Professional Documents
Culture Documents
INTRODUCTION
1.1. Canal
1
humble), generally requiring an external water source above the
highest elevation. Many canals have been built at elevations towering
over valleys and others water ways crossing far below. Cities need a lot
of fresh water and many canals with sources of water at a higher level can
deliver water to a destination where there is a lack of water. The Roman
GGEmpire's Aqueducts were such water supply canals.
Main Canal takes off directly from the upstream side of weir head
works or dam. Usually no direct cultivation is proposed. Most of the main
canals are aligned as contour canals to derive benefit.
2
1.2.2. Branch Canal
All off takes from main canal with head discharge of 14-15 cumecs
and above are termed as branch canals.
All off takes from main canal or branch canal with head discharge
from 0.028 to 15 cumecs are termed as major distributaries.
All off takes taking off from a major distributary serving more than
40.47 hectares are termed as minor distributaries. They are named after a
prominent place near about their tail ends.
3
1.2.5. Field Channel
All pipe off takes serving less than 40.47 hectares of ayacut are
called field channels and are denoted by numbering as left or right side
pipes
4
CHAPTER-2
LITERATURE REVIEW
5
Canals including further offerings by P A L Vine on southern
waterways - The Wey & Arun Junction Canal (1999), The Arun
Navigation (2000) and London’s Lost Route to Portsmouth - and by
David Viner’s The Thames & Severn Canal, History & Guide (2002),
Mike Taylor’s The Calder & Hebble Navigation (2002) 15 and two on the
Kennet & Avon Canal. In 2002 the international context for Britain’s
pioneer canal lifts was further established by Mike Clarke’s translation
and editing of H-J Ullemann’s Canal Lifts & inclines of the World re-
affirming their international significance.
6
Louisiana : From October through December of 2003, Coastal
Environments, Inc. (CEI), conducted a cultural resources literature search
and records review as part of a U.S. Army Corps of Engineers (COE)
New Orleans District re-evaluation study to determine if improvements to
navigation along the Houma Navigation Canal, in Terrebonne Parish,
Louisiana, are justified. These investigations are part of the planning to
evaluate several alternatives to deepening the HNC from the authorized
15-foot depth to an 18- or 20-foot depth while maintaining the existing
canal width. Both channel depths are being considered with a lock and
without a lock in place. If the canal itself is assumed to be approximately
1000 ft (305m) wide, the HNC encompassed roughly 4969.69ac
(2012.05ha), including 2909.09ac (1177.78ha) of canal and 2060.60ac
(834.26ha) of navigation channel. Three previously recorded
archaeological sites and 13 sunk or salvaged vessels exist within the
project's Area of Potential Effects (APE). In addition, seven unrecorded
sites and 23 potential site loci were noted on the HNC during the project
area site inspection conducted during this study. Those portions of the
project area with a high probability for containing cultural resources have
been defined on project plans and encompass 691.48ac. A research design
to guide future cultural resources fieldwork in the project area is
presented.
7
Endodontics PDU Dental College Solapur 5,6 Senior Lecturer;
Department Of Conservative Dentistry and Endodontics PDU Dental
College Solapur Abstract: The basics of root canal preparation are to
enlarge the root canal for proper disinfection and to prevent reinfection
with the use of irrigation agents. It also facilitates the placement of root
canal filling material with proper fluid tight seal. As most root canals are
curved, a high prevalence of procedural errors has been reported. Canal
transportation is one of the main procedural errors. The position of
physiologic terminus of the canal to a new iatrogenic location on the
external root surface is transportation of the foramen. Several studies
have shown that Ni-Ti instruments demonstrated less canal transportation
than stainless steel files. Considerable research has been undertaken to
understand the several factors related to canal transportation. In this
article, we have discussed the influence of various parameters such as
alloys used in the manufacture of instruments, instrument cross-section,
tip, taper, and explained about clinical consequences of canal
transportation. Keywords: Root Canal Transportation, root canal
treatment, NiTi, stainless steel hand instruments, cross section,
Summary:
I would like to conclude that the project, we are going to do this based
on stability, durability, economic and safety.
Navigation system can be made possible with the help of the project
Water will not be evaporated and water will be made to retain for 10m
height.
