You are on page 1of 38

Prof.Dr.Ir. Masyhur Irsyam, MSE.

(ITB - HATTI) 5 November 2018

On behalf of:
BAMBOO PILE-MATTRESS SYSTEM AS AN ALTERNATIVE OF
The Indonesian Society for Geotechnical Engineering (HATTI)
SOFT GROUND IMPROVEMENT
FOR COASTAL EMBANKMENT IN INDONESIA
Masyhur Irsyam*
*President - Indonesian Society for Geotechnical Engineering
*Member - Indonesian Academy of Sciences
*Chair - Team for Revision of Seismic Hazard Maps of Indonesia 2010 and 2017 Acknowledgement:

The Organizing Committee

Part of this material has ben presented in:

Content:
1. Ground Improvement Methods for Recent Major Infrastructure Projects in
Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:


a. For Railway Embankment
b. For Container Yard

4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

5. Conclusions

Workshop HATTI 2018 1


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

TRANS SUMATERA
TOLL ROAD 2015 Geotechnical and Hydrological Condition
Soil Surface Condition

• Swampy area, with about 1.5m to 2m depth of water (STA 0+000 to STA 17+000)
• Flooding (5 years return period), the water level increase about 1m from initial elevation
• Total area of submerged zone until STA 18+000

Technical Requirement for Improvement of Soft Soils for Toll Road Construction
(Department of Public Works 2002 and 2013)
Soil Stratification Profiling

Inderalaya Palembang

Fill Height : 1m – 6m Surcgarge load during preloading > 1.2qfinal qfinal


Consolidation > 90% Settlement < 20 mm/year
< 100 mm

Subgrade level:
qall 110 kPa from
Plate Loading Test (1m x 1m)
Safety Factor againts Slope Stability SF> 1.5

Workshop HATTI 2018 2


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

SELECTED SOLUTION
Comparison: Soil Preloading and Vacuum Preloading

Soil Preloading Vacuum Preloading


ROW ROW
Surcharge
Surcharge Surcharge
Surcharge
Pavement

SandBlanket
Sand Blanket Berm
Berm Berm
Berm

Vertical
Vertical Vertical
Vertical
Drain
Drain Drain
Drain
SoftClay
Soft Clay SoftClay
Soft Clay

Masse et al, 2001 Geotekindo, 2015


VACUUM PRELOADING • Wide ROW • Narrow ROW
• Negative pressure from vacuum will generates negative pore water pressure, • High soil surcharge • Lower or no soil surcharge
increase effective stress in the soils, and results in accelerating consolidation • Need thick horizontal drain • Relatively thin horizontal drain
process • Lower Stability • Better Control of Stability
• Much smaller amount of fill material that is needed • Greater Lateral Movement • Lesser Lateral Movement
• There is no slope instability problem because the soil is in isotropic • Longer Construction Time • Shorter Construction Time
consolidation condition
• Shorter time for construction
Chu Jian, Guo Wei, Yan Shuwang, 2015

CONSTRUCTION OF VACUUM PRELOADING CONSTRUCTION OF VACUUM PRELOADING


1. Geotextile 2. Sand Filling 5. Geo Membrane Installation 6. Instrumentation

3. PVD Installation 4. PHD Installation


7. Vacuum Process 8. Backfilling during vacuum

Workshop HATTI 2018 3


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

CPT TEST : ZONE 1

Map of Earthquake Sources for Indonesia 2017 TYPICAL SOIL PROFILE


Subduction Megathrust
Pavement surface Long Section Runway

Ground water surface

Earthquake Hazard:
- Tsunami
- Ground Shaking
- Liquefaction Long Section Pararel Taxiway
Pavement surface

Ground water surface

Kedalaman
▪ 0 – 3 m = Very Loose to Loose SAND
▪ 3 – 7 m = Loose to Medium SAND
▪ > 7 m = Dense to V Dense SAND

Workshop HATTI 2018 4


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

PAVEMENT FOR AIR SIDE AREA Liquefaction Susceptibility


Historical Criteria

Relationship between limiting


Palu
epicentral distance of sites at which
Design Criteria: liquefaction has been observed and
moment magnitude for shallow
•Safety Factor for Liquefaction >1.30 based on NCEER method with PGA 0.4g. earthquakes (Ambrassey, 1988)
•Settlement < 10cm in future 10 years
•Post Improvement requirements:

