Name Lewek Altair Lift and Intermediate Stability Period Current Month Task Status All Open
Apr '19
TITLE % OWNER DURATION START DATE END DATE COMPLETED ON
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
LA2-T1 Accommodation Lift and Removal
0
Apr 10 - 17 Unas s igned
LA2-T17 FE modelling and Analysis 0
Apr 10 - 17 rajat.gupta
LA2-T12 Review Calculation 0
Apr 10 - 17 Ameya Kannamwar, Admin
LA2-T2 Intermediate Stability Intact
0
Apr 10 - 17 Unas s igned
LA2-T6 Get Weight Distribution 0
Apr 10 - 12 Rahul Kamilla
LA2-T7 Get Weights of the Removal Items 0
Apr 10 - 12 Rahul Kamilla
LA2-T18 FE Modelling Analysis and Reporting 0
Apr 10 - 17 gundu.hars havardhan
LA2-T13 Review Calculation 0
Apr 10 - 12 Ameya Kannamwar, rkv
LA2-T3 Crane Pedestal Removal
0
Apr 10 - 19 Unas s igned
LA2-T8 Weight Of the removal items 0
Apr 10 - 12 Rahul Kamilla
LA2-T9 Lifting and Rigging Arrangement 0
Apr 10 - 12 Rahul Kamilla
LA2-T19 FE analysis and Reporting 0
Apr 10 - 17 Rahul Kamilla
LA2-T14 Review Calculation 0
Apr 18 - 19 Admin
LA2-T10 Lifting Drawings for Accommodation
0
Apr 17 - 21 Unas s igned
LA2-T20 Drawing and Procedure CAD 0
Apr 17 - 21 s us hant.jadhav
LA2-T15 Review Drawings 0
Apr 17 - 21 Admin, rkv
LA2-T11 Lifting Drawing for Crane
0