018 Student Test Report | TestMent

Unattempted

Your Ans

Correct Ans c

Time (Secs) 10

 Bookmark

Q.9

Among the following given equipments, which are excavating and moving type

I.Belt conveyors

II.Clamshell

III.Power shovels

IV.Dumptruck

I and II

II and III

I, II and III

III and IV

Solution

Correct

Your Ans b

Correct Ans b

Time (Secs) 42

 Bookmark

Q.10

A 2 m3 dipper is excavating a material whose swell is 25%, will handle an


average loose volume of 2.25 m3. If the shovel can make 2.5 cycles/min, the
output will be

200 m3/hour

210 m3/hour

270 m3/hour

250 m3/hour

Solution

Unattempted

Your Ans

Correct Ans c

Time (Secs) 30

 Bookmark

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 5/26
12/19/2018 Student Test Report | TestMent

Q.11

Suppose in an IC engine, a region where pressure and temperature are


changing adiabatically ( = 0.5). Find out horse power of engine if pressure get
doubled.

{Given : Hinitial = 80 HP, For = 0.5, PT = constant }

where P and T are pressure and temperature respectively.

100 HP

226.27 HP

321.7 HP

440 HP

Solution

Unattempted

Your Ans

Correct Ans b

Time (Secs) 24

 Bookmark

Q.12

Which of the following do not characterize the critical path?

1.Falls on a single straight line between start and end nodes.

2.It has no dummies.

3.It indicates the minimum feasible duration for the complete project.

4.It has no parallel sub-paths between any two nodes on it.

1 and 2 only

1, 2 and 4

2 and 3 only

2, 3 and 4

Solution

Correct

Your Ans b

Correct Ans b

Time (Secs) 113

 Bookmark

Q.13

The following are the details of estimated time of activities of a certain project.

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 6/26
12/19/2018 Student Test Report | TestMent

Expected project completion time is

36 days

40 days

42 days

38 days

Solution

Correct

Your Ans c

Correct Ans c

Time (Secs) 114

 Bookmark

Q.14

In time-cost optimisation of a project, the project can be crashed by expediting

Any activity on the critical path

Critical activities having minimum cost slope

Activities on sub-critical path

Critical activities having maximum cost slope

Solution

Correct

Your Ans b

Correct Ans b

Time (Secs) 12

 Bookmark

Q.15

Which of the following is the correct sequence to analyse a project for


implementation.

Time-cost study, network, WBS, scheduling with resource allocation

Network, time-cost study, scheduling with resource allocation, WBS

WBS, network, scheduling with resource allocation, time-cost study

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 7/26
12/19/2018 Student Test Report | TestMent

WBS, time-cost study, network, scheduling with resource allocation

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 63

 Bookmark

Q.16

Consider the following statements :

1.Scheduling gives a clear idea regarding the required men, materials and
equipments at different stages of the work.

2.Resource utilisation is optimised

3.It helps in fixing various activities at different stages according to their


priorities..

4.It helps in choosing the best alternatives.

Which of the above statements are correct with respect to project scheduling?

1, 2 and 3 only

1, 3 and 4 only

2, 3 and 4 only

All of the above

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 78

 Bookmark

Q.17

A bar chart of four activities indicating the scheduled start and finish “end-of-day”
values and the resource requirement per day are given below. What will be the
maximum and minimum resource requirement on any of the days?

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 8/26
12/19/2018 Student Test Report | TestMent

22, 6

21, 6

21, 8

20, 8

Solution

Unattempted

Your Ans

Correct Ans a

Time (Secs) 93

 Bookmark

Q.18

Consider the following statements regarding resource allocation/adjustment.

1.Economical utilisation of resources

2.Adjustment of resources to have least variation in resource histogram

3.Gradual increase in resources.

4.Activities are so rescheduled that maximum project need of any resource cross
the limit of available resources.

Which of these statements are correct?

1 and 2

2 and 3

3 and 4

2 and 4

Solution

Correct

Your Ans a

Correct Ans a

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 9/26
12/19/2018 Student Test Report | TestMent

Time (Secs) 119

 Bookmark

Q.19

Which of the following statement(s) is/are incorrect?

I.The planning stage in more related to the duration of project rather than its
know-how.

II.Controlling involves the execution of planning and scheduling.