Dynamic Compaction for


Counter Measure of Liquefaction

Liquefaction Susceptibility
Compositional criteria
Necessary Conditions:
1. Sands (and Silty Sands and Clayey Sands),
if fine content < 15%
1. Potentially liquefiable soil (soil type, condition)

2. Silt:
2. Saturation
Low Plasticity (PI < 15%)
Higher Plasticity
3. Undrained loading:
-Earthquake 3. Clays:
-Blasting -Fraction finer than 0.005 mm < 15%
-Pile driving -Liquid limit, LL < 35%
-Trains, etc -Natural water content > 0.9 LL

Workshop HATTI 2018 5


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Sieve no: 270 200 100 60 40 20 10 4 3/4"


100 100 100

90 90
Most likely to
be liquefied
80 80 80

Percent finer by weigth (%)


Percent finer by weight

70 70

60 60 60
D50 range per JRA
50 50

40 Tsuchida (1970) boundaries for:


40 Potentially liquefiable soils
40
Most liquefiable soils
30 30

20 20 Palu soils: 20
Likely to be liquefied Jl. Kenduri (Balaroa)
10 Soccer Field Jl. Lasoso 10
Residential Jl. Kedondong
Noodle Factory Jl. Kedondong
0 0 0
0.001 0.01 0.1 1 10 100 0.001 0.01 0.1 1 10 100
Particle Size (mm) Grain size (mm)
SAND
C LA Y SILT G RA VEL
F I NE M ED I UM C O AR S E

Gradation Range for Potentially Liquefiable Sand (Hatanaka et al., 1997)


Cyclic Stress Ratio, (CSR7.5) or Cyclic Resistance Ratio (CRR7.5)1 atm

t
CSR=
sn
Magnitude gempa
Kandungan butir halus
Percepatan gempa
Muka air tanah
Liquefied
Kedalaman yg ditinjau

Non-Liquefied

Corrected SPT Blow Counts, (N1)60 or (N1)60CS


N-SPT
Correction Due to Fine Content
(Seed et al., 1985 and Youd et al., 2001)

Workshop HATTI 2018 6


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

TRIAL TEST OF OF DYNAMIC COMPACTION

• Pelaksanaan dilakukan dengan menentukan konfigurasi jumlah pukulan yang


harus dilakukan melalui tahapan percobaan.
• Dari proses tersebut, jumlah pukulan jika diperlukan dapat dibagi menjadi
beberapa tahap pemukulan dan fase ironing.
Drop height: 15 m to 17 m Zona Zona
Zona Zona
Zona
Zona
Hammer weight: 15, 17, dan 23 Ton

Fase
Fase 111
DC Phase
THE PROCESS

H
Fase
Fase 222
DC Phase W

(if necessary)

Fase
Fase 33
VC Ironing

Result of Dynamic Compaction New Yogyakarta International Airport


Zona B - 6 Pukulan
Rapid Impulse Compaction for Land Site Area, 2018
Hasil Uji CPT Hasil Uji
N-SPT
SPT
0 10 20 30 40 50 60
0

2
after
3
Depth (m)

Kriter ia Desain
Pre-SPT
before 5
before Post-SPT

specification 6
after
7

specification
8

Proses Trial (Percobaan) menghasilkan konfigurasi pemukulan sebagai berikut:


1. Berat tamper: 17 Ton
2.Tinggi jatuh: 15 m
3.Jumlah pukulan: 6 pukulan

Workshop HATTI 2018 7


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Impulse Compaction for Land Site Area


New Yogyakarta International Airport

0.50 m

CONSTRUCTION OF RUNWAY 3
TIPIKAL MELINTANG TAXIWAY
SOEKARNO – HATTA INTERNATIONAL AIRPORT SECTION 1
60,00

JAKARTA 2018 27,50 17,50


SHOULDER
25,00
MAIN LINE
17,50
SHOULDER
27,50 1.50 m
CL

Saluran-1
RUNWAY 3 TIMBUNAN
TIMBUNAN
Saluran-2
Kolam
Saluran-3 TAXIWAY retensi
`
RUNWAY 2 Stone Column
Pola Segitiga spasi 1,5m, t = 4,5m & 5m