8
CHAPTER-3
METHODOLOGY
1. Data collection
3. Design of canals
4. Design of lining
5. Design of berms
9
3.1. Data collection
1. Irrigation canal
2. Navigational canal
3. Power canal
4. Feeder canal
10
3.4. Design of Lining
Types of lining
11
FIGURE-5 LINED CANAL
12
FIGURE-7 GEOPOLYMER CANAL LINING
Berm is the horizontal distance left at the ground level between the
toe of the bank and the top edge of cutting and toe of banks. When water
flow in the canal at FSL (full supply level), silt particles are deposited on
theberms and make the final side slope to1.5.1
13
3.6. Design of canal Regulator
14
CHAPTER-4
DEIGN OF CANALS
Many procedures have been developed over the years for the
hydraulic design of open channel sections. The complexity of these
procedures vary according to flow conditions as well as the level of
assumption implied while developing the given equation. The Chezy
equation is one of the procedures that was developed by a French
engineer in 1768. The development of this equation was based on the
dimensional analysis of the friction equation under the assumption that
the condition of flow is uniform. A more practical procedure was
presented in 1889 by the Irish engineer Robert Manning. The Manning
equation has proved to be very reliable in practice.
One of the important topics in the area of free surface flows is the
design of channels capable of transporting water between two locations in
a safe, cost - effective manner. Even though economics, safety, and
15
aesthetics must always be considered, in this unit thrust is given only to
the hydraulic aspects of channel design. For that discussion is confined to
the design of channels for uniform flow. The two types of channels
considered are
There are some basic issues common to both the types and are presented
in the following paragraphs.
5. Roughness coefficient.
6. Free board.
16
sections are summarized in Table. It should be noted that, the
hydraulically efficient section is not necessarily the most economic
section.
17
same material. In many cases, side slopes are determined by the
economics of construction. In this regard following observations are
made: a. In many unlined earthen canals, side slopes are usually 1.5: 1;
However, side slopes as steep as 1:1 have been used when the channel
runs through cohesive materials. b. In lined canals, the side slopes are
generally steeper than in an unlined canal. If concrete is the lining
material, side slopes greater than 1: 1 usually require the use of forms,
and with side slopes greater than 0 .75 : 1 the linings must be designed to
withstand earth pressures. Some types of lining require side slopes as flat
as those used for unlined channels.
TABLE -1: Suitable side slopes for channels built in various types of
materials
18
TABLE-2: Indian standards for canal in cutting and embankment
Side slop (Horizontal to Vertical m: 1)
19
FIGURE-9: Graph Drawn Bank full discharge VS Channel Slope
The designer should look into these aspects before finalizing the
minimum permissible velocity. "Minimum permissible velocity" refers to
the smallest velocity which will prevent both sedimentation and
vegetative growth in general. An average velocity of (0.60 to 0.90 m/s)
20
will prevent sedimentation when the silt load of the flow is low. A
velocity of 0.75 m /s is usually sufficient to prevent the growth of
vegetation which significantly affects the conveyance of the channel. It
should be noted that these values are only general guidelines. Maximum
permissible velocities entirely depend on the material that is used and the
bed slope of the channel. For example: in case of chutes, spillways the
velocity may reach as high as 25 m/s. As the dam heights are increasing
the expected velocities of the flows are also increasing and it can reach as
high as 70 m/s in exceptional cases.
Hence, following table gives the maximum permissible velocity for some
selected materials
21
TABLE-4 : Maximum permissible velocities and n values for
different materials
Material V (m / s) n
Gravel 1.2
Concrete 6.0
22
4.1.5. Resistance to the flow
23
These values should, however, be adopted only where the channel
has flushing velocity. In case the channel has non-flushing velocity the
value of n may increase due to deposition of silt in coarse of time and
should in such cases be taken as that for earthen channel.
24
4.1.6. Freeboard
(4) Super elevation of the water surface as the flow goes round curves at
high velocities,
(6) The occurrence of greater than design depths of flow caused by canal
sedimentation or an increased coefficient of friction, or
The freeboard associated with channel linings and the absolute top
of the canal above the water surface can be estimated from the empirical
curves. In general, those curves apply to a channel lined with either a
hard surface, a membrane, or compacted earth with a low coefficient of
25
permeability. For unlined channels, freeboard generally ranges from 0.3m
for small laterals with shallow depths of flow to 1.2m for channels
3
carrying 85 m /s at relatively large depths of flow. A preliminary
estimate of freeboard for an unlined channel can be obtained from USBR
formula.
FB=
The free board (measured from full supply level to the top of
lining) depends upon the size of canal, velocity of water, curvature of
alignment, wind and wave action and method of operation. The normal
free board is 15 cm for small canals and may range up to 1.0 m for large
canals. The U.S.B.R. practice for the minimum permissible free board for
various sizes of canal is given in Figure. Indian Standard IS : 4745
recommends a free board of 0.75 m for canal carrying a discharge of
3
more than 10 m /sec.