III.Controlling does not deal with the rescheduling of the work.

IV.Planning and scheduling are done before the start of a project where as
controlling is performed after the start of a project.

I and III

II and IV

I and II

I, II, and III.

Solution

Correct

Your Ans a

Correct Ans a

Time (Secs) 87

 Bookmark

Q.20

Which of the following statements is/are correct with respect to Bar Chart.

1.Bar chart is a graphical representation of event v/s time.

2.The progress achieved at site is expressed in terms of percentage.

3.Length of the bar represents the amount of work completed.

4.No trained personnel are required the make the bar chart.

1, 2 and 3

2 and 4

1 and 3

All are correct.

Solution

InCorrect

Your Ans d

Correct Ans b

Time (Secs) 43

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 10/26
12/19/2018 Student Test Report | TestMent

 Bookmark

Q.21

Consider the statements regarding milestone charts :

1.This chart is an improvement over the original bar chart.

2.The relationship between two specific milestones is revealed within an activity.

3.Milestone chart is activity oriented whereas Bar chart is event oriented.

4.In this chart, the relationship between and among milestones contained in
different activities is not indicated.

1, 2 and 3 are correct.

1, 2 and 4 are correct.

3 and 4 are correct.

All are correct.

Solution

Correct

Your Ans b

Correct Ans b

Time (Secs) 27

 Bookmark

Q.22

Which of the following statements are correct.

1.Network Analysis is a graphical and logical plan which shows


interdependencies between various activities or events.

2.Network Analysis can be used for big and complex projects.

3.Network analysis cannot be used for projects having uncertainty.

4.A-0-A is also known as precedence diagram.

1 and 2

1, 2 and 4

3 and 4

All are correct.

Solution

Correct

Your Ans a

Correct Ans a

Time (Secs) 89

 Bookmark

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 11/26
12/19/2018 Student Test Report | TestMent

Q.23

Consider the following statements :

1.In complex projects, network diagram gives better controlling over the project
and planning whereas scheduling is done by linked bar-chart or milestone
charts.

2.A-O-N system of network completely eliminates the use of dummy activities.

Both 1 and 2 are correct.

Only 1 is correct

Only 2 is correct

None are correct

Solution

Correct

Your Ans c

Correct Ans c

Time (Secs) 50

 Bookmark

Q.24

Which of the following statements are incorrect?

1.Activity consumes time or resource.

2.An event does not consume any time or resource.

3.Serial activities are performed one after the other sequently.

4.Concurrent activities are performed simultaneously.

1 and 2 are

3 and 4

1, 2, 3 and 4

None

Solution

InCorrect

Your Ans c

Correct Ans d

Time (Secs) 33

 Bookmark

Q.25

Activities A and B can be started independently. Activity E can be started only


when A and B have been completed. Activity D follows A and proceeds F.
Activity E and F merge at the final event. The network plan will be

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 12/26
12/19/2018 Student Test Report | TestMent

Solution

Correct

Your Ans c

Correct Ans c

Time (Secs) 31

 Bookmark

Q.26

Which of the following statement(s) is/are correct for a dummy activity?

1.It is a type of activity in the network which does not consume any time but
consumes resources.

2.Dummy activity maintains the logic of network diagram

3.Dummy activity keeps the numbering system of the network unique.

Only 1 is correct.

Only 2 and 3 are correct.

Only 1 and 2 are correct.

All are correct.

Solution

Correct

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 13/26
12/19/2018 Student Test Report | TestMent

Your Ans b

Correct Ans b

Time (Secs) 19

 Bookmark

Q.27

With reference to the activity on arrow network shown below, which statement is
incorrect?

Events C and D occur after event B

Events G precedes event F

Events E follows event C

Events G can occur after event C

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 58

 Bookmark

Q.28

Match List - I with List - II.

List - I

A.Dummy Activity

B.Fulkerson’s Rule

C.Preceding Event

D.Succeeding Event

List - II

1.Marks the beginning of an activity

2.Maintains numbering system of network unique

3.Marks the completion of an activity.

4.Represents numbering of events.

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 14/26
12/19/2018 Student Test Report | TestMent
A - 4, B - 2, C-1, D-3

A - 4, B - 2, C-3, D-1

A - 2, B - 4, C-1, D-3

A - 2, B - 4, C-3, D-1

Solution

Correct

Your Ans c

Correct Ans c

Time (Secs) 70

 Bookmark

Q.29

Which one is the conceptual kind of error in network diagram.