KETERANGAN PVD Pola Segitiga spasi 1m, t = 8 – 16 m

Jalan Perimeter P-401 AC-WC, t = 5 cm P-401 AC-WC, t = 5 cm


P-401 AC-BC, t = 5 cm
Jalan Inspeksi P-304 Cement Treated Base course, CBR >100%, t = 13
P-401 AC-BC, t = 10 cm
P-304 Cement Treated Base course, CBR >100%, t = 30 cm
Saluran cm P-209 Crushed Agregate Subbase, CBR >80%, t = 42 cm
P-209 Crushed Agregate Subbase, CBR >80%, t = 20 cm Control Fill CBR 6%, t = 165 cm
Gardu Catu daya listrik Control Fill CBR 6%, t = 165 cm Sand Blanket, t = 60 cm
Sand Blanket, t = 60 cm
TYPICAL POTONGAN LAPISAN PERKERASAN

Preloading, t = 228 cm Stone Column Pola Segitiga spasi 1,5m,


Control Fill CBR 6%, t = 165 cm t = 4,5m & 5m

Liquefaction → Stone Column


Sand Blanket, t = 60 cm
PVD Pola Segitiga spasi 1m, t = 8 – 16 m

Consolidation → PVD TYPICAL POTONGAN SOIL IMPROVMENT

Workshop HATTI 2018 8


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

2nd Trial, 11 April 2018

East Connection Taxiway


Soekarno Hatta International Airport
Jakarta – Indonesia
2018

Application of
Full Displacement Column f 32 cm
for solving Bearing Capacity and
Consolidation problems

Workshop HATTI 2018 9


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

► LONG SECTION
► DETAIL PROJECT LOCATION PROFILE OF CONSTRUCTION HEIGHT

EAST SIDE TAXIWAY


CONNECTION NP1 SECONDARY APRON Hmax ≈ 10.3 m
COMPLETED ON PROGRESS
(Previous Phase 2016 – 2017) 2017
Phase I 2016 Phase2018
I 2018
Hmax ≈ 8.6 m
BRIDGE

WEST CONNECTION TAXIWAY


TAHAP 1 TAHAP 2
0.92%
1.30%

1.280%

TERMINAL 1 TERMINAL 3

BRIDGE

TERMINAL 2 EAST CONNECTION TAXIWAY


(Current Phase 2018) Hmax ≈ 8.7 m

Phase I 2016 ON
COMPLETED Phase I 2018
PROGRESS
2017 2018 Hmax ≈ 9.4 m

TAHAP 1 TAHAP 2
WEST SIDE TAXIWAY

BRIDGE

► SEQUENCE OF WORK

q badan taxiway=5 ton/m2

q bahu taxiway=1 ton/m2


q bahu taxiway=1 ton/m2

FDC or KGM

FDC = Full Displacement Column Design Criteria: Step 1: Step 3: Step 4:


Positioning of FDC rig Installation to Once the displacement tool
KGM = Kolom Grout Modular • Minimal Subgrade CBR 6% required founding reached the required depth,
• Settlement post construction < 100mm depth simultaneously it will extract and
pump in-situ fill material (mortar)
• FS static > 1.5 and FS earthquake > 1.0 through the hollow rod. The tool is
Step 2: rotated in the same direction
Lowering the displacement tool into the ground by during installation phase
rotating and pushing. Soil is loosen by the auger starter
and the pushed into the surrounding soil by the
displacement body

Workshop HATTI 2018 10


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

► FDC TYPICAL SETUP

MIXER
FDC RIG TRUCK

MORTAR
SUPPLY LINES
PUMP

FDC RIG

MIXER
TRUCK

GROUNDAPRON
PERLUASAN IMPROVEMENT
5.8 Ha WORK FOR WEST APRON DEVELOPMENT
I GUSTI NGURAH RAI AIRPORT, BALI

 Konsep Desain
Load
Vibro-Compaction
AREA 5.8 Ha
1. Pemasangan FDC dan LTP
Loading Transfer Platform (LTP)
2. Pembebanan dan distribusi tegangan oleh LTP
ke FDC dan tanah sekitarnya
F F F F
3. Selama proses konsolidasi. Pada saat
D D D D
displacement tanah terjadi lebih besar
C C C C
daripada displacement FDC, sebagian
tegangan pada tanah tertransfer pada FDC
akibat negative skin friction pada bagian atas Header Pit 2B
Compressible Soil Layer FDC Header Pit 2A

4. Pada saat tercapai kondisi displacement tanah


mengecil sehingga kurang dari displacement
FDC pada kedalaman tertentu, terjadi transfer
tegangan kembali dari FDC ke tanah sekitarnya.
Hal ini memobilisir positive skin friction dan
tahanan ujung bawah FDC
Bearing Layer/ 5. FDC dan tanah sekelilingnya bersama-sama
Less Compressible Soil Layer menahan beban secara komposit