26
TABLE- 8: Free board as per Indian Standards (IS 4745 - 1968)
3
Discharge Q (m /s) Free board (m)
Unlined Lined
27
TABLE-9: Actually adopted free board for different ranges of
discharge in India are below
3
Q (m /s) < 0.15 0.15 - 0.75 0.75 - 1.50 1.50 - 9.00 > 9.00
4.1.7. References
1. IS: 4745 - 1968, Code of practice for Design of Cross Section for
Lined Canals, Indian Standards Institution, New Delhi, 1968.
2. IS: 7112 - 1973, Criteria for Design of Cross Section for Unlined
Canals in Alluvial Soil, Indian Standards Institution, New Delhi, 1974.
When flow moves around a curve, a rise in the water surface occurs at the
outer bank with a corresponding lowering of the water surface at the inner
bank. In the design of a channel, it is important that this difference in
water levels be estimated. If all the flow is assumed to move around the
curve at the subcritical average velocity, then super elevation is given by
Ymax=
28
4.2. Radius of curves for lined canals
3
Discharge (m /s) Radius (minimum) in m
Note: Where the above radii cannot be provided, proper super elevation
in bed shall be provided.
29
efficient channel. But this is popularly referred as Best Hydraulic section.
The semi circle has the least perimeter among all sections with the same
area; hence it is the most hydraulically efficient of all sections. The
geometric elements of six best hydraulic sections are given in Table. It
may be noted that it may not be possible to implement in the field due to
difficulties in construction and use of different materials. In general, a
channel section should be designed for the best hydraulic efficiency but
should be modified for practicability. From a practical point of view, it
should be noted that a best hydraulic section is the section that gives the
minimum area of flow for a given discharge but it need not be the
minimum excavation.
30
TABLE-11: Geometric elements of best hydraulically efficient
section.
Cross A P R T D Z=AD
Section
2 2.5
Rectangula 2y 4y 0.5 y 2y y 2y
r
Trapezoida 2 3y 2 3y 0.5 y 433y 34 y 2532.y
l () 2 1732.y (0.75y) () 25 15..y
(3.464y) (2.3094y)
Triangular 2y 2 2y 24y 2y 2y 2522.y
2.828y 0.3535y 0.5y 25 0707..y
2 2.5
Hydrostatic 1.40 y 2.98 y 0.468 y 1.917 y 0.728y 1.91 y
Caternary
Flexible sheet: Filled with water up to rim, and held firmly at the top ends
without any effect of fixation on shape. Shape assumed under self height
of water is called Hydrostatic Catenary.
31
4.4. Selection of Lining
4.4.1. Introduction
The need for lining channels in alluvium has long been identified
to conserve every bit of water for more and more utilisation. Lining of an
irrigation channel is restored to achieve all or some of the following
objectives keeping in view the overall economy of the project. The major
advantages of rigid impermeable linings are as follows of Technology
Madras (a) Reduction of seepage losses resulting in a saving of water
which can be utilised for additional irrigation.
(i) Insure Cross section stability from scour, low flow conditions etc.
32
4.5. Canal Lining
1. Rigid-impermeable Lining,
33
FIGURE-12: LINED CANAL
34
FIGURE-14: INTAKE CANAL
35
4.5.1. Design of Lined Channels
36
TABLE-12 Design flow
Step Process
1 Estimate n or C for specified lining material and S
0
2 Compute the value of section factor ( ) 2/3 1/2 o o AR nQ/ Sor AR Q/ C S=
3 Solve section factor equation for yn given appropriate expressions for A and R ( Table )
Note: This step may be required with assumptions regarding side slopes, bottom widths,
etc. (As a thumb rule for quick computation y can be taken as 0.5 A
and for trapezoidal section it can be shown as b 4 m y = −
. In India, y for the trapezoidal channel can be taken as 0.577 A
which corresponds to b 3 m y = −
for earth canals).
4 If hydraulically efficient section is required, then the standard geometric characteristics
(click) are used and yn is to be computed.
5 Check for
1. Minimum permissible velocity if water carries silt and for vegetation
(Check whether the velocity is adequate to prevent sedimentation (V= 0.6 to 0.9 m / s).
Check whether velocity is adequate to prevent vegetation growth (V = 0.75 m/s)).
2. Froude number
(Check Froude number and other velocity constraints such as ( for non-reinforced
concrete linings V 2.1 m/s ≤
and Froude number . For reinforced linings )). 0.8 ≤
V 5.5 m/s ≤
Generally, Froude number should be as small as possible for Irrigation canals and should
be less than 0.35. Higher Froude numbers is permitted as in the case of super critical
flows such as in chutes, flumes. Decide the dimensions based on practicability.
