Designed by:
Project Name : Gadag - Hotgi Doubling
Bridge No : 9B
Chainage : 53.250 Km
Hydrometeorological Sub zone : 3h
Type of Bridge : RCC BOX
Avg. Span : 4.50 m
No.of Spans : 1 nos
Height of Box 4.75 m
TOPOSHEET DATA
Latitude : N
Longitude : E
Catchment Area : 0.467 Km2
Length of Stream : 0.763 Km
Level at stream origin : 600.000 m
FIELD DETAILS
Type of bed material at
: Brownish Silty Sand with Clay & Gravel
Catchment area
Rail Level : 568.553 m
Formation Level : 567.865 m
Bed Level : 556.570 m EXG. BL : 564.645
Box invert level : 556.420 m
OHFL : 565.255 m
OTHER DETAILS
R-50Yr 24hr point rain fall in mm : 160 (Isopolivual Map-6.1 x 1.15)
R : 184.2 : 18.42 cm
Mannings co-eff (n) for sandy
: 0.03 (Poor condition of channel)
bed.
Runoff Coefficient Factor based
(Type of bed material)
on nature of soil,soil : 0.415
(Sandy Soil/Sandy Loam/Arid Area)
cover,location of the Catchment
F-areal reduction factor : 0.72 (From Table 6.2 of Technical Monograph No-50)
CALCULATIONS
tc : [0.763^3/43.43]^0.345
: 0.206 hrs
: 12.346 min
Intensity of Rainfall, I
580.000
C.L of Bridge LEVEL
BED LEVEL
564.645
LEVEL
540.000
250 m D/S 250 m U/S
s : 0.0800
2/3 0.5
Velocity, V : 1/n x r xs Mannings formula
2/3 0.5
: 1/0.03 X 0.543 X 0.0800
: 6.276 m/s
Waterway Area
Required : 3.222 m2
Provided : 21.375 m2 > 3.222 Safe
Free Board
Availiable : Formation level-Q50 HFL
: 567.865 - 557.286
: 10.579 m > 1.000 Safe
Verical Clearance
V.C : Soffit of box -Vent Height level
: 561.170 - 561.170
: 0.000 m = 0.000 Safe
Scour Depth
Design Discharge (+30%)(for
foundation design), Qf
: 1.3 X Q50
: 1.3 x (20.223)
: 26.290 cum/sec
Design Discharge intensity per m
26.29/1x4.5
width, Qf
Qf/m 5.84 cum/sec
(As per cl:4.5.3 of Sub-Structure Code)
Lacey's regim width, PW : 1.811*C*Q
0.5
m C : 2.67
: 1.811 x 2.67 x ((20.223)^0.5 )
: 21.745 m
The width of water way provided is less than The Laceys regime width
(As per cl:4.6.3 of Sub-Structure Code)
Qf depth : (Qf/Velocity)/Span
: 26.29/(6.276) / ((4.5 x 1))
: 0.931 m
Note:- Hard Strata is available at avg. 3.0m(BOULDERS)from bed level.The calculated scour depth
below bed level is 1.59m. The foundation is resting on Hard strata, but will be decided by the site incharge
during execution of the work.
RESULTS
CERTIFICATE
Certified that the water way and depth of foundation have been checked as per latest guidelines of RDSO
and found safe for up line D/S side. Available free board is more than the required free board and the vent
provided is more than the required. Hence the bridge is safe for passing Q 50 discharge.
And also certified that the catchment area, longest stream length, level of origin of stream,bed slope,bed
level etc are verified from field survey & found correct.
DY.CE/CN/III/UBL
SILT FACTOR CALCULATION
1.000 1.100 8.113 3.300 11.138 5.600 6.793 8.100 2.025 81.900 20.475 48.543 0.485 1.226
BOX
2.000 1.800 13.275 3.500 11.813 6.800 8.248 9.600 2.400 78.300 19.575 55.311 0.553 1.309
SCOUR DEPTH CALCULATION
THE DESIGN SCOUR DEPTH CONSIDERED FOR BOX FROM Qf LEVEL IS = 5.07 m
SCOUR LEVEL = 552.43 m