Cyclic error

Dangling error

Looping error

Wagon wheel error

Solution

InCorrect

Your Ans c

Correct Ans d

Time (Secs) 22

 Bookmark

Q.30

Consider the following statements for A-O-N diagram :-

1.Float calculations in A-O-N network is different from A-O-A network and is


simpler.

2.A-O-N diagram eliminates the use of dummies.

3.When a number of activities start simultaneously, an activity is called “DEBUT.”

4.Debut activity has ‘o’ time duration.

1, 2 and 3 are correct.

1, 3 and 4 are correct.

3 and 4 are correct.

2, 3 and 4 are correct.

Solution

Correct

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 15/26
12/19/2018 Student Test Report | TestMent

Your Ans d

Correct Ans d

Time (Secs) 43

 Bookmark

Q.31

Which statement(s) holds true for PERT.

1.Three time estimates are made for each activity.

2.Suitable for new type of projects.

3.Each activity follows normal distribution

All are true.

1 and 3 are true.

Only 1 is true.

1 and 2 are true.

Solution

InCorrect

Your Ans a

Correct Ans d

Time (Secs) 15

 Bookmark

Q.32

A project is expected to take 15 months along the critical path, having a variance
of 9 months. What is the probability of completing the project within 21 months?

The probability percentage for different value of probability factors are

15.87% 1

50.00% 0

97.72% 2

15.87%

50.00%

97.72%

100%

Solution

Correct

Your Ans c

Correct Ans c

Time (Secs) 51

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 16/26
12/19/2018 Student Test Report | TestMent

 Bookmark

Q.33

Following graph is obtained from Break even analysis.

The margin of safety for given Break point Analysis diagram will be

20%

80%

60%

40%

Solution

Unattempted

Your Ans

Correct Ans d

Time (Secs) 10

 Bookmark

Q.34

A project consists of seven activities with the following details:

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 17/26
12/19/2018 Student Test Report | TestMent
The minimum number of dummy activities required in the network diagram is

Solution

Unattempted

Your Ans

Correct Ans c

Time (Secs) 7

 Bookmark

Q.35

Consider the following statements:

1.Total float is the maximum time by which an activity can be delayed without
delaying the project.

2.Free float is difference between earliest start time of successor & predecessor
activity.

3.Independent float is the amount of time by which an activity can be delayed


when all the preceding activities can be delayed as late as possible and all
succeeding activities started as early as possible.

4.Interfering float is the difference of total float and free float of an activity.

Select the correct statement(s):

1, 2, 3

2, 3, 4

1, 3, 4

1, 2, 4

Solution

Correct

Your Ans c

Correct Ans c

Time (Secs) 76

 Bookmark

Q.36

The given figure shows the arrow diagram for a particular project. The arrow F is
known as

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 18/26
12/19/2018 Student Test Report | TestMent

Critical activity

Logic arrow

Dummy activity

Subcritical activity

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 79

 Bookmark

Q.37

Consider the following statements:

1.The Total float can be defined as the latest occurrence time Lj of succeeding
event minus the earliest occurrence time Ei of the preceding event minus the
duration of the activity defined between these events.

2.Free float is defined as earliest occurrence time of the preceding event Ei


minus the earliest occurrence time of the following event Ej minus the duration of
the activity.

3.Independent float is defined as the earliest occurrence time Ej of the following


event minus the latest occurrence time Li of the preceding event minus duration
of the activity defined between these events.

Select the correct statement(s).

1, 2

1, 3

2, 3

1, 2 and 3

Solution

Unattempted

Your Ans

Correct Ans b

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 19/26
12/19/2018 Student Test Report | TestMent

Time (Secs) 49

 Bookmark

Q.38

A curve is plotted between the elapsed time of an activity and frequency.

The point C corresponds to:

Optimistic time

Pessimistic time

Most likely time

Expected time

Solution

InCorrect

Your Ans a

Correct Ans b

Time (Secs) 20

 Bookmark

Q.39

For an activity P, details are shown in table below :

What is the probability that activity P is likely to be completed in 6 to 14 days?