6 Estimate
1. Required height of lining above water surface,
2. Required freeboard, Figure.
Balance excavations costs, costs of channel lining and assess the needs to modify
"Hydraulically efficient section".
7 Summarize the results with dimensioned sketch.
Solution
37
A=1.73y2,P=3.46y,R=y/2
n=0.015
20=
Y8/3=7.107
Y=2.086m
b= y,
b =1.15y = 2.409 m
Velocity= = =2.656m/s
38
FIGURE-16 LINED CANAL DESIGN
R=
A = =0.025* =12.656
Area=Discharge/Velocity=20.25/1.5=1.5m2
Solving for y, we get y=1.5m, b/y= 4 ,
Add a free board of 0.75 m
39
FIGURE-17 DESIGNED CANAL
FORMULAE
In the design of channel sections, the various formulae generally used are
as follows:
2) Manning’s formula: V=
40
(This corresponds to the formula, V = 16 in F.P.S system.)
Where,
n = Coefficient of Rugosity
41
Thus the use of this formula is a bit cumbersome. However, the
form of this equation has been simplified as shown below and the use of
this formula has been further simplified with the result of values.
V=
N= + (23+
D = (23+
42
4.6.1. Discharge flowing
= 1.510
43
4.6.2. Values of C for Manning’s Formula
0.025 Canals and rivers in earth in tolerably good order and regime
0.0275Canals and rivers in earth below the average in order and regime
0.035 Canals and rivers obstructed by detritus and in bad order and
regime
44
TABLE-13 (a) In soils other than rock
Capacity Value of N
(cubic meters/sec.)
0.15 0.030
0.15 to 1.40 0.025
1.40 to 14.10 0.0225
Above 14.10 0.020
(b)Rock cuts
45
nor erodes, picking up fresh silt from the channel surface, widening it
further, there is likely to be recurring expenditure in silt clearance or
restoring them to normal sections if eroded. So, it is very important to
design earthen channels with such shapes (cross-sections) and
longitudinal slopes such that the water way is neither obstructed by the
deposition of fresh silt nor injured by further erosion on bed sides.
In case of non-deltaic channels, taking off from big reservoirs, the
river flows are detained for some time in the water spread. This gives
time for the rolled and suspended silt to settle down in the reservoir bed.
So, practically clear water with very little silt suspended is drawn through
the channel. In all such cases the maximum velocity for which the
channel has to be designed, depends upon the velocity of flow that can be
withstood by the soil through which the channel runs without erosion.
46
Till the year 1895, all Channels were designed by the aid of
Chazey’s equation V=C and it was a common thing to expect heavy
silt deposits that had to be cleared at enormous costs. This state of affairs
changed when B.G.Kennedy found from his extensive experimental
studies on a number of Regime channels in Punjab (Bari Doap system)
that there was a critical velocity at which the canal neither silted nor
scoured. He stated that within reasonable limits of deviation, there existed
a constant relation between the depth of flow and the velocity expressed
by the equation
Where,
d= depth of flow.
(iii) It also varies with the velocity of the stream, the variation is as
47
(iv) All silt in suspension and a certain amount of bed rolled silt is carried
by the stream.
Q = Vd.
Therefore, q = PQ = P×V×D.
But the quantity of silt transported per meter width of the channel is
also equal to A where, A is the area per meter width of the channel.
Therefore, PVD =A
V = (P/A) 1/n-1 ×
Silt M n
48
Kennedy later recognized that the grade of silt played a
prominent part in this relationship and introduced another factor into his
equation called by him as “Critical Velocity Ratio” (C.V.R).
critical velocity.
The values of C.V.R for sands coarser than standard are assigned
from finer from 0.9 to 0.8.
In Lacey’s formula,
Or
And = 0.6377
R = 2.46 )
F = Silt factor.
R=
49
=
q=
R=
This scour depth will be reckoned below the maximum flood level.
50
4.10. SELECTION OF SUITABLE BED SLOPE
In general, the channels are divided into two main groups’ namely
contour canals and ridge canals. While aligning contour canals, care has
to be taken to obtain maximum commend, and cross minor valleys with
masonry structures. It is these aspects along with certain obligatory
conditions like negotiating an existing reservoir by a level crossing etc.
that fix the general slope to be adopted.
51
distance. Similarly, if the country is very steep, a flatter slope has to be
adopted, keeping the cost of masonry-drops to the minimum.
After arriving at a possible bed slope for the channel, the next step
is to decide the bed width to depth ratio.
The best discharging channel is one which for the same cross-
sectional area, and slope passes water with the greatest velocity, or which
has the greatest hydraulic mean depth.