Workshop HATTI 2018 11


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Map of Earthquake Sources for Indonesia 2017 RENCANA DESIGN AREA 5.8 Ha
Subduction Megathrust
RENCANA DESIGN

SALURAN EKSISTING

RENCANA SALURAN

DESAIN PEMINDAHAN SALURAN EKSISTING


POTONGAN MELINTANG PERKERASAN

RENCANA PERKERASAN APRON

Earthquake Hazard:
- Liquefaction
TANAH EKSISTING (SEBELUM VIBRO FLOATATION)

TANAH EKSISTING (SESUDAH VIBRO FLOATATION)

VIBRO FLOATATION 10 m

DESAIN RENCANA PEKERJAAN BREAKWATER


RENCANA PEKERJAAN PERKERASAN APRON BARAT

Working Progress

Content:
1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:


a. For Railway Embankment
b. For Container Yard
4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

Assembly and testing of Vibro-Flotation Equipment 5. Conclusions

Presentation for PT Pembangunan Perumahan


11/2/2018
(Persero)

Workshop HATTI 2018 12


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Embankment on Soft Soils

Low bearing capacity


For:
Limited Height - Embankment with limited height
Very soft soil
- Embankment in submerge area
- Embankment with tolerable settlement
- Embankment in remote area

Large and Uneven settlement

Very soft soil

BAMBOO PILE-MATTRESS SYSTEM Stability of Embankment Without Reinforcement

Critical hc 
height

Soft Soil

Workshop HATTI 2018 13


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Stability of Embankment With Geotextile Stability of Embankment With Bamboo Mattress

It enforces the failure surface not to pass


through middle of the embankment

Distribute embankment load more


uniformly
Reduce differential settlement due to it
stiffness

Provides buoyancy

Stability of Embankment With Bamboo Pile- Mattress Consolidation Settlement

6.00 m 6.00 m

0.75 m 1.5 1.5 1.5 1.5


0.75 m
1 1 1 1

2.50 m 2.50 m

1 1

4 4

Increase resistance due to side friction from bamboo piles

However, embankment is still subjected to consolidation


Bamboo mattress only Bamboo pile-mattress system
settlement!!!

Workshop HATTI 2018 14


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Coastal Embankment 1995

Durability? 3m

Bamboo is durable Very Soft-Soft Clay


as long as it is always saturated N-SPT = 0-1
25 m qc = 1-2 kg/cm2
C = 0.65 t/m2

Appropriate for embankment in


coastal and swampy area where
it is always saturated Stiff-Very Stiff Clay
N-SPT = 16
C = 9 t/m2

4m

3m
High Strength Woven Geotextile

Workshop HATTI 2018 15


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Utilization of Bamboo Mattress for Coastal Embankment


at Tambaklorok - Semarang

Laboratorium Geoteknik
Pusat Penelitian Antar Universitas, PPAU
Institut Teknologi Bandung

Embankment for Land Reclamation on Very Soft Soil


Morokrembangan-Surabaya 1999

Workshop HATTI 2018 16


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Dermaga dan Breakwater, Muara Angke 2003


D
F

C E

Quarry run/
Seabed kerikil/sand bags Seabed

Ma tra s Bamboo 5 l apis

Cerucuk Ba mboo
Spa si = 1 m, L = 6 m
B

Tipikal Potongan Melintang


A

Armor: Rubl e mount


W50 = 370 Kg, Ø59 - 70 cm
Tipikal Potongan Armor: Ruble mount
W50 = 400 Kg

Sekitar Dermaga
Fi l ter: W50 = 37 Kg 2% 2%
Ø27 - 33 cm

Pa s i r
Sea bed Qua rry run/ 1:1 Seabed
keri kil/sand bags

Matras Bamboo 5 lapis Woven Geotextile


Cerucuk Bamboo
L=6m

Workshop HATTI 2018 17


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Prefabricated
Segmental Raft

Content:
1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia

2. Previous Experiences Using the Bamboo Pile-Mattress System

3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:


a. For Railway Embankment
b. For Container Yard
4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System