68%

95%

50%

88%

Solution

Unattempted

Your Ans
https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 20/26
12/19/2018 Student Test Report | TestMent

Correct Ans b

Time (Secs) 170

 Bookmark

Q.40

A construction equipment has a useful life of 3 years after which it is to be


replaced by a new one. If the interest rate is 1%, the sinking fund factor will be:

0.330

0.184

0.224

0.232

Solution

Unattempted

Your Ans

Correct Ans a

Time (Secs) 6

 Bookmark

Q.41

Statement for Q. No. 41 to 50

Each of the item consists of two statements are labelled as the ‘Assertion (A)’
and the other as ‘Reason (R)’. You are to examine these two statements
carefully and select the answers to these items using the codes given below:

Codes:

a)Both Assertion (A) and Reason (R) are individually true and Reason (R) is the
correct explanation of Assertion (A)

b)Both Assertion (A) and Reason (R) are individually true but Reason (R) is NOT
the correct explanation of Assertion (A)

c)Assertion (A) is true but Reason (R) is false

d)Assertion (A) is false but Reason (R) is true

Assertion (A) : The size of the hauling units must balance with the output of the
excavator.

Reason (R) : If the balance of hauling units is not achieved, it increases the cost
of operation.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 21/26
12/19/2018 Student Test Report | TestMent
Solution

Unattempted

Your Ans

Correct Ans a

Time (Secs) 43

 Bookmark

Q.42

Assertion : Network analysis techniques can not be used for new and
complicated projects/activities.

Reason : PERT has the ability to cope with uncertain completion time of activity.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 30

 Bookmark

Q.43

Assertion : PERT network is event-oriented.

Reason : In PERT analysis, Planners can decide about the uncertainties


involved in time duration while planning itself.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

InCorrect

Your Ans a

Correct Ans b

Time (Secs) 16

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 22/26
12/19/2018 Student Test Report | TestMent

 Bookmark

Q.44

Assertion : AOA network must be drawn with simultaneous due regard and
recognition of each of the activity duration.

Reason : Dummy activity can be used to emphasize procedure and follow-up


dependencies between activities.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

InCorrect

Your Ans a

Correct Ans b

Time (Secs) 54

 Bookmark

Q.45

Assertion : In a normal distribution, the probability of completion of a multipath


project at the most probable time is 0.5.

Reason : In normal distribution, mean = median = mode

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

InCorrect

Your Ans b

Correct Ans a

Time (Secs) 18

 Bookmark

Q.46

Assertion : Smooth wheel roller are used on cohesive soil.

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 23/26
12/19/2018 Student Test Report | TestMent

Reason : Smooth wheel roller tend to form crust over the surface in cohesive
soil.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 14

 Bookmark

Q.47

Assertion : In any construction project, Work Breakdown Structure follows


bottom to top approach.

Reason : WBS is a technique that identifies the functional elements of a project


and their interrelationship.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

Correct

Your Ans d

Correct Ans d

Time (Secs) 23

 Bookmark

Q.48

Assertion : Activity on Node network will not have redundancy error.

Reason :Dummy Activities are not required in AON Network.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 24/26
12/19/2018 Student Test Report | TestMent

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

InCorrect

Your Ans b

Correct Ans a

Time (Secs) 17

 Bookmark

Q.49

Assertion :In Gantt chart, it is not possible to crash the activities and get the
optimum cost and duration of the project.

Reason : Milestone chart is activity oriented while Bar chart is event oriented.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

Correct

Your Ans c

Correct Ans c

Time (Secs) 630

 Bookmark

Q.50

Assertion :Updating is the process of incorporation of change and replanning or


rescheduling.

Reason : If all activities are progressing according to the schedule, even though
there is a need for updating the network.

Both Assertion (A) and Reason (R) are individually true and Reason (R) is
the correct explanation of Assertion (A)

Both Assertion (A) and Reason (R) are individually true but Reason (R) is
NOT the correct explanation of Assertion (A)

Assertion (A) is true but Reason (R) is false

Assertion (A) is false but Reason (R) is true

Solution

InCorrect

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 25/26
12/19/2018 Student Test Report | TestMent

Your Ans a

Correct Ans c

Time (Secs) 53

 Bookmark

https://iesmaster.org/onlinetestseries/tm/studentpanel/page.php?page=report&view=test_report&test_id=232 26/26

You might also like