52
TABLE-17 Discharge VS B/D ratio
0.30 2.9
0.75 3.4
1.50 3.7
3.00 4.2
7.50 4.8
15.00 5.7
30.00 7.6
60.00 11.3
150.00 22.5
300.00 41.0
53
TABLE-18 DISCHARGE VS B/D ratio
0.30 2.9
0.75 3.3
1.50 3.7
3.00 4.2
7.50 4.5
15.00 6.00
30.00 7.4
60.00 9.6
150.00 13.5
300.00 18.0
54
relatively smaller than the canal bed levels are attained with minimum
cutting in Harden soils.
55
4.12. LINING
In all the formulae used for calculating the velocity of flow through
an unlined channel, we take the value of coefficient of rugosity between
0.02 to 0.03. The value of 0.02 is taken for channels, which are in very
good order.
If the canal section is lined in the bed and sides, the lining
presenting a hard and smooth surface for the flow, a coefficient of
rugosity as low as 0.014 can be used. Thus, for a given channel section
and slope remaining same, we can discharge a larger quantity through a
lined canal than through an unlined canal. Thus an existing canal can be
made to discharge more by lining it. If this alone is not sufficient to meet
the requirement as previously suggested, the section can be widened,
depth increased and ultimately lined.
Depth 5 meters
56
The flume portion is assumed to be in hard rock where a side slope
of ¼ to 1 is permissible. The maximum velocity assumed in the flume
may be taken as 2.5meters per second. Assume the whole flume also be
lined (n=0.018)
=(25+
57
The land commanded by the main canal will be subdivided into irrigation
units of about 10 ha each.
From the main canal, secondary canals will be laid out to each
irrigation unit, following the line of highest elevation in each unit so as to
maximize the area served by each secondary canal. Tertiary canals, or
field channels, will then be laid out from the secondary to deliver water
throughout the unit
4.14.2. Bed slope
On flat sloping, non-undulating lands, canals will generally have
the same slope as the terrain. In steeply sloping lands, canals will be
given a slope which is less than the terrain to avoid high flow velocities.
In such cases, drop structures will have to be installed to connect the
canal sections. See also Section 5.6.2 of this manual. When a canal
crosses a depression or a gully, it cannot follow the terrain and should be
constructed in fill, and if a ridge in the terrain has to be crossed the canal
will have to be constructed in cut.
Whatever the slope of the canal, abrupt changes in the slope
should be avoided. If the bed slope changes suddenly the flow velocity in
the canal will also change, and such a change in flow velocity can cause
erosion or may lead to siltation in the canal bed.
4.14.3. Bed elevation
Depending on local circumstances, canals can be built in fill or in
cut. A typical cross-section of a canal in fill. There are three factors that
play a role in deciding the level of the canal bed. The first factor is that
the slope of a canal should be as constant as possible. Abrupt changes in
slope should be avoided. This may result in canal sections having to be
constructed in cut or in fill, depending on topography.
Another factor is that the volume of cut should preferably equal the
volume of fill when constructing the canal Cross-section of a canal with
58
balance between cut and fill when the elevation of a canal bed is so high
that the volume of fill is larger than the volume of cut, soil has to be
brought from elsewhere. This may result in high construction cost. Also,
if a canal is to be constructed in cut, the excavated soil is to be spread out
over the fields or it should be used elsewhere, which also increases the
cost of canal construction.
Construction costs are usually at a minimum when there is a
balance between the volumes of cut and fill. The third factor to take into
account when determining the bed level of a canal is the Water level in
the canal. The water level in field channels should be about 0.10 m higher
than the level of the fields to be irrigated from those canals, and the water
level in a secondary canal which supplies a field channel should be about
0.05 m higher than the design level in the field channel.
This is because of the loss in water level at the canal off take. The
bed elevation and water level at the downstream end of a tertiary canal is
determined as the first step, assuring at least 0.10 m difference between
the water level in the canal and the field level. Going upstream, it should
be checked that the water level in the field channel all along the channel
is at least 0.10 m higher than the fields. Further upstream, the water level
in the secondary canal can also be determined, taking into account the
0.05 m loss at the canal off takes
59
embankment is constructed, and then the Canal cross-section is excavated
in the middle.
60
Step 2: Hammer pegs in the soil every 50 m in a line to mark the
centre line of the Embankment and its final level.
The top of each peg should indicate the top level of the
embankment at that point. Mark the centre line of the embankment in
between these points with boning rods every 10 m.
Step 3: Every 10 m, mark the outer line of the body of the
embankment to be constructed
The top level of the embankment has been marked in Step 2. The
outside slope of the embankment must be stable and depends on the
material which is used. As a rule of thumb, a slope of 1:2 [1 vertical to 2
horizontal] may be taken. Marking for the outside line of the embankment
can be done by using a template, which can be made from sticks, bamboo
or other material.