5. Conclusions

Workshop HATTI 2018 18


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

UTILIZATION OF BAMBOO PILE-MATTRESS SYSTEM FOR


RAILWAY EMBANKMENT ON VERY SOFT SOIL CONDITION
SEMARANG –TAWANG, 2012-2013

Workshop HATTI 2018 19


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Cara Meletakkan Bambu


Pada Matras

Untuk 5 lapis

Workshop HATTI 2018 20


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 21


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 22


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Workshop HATTI 2018 23


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Loading Test Cargo Train

UTILIZATION OF BAMBOO PILE-MATTRESS SYSTEM FOR CONTAINER YARD


ON VERY SOFT SOIL CONDITION
New Priok Port Project:
JAKARTA PORT TERMINAL, KALIBARU, 2013

Masyhur Irsyam Bangun Sucipto Andi Kartawiria


Ketua - Himpunan Ahli Teknik Tanah Indonesia PT. Pembangunan Perumahan PT. Promisco
Ketua - Pusat Penelitian Mitigasi Bencana ITB
Ketua - Tim Revisi Peta Gempa Indonesia
Anggota - Tim Penasehat Konstruksi Bangunan DKI

CT 1 SUPPORTI
NG
AREA

CT : Container Terminal
PT : Product Terminal

FERIALDY NOERLAN – Direktur Teknik PT PELABUHAN INDONESIA II (Persero)


Surabaya, 4 Juli 2013 Seminar HATTI, Desember 2012

Workshop HATTI 2018 24


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Reklamasi:
Sebagian besar area yang
tersedia untuk reklamasi berada
di atas tanah lunak → complicated
design (matras bambu untuk
pondasi revetment);

Permasalahan ketersediaan
pasir untuk material reklamasi;

Owner : PT PELABUHAN INDONESIA II (Persero)


Konsultan : direncanakan oleh PT LAPI ITB
Kontraktor : PT Pembangunan Perumahan
(Penulis terlibat sbg Geotechnical Expert PT PP)

FERIALDY NOERLAN
Seminar HATTI, Desember 2012

VERY SOFT TO SOFT CLAY

MEDIUM TO STIFF CLAY

VERY HARD CLAY

STIFF TO VERY STIFF CLAY

Panjang daerah yang diperkuat dng cerucuk matras bambu > 5.o km
Jumlah matras > 360 ribu
FERIALDY NOERLAN
Seminar HATTI, Desember 2012

Workshop HATTI 2018 25


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

PT. PP (Persero)

Workshop HATTI 2018 26


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

PT. PP (Persero)
PT. PP (Persero)

Alat pancang cerucuk cluster bambu dipatenkan oleh PT .PP Alat pancang cerucuk cluster bambu dipatenkan oleh PT. PP

PT. PP (Persero) Alat pancang cerucuk cluster bambu dipatenkan oleh PT. PP

Workshop HATTI 2018 27


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

PT. PP (Persero)

Workshop HATTI 2018 28


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

PT. PP (Persero)

Workshop HATTI 2018 29


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

PT. PP (Persero)

Semarang
Giant Sea Wall and Shoreline Belt

Demak

Shoreline Belt
Kendal

Workshop HATTI 2018 30


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Semarang-Demak Toll Road and Sea Dyke Semarang-Demak Toll Road and Sea Dyke

TITIK AWAL

INUNDATION DURING HIGH TIDE SEA DYKE


Luas genangan ROB + 4.500 ha (2007), dan akan meningkat terus
Penyebab : penurunan muka tanah (land subsidence); abrasi pantai;
Tetrapod
dan kenaikan muka air laut (SLR). Geomembran
+4.30 m
1.00
1:3
+7.50m
1:3
DWL = +3,36 m Batu Gradasi 60 - 300 kg, +3.50m
1:5 1:5
MSL = +0,00 m
Matras Bambu 14 Lapis

Crucuk bambu + Pvd

124 125

Workshop HATTI 2018 31


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Sea Dyke
 Tahapan :
 Urug pasir 1 m
 Pasang cerucuk cluster bamboo L = 10 m, spasi 1.0 m Content:
 Pasang matras bambu 14 lapis
 Pasang PVD L = 20 m 1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia
 Timbunan bertahap 1 m (termasuk batu dan tetrapod) dengan waktu konsolidasi
2. Previous Experiences Using the Bamboo Pile-Mattress System
14 hari per tahap hingga elevasi + 5.70 (as). Pada tahap akhir hingga elevasi + 7.20
as, waktu konsolidasi selama 90 hari sebelum pelaksanaan perkerasan fleksibel. 3. Utilization of Bamboo Pile-Mattress System for Soil Improvement:
a. For Railway Embankment
b. For Container Yard
4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System
Tetrapod
+4.30 m +7.50m
1:3
DWL = +3,36 m
Geomembran
Batu Gradasi 60 - 300 kg, 1.00 1:3
+3.50m
5. Conclusions KOLAM RETENSI