Step 4: Construct the embankment
The embankment is constructed by adding soil in 5 cm thick layers,
with each layer compacted moist.
4.16. CONSTRUCTION OF A CANAL - AN EXAMPLE
Small irrigation canals are either dug in the original soil or they are
excavated in an embankment, constructed as described in the previous
section. In the former case the soil is generally well compacted and
stable, while in the latter case the embankment may not be very stable
even after elaborate compaction during construction. Therefore it is good
practice to wait at least one rainy season before excavation of a canal in
an embankment can start, having thus allowed the soil in the embankment
to fully settle down.
In this section the procedure for canal construction is presented. As
an example the section of the embankment which was determined in
Section will be used. The embankment has been constructed and has been
61
allowed to settle. The elevation and size of the embankments has been
checked, and is according to the specification.
NOTE 1
Larger canals in fill or partly in fill are usually constructed by
bringing up soil from two sides. The two canal banks are then re-shaped
to conform to the designed cross section of the canal.
NOTE 2
The construction of small canals in cut is identical to the
construction of small canals in fill, assuming that the latter is excavated in
an embankment.
NOTE 3
Canals should be built continuously from one end, not as scattered
small sections.
This results in uniform construction, and makes supervision easier.
Before the canal is constructed, all plant growth, rubbish, stones and other
debris should be removed from the site. The procedure for constructing a
canal is given in steps. The dimensions of the canal are as follows
Height of the cross-section: h = 0.70 m
Bed width: b = 0.30 m
Side slop: s = 1/1.5 or 1:1.5
Top width of canal banks: top = 0.40 m
Step 1 Mark the cross-section with pegs
Hammer a peg in the centre line of the canal, which is usually done
during the embankment construction period. This is Peg 1. Measure the
bed width: 0.15 m to each side of Peg 1. Place Pegs 2 and 3 perpendicular
to the centre line of the canal. Calculate the width of the inner side of the
canal bank by dividing the height of the cross section by the side slope.
62
In this case, w = h / ss = 0.7 / (1/1.5) = 1.05 m. Measure 1.05 m
from Peg 2 and from Peg 3, and drive Pegs 4 and 5 firmly into the soil,
because later they will serve as reference pegs. Fix the level of these pegs
in relation to the top of the embankment, by, for instance, putting a mark
at 0.10 m above the design top of the embankment. The difference in
level between the marks at Pegs 4 and 5 and the canal bed is then 0.80 m
(height of the cross-section + 0.10 m). For a canal in cut, measure a path
of 0.50 m next to Pegs 4 and 5, marking the points with Pegs 6 and 7. As
earth is excavated it should be placed outside of these pegs so that the
earth will not fall back into the excavated canal section.
Step 2 Excavate a trench
63
FIGURE 21 Canal construction
64
Step 2
Measure the elevations of the marked points and calculate the
differences
Calculation of the difference in elevation between distant points is
described in Training Manual 2: Elements of Topographic Surveying.
The following data have been obtained by the field survey for canal
alignment b:
Difference in elevation between point 1 and point 2: 0.16 m
Difference in elevation between point 2 and point 3: 0.12 m
Difference in elevation between point 3 and point 4: 0.13 m
Step 3
Determine the average slope between the marks For determination
of the average slope, the differences in elevation are divided by the
distance between the two marks concerned. As a formula: s1 = difference
in elevation1 / distance1 where: s1 is the average slope of the terrain
between points 1 and 2; difference in elevation1
is difference in elevation between points 1 and 2, in meters; distance1 is
the distance between points 1 and 2, in meters.
The following average slopes have been calculated for canal alignment b:
Average slope between points 1 and 2: s1 = 0.16 / 100 = 0.0016
Average slope between points 2 and 3: s2 = 0.12 / 100 = 0.0012
Average slope between points 3 and 4: s3 = 0.13 / 100 = 0.0013
Step 4
Determine the average slope of the field where canal alignment b is
projected
The average slope of (future) canal b is determined by adding up the
different average slopes of the sections and by dividing this sum by the
number of measurements. In this example, three Measurements were
65
made, thus Average slope of canal alignment b: Sb = (s1 + s2 + s3) / 3 Sb
= (0.0016 + 0.0012 + 0.0013) / 3 = 0.0014
Step 5
Check whether the average slope of the canal alignment is within
the range
0.0005 (0.05%) and 0.0015 (0.15%) The slope of the alignment
calculated (0.14 %) is within the range of 0.05 to 0.15%, and so in this
case the canal can be given the same slope as the terrain. If the calculated
slope falls outside of this range, an irrigation engineer should be
contacted for advice.