1:5 1:5
MSL = +0,00 m
Matras Bambu 14 Lapis -1.50 m
- 2.50 m
1:3
- 5.72 m
Crucuk bambu + Pvd

How to calculate? Coceptually, it is similar with pile-raft system for high rise buildings

2-Dimention

3-Dimention

BAMBOO PILE-MATTRESS SYSTEM Pile-Raff Foundation

Firmansyah, 2013

Workshop HATTI 2018 32


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

FEM Modelling
Embankment soil
Beam

Beam with interface Node-to-Node Spring

Very Soft Soil

FEM 3D FEM 2D

Configuration of bamboo cluster pile

Beam

Beam dng interface element

Very Soft Soil

FEM 2D

Workshop HATTI 2018 33


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Matt and Pile Properties

Tetrapod
+7.50m
Beam Element Geomembran
+4.30 m
1.00
1:3
1:3
DWL = +3,36 m Batu Gradasi 60 - 300 kg, +3.50m
EI = E x Imatras 1:5 1:5
MSL = +0,00 m
Imatras =  Ibambu +  (Ar2) Matras Bambu 14 Lapis

I =
(
 D o4 − D i4 ) Crucuk bambu + Pvd
0.7m 64

1.0m
K = Node to Node Spring/ Anchor

- Fmax

FEM 2D

Verification and Numerical Modeling


By Using
Instrumented Trial Embankment
at Tambak Oso Surabaya Pembuatan Matras bambu

Pemancangan Cerucuk Bambu

Workshop HATTI 2018 34


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Pemasangan Instrumentasi di lapangan : Pemasangan Instrumentasi di lapangan :

Pemasangan Settlemetn Plate Pemasangan Piezometer dan tipe alat baca

Grafik Penurunan-Waktu pada Settlement Plate 4

Tinggi Timbunan (m)


4
konstruksi
3

0
0 20 40 60 80 100 120

10
Elastic settlement = 48 cm
Elastic settlement Consolidation settlement = 17 cm
20

Penurunan (cm)
30

Consolidation settlement
40
Elastic settlement
50

Consolidation settlement
60
Elastic settlement
Consolidation settlement
70
0 20 40 60 80 100 120

Hari Pengamatan

Workshop HATTI 2018 35


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Embankment Height (m)


4
3
2
1
0
0 20 40 60 80 100 120 140 160 180 200

(a) Shading of Deformation (b) Arrow of Deformation 10

Elastic Deformation 20

30

Settlement (cm)
40

50

60
30.17241
70

80

90

100
0 20 40 60 80 100 120 140 160 180 200

Analytical Method Prediction DayPrediction


Finite Element Method Settlement Plate 1
Settlement Plate 2 Settlement Plate 3 Settlement Plate 4
(a) Shading of Deformation (b) Arrow of Deformation Settlement Plate 5 Settlement Plate 6 Settlement Plate 7

Consolidation Settlement

Analisis Stabilitas Timbunan Double Track


Tawang, Semarang

Workshop HATTI 2018 36


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Initial Condition Timbunan Track Baru Track Baru Opersional

Peninggian Track Lama Peninggian Track Lama Peninggian Track Lama


Matras saja Matras + Cerucuk Matras + Cerucuk

Conclusions
• Recent major infrastructure projects in Indonesia used Vacuum
Content: Consolidation, Dynamic Compaction, Rapid Impulse Compaction,
1. Ground Improvement Methods for Recent Infrastructure Projects in Indonesia Stone Column, and Full Displacement Column etc.

2. Previous Experiences Using the Bamboo Pile-Mattress System • Bamboo pile-mattress system is proven to be reliable, and therefore,
can be used as ground reinforcement for coastal/ swampy
3. Utilization of Bamboo Pile-Mattress System for Soil Improvement: embankment on soft soil layer.
a. For Railway Embankment
b. For Container Yard • Performance of the system can be predicted accurately as long as it is
4. Modelling of Load Transfer Mechanism in Bamboo Pile-Mattress System modeled correctly.

5. Conclusions • Consolidation settlement has to be accounted for during the design


life.

Workshop HATTI 2018 37


Prof.Dr.Ir. Masyhur Irsyam, MSE. (ITB - HATTI) 5 November 2018

Thank You

Workshop HATTI 2018 38

You might also like