66
CHAPTER-5
CANAL REGULATOR
5.1CANAL REGULATOR
67
The right bank is 5 meters wide and left bank is 2 meters wide.
Top widths of banks are the same as those on the upstream side.
The regulators carries a road way single lane designed for I.R.C loading
class ‘A’. Provide clear freeboard of one meter above F.S.L. for the road
bridge.
5.2. DESIGN
In this case, the bed level of the canal both upstream and
downstream is the same. The depth of flow upstream is 2 meters while on
the downstream it is 1.75 meters. Thus, there is a drop of 0.25 meters in
the F.S.L. at the site of structure. This difference in levels at the structure
can conveniently be made use of the regulator will be a rectangular
opening with its still at the canal bed level. If A be the area of the opening
and h is the difference in water elevations on both sides, then the
discharge through the opening (submerged orifice) is given by the
equation:
Q= where
Q = 16 cubic meters/second
h = 0.25 meters
16 = 0.75A
69
From the above, it can be seen that the canal water way has been
37percent.
70
Where, C is a coefficient depending upon the drowning ratio(upstream
and downstream of regulator)
Upstream of regulator
71
Area of waterway (15+1) × 2 = 32 sq. meters.
=20.00+2.00+ =+22.02
Drowning ratio =
72
Including end contractions, assume the lineal waterway as 6.00 meters.
5.4. ROADWAY
The road way consists of a clear width of 3.65 meters (12 feet clear)
between kerbs, each of which will be 23 cms (9inches) wide. It will be a
through R.C. Slab directly resting over the piers and abutments. The slab
will be continuous over piers and adopting I.R.C. ‘A’ class loading,
single lane of traffic, a slab thickness of 20 cms will be more than
enough. Detailed design of road slabs is not attempted here.
The bottom of the road slab is kept one meter above the upstream
side F.S.L., at level +23.00.
Top level of the road slab with a 7.5 cms, thick wearing coat will be
+23.275 or 23.28
5.5. PIER
The pier has to be checked for stability. The forces acting on the pier are
as follows:
73
(b) Weight of roadway with the live load
Under these, the pier must be stable. Generally, the weight of pier
and roadway give the stability to the pier in overcoming the horizontal
thrust. So, the worst case is to check the stability of the pier when there is
no love load on the road with the regulator shutters completely closed,
water on the upstream side at F.S.L. and no water downstream. The live
load on the roadway will increase the stability of the pier.
The top of pier under the shutter operating platform will be higher
and this depends upon the height of shutter to be used.
5.6. SHUTTERS
The dimensions of the vent way are 2.00 and 1.75 meters.
Downstream F.S. depth is 1.75 meters whereas the upstream F.S. depth is
2.00 meters. The shutter top is to be at least 30 cms above the upstream
F.S.L. Assuming that the shutter rests in a 7.5 cms deep groove in the
still, the total height of shutter is to be 2.00+0.30+0.08 2.38 meters.
74
If a single shutter is provides, when a vent way is to be clearly
opened, the bottom of shutter will have to be lifted clear over the
upstream F.S.L. Assuming that the bottom of shutter is lifted say 25 cms,
above the upstream F.S.L. the top of shutter will be at a level of
22.00+2.38+0.25
FIGURE 23 SHUTTER
75
FIGURE-23 SHUTTERS
5.7. LOADS
=3.00×4.11
Kerbs: 2
Total = 8555 Kg
76
(2) Weight of pier under the road portion
=4.11
=1.50
1000
Arm of resultant =
77
Eccentricity =
Allowable eccentricity =
This is within safe limits of masonry. Hence the design is safe and the
length of pier as proposed can be adopted.
5.8. ABUTMENTS
The top level of abutment is +23.00 the bottom level of R.C slab of the
road way. The bottom of foundation concrete is +18.80. Adopting 60 cms
thick foundation concrete the top of foundation concrete is +19.40
The abutment will have its front face vertical to facilitate the
working of the regulator shutters in the vertical grooves, inserted in the
front face of the abutment. The abutment carries (in addition to the
sideward thrust due to earth and also surcharge due to live load) a vertical
load, being that due to dead and live loads transmitted by the road slab.
Keep the top width of abutment as 1.00 meter out of which 50cms will be
bearing for the R.C. Slab. The bottom width of abutment may be kept at
2.00 meters. I accurate design, the section will have to be checked for
stability and the most economical section adopted vide.
78
FIGURE-24 ABUTMENTS
5.9. WINGWALLS
The wing walls both on the upstream and downstream side of the
regulator will be of the sloping type, sloping from +23.28, junction with
abutment to +23.00 top of the bank level on the upstream side and 22.75
on the downstream side.
79
FIGURE-25 WINGWALLS
The top of level wings and returns on both sides will be at the respective
T.B.Ls on either side. Since the difference in levels of T.B.Ls on either
side is only 25cms, the same section will be adopted on either side except
that the top level of level wing and return on the downstream side will be
kept at 22.75,and top level 23.00, top width 50cms, top of foundation
concrete +19.40 for the upstream side.
80
FIGURE-26 SECTION OF LEVEL WING AND RETURN
This depends on the length of solid aprons provided on both sides of the
regulator.
The canal bed width is 15 meters. At the end of solid aprons, the distance
between masonry returns will be kept at 15 meters
Assuming the bed material of the canals as sandy and also the
hydraulic gradient in the soil as 1/10, we require 10×2= 20meters length
of apron, as the head of flow is 2meters.
81
This 20 meters of floor is provided as 6.00meters on the upstream
side, 5.6 meters under the regulator and the balance downstream. The
maximum uplift is experienced just downstream of shutter.
Assuming that the shutters are located in the center of the operating
platform, the head lost in creep by the time the seepage reaches the
shutter
=6
Assuming that the tail water is at the downstream bed level, the
thickness of apron required
This can be gradually reduced to 60cms thick at the end of the apron
So, the thickness of apron can be nominal and can be limited to 30cms
5.10. REVETMENTS
Provide for the same length of rough stone revetments on the canal
slopes to a thickness pf 45 cms.
82
vent is closed, the rear water backs up, and the water level will practically
be same on both sides of the pier. Hence, there is no cross thrust.
In case of river and spillway regulators when all vents are closed
and one vent open, there will be water standing against the pier on one
side only. It is then necessary to check the pier for stability against cross
thrust, and to provide enough thickness of pier to see that no tension is
developed across the thickness of pier.
The actual position and type of friction blocks can best be decided
by hydraulic model experiments only.
5.12. GENERAL
83
developing under the floor may be calculated by Khosla’s method and
thickness computed.
5.12.1. SPECIFICATIONS
For regulators of smaller height and those that do not carry road
slabs, a leaner proportion of concrete, say 1:4:8 will surface.
For piers and abutments, the top 30 cms height is made up with
1:2:4 cement concrete with the top surface rendered smooth, for thee slab
to rest uniformly. Before laying the road slab the top surface of the piers
and abutments is painted with one or two coats of hot bitumen. Instead of
this craft paper may be laid just before laying the road slab concrete. This
84
arrangement will facilitate free movement of the slab over the supports
while expanding or contracting during variation of temperature. This will
prevent developments of unsightly cracks in masonry just below the road
slab, due to pulling effect of the road slab.
4. Road slab: In the preset case, there is a continuous road slab over all
the three spans. With the calculated reinforcement, the road slab and
kerbs are laid in cement concrete 1:2:4
The wearing coat is laid as a separate entity a long time after the
road slab is laid. The wearing coat is laid in cement concrete 1:1½ :3 with
a maximum thickness of 7.5 cms at center of road slab, sloping down to a
thickness of 5 cms towards the kerbs. This is to facilitate easy draining of
rainwater towards the kerbs where drainage sprouts are inserted.
Before laying this wearing coat, tell-tale steel sheet strips or 5mm
tell-tale roads are spread at intervals over the road slab. Sometimes hot
bitumen is also applied on strips. The idea behind this arrangement is that
due to vehicular traffic, the wearing coat will slowly wear down resulting
in reduction of thickness. Sometimes, the wear may be so much that the
tell-tale strips or rods may get exposed. This is an indication that the
wearing coat is almost gone and has to be relaid. If this is not done,
damage will encroach into the main road slab and this is not desirable.
5. Weep holes: these are left in the wing walls and abutments above canal
F.S.L. with inverted filters, so as to drain off any saturation from the
earthen embankment under the road.
85
CHAPTER-6
CONCLUSION
6.1. Conclusion
86
CHAPTER-7
REFERENCE
7.1. References
[2] Bhowmik, G.N., Xia, R., Mazumder, S.,B., Soong T., W.,
"Return Flow in Rivers due to Navigation Traffic", J. of Hydraulic Eng.,
ASCE, Vol. 121, No. 12, Dec. 1995.
87
[4] Hofman, M., Radojcic, D., Ship resistance in shallow water (in
Serbian), Faculty of Me- chemical Engineering, University of Belgrade,
1997.
88
7.1.3. Reference from website
2. http://canalrivertrust.org.uk
3. www.oxfordreference.com
89
7.2. Discussion with Nawad Tech
90
91
92
93
94
95